Loft conversion with a dormer takeoff
Turn a loft into a room under a rear box dormer: the dormer's deck, warm-roof insulation and waterproofing, the cheeks' membrane and flashings, the knee wall and partitions, insulation, boards and finishes, and an optional shower room, with the floor, the steels, the dormer's frame and the stair listed and never sized.
- Measurements in
- 17
- Trades out
- 3231
- Calculators
- 2524
- Going in
- 3231of 3231
- My Project
- Not in it
No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.
Dimensions
Give the job once
Every figure on the right follows these, in the units you choose.
Choose the build-up
Each layer changes the materials below; the dimensions stay the same.
Calculators behind the other choices:
Calculators behind the other choices:
Every trade, from those dimensions
then change a dimension, and each line shows what moved.
Every trade's quantity · 32 rows
Every trade's quantity · 31 rows
Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.
About this job
A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.
A dormer loft (attic) conversion is a new storey built inside a roof that is still keeping the rain off the rooms below, and the order of work follows from that. The scaffold and a cover go up first; the new floor joists and any steel go in while the roof is still whole; then the back slope is opened only for as long as it takes to frame the dormer, deck it and get a waterproof layer on. Nothing inside starts until the dormer is watertight.
The dormer is three surfaces. Its flat roof is built warm, insulation boards on the deck under the waterproofing, so the joists inside stay at room temperature and need no ventilated gap. Its face carries the windows. Its two cheeks, the triangular side walls between the dormer's roof and the main roof, are tile-hung over a breathable membrane to match the roof, and each meets the main roof along a sloping edge that is flashed from top to bottom; that edge is the dormer's depth lengthened by the main roof's slope factor.
Inside, the boarded surfaces are measured from the loft's own shape: the flat ceiling, the slope above the knee wall on the other side of the roof, the knee wall, the dormer's face, and the two end walls, taken at full height right back to the face, so the inside of each cheek is part of them. The heat insulation goes in the slope, the knee wall, the dormer's roof, cheeks and face, and over the flat ceiling wherever the dormer's warm roof is not above it; the floor takes insulation against sound. An end wall that is a gable facing outside needs insulating as well, and a party wall shared with next door does not. The new partitions round the stair are boarded both sides, because they enclose the way out. How the boards are finished follows the units: skimmed in plaster, the usual British finish, when metric is showing, and taped and filled with joint compound, the North American one, when imperial is, with either one choice away.
The parts that decide whether the room can be slept in are the ones this page never measures. The floor joists, the steels and their padstones, the trimmers round the stair opening and the dormer's frame are the engineer's; the stair's rise, going and headroom, the fire doors onto the stair, the alarms and the escape route are set by the building regulations or code where the house is, and building control signs them off. Each is an item here with no quantity. A shower room is optional: give it a size of 0 and its tanking, tiles, adhesive and grout drop out.
How each line reads
- Base
- What the calculator gives for these dimensions, before anything is added.
- Allowance
- Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
- Adjusted
- The base with its allowance on top.
- Order
- What to buy: the adjusted figure in whole boards, bags, rolls or lengths.
The order this happens in
Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.
- Have the floor, the steels and the dormer designed, lodge the plans or the notice with building control, and serve any party wall notice before the scaffold goes up.
- Scaffold the back of the house with a cover ready over the roof, then clear the loft: the old insulation, any boards, and the cold-water tank if it is going.
- Set the steels on their padstones and lay the new floor joists clear of the ceiling below, before a single rafter is cut.
- Strip the tiles where the dormer goes, prop and cut the rafters, frame the face, the cheeks and the dormer's roof, then deck it and lay the vapour control layer, the insulation and the waterproofing, sheeting the opened slope under the scaffold's cover every night until the waterproofing is on; any rafter, purlin or wall plate found rotten once the tiles are off is repaired before it is built on.
- Membrane, batten and tile-hang the cheeks, dress the flashings where they meet the main roof, fix the fascia and the dormer's gutter, fit the windows, and fit any rooflights in the other slope.
- Trim the stair opening and fit the stair, build the knee wall and the partitions round the escape, and run the cables, the pipes and the shower room's extract duct.
- Insulate the slope, the knee wall, the cheeks, the face and the flat ceiling beyond the dormer's roof, lay sound insulation between the floor joists and deck the floor, then board the room and finish the boards, skimmed in plaster or taped and filled, and tank the shower room once its boards are up.
- Hang the fire doors, fit the handrail, the alarms, the radiator and the shower room, tile it, decorate, lay the floor, and have the electrical test and the completion inspection before the room is used.
What this takeoff does not cover
- The structure: the floor joists, the steels, their padstones and bearings, the trimmers round the stair and the dormer's frame. Each is listed as work with no quantity; the engineer sizes it and building control inspects it.
- The stair and its balustrade, made to the loft's rise and headroom and listed as items. The stair page on this site can check a flight's rise and going, but this page orders no flight.
