Loft room with rooflights takeoff

Turn a loft into a room under its own roof, lit by rooflights (roof windows) and with no dormer: insulation in the slopes, knee walls and over the flat ceiling, sound insulation in the new floor, studs for the knee walls, boards on the ceilings, slopes, reveals and walls, skimmed or taped, paint, skirting and the skip, with the floor, any beam, the trimming and the stair listed and never sized.

Measurements in
11
Trades out
1615
Calculators
109
Going in
1615of 1615
My Project
Not in it

No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.

Dimensions

Give the job once

Every figure on the right follows these, in the units you choose.

Step 1 of 3

Choose the build-up

Each layer changes the materials below; the dimensions stay the same.

Board finish
Floor finish
Board finish
Floor finish

Every trade, from those dimensions

then change a dimension, and each line shows what moved.

Every trade's quantity · 16 rows

16 of 16 going in
ItemQuantityOrderWaste / allowance
Dust sheets in the rooms below5 items5 itemsno pack size recordednone
Studs for the two knee walls39 studs39 studsalready whole10%
Boards between and under the sloped rafters7 sheets (4x8 ft)7 sheets (4x8 ft)already whole10%
Batts in the knee walls4 packages4 packagesalready whole5%
Sound insulation between the floor joists7 packages7 packagesalready whole5%
Insulation over the flat ceiling4 packages4 packagesalready whole5%
Plasterboard (drywall) on the ceiling, slopes and reveals13 sheets13 sheetsalready whole10%
Plasterboard (drywall) on the walls13 sheets13 sheetsalready whole10%
Joint compound for taping and filling every board2 x 4.5 gal boxes2 x 4.5 gal boxesalready whole10%
Paper joint tape over every board439.94 ft439.94 ftno pack size recorded10%
Mist coat or primer on the ceiling, slopes and reveals0.8835 gal0.8835 galno pack size recordednone
Mist coat or primer on the walls0.8825 gal0.8825 galno pack size recordednone
Skirting (baseboard)72.65 linear ft72.65 linear ftno pack size recorded10%
Ceiling, slopes and reveals, two coats1.77 gal1.77 galno pack size recordednone
Walls, two coats1.77 gal1.77 galno pack size recordednone
Skip (dumpster) for the strip-out5.29 yd³5.29 yd³no pack size recordednone

Every trade's quantity · 15 rows

15 of 16 going in
ItemQuantityOrderWaste / allowance
Dust sheets in the rooms below5 items5 itemsno pack size recordednone
Studs for the two knee walls39 studs39 studsalready whole10%
Boards between and under the sloped rafters7 sheets (2400x1200 mm)7 sheets (2400x1200 mm)already whole10%
Batts in the knee walls4 packages4 packagesalready whole5%
Sound insulation between the floor joists6 packages6 packagesalready whole5%
Insulation over the flat ceiling3 packages3 packagesalready whole5%
Plasterboard (drywall) on the ceiling, slopes and reveals13 sheets13 sheetsalready whole10%
Plasterboard (drywall) on the walls13 sheets13 sheetsalready whole10%
Skim over every board185.71 kg185.71 kgno pack size recorded15%
Mist coat or primer on the ceiling, slopes and reveals3.24 L3.24 Lno pack size recordednone
Mist coat or primer on the walls3.22 L3.22 Lno pack size recordednone
Skirting (baseboard)21.89 m21.89 mno pack size recorded10%
Ceiling, slopes and reveals, two coats6.48 L6.48 Lno pack size recordednone
Walls, two coats6.44 L6.44 Lno pack size recordednone
Skip (dumpster) for the strip-out3.96 m³3.96 m³no pack size recordednone

Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.

1615 of 16 trades15 trades chosenNot pricedNot in project
Kept on this deviceUnitsImperialMetricMy Projectnot in it yetQuantities only · your own rates · not a structural check

About this job

A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.

A loft room without a dormer keeps the roof as it is and builds the room inside it. The floor goes in on new joists clear of the ceiling below, a low knee wall is framed under each slope where the headroom runs out, and the ceiling follows the rafters up from the top of each knee wall to a flat ceiling at collar height. What is left of the triangle is cold: the voids behind the knee walls and over the flat ceiling stay outside the insulated room.

