Building envelope

Warm Deck or Cold Deck on a Flat Roof Over a Room

Insulation above the deck or between the joists: on an extension or a dormer the answer is settled by how far the roof can rise.
  • 20 minReading time
  • 12Sections
  • 8Calculators inline
  • Last reviewed

The tape that settles this is held vertically

Before any of it becomes an insulation question, go up the ladder with a tape and take four measurements off the existing roof surface at the wall of the house. Up to the underside of the bedroom sill. Up to the chase where the old lead is wedged, and to the course of bricks the cavity tray is sitting in above it. Up to the head of the door onto the terrace, if there is one. Up to the top of the gutter at the far edge, which is where all of it eventually has to arrive. Write the four numbers on the brickwork in pencil. That column is the specification.

Both answers on offer will heat the room to the same figure. What separates them is where the thickness goes. Insulation laid above the deck adds its whole depth on top of what is already there — a hundred and fifty of board, plus whatever the fall costs, plus a board and a membrane, and the finished surface is comfortably two hundred millimetres higher than the felt you are standing on. Insulation packed between the joists adds nothing above at all: it spends the room's ceiling height, or spends nothing if the joists are deep enough to hold it, and leaves the roof line exactly where the planners last saw it.

That is why the vertical survey comes before the merchant call and before anyone opens a lambda table. A dormer with two brick courses between the felt and the window head has already answered the question, and answered it badly, which is a different conversation from the one where the answer is free. Everything downstream — how much fall you can buy, whether an overlay board is affordable in millimetres, how tall the upstand ends up, whether the existing tray survives — falls out of those four pencil marks.

The roof you are stripping is a cold deck, and it is why you are up here

Lift the felt on a flat roof built any time from the sixties to the nineties and the section is nearly always the same. Joists, mineral wool or a shallow board pushed between them, a gap above the insulation, boarding across the joist tops, felt over that. Sometimes a sheet of polythene under the plasterboard, more often a foil-backed board, frequently nothing. The gap is the load-bearing idea in that assembly: it is meant to be cross-ventilated from one outside edge to the other, so that whatever moisture gets past the ceiling is carried away before it meets the cold underside of the deck.

On the buildings this guide is about, that gap has no chance. A single-storey extension has joists running from the house wall to the outer wall, which means one end of every void terminates in the solid masonry of the original building — there is nothing to ventilate to. A dormer is worse: cheeks on two sides, the window head on the third, the main roof on the fourth. Under both is exactly the room that generates the moisture, a bedroom with an en-suite or a kitchen extension with a hob, and the ceiling between them is punctured by downlights, an extract duct and a loft hatch. Air leakage through those punctures moves far more water into a roof void than vapour diffusion through plasterboard ever does, which is the reason a sealed ceiling matters more than the sheet material behind it. The coldest surface up there is the underside of the boarding, and the boarding is timber.

The standing advice reflects that. BS 6229, Flat roofs with continuously supported flexible waterproof coverings — Code of practice, and BS 5250, Management of moisture in buildings — Code of practice, both set out why the cold deck flat roof is the highest-risk of the flat roof options and steer new work away from it; read the wording in the edition current at the date of your application rather than taking it second hand. In North America the vented route is governed by the International Residential Code, Section R806, Roof Ventilation, which fixes a clear space and a net free ventilating area, and the unvented alternative sits alongside it with its own conditions. None of that forbids the assembly outright. What it does is move rebuilding what you removed from a default into a decision somebody has to defend.

Its fields name a vapour barrier, but the arithmetic returns the temperature at any plane you can put an R-value in front of — so name the deck. Enter the whole assembly's resistance, then enter almost all of it again as the resistance between the room and that plane, which is what a cold deck is, and watch the verdict.

The assumed indoor air temperature.

The outdoor winter design temperature for the site's climate zone.

The full wall assembly's total thermal resistance, interior surface to exterior surface.

The portion of the total R-value between the interior face and where the vapor barrier sits.

The dew point temperature of the interior air, based on its temperature and relative humidity.

Temperature at vapor barrier location

55.9 °F

ComparisonA comparison, not a check — no result here is an approval.

The temperature at this location stays above the interior dew point shown below, so condensation is not predicted under the design conditions entered. No risk predicted under these conditions is not the same as none. The conditions are the ones you entered, and one surface is not the assembly.

