Job takeoff
External wall finish takeoff
Wrap, cladding and finish over a measured wall area.
A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.
- 2Measurements in
- 3Trades out
Give the job once
Every figure on the right follows these, in the units you choose.
Been given a quote for this job?
Paste it into the external wall finish quote check: each line is read against these same calculators — what it leaves out, what it adds, and what to ask.
Check the quoteEvery trade, from those dimensions
then change a dimension, and each line shows what moved.
| Trade | Quantity | |
|---|---|---|
House Wrap Calculator
Why this quantity?
Resting on
The lap allowance: the calculator's working figure, a trade convention. | 1 roll | |
Siding CalculatorThe area to be covered, with a cutting allowance — not board face or a panel count. Divide it by the product's stated coverage, or for boards by the exposure for the run and then by the board length.
Why this quantity?
Resting on
The waste factor: the calculator's working figure, a trade convention. | 3.27 squares | |
Exterior Paint Calculator
Why this quantity?
Resting on
| 2 gallons | |
House Wrap Calculator
Why this quantity? | 1 roll | |
Siding CalculatorThe area to be covered, with a cutting allowance — not board face or a panel count. Divide it by the product's stated coverage, or for boards by the exposure for the run and then by the board length.
Why this quantity? | 29.7 m² | |
Exterior Paint Calculator
Why this quantity? | 7.57 L |
Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance on the row, or open its reasoning to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.
Labour and programme
Person-hours for the rows going in, from trade rules of thumb: a range for each piece of work, never a price.
- House Wrap1.1 h (0.6–2.2)
- Siding17 h (9.1–33)
- Exterior Paint5.0 h (2.8–11)
About 23 person-hours in all, between 12 and 47.
Trade by trade
- Carpenter1 carpenter + 1 labourer1 day
- Painter1 painterhalf a day
About 1½ days, one trade after another at eight hours a day. Left out: drying and curing, deliveries, inspections, trades overlapping.
Labour and programme
Person-hours for the rows going in, from trade rules of thumb: a range for each piece of work, never a price.
- House Wrap1.1 h (0.5–2.2)
- Siding16 h (8.9–33)
- Exterior Paint4.9 h (2.7–11)
About 22 person-hours in all, between 12 and 46.
Trade by trade
- Carpenter1 carpenter + 1 labourer1 day
- Painter1 painterhalf a day
About 1½ days, one trade after another at eight hours a day. Left out: drying and curing, deliveries, inspections, trades overlapping.
Setups you have saved
The build-up, the dimensions and any allowance you changed — kept on this device, and reusable on any job. Your prices are not copied in: they stay in your price book, so a setup never holds a stale one.
How far does a budget go?
At your own prices, with this build-up unchanged.
About this job
Cladding a wall is a layered job where each layer is measured differently. The weather-resistive barrier goes by area with laps, the cladding goes by the area it has to cover, which the product's exposure then turns into boards or panels, and the finish goes by area again but against a coverage rate that changes with the profile and how absorbent the surface is. One wall measurement feeds all three; the layers between them do not come from it.
Exposure is the thing a wall's dimensions cannot tell you. The same elevation in a sheltered courtyard and on an exposed gable takes different laps, different fixings and often a different finish specification.
The cladding row is the area to be covered, with a cutting allowance, and it does not move with the exposure. Panels sold by stated coverage are divided by the coverage on the box. Boards differ from their face by more than people expect: a lap board 150 mm (6 in) wide laid to a 125 mm (5 in) exposure covers five sixths of what its width suggests, so the run to order is the area divided by the exposure, not by the board — and the exposure is set by the fixing pattern and the manufacturer, not chosen. Change it by a single course to land the courses level at a window head and that run moves with it.
How each line reads
- Base
- What the calculator gives for these dimensions, before anything is added.
- Allowance
- Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
- Adjusted
- The base with its allowance on top.
- Order
- What to buy: the adjusted figure in whole boards, bags, rolls or lengths.
The order this happens in
Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.
- Sheathe and make good, then check the openings are square and the sills fall outward.
- Hang the weather-resistive barrier from the top down so every lap sheds water.
- Flash the openings and any penetration before the cladding hides them.
- Batten where the build-up calls for a drained and ventilated cavity.
- Clad from the bottom up, keeping the courses level around the building.
- Finish, and keep the first coat within the manufacturer's window after fixing.
What this takeoff does not cover
- Sheathing, battens and the cavity itself — the build-up is a specification, not a consequence of the wall's size.
- Flashings, trims, corners, starter strips, soffits and everything around an opening. These follow the building's detail and are where a cladding estimate usually falls short.
- Insulation, whether in the wall or over it.
- Openings are not deducted: the area here is the gross elevation, which is the right basis for ordering barrier and finish and an over-estimate for cladding on a heavily glazed wall.
- Access. Scaffold or a tower is usually the largest single cost on an elevation and does not scale with area.
Quote check
Been given a quote for this job?
Paste it into the external wall finish quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.
What it leaves out
Every line this takeoff has that nothing on the quote reads as.
What it adds
Labour, removal, hire, fees — each named for what it is.
What to ask
One list of questions, ready to copy. Never a verdict.
More takeoffs
Other job takeoffs
Insulate a floor
3 tradesInsulation, vapour control and underlayment over a floor area.
Run this takeoffFibre cement siding
5 tradesCourses, cutting waste, corner posts, fasteners and caulk for a lap-sided elevation.
Run this takeoffAsphalt shingle roof
5 tradesShingles, underlayment, ice-dam membrane, ridge cap and ridge vent from the roof's footprint.
Run this takeoff
Frequently asked questions
- What does the external wall finish takeoff give for a typical job?
- Opened at Wall length 10 m · Wall height 2.7 m, it orders: House Wrap, 1 roll; Siding, 29.7 m²; Exterior Paint, 7.57 L. Opened at Wall length 33 ft · Wall height 9 ft: House Wrap, 1 roll; Siding, 3.27 squares; Exterior Paint, 2 gallons. Every figure follows the dimensions you give it.
- Which calculators does the external wall finish takeoff run?
- 3 calculators, one to a line: House Wrap Calculator, Siding Calculator, Exterior Paint Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
- What does the external wall finish takeoff leave out?
- 5 things, each named on this page: Sheathing, battens and the cavity itself; Flashings, trims, corners, starter strips, soffits and everything around an opening; Insulation, whether in the wall or over it; Openings are not deducted; Access.
- Can I check a quote for this job against the takeoff?
- Yes. The external wall finish quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.