The light comes from rooflights (roof windows), each fitted between two rafters or in an opening trimmed across a cut rafter, with the maker's flashing kit dressed into the tiles or slates round it. A rooflight is bought as a unit, so this page asks for how many and their size and lists the fitting; what it measures is what they change inside: the glass comes off the sloped ceiling's insulation and boards, and each takes a reveal lined on its four sides at the depth of the rafters and the insulation, boarded and finished with the ceilings.

The insulation is the energy calculation's, in the slopes between and under the rafters, in the knee walls, and over the flat ceiling; an end wall that is a gable facing outside needs insulating too, and a party wall does not. The parts that decide whether the room can be used as one are the ones this page never sizes: the floor joists, any beam that takes the place of a purlin or strut, the trimmers, the stair to it with its headroom, and the fire doors and alarms on the way out, which building control or the building official signs off.

How each line reads

Base
What the calculator gives for these dimensions, before anything is added.
Allowance
Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
Adjusted
The base with its allowance on top.
Order
What to buy: the adjusted figure in whole boards, bags, rolls or lengths.

The order this happens in

Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.

  1. Have the floor, any beam and the trimming designed, check the headroom for the room and for the stair, and lodge the plans or the notice with building control, with any party wall notice served.
  2. Clear the loft, protect the rooms below and the way up, and lay the new floor joists clear of the ceiling below; set any beam that replaces a purlin or strut before anything is cut.
  3. Cut and trim the rooflight openings, fit the rooflights with their flashing kits from inside or from a scaffold, and make the tiles or slates good round them the same day.
  4. Trim the stair opening and fit the stair, frame the knee walls, run the cables and any pipes, lay sound insulation between the floor joists and deck the floor.
  5. Insulate the slopes between and under the rafters, the knee walls and over the flat ceiling, then board the slopes, the flat ceiling, the rooflights' reveals and the walls, and skim or tape and fill them.
  6. Hang the door, fit the handrail and the alarms, decorate, fix the skirting and lay the floor, then have the electrical test and the completion inspection before the room is used.

What this takeoff does not cover

  • The structure: the floor joists, any beam replacing a purlin or strut and its bearings, the trimmers round each rooflight and the stair, and the stair itself. Each is listed as work with no quantity; the engineer or the stair maker sizes it and building control inspects it.
  • The rooflights themselves, their flashing kits, blinds and any electric opener: bought as units to the sizes given and fitted as listed work.
  • The floor deck, listed as work: a British loft floor is usually tongue-and-groove chipboard in narrow boards and a US attic floor tongue-and-groove sheets, laid over the floor's area.
  • Ventilation of the cold voids behind the knee walls and over the flat ceiling, and insulation of a gable end wall facing outside.
  • Tiles, slates and battens round each rooflight beyond making them good, and any re-covering of the slopes.
  • A shower room or bathroom in the loft, its drainage and the heating extended to the room beyond a radiator listed as work.
  • Undercoat and gloss (trim enamel) on the new woodwork: the door, the architraves (casings) and the rest of the trim.

Labour by trade

Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.

Metric opening

Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m and 8 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer13 h (6.9–34)1½ days
Carpenter2 carpenters11 h (5.8–22)half a day
Drywaller1 drywaller + 1 labourer8.3 h (4.7–16)half a day
Plasterer1 plasterer11 h (6.5–23)1½ days
Painter1 painter12 h (6.5–26)1½ days
In all55 h (30–120)5½ days

Imperial opening

Loft length, wall to wall 20 ft · New floor, knee wall to knee wall 14.5 ft · Knee wall height 4 ft and 8 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer14 h (7.0–35)1½ days
Carpenter2 carpenters11 h (5.9–22)half a day
Drywaller1 drywaller + 1 labourer8.3 h (4.7–16)half a day
Taper1 taper + 1 labourer11 h (5.9–21)half a day
Painter1 painter12 h (6.6–26)1½ days
In all55 h (30–120)5 days

Quote check

Been given a quote for this job?