Interior air dew point
50 °F

What this calculation does not cover

  • Air leakage, not diffusion, is what usually wets a wall, and there is nothing about it here. The gradient gives the temperature at the plane; it cannot say how much moisture arrives there. A wall that passes this check and leaks warm interior air through a top plate, a service penetration or an unsealed electrical box deposits far more water at that plane than vapor diffusion through an intact assembly ever could.
  • The R-values entered describe the clear field of the wall, between the framing. The path through every stud, plate and header is colder than this straight line says, and at a steel stud or an uninsulated slab edge much colder — so an assembly that passes in the middle of a bay can be sitting below dew point on the back of the sheathing at every framing member, which is exactly where mold turns up.
  • It is one snapshot at one pair of temperatures, and it totals nothing. What damages an assembly is how many hours a year it spends below dew point and whether it dries out in between. A wall that dips below on a few cold nights and recovers is not the same wall as one that stays below for a month, and this returns the identical verdict for both.
  • The obvious fix for a failing result can produce a wall that cannot dry. Moving the barrier inboard is right only if the outboard side is open to vapor. Where a low-perm layer already sits outside — exterior foam, a self-adhered membrane, an impermeable sheathing — a second one inside traps whatever gets past either of them, and the assembly then passes this temperature check with no drying path in either direction.

Warm deck: the same materials, the other side of the boarding

Turn the section inside out and the order becomes deck first, vapour control layer bonded to it, insulation on that, waterproofing on top. Nothing goes between the joists. The consequence is worth stating plainly, because it is the whole case for the assembly: the deck and the joists now sit inboard of the insulation and run within a few degrees of the room below them all winter. They stop being condensing surfaces. The coldest plane in the build-up moves to the underside of the membrane, which is outboard of everything, and the layer with the vapour resistance is at the bottom where the warm air arrives rather than at the top where it would trap.

Two habits have to be unlearned on the way. The first is the fascia vents: if the old roof had them, they close. A void ventilated to outside air, under a vapour control layer, beneath a warm deck, is a cold stripe running through the middle of what is supposed to be a heated envelope, and half the failed warm decks in the country are cold decks with the insulation moved and the vents left alone. The second is the leftover wool. Insulation between the joists on a warm deck is not a bonus; it is resistance on the wrong side of the deck, and it cools the deck by exactly the amount it adds. Either it comes out, or the assembly becomes a hybrid, which is a calculation rather than a saving.

The vapour control layer is the item to get right while the deck is bare and easy. It is bonded or fully supported, lapped and sealed at every joint, carried up every upstand and turned over the head of the kerb so the insulation is enclosed rather than merely covered, and terminated into the wall's damp proof course or cavity tray at the abutment. Treat it as the air barrier and not only as the vapour check — that is the substance of what BS 5250 and Approved Document C, Site preparation and resistance to contaminants and moisture, are asking for. The reward is that every downlight, cable and extract duct in the ceiling below is now a hole in the plasterboard rather than a hole in the control layer, because the control layer is a whole deck thickness above the electrician.

Rigid polyisocyanurate under BS EN 13165, Thermal insulation products for buildings — Factory made rigid polyurethane foam (PU) products — Specification, or ASTM C1289, Standard Specification for Faced Rigid Cellular Polyisocyanurate Thermal Insulation Board, is the usual board here for one reason: it buys the most resistance per millimetre, and millimetres are the currency. Lay it in two staggered layers rather than one thick one wherever the vertical allows, because the joint pattern of a single layer is a set of straight lines running from the membrane down to the deck.

A warm deck, taken apart

A flat roof over a heated room shown in section, outermost first: the membrane, an overlay board, insulation falling to the right, the vapour control layer sealed to the deck, the deck boarding, and beneath it the joists with an empty unventilated void and the ceiling.
  1. Single-ply membrane — the only layer outboard of the insulation, which makes its underside the coldest plane in the assembly and the one place condensation is designed to be harmless EPDM Single-Ply Roofing Roll Calculator
  2. Overlay or cover board — present when the membrane cannot bond to a foam facer, or when anyone will walk this roof to reach a flue, an aerial or a rooflight Roof Insulation Cover Board Calculator
  3. Insulation above the deck — continuous over the joists with no framing to interrupt it, thickest at the abutment when the fall runs away from the house Tapered Roof Insulation Slope Calculator
  4. Vapour control layer — bonded to the deck, sealed at every lap and carried up each upstand, and doing as much work as an air barrier as it does as a vapour check Vapor Barrier Dew-Point Condensation Risk Calculator
  5. Deck boarding — now inboard of the insulation and running near room temperature all winter, which is the entire argument for building the roof this way Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof)
  6. Joists, empty void and ceiling — deliberately unventilated and inside the heated envelope, which is why the old fascia vents are closed rather than kept Ceiling Joist Spanning Lineal Lumber Aggregator

Board is ordered in sheets and the sheet is not the same object in the two markets — 2400 by 1200 is 2.88 m², the 4 by 8 is 2.97 m², and this counter divides by whichever one your unit toggle is showing. Its ten per cent waste allowance is fixed with no field to raise it, so a roof kerbed on three sides and cut on every edge wants an area entered above the measured one.

