Detached garage (new build) takeoff

Build a detached timber-framed garage on a concrete slab: the dig, the slab, studwork sheathed, wrapped and sided, a gable roof on trusses with its deck, underlayment, shingles and ridge cap, fascia, soffit and gutters, from its footprint, wall height, roof pitch and openings, with the slab, trusses and door header listed and never sized.

Measurements in
14
Trades out
18
Calculators
15
Going in
18of 18
My Project
Not in it

No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.

Dimensions

Give the job once

Every figure on the right follows these, in the units you choose.

Step 1 of 4

Every trade, from those dimensions

then change a dimension, and each line shows what moved.

Every trade's quantity · 18 rows

18 of 18 going in
ItemQuantityOrderWaste / allowance
Topsoil and ground dug out over the footprint15.05 yd³15.05 yd³no pack size recorded25%
Slab concrete, with its sub-base and edge forms5.43 yd³5.43 yd³no pack size recorded10%
Wall studs (studwork)68 studs68 studsalready whole10%
Wall sheathing, OSB or plywood18 sheets (4x8 ft)18 sheets (4x8 ft)already whole10%
House wrap (breather membrane) on the walls1 roll1 rollalready whole10%
Flashing tape round each window opening19.8 ft19.8 ftno pack size recorded10%
Flashing tape round each side door's opening27.53 ft27.53 ftno pack size recorded10%
Siding on the walls5.24 squares5.24 squaresno pack size recorded10%
Roof trusses11 trusses11 trussesalready wholenone
Roof deck, OSB or plywood19 sheets (4x8 ft)19 sheets (4x8 ft)already whole10%
Roof underlayment1 roll1 rollalready whole10%
Asphalt shingles6.04 squares6.04 squaresno pack size recorded12%
Ridge cap1 bundle1 bundlealready whole10%
Fascia boards along both eaves5 x 12 ft boards5 x 12 ft boardsalready whole10%
Soffit under both eaves4 x 12 sq ft panels4 x 12 sq ft panelsalready whole10%
Gutters and downspouts along both eaves5 x 10 ft sections5 x 10 ft sectionsalready whole0%
Skip (dumpster) or muck away for the spoil15.05 yd³15.05 yd³no pack size recordednone
Skip or bags for the offcuts and packaging6.08 yd³6.08 yd³no pack size recordednone

Every trade's quantity · 18 rows

18 of 18 going in
ItemQuantityOrderWaste / allowance
Topsoil and ground dug out over the footprint11.25 m³ (loose)11.25 m³loose) (no pack size recorded25%
Slab concrete, with its sub-base and edge forms3.96 m³3.96 m³no pack size recorded10%
Wall studs (studwork)68 studs68 studsalready whole10%
Wall sheathing, OSB or plywood18 sheets (2440x1220 mm)18 sheets (2440x1220 mm)already whole10%
House wrap (breather membrane) on the walls1 roll1 rollalready whole10%
Flashing tape round each window opening5.94 m5.94 mno pack size recorded10%
Flashing tape round each side door's opening8.36 m8.36 mno pack size recorded10%
Siding on the walls47 m²47 m²no pack size recorded10%
Roof trusses11 trusses11 trussesalready wholenone
Roof deck, OSB or plywood18 sheets (2440x1220 mm)18 sheets (2440x1220 mm)already whole10%
Roof underlayment1 roll1 rollalready whole10%
Asphalt shingles54.55 m²54.55 m²no pack size recorded12%
Ridge cap1 bundle1 bundlealready whole10%
Fascia boards along both eaves5 x 3.6 m boards5 x 3.6 m boardsalready whole10%
Soffit under both eaves4.36 m² of soffit board4.36 m² of soffit boardno pack size recorded10%
Gutters and downspouts along both eaves4 x 4 m sections4 x 4 m sectionsalready whole0%
Skip (dumpster) or muck away for the spoil11.25 m³11.25 m³no pack size recordednone
Skip or bags for the offcuts and packaging4.5 m³4.5 m³no pack size recordednone

Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.

18 of 18 trades chosenNot pricedNot in project
Kept on this deviceUnitsImperialMetricMy Projectnot in it yetQuantities only · your own rates · not a structural check

About this job

A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.

A detached garage is a small house shell with one very large hole in it. Every layer a house wall has is here, from the slab to the ridge cap, but the front wall is mostly door: a 4.8 m (16 ft) door takes most of a 6 m (20 ft) front, so the studs, the sheathing and the siding on that wall are a short return each side and a band over the head. This page measures the walls along their length less the door's width, so those rows count what is actually built.

The slab is the part to settle first and the part this page decides least. Its thickness, any mesh or bars, a thickened edge or a separate footing under the walls, and how deep that goes where the ground freezes, are the designer's or the building department's answer for the ground and the loads. The slab row works at the concrete page's opening thickness, with its sub-base and its edge forms, as a quantity for the figures it is given and nothing more.