Paste it into the loft room quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.

  • What it leaves out

    Every line this takeoff has that nothing on the quote reads as.

  • What it adds

    Labour, removal, hire, fees — each named for what it is.

  • What to ask

    One list of questions, ready to copy. Never a verdict.

More takeoffs

Other job takeoffs

All job takeoffs

Frequently asked questions

What does the loft room takeoff give for a typical job?
Opened at Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Sloped ceiling on each side, on plan 1.1 m · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 0.78 m · Rooflight height, each 1.18 m · Reveal depth round each rooflight 300 mm · Doors into the room 1, it orders: Dust sheets in the rooms below, 5 items; Studs for the two knee walls, 39 studs; Boards between and under the sloped rafters, 7 sheets (2400x1200 mm); Batts in the knee walls, 4 packages; Sound insulation between the floor joists, 6 packages; Insulation over the flat ceiling, 3 packages; Plasterboard (drywall) on the ceiling, slopes and reveals, 13 sheets; Plasterboard (drywall) on the walls, 13 sheets; Skim over every board, 186 kg; Mist coat or primer on the ceiling, slopes and reveals, 3.24 L; Mist coat or primer on the walls, 3.22 L; Skirting (baseboard), 21.9 m; Ceiling, slopes and reveals, two coats, 6.48 L; Walls, two coats, 6.44 L; Skip (dumpster) for the strip-out, 3.96 m³. Opened at Loft length, wall to wall 20 ft · New floor, knee wall to knee wall 14.5 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Sloped ceiling on each side, on plan 3.5 ft · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 2.5 ft · Rooflight height, each 4 ft · Reveal depth round each rooflight 11.8 in · Doors into the room 1: Dust sheets in the rooms below, 5 items; Studs for the two knee walls, 39 studs; Boards between and under the sloped rafters, 7 sheets (4x8 ft); Batts in the knee walls, 4 packages; Sound insulation between the floor joists, 7 packages; Insulation over the flat ceiling, 4 packages; Plasterboard (drywall) on the ceiling, slopes and reveals, 13 sheets; Plasterboard (drywall) on the walls, 13 sheets; Joint compound for taping and filling every board, 2 x 4.5 gal boxes; Paper joint tape over every board, 440 ft; Mist coat or primer on the ceiling, slopes and reveals, 0.88 gal; Mist coat or primer on the walls, 0.88 gal; Skirting (baseboard), 72.7 linear ft; Ceiling, slopes and reveals, two coats, 1.77 gal; Walls, two coats, 1.77 gal; Skip (dumpster) for the strip-out, 5.29 yd³. Every figure follows the dimensions you give it.
Which calculators does the loft room takeoff run?
10 calculators, for 16 lines: Masking and Protection Materials Calculator, Framing Stud Calculator, Foam Board Insulation Calculator, Mineral Wool Insulation Batt Calculator, Ceiling Plasterboard Calculator (Gypsum Board Sheets), Drywall Joint Compound Calculator, Drywall Joint Tape Calculator, Ceiling Paint Calculator, Baseboard & Trim Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.9 calculators, for 15 lines: Masking and Protection Materials Calculator, Framing Stud Calculator, Foam Board Insulation Calculator, Mineral Wool Insulation Batt Calculator, Ceiling Plasterboard Calculator (Gypsum Board Sheets), Skim Coat Plaster Calculator, Ceiling Paint Calculator, Baseboard & Trim Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
What does the loft room takeoff leave out?
7 things, each named on this page: The structure; The rooflights themselves, their flashing kits, blinds and any electric opener; The floor deck, listed as work; Ventilation of the cold voids behind the knee walls and over the flat ceiling, and insulation of a gable end wall facing outside; Tiles, slates and battens round each rooflight beyond making them good, and any re-covering of the slopes; A shower room or bathroom in the loft, its drainage and the heating extended to the room beyond a radiator listed as work; Undercoat and gloss (trim enamel) on the new woodwork.
Can I check a quote for this job against the takeoff?
Yes. The loft room quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.