SettingsSettings for this calculation
Who is doing the work?

The standard allowance most suppliers and estimating guides assume for ordinary work.

The total wall, foundation, or roof deck area to cover.

Offcuts from fitting boards between framing, around openings and at corners.

Foam board sheets needed

15 sheets (4x8 ft)

High confidence
Area to cover (with waste)
473 sq ft

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

What this calculation does not cover

  • This counts sheets to cover an area. It does not choose a thickness or R-value, check your climate zone's requirement for continuous insulation, or confirm the board's compressive strength grade suits a load-bearing position under a slab or screed.
  • The count is for a single layer. A staggered two- or three-layer build-up is a separate full-area order for each layer, so run the area through once per layer rather than entering the combined thickness.
  • The waste allowance is a flat uplift on area, not a cutting layout. Rafter bays, hips, curved walls and dense penetrations throw off more offcuts than that, and offcuts from one bay are often unusable in the next. A wall whose window and door openings you did not deduct is over-ordered by roughly their area.
  • It assumes every board is the market's standard full sheet. It does not cover the 2 ft wide XPS or 1200 x 600 mm half boards some ranges are sold in, and it does not deduct the overlap on tongue-and-groove or shiplap edges, which cover less than the board's nominal face area.
  • Nothing beyond the boards is counted: seam tape, adhesive or foam, fixings and washers sized to the board thickness, furring, and any separate vapour or air control layer. Rigid foam is also combustible, and building codes generally require a thermal or ignition barrier between it and an occupied space. This calculator neither sizes nor includes that.

Making a fall out of a deck that has none

A flat roof is not flat and never was. UK practice takes its numbers from BS 6229, which pairs a design fall with a smaller finished fall so that deflection, joist settlement and ordinary workmanship still leave water moving — the pairing most detailers carry in their heads is a design fall of one in forty against a finished one in eighty, and the current edition is where to confirm it before it goes on a drawing. Where the building code is the governing document instead, it sets its own minimum for a membrane roof and the adopted amendments decide the figure you have to meet.

Where the fall comes from is the decision. Firrings ripped and fixed along the joists put it under the deck and cost nothing in height above; if the roof you are re-covering already has them, and the survey says the fall still works, a warm deck can be flat board on a sloping deck and you have bought the fall for free. Tapered insulation puts it above the deck instead, which is tidier, more expensive per square metre, and adds every millimetre of the taper to the four pencil marks on the brickwork. Most domestic warm decks end up as flat base board bringing the resistance up to target with a tapered layer over it doing the drainage, because tapered stock is the costly way to buy thermal performance.

Direction is where this job differs from a commercial roof draining to a middle. On an extension the water leaves at the outer edge into a gutter, so the fall runs away from the house and the thick end of the taper lands at the abutment — precisely where the vertical was tightest and where the upstand still has to be found. A dormer usually falls forward to a small gutter at the front, which puts the thick end under the window it was built to serve. Neither direction is negotiable, and both put the deepest part of the build-up against the most sensitive dimension on the survey, which is worth knowing before the boards are ordered rather than on the morning they arrive.

Falls in both systems, and what each one adds across a domestic run
FallAs a decimal ratioRise over a 4 m runRise over a 12 ft run
1 in 800.012550 mm1.8 in
1 in 600.016767 mm2.4 in
1 in 400.025100 mm3.6 in
1/8 in per ft0.010442 mm1.5 in
1/4 in per ft0.020883 mm3.0 in
Falls in both systems, and what each one adds across a domestic run

Its slope field wants the decimal from the table above rather than a ratio written as one in forty, and it works from the thin end of the taper to the thick end: give it the run and the thickness you are holding at one end, and the figure it returns is what has to be found at the other.

The horizontal distance from the roof's high point to the drain or low point.

The target drainage slope, expressed as a ratio (rise ÷ run).

The thinnest board in the system, laid AT the drain or scupper — the taper builds up from here.

The board's width measured along the run, which is the direction the taper climbs.

The thickest board in the tapered range, where the sequence has to restart.

