Check a loft room quote
Each line read against your measurements: 1514 lines, 11 measurements. Quantities, never prices.
Step 1
Your measurements
Measured this job on the loft room with rooflights takeoff? Send it to My Project, or save a setup, and these boxes fill in one press.
Worked from Loft length, wall to wall 20 ft · New floor, knee wall to knee wall 14.5 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Sloped ceiling on each side, on plan 3.5 ft · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 2.5 ft · Rooflight height, each 4 ft · Reveal depth round each rooflight 11.8 in · Doors into the room 1Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Sloped ceiling on each side, on plan 1.1 m · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 0.78 m · Rooflight height, each 1.18 m · Reveal depth round each rooflight 300 mm · Doors into the room 1
How to take each of these, and what each one feeds, is under the same field on the loft room with rooflights takeoff.
Step 2 · Your quote
The loft room quote you were given
Paste from an email, or open or drop a PDF, Excel, CSV or text file, or a photo of the quote. Amounts of money are taken out before anything is read — this page compares quantities, never prices.
Nothing you paste or open leaves this device.
Step 3 · The reading
What the quote says, against the job
Loft room · Loft length, wall to wall 20 ft · New floor, knee wall to knee wall 14.5 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Sloped ceiling on each side, on plan 3.5 ft · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 2.5 ft · Rooflight height, each 4 ft · Reveal depth round each rooflight 11.8 in · Doors into the room 1Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Sloped ceiling on each side, on plan 1.1 m · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 0.78 m · Rooflight height, each 1.18 m · Reveal depth round each rooflight 300 mm · Doors into the room 1
What it leaves out
Every line the job needs that nothing on the quote reads as, with the quantity your measurements produce.
What it adds
Lines this job's takeoff does not measure — labour, removal, hire, fees, anything else — each named for what it is.
What sits outside the range
Quantities above or below the computed range, by how much, in the quote's unit or converted and shown.
What to ask
One list of questions, in the quote's order, ready to copy and send. Questions, never a verdict.
Paste the quote above, or add its lines one at a time. The reading appears here as each line is read.
Outside what this takeoff measures
7Nothing in the reading measures these. Whether the quote covers each is worth asking in its own right: a scope missing from a quote tends to become a cost after work has started. Why each is left out is on the takeoff.
- The structure
- The rooflights themselves, their flashing kits, blinds and any electric opener
- The floor deck, listed as work
- Ventilation of the cold voids behind the knee walls and over the flat ceiling, and insulation of a gable end wall facing outside
- Tiles, slates and battens round each rooflight beyond making them good, and any re-covering of the slopes
- A shower room or bathroom in the loft, its drainage and the heating extended to the room beyond a radiator listed as work
- Undercoat and gloss (trim enamel) on the new woodwork
More than one quote
Level the quotes side by side
Two to six loft room quotes, each read against this job: included, left out, excluded or added, line by line.
How the quote is read
Each line of a loft room quote is matched to the line of the job it names, or marked as something the Loft room with rooflights takeoff does not measure — labour, removal, hire, fees, or anything else. Work the takeoff lists as part of the job but gives no quantity for is read as that work, not as something the quote adds.
The job’s own figures come from 11 measurements — loft length, wall to wall, new floor, knee wall to knee wall, knee wall height, floor to flat ceiling, sloped ceiling on each side, on plan, roof slope factor, rooflights (roof windows), rooflight width, each, rooflight height, each, reveal depth round each rooflight, doors into the room — run through the same calculators as the takeoff, so the two give the same figure for the same job.
Reading a loft room quote
A loft room quote rests on the structure nobody sees once the room is finished: the new floor joists, a beam put in where a purlin or a prop comes out, and the trimming round the stair and each rooflight. Worth asking who designs them, whether the engineer's fee and the building control or permit fees are in the price, and whether the headroom over the stair and in the room was measured before the figure was written.
Rooflights are usually priced by the unit, each with its flashing kit. Worth seeing the make and size of every one named, whether they are fitted from inside or need a scaffold, whether the tiles or slates round them are made good, and whether the reveals are lined, insulated and finished with the room or left for another trade.
Worth confirming the finishing lines one by one: the insulation, where each layer goes and how thick it is, the boards and whether they are skimmed or taped, the decoration, the skirting, the floor finish, the door, the handrail, the alarms and the electrics, and whether the strip-out and the skip are included.
Three steps
- Give your measurements, or fill them from your own takeoff in one press. The page opens on a typical job so it has something to show.
- Paste the quote's lines as they came, or add them one at a time. Leave the prices in — they are taken out, never read.
- Read the report: what is left out, what is added, what sits outside the range, and one list of questions to send.
The reference
Every line the reading looks for
For Loft length, wall to wall 20 ft · New floor, knee wall to knee wall 14.5 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Sloped ceiling on each side, on plan 3.5 ft · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 2.5 ft · Rooflight height, each 4 ft · Reveal depth round each rooflight 11.8 in · Doors into the room 1Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Sloped ceiling on each side, on plan 1.1 m · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 0.78 m · Rooflight height, each 1.18 m · Reveal depth round each rooflight 300 mm · Doors into the room 1. Each is the calculator linked under it, run with those measurements; a range is that calculator at both ends of one choice, not a margin for error.
