Flat roof replacement (warm roof) takeoff
Strip an old flat roof and rebuild it warm: deck, insulation on top of it, the waterproofing you choose, upstands, flashings, gutter and the skip.
- Measurements in
- 7
- Trades out
- 10
- Calculators
- 10
- Going in
- 10of 10
- My Project
- Not in it
No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.
Dimensions
Give the job once
Every figure on the right follows these, in the units you choose.
Choose the build-up
Each layer changes the materials below; the dimensions stay the same.
Calculators behind the other choices:
Every trade, from those dimensions
then change a dimension, and each line shows what moved.
Every trade's quantity · 10 rows
Every trade's quantity · 10 rows
Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.
About this job
A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.
Re-covering a flat roof means deciding where its insulation goes before a single roll is ordered. This page builds a warm roof: a vapour control layer laid on the deck, rigid insulation boards over that, and the waterproofing on top, so the joists and the ceiling void stay at room temperature and need no ventilation. The older way — insulation between the joists with a ventilated gap above it, the cold roof — keeps the deck cold, and a cold deck is where condensation collects. Warming the roof costs height: the finished surface rises by the insulation's thickness, so the upstands (base flashings, in US terms), the edge trims, the fascia and the threshold of any door onto the roof all move up with it.
The waterproofing is ordered for more than the roof. It runs up every wall the roof meets and turns down over every free edge, so the membrane rows here take the plan area plus a strip up each abutment at the upstand height you give and a strip along each free edge at the turn-down you give. The plan area alone buys the insulation, the dust sheets and a replacement deck. Where the roof butts against the house, the length against the wall also decides the cover flashing (counterflashing) and, on EPDM, the termination bar along the top of the upstand.
Two decisions change the item list most. The deck is kept by default, with its repair carried as a provisional item, because nobody can say how much of an old deck is rotten until the covering is off; choose to replace it and the boards become a row. And the falls: a flat roof built dead level holds ponds, so the fall comes either from timber firrings (tapered strips, called furring or sleepers in the US) under the deck or from tapered insulation boards cut to the falls — the second saves re-decking but makes the build-up deepest at the high end, where the upstands must clear it.
The membrane choice changes more than one line. EPDM (a synthetic rubber sheet) goes on cold as a single sheet cut to the roof, bonded down and held at the wall by a termination bar. Torch-on reinforced bitumen, the modern form of roofing felt, is two layers — an underlay and a mineral-surfaced cap sheet — melted on with a gas torch, which makes it hot work on a timber roof. GRP (glass-reinforced plastic, or fibreglass) is resin laid over glass mat on an overlay board with trims made for it. A liquid-applied membrane is brushed or rolled on cold over a primer, with a reinforcing mat bedded into it at every corner and upstand.
How each line reads
- Base
- What the calculator gives for these dimensions, before anything is added.
- Allowance
- Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
- Adjusted
- The base with its allowance on top.
- Order
- What to buy: the adjusted figure in whole boards, bags, rolls or lengths.
The order this happens in
Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.
- Before anything is ordered, open a corner: look at the deck, the joists and the wall plates, and whether the old layers are of an age that calls for an asbestos survey before they are disturbed.
- Put the edge protection up, sheet the room below, and have a temporary cover on site before the first strip — once the felt is off, the roof is a hole in the house.
- Strip in sections no bigger than can be made weathertight the same day, and bag the waste as it comes off rather than throwing it down.
- Replace rotten deck and fix the firrings, or check the existing falls, before anything covers them.
- Lay the vapour control layer over the whole deck, lapped and sealed and turned up at the edges, then the insulation boards tight and staggered, fixed through to the deck.
- Raise the edge timbers to the new height, fix the fascia, and set the drip trim along the gutter edge and the verge (rake) trims along the sides as the membrane system details them.
- Dress the membrane up the walls first where the system asks for it, then lay the field; on torch-on the underlay is completed before the cap sheet starts, with the laps of the two staggered.
- Finish the upstands under a cover flashing, hang the gutter to its fall, and run water across the roof to the outlet before the scaffold comes down.
What this takeoff does not cover
- The joists, the wall plates and whether they carry a warm roof's added weight. Any decay found is a provisional item here; how it is repaired, and whether the structure takes the new build-up, is for an engineer or the building control surveyor, and nothing on this page sizes a member.
- A cold roof, where the insulation stays between the joists under a ventilated void, and anything done inside the room: the ceiling, the vapour check in it and the lights in the void.
- Rooflights (skylights) and their kerbs, which are listed as work with no quantity row. On a warm roof the kerb stands on the insulation, and neither curb calculator on the site builds that detail.