Maximum insulation thickness needed

11.36 in

High confidence
Thickness rise across the run
9.36 in
Board courses from the drain to the high point
10
Rise across one board
0.96 in
Width of the last course
36 in
Courses before the taper restarts on fill
2
Flat fill under the high end
7.36 in

Add the equipment this sizes

This result is a specification — 11.36 in — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

39 ft4 ft2 in
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • Gives thickness, not R-value, and the thin end is where the energy code bites. The starter board at the drain is the lowest R anywhere in the assembly, so check the required minimum against that thinnest point — and against the assembly average if your code path allows one — before ordering, because raising the starter thickness raises every board above it and the whole build-up with it.
  • Solves one straight fall and leaves the water between the drains. Areas behind curbs, between adjacent drains and along the high line need crickets and saddles, and because a cricket falls diagonally its own slope has to be steeper than the field — commonly double it. A roof tapered only in the direction calculated here ponds in every one of those corners.
  • The last course is ripped to whatever the run has left, and a ripped tapered board carries only its own share of the rise — so the board against the high point is not the thickest board in the range, even though it sits at the thickest place. Where the rip lands is a decision the page does not make: put it at the high point and the cut edge is buried under the flashing, put it at the drain and it is under the sump, and the two are not the same job.
  • The board rows assume one tapered range at exactly the slope you asked for, laid in full-width courses from the drain outwards. Real schedules are lettered sets with their own fixed slopes, and the nearest one to your target is what gets delivered — so a 1 in (25 mm) 50 target is normally built with 1/4-in-per-foot board, which is 1 in (25 mm) 48, and the finished fall is the board's, not yours. Take the courses and the fill as the shape of the system rather than as an order.
  • Nothing here checks that the total fits what surrounds it, and on a deep build-up that is the constraint that bites first: flashing height at the parapet, door sills, curb heights and the depth of the drain bowl itself. A roof that needs more fill than the upstand allows is re-drained or re-divided rather than re-tapered, and that decision sits upstream of every figure on this page.

Getting the target and the arithmetic into the same units

Consent is granted against a number in whichever system the paperwork was written in, and the two systems are not a rounding apart. In England the standard is a maximum U-value in W/m²K, from Approved Document L, Conservation of fuel and power, Volume 1: Dwellings, with the row that applies depending on whether this roof counts as new, as a replacement, or as a retained element being upgraded. Across the Atlantic the target arrives as a minimum R-value by climate zone from the International Energy Conservation Code and the IRC. The imperial U-value is about 5.678 times smaller than the metric one for the same assembly, so a specification of 0.15 W/m²K is 0.0264 in BTU/hr·ft²·°F, whose reciprocal is R-37.9 — and the same assembly stated metrically is 6.67 m²K/W. Convert once, at the start, then work in one currency for the rest of the job.

The figures above are arithmetic, not a requirement: what applies at this address comes off the approved documents for the application, and a warm deck on an extension frequently lands in a stricter row than the roof it replaces because the work is new construction rather than a repair.

It takes an imperial U-value, so a target written in W/m²K goes through the 5.678 division before it is typed here — feed it the metric figure directly and the R-value comes back about five times too generous while looking entirely reasonable.

The assembly's thermal transmittance, as specified.

Equivalent R-value

20 hr·ft²·°F/BTU

High confidence

R = 1 ÷ U, the exact inverse relationship. The result is the whole assembly's resistance — subtract the other layers before choosing an insulation thickness.

Add the equipment this sizes

This result is a specification — 20 hr·ft²·°F/BTU — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

What this calculation does not cover

  • The conversion is arithmetic and takes the U-value at face value. It does not check that you have the right figure for the element: a window's whole-unit U-factor, its centre-of-glass value and its frame value are three different numbers, and only the whole-unit one describes what the opening actually loses.
  • The field is imperial only, and the site's metric/imperial toggle does not convert it. A W/m2K figure typed in unchanged returns the metric resistance in m2K/W, which is about a fifth of the imperial R the result is labelled as. Divide a metric U-value by 5.678 before entering it.
  • Thermal bridging is not in the number. A U-value quoted for a clear-wall build-up excludes studs, joists, rim boards, lintels and junctions, so the R returned describes the insulated bay rather than the whole element.
  • This is not a code compliance check. It does not test the figure against any energy code's prescriptive U-factor or R-value tables, and it does not perform the area-weighted or trade-off calculation a submission needs.
  • Steady-state conduction only: no air leakage, no thermal mass, no moisture. Insulation that is compressed, wind-washed or damp delivers less than its rated R, and a reciprocal cannot show that.