Studs for the two knee walls
39 studs
One figure, with the spare studs the material needs already inside it at 10%.
Open the Framing Stud CalculatorBoards between and under the sloped rafters
6–7 sheets (4x8 ft)
6 at 5% cutting waste, 7 at 15%.
Open the Foam Board Insulation CalculatorBatts in the knee walls
4 packages
The same at 5% waste allowance and at 15%, once rounded to what is bought.
Open the Mineral Wool Insulation Batt CalculatorSound insulation between the floor joists
7 packages
The same at 5% waste allowance and at 15%, once rounded to what is bought.
Open the Mineral Wool Insulation Batt CalculatorInsulation over the flat ceiling
4 packages
The same at 5% waste allowance and at 15%, once rounded to what is bought.
Open the Mineral Wool Insulation Batt CalculatorPlasterboard (drywall) on the ceiling, slopes and reveals
12–13 sheets
12 at 5% waste allowance, 13 at 15%.
Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)Plasterboard (drywall) on the walls
12–13 sheets
12 at 5% waste allowance, 13 at 15%.
Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)Joint compound for taping and filling every board
2 x 4.5 gal boxes
The same at 5% pan and sanding loss and at 15%, once rounded to what is bought.
Open the Drywall Joint Compound CalculatorPaper joint tape over every board
420–460 ft
420 at 5% waste allowance, 460 at 15%.
Open the Drywall Joint Tape CalculatorMist coat or primer on the ceiling, slopes and reveals
0.88–1.02 gal
Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 0.88 net, 1.02 with 15% added.
Open the Ceiling Paint CalculatorMist coat or primer on the walls
0.88–1.01 gal
Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 0.88 net, 1.01 with 15% added.
Open the Ceiling Paint CalculatorSkirting (baseboard)
69.3–76 linear ft
69.3 at 5% cutting waste, 76 at 15%.
Open the Baseboard & Trim CalculatorCeiling, slopes and reveals, two coats
1.77–2.03 gal
Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 1.77 net, 2.03 with 15% added.
Open the Ceiling Paint CalculatorWalls, two coats
1.77–2.03 gal
Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 1.77 net, 2.03 with 15% added.
Open the Ceiling Paint CalculatorSkip (dumpster) for the strip-out
at least 5.29 yd³
The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.
Open the Skip & Dumpster Size CalculatorDust sheets in the rooms below
5 items
Worked out, not compared with a quote
Dust sheets and tape together, which a quote prices as preparation rather than listing.
Open the Masking and Protection Materials Calculator
Studs for the two knee walls
39 studs
One figure, with the spare studs the material needs already inside it at 10%.
Open the Framing Stud CalculatorBoards between and under the sloped rafters
7 sheets (2400x1200 mm)
The same at 5% cutting waste and at 15%, once rounded to what is bought.
Open the Foam Board Insulation CalculatorBatts in the knee walls
4 packages
The same at 5% waste allowance and at 15%, once rounded to what is bought.
Open the Mineral Wool Insulation Batt CalculatorSound insulation between the floor joists
6–7 packages
6 at 5% waste allowance, 7 at 15%.
Open the Mineral Wool Insulation Batt CalculatorInsulation over the flat ceiling
3–4 packages
3 at 5% waste allowance, 4 at 15%.
Open the Mineral Wool Insulation Batt CalculatorPlasterboard (drywall) on the ceiling, slopes and reveals
12–13 sheets
12 at 5% waste allowance, 13 at 15%.
Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)Plasterboard (drywall) on the walls
12–13 sheets
12 at 5% waste allowance, 13 at 15%.
Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)Skim over every board
170–186 kg
170 at 5% waste allowance, 186 at 15%.
Open the Skim Coat Plaster CalculatorMist coat or primer on the ceiling, slopes and reveals
3.24–3.72 L
Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 3.24 net, 3.72 with 15% added.
Open the Ceiling Paint CalculatorMist coat or primer on the walls
3.22–3.71 L
Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 3.22 net, 3.71 with 15% added.
Open the Ceiling Paint CalculatorSkirting (baseboard)
20.9–22.9 m
20.9 at 5% cutting waste, 22.9 at 15%.
Open the Baseboard & Trim CalculatorCeiling, slopes and reveals, two coats
6.48–7.45 L
Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 6.48 net, 7.45 with 15% added.
Open the Ceiling Paint CalculatorWalls, two coats
6.44–7.41 L
Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 6.44 net, 7.41 with 15% added.
Open the Ceiling Paint CalculatorSkip (dumpster) for the strip-out
at least 3.96 m³
The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.
Open the Skip & Dumpster Size CalculatorDust sheets in the rooms below
5 items
Worked out, not compared with a quote
Dust sheets and tape together, which a quote prices as preparation rather than listing.