- Party wall matters: the notices where a steel bears on a party wall or the dormer is built up against one, and any survey or agreement that follows.
- Drainage beyond connecting the shower room to the existing soil stack, a new stack, and whether the boiler or heat pump can take another radiator.
- The tiles on the cheeks and in the made-good slope round the dormer, the cladding on the face beside the windows, and every fixing for them: the cladding and the tiling are listed as work, not measured.
- The floor deck over the new joists, listed as work. A British loft floor is usually decked in tongue-and-groove chipboard 600 mm (2 ft) wide, which the site's sheet page does not count; a US attic floor takes 1220 × 2440 mm (4 × 8 ft) tongue-and-groove sheets, which the plywood page counts over the floor's area.
- Ventilation of the cold roof spaces left behind the knee wall and over the flat ceiling, and the insulation of a gable end wall facing outside.
- The shower room's floor finish, its tray, basin and WC, and the tiling above the height you give.
- Render on the dormer's cheeks or face, where they are rendered rather than tiled or clad, with its primer, mesh and beads. It is not measured here.
- Undercoat and gloss (trim enamel) on the new woodwork: the doors, the architraves (casings) and the rest of the trim. The architraves are not counted, and the paint on the woodwork, with the knotting and priming bare timber needs first, is not measured here.
Labour by trade
Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.
Metric opening
Loft length, wall to wall 6 m · New floor, knee wall to dormer face 5.5 m · Sloped ceiling, on plan 1.25 m and 14 more of the page's opening figures
Imperial opening
Loft length, wall to wall 19.5 ft · New floor, knee wall to dormer face 18 ft · Sloped ceiling, on plan 4 ft and 14 more of the page's opening figures
Quote check
Been given a quote for this job?
Paste it into the loft conversion quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.
What it leaves out
Every line this takeoff has that nothing on the quote reads as.
What it adds
Labour, removal, hire, fees — each named for what it is.
What to ask
One list of questions, ready to copy. Never a verdict.
More takeoffs
Other job takeoffs
External wall finish
3 tradesWrap, cladding and finish over a measured wall area.
Run this takeoffInsulate a floor
3 tradesInsulation, vapour control and underlayment over a floor area.
Run this takeoffFibre cement siding
5 tradesCourses, cutting waste, corner posts, fasteners and caulk for a lap-sided elevation.
Run this takeoff
Frequently asked questions
- What does the loft conversion takeoff give for a typical job?
- Opened at Loft length, wall to wall 6 m · New floor, knee wall to dormer face 5.5 m · Sloped ceiling, on plan 1.25 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Main roof slope factor 1.3 · Dormer width 5 m · Dormer depth, on plan 3 m · Windows in the dormer face 2 · Window width, each 1.2 m · Window height, each 1.2 m · Doors in the new partitions 2 · New stud partitions 6 m · Height of the eaves above the ground 5.2 m · Shower room length (0 if none) 2 m · Shower room width 1.5 m · Tiled height in the shower room 2 m, it orders: Dust sheets in the rooms below, 5 items; Scaffold across the back, 45 m² of face; Deck on the dormer's roof, 6 sheets (2440x1220 mm); Warm-roof boards on the dormer, 6 sheets (2400x1200 mm); EPDM on the dormer, 1 roll; Termination bar at the back upstand, 5.25 m; Termination bar fixings, 19 fasteners; Fascia along the dormer's front, 2 x 3.6 m boards; Breathable membrane on the cheeks, 1 roll; Flashing down both cheeks, 3 sheets; The dormer's own gutter, 2 x 4 m sections; Flashing tape round the dormer windows, 14.5 m; Studs for the knee wall and the partitions, 43 studs; Boards between and under the sloped rafters, 4 sheets (2400x1200 mm); Batts in the knee wall, cheeks and face, 6 packages; Sound insulation between the floor joists, 8 packages; Insulation over the flat ceiling beyond the dormer, 3 packages; Plasterboard (drywall) on the ceiling and slope, 14 sheets; Plasterboard (drywall) on the walls, 16 sheets; Board on both faces of the partitions, 10 sheets; Skim over every board, 295 kg; Tanking in the shower room, 32.4 L; Wall tiles in the shower room, 86 tiles; Wall tile adhesive, 4 bags; Wall tile grout, 2.92 kg; Mist coat or primer on the ceiling and slope, 3.53 L; Mist coat or primer on the walls, 6.73 L; Skirting (baseboard), 25.3 m; Ceiling and slope, two coats, 7.05 L; Walls, two coats, 13.5 L; Skip (dumpster) for the strip-out, 4.95 m³. Opened at Loft length, wall to wall 19.5 ft · New floor, knee wall to dormer face 18 ft · Sloped ceiling, on plan 4 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Main roof slope factor 1.3 · Dormer width 16.5 ft · Dormer depth, on plan 10 ft · Windows in the dormer face 2 · Window width, each 