Building regulations and window schedules are written as maximum U-values, while insulation on a merchant's shelf is labelled in R, so specifying to a regulation means crossing between them. The arithmetic is a reciprocal and takes a second. The two traps are unit systems and scope. A metric U-value in watts per square metre kelvin is roughly 5.68 times its imperial counterpart, and mixing them produces an assembly that appears five times better insulated than it is. And the converted R covers the entire build-up, not the insulation alone: sheathing, cladding, internal linings and surface films all contribute, so the product you buy only needs to close the remaining gap.

Why the sum is shorter than you expect

Adding up a warm deck takes three lines, and one of them is nearly the whole answer. There is the insulation, the deck and any overlay above it, and the plasterboard ceiling below — and unlike a wall or a pitched slope, nothing punches through. The insulation runs continuously over the joists, so there is no framing fraction to correct for and no parallel path to average out; the only things crossing the layer are the mechanical fixings, at the density the manufacturer's wind uplift schedule sets. That is the quiet second argument for the warm deck, and it is worth more than the number suggests, because a bridged assembly always underperforms its calculation while an unbridged one roughly meets it.

Working an example through: a hundred and fifty of polyisocyanurate at a declared 0.022 W/m·K is 6.82 m²K/W, which is R-38.7; eighteen millimetres of ply deck is about R-0.8; the ceiling contributes the R-0.45 the calculator already offers as its own third default. Those three plus the air films land the assembly near R-40.8, or 7.19 m²K/W, or a U-value around 0.14 W/m²K. The layer fields are plain imperial R-values that ignore the metric toggle, so a resistance in m²K/W is multiplied by 5.678 on the way in; the air film allowance of R-0.85 is added for you, so do not spend a field on it; and the three fields cap at R-60, R-30 and R-10 in that order, so the board goes in the first one and a passive-standard thickness that passes R-60 has to be split across the first two rather than across any two.

Three fields is exactly the shape of this assembly — insulation, deck and overlay, ceiling — and totalling them as a stack is the only way the board thickness argument gets settled against the target rather than against a feeling.

R-Value Calculator

The R-value of your main insulation layer, printed on the product.

The R-value of a second layer, like exterior sheathing.

The R-value of interior finish material, like drywall (typically about R-0.45 for 1/2 in).

Total assembly R-value

15.8 R-value

High confidence
Sum of material layers
14.95 R
Air film allowance
0.85 R

Add the equipment this sizes

This result is a specification — 15.8 R-value — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

What this calculation does not cover

  • Layers are summed straight through the insulated cavity. Studs, joists, plates, headers and rim areas conduct several times faster than the insulation between them and are not deducted here, so the real whole-wall or whole-ceiling figure is lower than this total. Run the Thermal Bridging Effective R-Value Calculator on the same wall to see by how much.
  • The figures are imperial R-values in hr·ft²·°F/BTU, and so is the fixed R-0.85 air film allowance. Metric RSI values in m²K/W are about 5.68 times smaller, so entering those makes the film allowance alone roughly six times too generous. Convert before you type.
  • The air film allowance is one fixed number written for a wall: still indoor air with sideways heat flow, and an outside face exposed to wind. It does not change for heat flowing up or down, for a surface facing a vented attic or an enclosed crawl space, or for a reflective low-emissivity face, all of which shift the film values.
  • Product R-values are lab ratings for material at full thickness with no gaps. Batts compressed under wiring, voids at plates and corners, and loose fill that has settled all deliver less than the printed number, and nothing here downgrades the total for installation quality.
  • R-value covers conduction only. It says nothing about air leakage, wind washing through the insulation, or moisture in the assembly, and this total is not a code compliance check: the required figure depends on climate zone and on which element you are building, and codes are frequently verified against a whole-assembly U-factor that includes the framing this sum leaves out.

The board between the foam and the waterproofing

Whether an overlay is needed is a membrane question rather than an insulation one. A torch-applied or hot-air-welded system cannot be worked directly onto a foam facer, so it gets a substrate: glass mat gypsum to ASTM C1177/C1177M, Standard Specification for Glass Mat Gypsum Substrate for Use as Sheathing, or a mineral or wood-based board named in the system's own approval. Many fully adhered domestic EPDM systems, by contrast, bond straight to the insulation facer and want no board at all, and adding one there spends height and money for nothing.

The case for one anyway is traffic and point loads. Somebody will go up there — a boiler flue terminal, an aerial, a rooflight that needs cleaning, a window cleaner's ladder foot — and foam boards print their joints through a membrane under a heel long before they fail thermally. Where the roof will be walked at all, an overlay and a walkway are cheaper than the callback, and the fixing pattern for the board is the manufacturer's, not the deck's.