Open the Masking and Protection Materials Calculator
How the ranges are taken
Where the choice is cutting waste, the ends are the site’s own allowances: 5%, the tight buffer of a crew with a planned set-out, and 15%, the wider one a first-timer orders. Where the calculator decides between patterns or materials, the ends are the options it offers. Where it adds nothing for loss, the range runs from the net quantity to 15% over it.
A minimum — the fewest hangers a spacing allows, the least airflow a room needs — has no upper end. A single figure carries an allowance the material itself needs, such as a lap, and names it.
What a reading like this cannot see
- It does not know your prices, your market, or what the work ought to cost.
- It does not know the building — the access, the condition of what is there, or what has to happen first.
- It cannot check a lump sum, because there is no quantity in one.
- A line it reads as missing may be priced under another name. A quantity outside the range is not evidence of anything. Each is a reason to ask a question.
- Two quotes are not comparable until their scopes are.
- It is not advice, and it is no substitute for a second quote.
The full takeoff
Every quantity for this job, with its working
The Loft room with rooflights takeoff runs the same calculators on the same measurements and shows what sits under each line here.
Base, allowance, order
Each line's quantity before and after its allowance, and what to buy.
Every allowance editable
Change a waste figure and the order follows, with its source named.
Into a project
Add the whole job to a workspace with your own prices.
Frequently asked questions
- What quantities does a loft room job need?
- It depends on the measurements, so this page asks for yours. At the size it opens on — Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Sloped ceiling on each side, on plan 1.1 m · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 0.78 m · Rooflight height, each 1.18 m · Reveal depth round each rooflight 300 mm · Doors into the room 1 — the lines come to: Studs for the two knee walls, 39 studs; Boards between and under the sloped rafters, 7 sheets (2400x1200 mm); Batts in the knee walls, 4 packages; Sound insulation between the floor joists, 6–7 packages; Insulation over the flat ceiling, 3–4 packages; Plasterboard (drywall) on the ceiling, slopes and reveals, 12–13 sheets; Plasterboard (drywall) on the walls, 12–13 sheets; Skim over every board, 170–186 kg; Mist coat or primer on the ceiling, slopes and reveals, 3.24–3.72 L; Mist coat or primer on the walls, 3.22–3.71 L; Skirting (baseboard), 20.9–22.9 m; Ceiling, slopes and reveals, two coats, 6.48–7.45 L; Walls, two coats, 6.44–7.41 L; Skip (dumpster) for the strip-out, 3.96 m³. In imperial units — Loft length, wall to wall 20 ft · New floor, knee wall to knee wall 14.5 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Sloped ceiling on each side, on plan 3.5 ft · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 2.5 ft · Rooflight height, each 4 ft · Reveal depth round each rooflight 11.8 in · Doors into the room 1 — they come to: Studs for the two knee walls, 39 studs; Boards between and under the sloped rafters, 6–7 sheets (4x8 ft); Batts in the knee walls, 4 packages; Sound insulation between the floor joists, 7 packages; Insulation over the flat ceiling, 4 packages; Plasterboard (drywall) on the ceiling, slopes and reveals, 12–13 sheets; Plasterboard (drywall) on the walls, 12–13 sheets; Joint compound for taping and filling every board, 2 x 4.5 gal boxes; Paper joint tape over every board, 420–460 ft; Mist coat or primer on the ceiling, slopes and reveals, 0.88–1.02 gal; Mist coat or primer on the walls, 0.88–1.01 gal; Skirting (baseboard), 69.3–76 linear ft; Ceiling, slopes and reveals, two coats, 1.77–2.03 gal; Walls, two coats, 1.77–2.03 gal; Skip (dumpster) for the strip-out, 5.29 yd³.
- Which line on a loft room quote varies the most?
- The Insulation over the flat ceiling: 3–4 packages for a job measured Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Sloped ceiling on each side, on plan 1.1 m · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 0.78 m · Rooflight height, each 1.18 m · Reveal depth round each rooflight 300 mm · Doors into the room 1, depending on the waste allowance allowed, from 5% to 15%.
- What does a loft room quote often leave out?
- The reading names every line of the job that nothing on the quote reads as — any of the 15 lines the takeoff measures. The takeoff also lists 7 things it does not measure, shown under the reading, and each is worth asking about: a scope missing from a quote tends to become a cost after work has started.The reading names every line of the job that nothing on the quote reads as — any of the 14 lines the takeoff measures. The takeoff also lists 7 things it does not measure, shown under the reading, and each is worth asking about: a scope missing from a quote tends to become a cost after work has started.
- Can I paste the quote exactly as it came?
- Yes — from an email, a PDF or a spreadsheet, one item to a line. Amounts of money are taken out before anything is read, headings and totals are skipped, and each line is shown with what it was read as, so a misreading is one correction. Quantities in the other unit system are converted and the conversion is shown; a count of boxes is never compared with a count of tiles.
- Does this check the price as well?
- No. It reads quantities, never prices, and this site publishes none: an installed price moves with the market, the season, the access and the specification, so a figure for what the work ought to cost would give you confidence in a number nobody can defend. A quantity against your own measurements is checkable, and every figure here links to the calculator that produced it.