- Quantities for the vapour control layer, the edge trims, the membrane adhesive and primers, and the insulation's fixings. The work is listed; no row measures it. The vapour control layer is roughly the plan area plus its upturn at the edges, and the trims are the free edges' length.
- Internal outlets, scuppers and any pipework inside the building. This page drains the roof to a gutter along its low edge; the gutter row's working counts the downpipes (downspouts), and the pipe is the drop to the ground times that count.
- Parapet walls round the roof and their copings. Where the roof is walled round, enter those walls as length against the house and the upstand rows run up them, but the coping, the damp course under it and any repair to the parapet itself are not measured.
- The insulation's thickness and the thermal performance it reaches, which are a design choice for the rules where you build; the board count is the same at any thickness, and a two-layer build is this row twice.
Labour by trade
Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.
Metric opening
Roof length, along the gutter 5 m · Roof width, the direction of fall 4 m · Length against walls of the house 5 m and 4 more of the page's opening figures
Imperial opening
Roof length, along the gutter 16.5 ft · Roof width, the direction of fall 13 ft · Length against walls of the house 16.5 ft and 4 more of the page's opening figures
Quote check
Been given a quote for this job?
Paste it into the flat roof replacement quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.
What it leaves out
Every line this takeoff has that nothing on the quote reads as.
What it adds
Labour, removal, hire, fees — each named for what it is.
What to ask
One list of questions, ready to copy. Never a verdict.
More takeoffs
Other job takeoffs
External wall finish
3 tradesWrap, cladding and finish over a measured wall area.
Run this takeoffInsulate a floor
3 tradesInsulation, vapour control and underlayment over a floor area.
Run this takeoffFibre cement siding
5 tradesCourses, cutting waste, corner posts, fasteners and caulk for a lap-sided elevation.
Run this takeoff
Frequently asked questions
- What does the flat roof replacement takeoff give for a typical job?
- Opened at Roof length, along the gutter 5 m · Roof width, the direction of fall 4 m · Length against walls of the house 5 m · Upstand height 150 mm · Membrane turned over each free edge 100 mm · Height of the roof edge above the ground 3 m · Loose depth of the old roof, stripped 50 mm, it orders: Dust sheets and tape in the room below, 4 items; Scaffold along the free edges, 39 m² of face; Insulation boards, flat, over a deck laid to falls, 8 sheets (2400x1200 mm); EPDM membrane, 1 roll; Termination bar along the upstands, 5.25 m; Termination bar fixings, 19 fasteners; Cover flashing over the upstands, 2 sheets; Gutter along the low edge, 2 x 4 m sections; Gutter brackets (hangers), 10 hangers; Skip (dumpster) for the old roof, 1 m³. Opened at Roof length, along the gutter 16.5 ft · Roof width, the direction of fall 13 ft · Length against walls of the house 16.5 ft · Upstand height 6 in · Membrane turned over each free edge 4 in · Height of the roof edge above the ground 10 ft · Loose depth of the old roof, stripped 2 in: Dust sheets and tape in the room below, 3 items; Scaffold along the free edges, 425 sq ft of face; Insulation boards, flat, over a deck laid to falls, 8 sheets (4x8 ft); EPDM membrane, 1 roll; Termination bar along the upstands, 17.3 ft; Termination bar fixings, 19 fasteners; Cover flashing over the upstands, 2 sheets; Gutter along the low edge, 2 x 10 ft sections; Gutter brackets (hangers), 10 hangers; Skip (dumpster) for the old roof, 1.32 yd³. Every figure follows the dimensions you give it.
- Which calculators does the flat roof replacement takeoff run?
- 10 calculators, one to a line: Masking and Protection Materials Calculator, Scaffold Face Area and Hire Quantity Calculator, Foam Board Insulation Calculator, EPDM Single-Ply Roofing Roll Calculator, Roof Perimeter Termination Bar Calculator, Roof Membrane Termination Bar Fastener Calculator, Exterior Flashing Layout Trim Sheet Calculator, Gutter Calculator, Gutter Hanger Spacing Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
- What does the flat roof replacement takeoff leave out?
- 7 things, each named on this page: The joists, the wall plates and whether they carry a warm roof's added weight; A cold roof, where the insulation stays between the joists under a ventilated void, and anything done inside the room; Rooflights (skylights) and their kerbs, which are listed as work with no quantity row; Quantities for the vapour control layer, the edge trims, the membrane adhesive and primers, and the insulation's fixings; Internal outlets, scuppers and any pipework inside the building; Parapet walls round the roof and their copings; The insulation's thickness and the thermal performance it reaches, which are a design choice for the rules where you build; the board count is the same at any thickness, and a two-layer build is this row twice.
- Can I check a quote for this job against the takeoff?
- Yes. The flat roof replacement quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.