Take the sheet size off the actual data sheet. A 1200 by 2400 board is 2.88 m² and a 4 by 8 is 2.97 m², which is a three per cent difference in count that compounds on a nine-sheet order into whether the last one gets cut or bought.

It divides area by sheet coverage and rounds up, with no waste built in at all, so the cuts around a kerb, a rooflight and the drip edge are yours to add before the number is trusted as an order.

The total roof area to be covered with cover board.

The coverage area of a single cover board sheet.

Cover board sheets needed

51 sheets

High confidence

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

What this calculation does not cover

  • Counts boards and nothing that holds them down. In many assemblies one screw and plate passes through the cover board AND the insulation beneath it in a single shot, so the fastener length is set by board thickness plus the whole insulation stack plus the embedment the deck needs, and that fastener quantity belongs to the stack rather than to this layer. A board count on its own will not tell you whether you are buying one set of fasteners or two.
  • Board thickness and type are not asked, and the sheet count comes out identical whichever you pick. What the board has to be — gypsum, HD polyiso, cement board, mineral — is set by the assembly's fire and hail classification and by what the membrane above it has to bond to, and those are the decisions carrying the cost difference between two roofs of the same area.
  • An adhered installation is not ordered by sheet count at all. Adhesive goes on by coverage rate — a volume per unit of area, or ribbon spacing across each board, tightened at the perimeter and corners — so the pail count follows that rate and the zone layout, and it does not track the number of boards.

One sheet, or a roof with seams in it

Single-ply took the domestic extension market because a small roof can be a single piece of rubber with no field seams anywhere on it, which is a claim felt could never make. The limit is the widest sheet the supplier stocks, and above it the roof has seams — so establish that dimension before the roof is designed around it, not after the survey. EPDM sheet is specified under ASTM D4637/D4637M, Standard Specification for EPDM Sheet Used in Single-Ply Roof Membrane, and in Europe under BS EN 13956, Flexible sheets for waterproofing — Plastic and rubber sheets for roof waterproofing — Definitions and characteristics.

Membrane area is never the plan area, and a warm deck makes the gap wider than a cold one did. Every upstand is sheet turned vertical: the height up the kerb on each edge, the return over its head, the dressing down into the gutter, the wrap into each corner. Raising the roof raised those upstands too. Add the perimeter development to the measured field before anything is ordered, and remember that the roll counter has no idea any of it exists.

It counts whole rolls against a coverage area you supply, with nothing allowed for laps, upstands or the wrap at a corner — so the area typed in is the developed one. It counts area against a roll, which is not the same test as the seam question above it: the default 46.5 m² roll is only about three metres wide, so a one-roll answer settles how much rubber to buy and settles nothing about whether the roof can be covered without a field seam. That one is decided by the sheet width your supplier stocks against the shorter dimension of the roof.

The total roof area to be covered with EPDM membrane.

The area a single roll of EPDM membrane covers.

EPDM rolls needed

5 rolls

High confidence

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

What this calculation does not cover

  • The same roll count buys any thickness. EPDM is stocked at 45, 60 and 90 mil, reinforced and unreinforced, and thickness is what the warranty term and the hail and foot-traffic tolerance key off. The area arithmetic is identical for all of them, so this figure cannot tell you the wrong sheet came off the truck.
  • Says nothing about what holds it down. Fully adhered, mechanically attached and ballasted roofs need different quantities of bonding adhesive, plates and fasteners or ballast, and that density rises sharply in the perimeter and corner zones set by wind uplift on the particular building. Those lines are usually the larger part of the order and none of them follow from area.
  • Roll width decides how much seam the roof has. Covering the same area in wider sheets roughly halves the length of field seam, and seams are where single-ply roofs leak — entering a bare coverage area hides that trade-off completely.

Seams you did not draw

Count the seams as two populations. Field seams are the ones on a drawing, and on a small warm deck there may be none. Flashing seams are the ones nobody schedules: every internal and external corner of the kerb, every rooflight upstand, every pipe and flue penetration, and each of them is a separate piece with its own perimeter to seal. An extension roof kerbed on three sides with a rooflight in the middle can carry more taped length in details than a much larger open field does in the middle.

Whatever the length, the seam lives or dies on preparation. Cured EPDM has a surface tape will not hold reliably without primer, and a seam taped over an unprimed or under-primed sheet looks perfect on the day and lets go within a couple of seasons. Manufacturers publish a minimum application temperature and it is not advice; the seams that fail first are almost always the last ones made on the coldest afternoon of the job. T-joint patches, where three sheets overlap, are a separate item that no length calculation contains.

Give it field seams and flashing seams added together rather than the field alone, and set the waste percentage against how many short detail runs are in that total — splice waste on twenty corner pieces is a different fraction from splice waste on one long lap.