4 ft · Window height, each 4 ft · Doors in the new partitions 2 · New stud partitions 19.5 ft · Height of the eaves above the ground 17 ft · Shower room length (0 if none) 6.5 ft · Shower room width 5 ft · Tiled height in the shower room 6.5 ft: Dust sheets in the rooms below, 5 items; Scaffold across the back, 478 sq ft of face; Deck on the dormer's roof, 6 sheets (4x8 ft); Warm-roof boards on the dormer, 6 sheets (4x8 ft); EPDM on the dormer, 1 roll; Termination bar at the back upstand, 17.3 ft; Termination bar fixings, 19 fasteners; Fascia along the dormer's front, 2 x 12 ft boards; Breathable membrane on the cheeks, 1 roll; Flashing down both cheeks, 3 sheets; The dormer's own gutter, 2 x 10 ft sections; Flashing tape round the dormer windows, 48.4 ft; Studs for the knee wall and the partitions, 43 studs; Boards between and under the sloped rafters, 4 sheets (4x8 ft); Batts in the knee wall, cheeks and face, 6 packages; Sound insulation between the floor joists, 8 packages; Insulation over the flat ceiling beyond the dormer, 3 packages; Plasterboard (drywall) on the ceiling and slope, 13 sheets; Plasterboard (drywall) on the walls, 15 sheets; Board on both faces of the partitions, 10 sheets; Joint compound for taping and filling every board, 3 x 4.5 gal boxes; Paper joint tape over every board, 629 ft; Tanking in the shower room, 8.51 gal; Wall tiles in the shower room, 85 tiles; Wall tile adhesive, 4 bags; Wall tile grout, 6.65 lb; Mist coat or primer on the ceiling and slope, 0.94 gal; Mist coat or primer on the walls, 1.8 gal; Skirting (baseboard), 82.5 linear ft; Ceiling and slope, two coats, 1.87 gal; Walls, two coats, 3.59 gal; Skip (dumpster) for the strip-out, 6.4 yd³. Every figure follows the dimensions you give it.
- Which calculators does the loft conversion takeoff run?
- 25 calculators, for 32 lines: Masking and Protection Materials Calculator, Scaffold Face Area and Hire Quantity Calculator, Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof), Foam Board Insulation Calculator, EPDM Single-Ply Roofing Roll Calculator, Roof Perimeter Termination Bar Calculator, Roof Membrane Termination Bar Fastener Calculator, Fascia Board Calculator, Roofing Underlayment Calculator, Exterior Flashing Layout Trim Sheet Calculator, Gutter Calculator, Window Opening Flashing Membrane Calculator, Framing Stud Calculator, Mineral Wool Insulation Batt Calculator, Ceiling Plasterboard Calculator (Gypsum Board Sheets), Multi-Layer Fire-Rated (Type X) Gypsum Sheet Calculator, Drywall Joint Compound Calculator, Drywall Joint Tape Calculator, Cold-Applied Liquid Waterproofing Membrane Volume Calculator, Floor & Wall Tile Calculator, Thinset & Tile Adhesive Calculator, Grout Calculator, Ceiling Paint Calculator, Baseboard & Trim Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.24 calculators, for 31 lines: Masking and Protection Materials Calculator, Scaffold Face Area and Hire Quantity Calculator, Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof), Foam Board Insulation Calculator, EPDM Single-Ply Roofing Roll Calculator, Roof Perimeter Termination Bar Calculator, Roof Membrane Termination Bar Fastener Calculator, Fascia Board Calculator, Roofing Underlayment Calculator, Exterior Flashing Layout Trim Sheet Calculator, Gutter Calculator, Window Opening Flashing Membrane Calculator, Framing Stud Calculator, Mineral Wool Insulation Batt Calculator, Ceiling Plasterboard Calculator (Gypsum Board Sheets), Multi-Layer Fire-Rated (Type X) Gypsum Sheet Calculator, Skim Coat Plaster Calculator, Cold-Applied Liquid Waterproofing Membrane Volume Calculator, Floor & Wall Tile Calculator, Thinset & Tile Adhesive Calculator, Grout Calculator, Ceiling Paint Calculator, Baseboard & Trim Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
- What does the loft conversion takeoff leave out?
- 10 things, each named on this page: The structure; The stair and its balustrade, made to the loft's rise and headroom and listed as items; Party wall matters; Drainage beyond connecting the shower room to the existing soil stack, a new stack, and whether the boiler or heat pump can take another radiator; The tiles on the cheeks and in the made-good slope round the dormer, the cladding on the face beside the windows, and every fixing for them; The floor deck over the new joists, listed as work; Ventilation of the cold roof spaces left behind the knee wall and over the flat ceiling, and the insulation of a gable end wall facing outside; The shower room's floor finish, its tray, basin and WC, and the tiling above the height you give; Render on the dormer's cheeks or face, where they are rendered rather than tiled or clad, with its primer, mesh and beads; Undercoat and gloss (trim enamel) on the new woodwork.
- Can I check a quote for this job against the takeoff?
- Yes. The loft conversion quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.