SettingsSettings for this calculation
Who is doing the work?

Waste is set to 5% by hand. Pick a tier above to replace it, or keep your own figure.

The total length of all EPDM membrane seams to be taped or adhered.

Extra tape or adhesive to allow for splices and application waste.

Seam tape needed

273 ft

High confidence

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

260 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • Takes the seam length on trust, and that is the largest number in the result. Field seam length is set by the membrane roll width and the direction the sheets run — the narrower the sheet, the more seam per square metre — plus an end lap wherever a roll runs out. A guessed seam length moves the answer far more than the waste allowance ever will.
  • Blind to tape width. Seam tape is sold in more than one width, commonly 3 in and 6 in, and a detail that calls for the wider tape roughly doubles the cost of every metre counted here. Linear metres alone do not identify what to buy.
  • Primer is quantified nowhere on this page, though it has its own coverage rate and its own order line. It goes on both mating faces of every seam, which is twice the width being taped, and running out of it stops the crew with a full box of tape sitting on the roof.

What two hundred millimetres does at the wall

The upstand is the first thing the extra height eats. Waterproofing manufacturers set a minimum height from the finished roof surface to the top of the upstand — 150 mm is the figure most UK flat roofing details carry, and the system's own data sheet is what governs on your roof. That dimension is measured from the new surface, not the old one, so raising the roof by the full thickness of a warm deck raises the top of the upstand by the same amount, and the flashing that covers it has to arrive above that.

Which is where the cavity tray becomes the difficult item. In a cavity wall the tray and its weep holes are what stop water crossing the cavity above the abutment, and the existing tray is now somewhere in the middle of your new upstand rather than above it. That is a new tray cut into the wall, in short lengths, with the leaf supported as it goes — not a flashing lifted and re-pointed higher. On a solid wall the equivalent is a new chase at the new height and the old one made good. Either way it is a bricklayer's day that gets left out of flat roofing quotes with tedious regularity.

Then the rest of the survey. A threshold onto a terrace has a level relationship to the roof that a warm deck can destroy, and an accessible threshold has less tolerance again. A sill above needs clearance for the upstand and the flashing both. The gutter at the far edge has to sit below the new drip, which usually means the fascia is remade rather than reused. And the height may be a planning question before it is a building one: a rear extension or a dormer built under a permitted development right has dimensional limits attached to that right, and a roof that rises can leave them. That one cannot be fixed with a longer screw, so establish it before the boards are on site.

When the height genuinely is not there

Three honest routes exist when the pencil marks say no, and each takes the depth from somewhere different. The first is a hybrid: some resistance between the joists, most of it above the deck, in a proportion that keeps the deck warm enough not to condense. That proportion is not a matter of taste — the IRC's unvented assembly provisions fix a minimum share of the total for the insulation above the deck by climate zone, and the UK route runs through BS 5250 with the position verified by calculation to BS EN ISO 13788, Hygrothermal performance of building components and building elements — Internal surface temperature to avoid critical surface humidity and interstitial condensation — Calculation methods. Run the deck plane through the dew-point gradient before committing, exactly as in the second section above: a hybrid that has not been checked is a cold deck with extra steps.

The second is to invert the roof: membrane directly on the deck, extruded polystyrene to BS EN 13164 or ASTM C578 laid loose above it, and ballast on top to hold the boards down and keep ultraviolet off the waterproofing. It keeps the membrane warm and protected and it moves nothing structurally except the ballast load, which is the reason it is rare on a domestic extension — a joisted timber roof is usually the wrong structure to ask for that weight. It also carries a thermal penalty that is easy to forget: rainwater running between the boards and the membrane cools the assembly, and BS EN ISO 6946, Building components and building elements — Thermal resistance and thermal transmittance — Calculation methods, includes the correction that has to be applied to an inverted roof's calculated U-value.

The third is to buy the height from the room instead of from the roof, with continuous board and a fresh ceiling under the joists. It is thermally sound and it costs headroom in a space that may not have any to give, which makes it a conversation with whoever lives there rather than a detail. Where foam ends up inside the room the lining over it is doing a fire duty as well as a decorative one; the covering above is judged separately, against external fire spread, under Approved Document B and BS EN 13501-5 with the distance to the boundary deciding what is permitted.

The order it closes in, and what to photograph

Nothing in a warm deck can be inspected after the membrane is bonded. The vapour control layer, the joint pattern of the boards, the sealing at each upstand and the state of the deck beneath all disappear on the same afternoon, and the only record that survives is the one made while they were open. Photograph with something in frame that says which edge of the roof you are looking at — a rule against the abutment, the rooflight kerb in the corner of the shot — because a folder of forty pictures of grey board is worth nothing to whoever opens it in ten years.

The sequence below assumes the covering is coming off, the deck is sound, and the fall is being made above it. Where the deck is being renewed, the firring decision moves up to step two and the taper often disappears entirely.

  1. Take the vertical survey at the abutment — sill, tray, chase, threshold, gutter — and write the finished roof level it allows before choosing any thickness.
  2. Strip, then survey the deck and joists for the rot the old cold deck was quietly making, and confirm whether firrings already give you a usable fall.
  3. Close the fascia vents and any other route from outside air into the joist void, and seal the ceiling penetrations you can reach.
  4. Lay and seal the vapour control layer across the deck, carrying it up every upstand and terminating it into the wall's damp proof course or tray.
  5. Set the insulation in staggered layers to the fixing pattern the wind uplift schedule sets, working the flat base board first and the taper over it.
  6. Photograph every upstand, every corner and the full field before the overlay board or membrane covers any of it.
  7. Fit the overlay board if the system needs one, then the membrane, with the field bonded before any detail piece is primed.
  8. Cut in the new cavity tray and flashing at the height the finished surface now demands, and hang the gutter to the new drip rather than to the old fascia line.
  9. File the board certificates, the membrane system data sheet and the fixing schedule with the completion paperwork, alongside the photographs.

Settle the vertical before anything is ordered

Every line below is either a millimetre added above the deck or a constraint that decides whether you can afford it, and they are in the order the decisions actually get made.

  • Finished roof level the abutment will accept — From the sill, the tray course, the chase and any threshold. This is the ceiling on the whole build-up, and it is a measurement rather than an assumption.
  • Longest run from the high point to the gutter, and its direction — On an extension the fall runs away from the house, which puts the thick end of the taper at the tightest dimension on the survey.
  • Target U-value or R-value off the paperwork for this address — Converted once into a single currency. A metric U-value divided by 5.678 before it meets any imperial field, not after.
  • Flat base board and tapered board as separate quantities — Tapered stock is the expensive way to buy resistance; the base layer does the thermal work and the taper does the drainage.
  • Membrane area developed, not plan area — Field plus every upstand height, the return over each kerb head, the dressing into the gutter and the wrap at each corner.
  • Bricklayer's time for the new tray or chase — The existing one is below the new upstand by the full thickness of the warm deck. It is a rebuild, not a re-point, and it is the line most often missing from a flat roofing price.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • BS 6229, Flat roofs with continuously supported flexible waterproof coverings — Code of practice
  • BS 5250, Management of moisture in buildings — Code of practice
  • BS EN ISO 6946, Building components and building elements — Thermal resistance and thermal transmittance — Calculation methods
  • BS EN ISO 13788, Hygrothermal performance of building components and building elements — Internal surface temperature to avoid critical surface humidity and interstitial condensation — Calculation methods
  • BS EN 13165, Thermal insulation products for buildings — Factory made rigid polyurethane foam (PU) products — Specification
  • BS EN 13164, Thermal insulation products for buildings — Factory made extruded polystyrene foam (XPS) products — Specification
  • BS EN 13956, Flexible sheets for waterproofing — Plastic and rubber sheets for roof waterproofing — Definitions and characteristics
  • BS EN 13984, Flexible sheets for waterproofing — Plastic and rubber vapour control layers — Definitions and characteristics
  • BS EN 13501-5, Fire classification of construction products and building elements — Classification using data from external fire exposure to roofs tests
  • ASTM C1289, Standard Specification for Faced Rigid Cellular Polyisocyanurate Thermal Insulation Board
  • ASTM C578, Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation
  • ASTM C1177/C1177M, Standard Specification for Glass Mat Gypsum Substrate for Use as Sheathing
  • ASTM D4637/D4637M, Standard Specification for EPDM Sheet Used in Single-Ply Roof Membrane
  • Approved Document L, Conservation of fuel and power, Volume 1: Dwellings (England), edition in force at the date of application
  • Approved Document C, Site preparation and resistance to contaminants and moisture (England)
  • Approved Document B, Fire safety, Volume 1: Dwellings (England)
  • International Residential Code, Section R806, Roof Ventilation, and its unvented assembly provisions, as adopted and amended locally
  • International Energy Conservation Code, as adopted and amended by the authority having jurisdiction
  • Membrane and insulation manufacturers' own system data sheets for upstand heights, substrate approvals, fixing schedules and minimum application temperatures

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.