The roof is a plain gable across the width, ridge along the length, on trusses the truss maker designs and this page counts at its spacing. The roof's outline runs past the walls by the eave overhang down each side and the gable overhang at each end, and the deck and underlayment take the sloped area from the slope factor you give for the pitch, so the slope factor must be the one for that same pitch: 1.118 at 6 in 12.

How each line reads

Base
What the calculator gives for these dimensions, before anything is added.
Allowance
Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
Adjusted
The base with its allowance on top.
Order
What to buy: the adjusted figure in whole boards, bags, rolls or lengths.

The order this happens in

Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.

  1. Settle the garage's size and where it stands against the zoning setbacks, height and lot-coverage limits, or permitted development in England; apply for the permit or building control approval where it is needed; have the slab and any footing designed for the ground; and trace any buried service under the footprint.
  2. Peg the footprint out square by its diagonals, strip the topsoil and dig to formation, then lay and compact the stone sub-base.
  3. Set the edge forms to line and level, lay the membrane, fix any mesh or bars the design calls for, set the anchor bolts where the sole plate will run, pour, finish and cure the slab, cutting its control joints as soon as it will take a saw.
  4. Frame the walls on the slab with a sill gasket or damp-proof course under the sole plate, leaving the garage door opening, the side door and the windows framed with their headers; stand, plumb, brace and anchor them, then sheathe them.
  5. Lift the trusses on at their spacing, brace them as the truss maker's drawing shows, fix the fascia, deck the roof, lay the underlayment and shingle it, with the drip edge, the ridge cap and any ridge vent.
  6. Wrap the walls, fit and tape the windows and the side door, side the walls with their trims, fix the soffit, and hang the gutters with their downspouts.
  7. Have the garage door supplier fit the door, its track and its opener; run any power; then clear the spoil and the offcuts and book the final inspection.

What this takeoff does not cover

  • What the slab and the frame must be to carry the garage: the slab's thickness, its mesh or bars, a thickened edge or separate footing and its depth below frost, the anchor bolts' size and spacing, the header over the garage door, and the trusses' design. Each appears as work, or as a count at the page's spacing, never with a size; the trusses are their maker's design.
  • The garage door itself, its track, springs and opener, and the side door and windows as products: their maker supplies and usually fits them, and this page takes their openings as entered.
  • The top and sole plates, the corner posts and the headers over the openings: listed as framing work and not counted, as the stud row's note says.
  • Ice-dam membrane at the eaves: the US model code (IRC R905.1.2) exempts a detached garage with no conditioned floor area. A heated garage where winters freeze takes the strip the shingle roof page counts.
  • Drip edge, starter strip, ridge vent and any roof penetration: details rather than areas, and on the shingle roof page where they are needed.
  • Insulation, an inside lining, a floor coating or paint inside: a garage built cold has none, and a finished one takes them from the garage conversion and garage floor coating pages.
  • Power, lighting and any circuit to the garage: the electrician's, listed as work where there is power, with the trench on the garden room page.
  • A driveway or apron in front of the door, and where the downspouts discharge.
  • Zoning, planning and permit decisions: whether a garage this size, this tall and this near the boundary is allowed, and whether it needs a permit, which the local building department or council answers.

Labour by trade

Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.

Metric opening

Length, along the ridge 6 m · Width, the garage door's wall 6 m · Wall height 2.4 m and 11 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer54 h (29–122)6½ days
Carpenter2 carpenters61 h (33–128)4 days
Glazier2 glaziers8.0 h (2.0–16)half a day
Roofer2 roofers15 h (8.5–33)1 day
Rated rows138 h (73–299)12 days

Imperial opening

Length, along the ridge 20 ft · Width, the garage door's wall 20 ft · Wall height 8 ft and 11 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer55 h (30–125)7 days
Carpenter2 carpenters63 h (34–131)4 days
Glazier2 glaziers8.0 h (2.0–16)half a day
Roofer2 roofers16 h (8.7–34)1 day
Rated rows142 h (75–306)12½ days

Quote check

Been given a quote for this job?

Paste it into the detached garage quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.

  • What it leaves out

    Every line this takeoff has that nothing on the quote reads as.

  • What it adds

    Labour, removal, hire, fees — each named for what it is.

  • What to ask

    One list of questions, ready to copy. Never a verdict.

More takeoffs

Other job takeoffs

All job takeoffs

Frequently asked questions

What does the detached garage takeoff give for a typical job?
Opened at Length, along the ridge 6 m · Width, the garage door's wall 6 m · Wall height 2.4 m · Roof pitch (rise per 12) 6 · Slope factor 1.12 · Eave overhang, each side 300 mm · Gable overhang, each end 300 mm · Garage door opening width 4.8 m · Garage door opening height 2.1 m · Side doors 1 · Windows 1 · Window opening width, each 0.9 m · Window opening height, each 0.9 m · Dig over the footprint 250 mm, it orders: Topsoil and ground dug out over the footprint, 11.3 m³ (loose); Slab concrete, with its sub-base and edge forms, 3.96 m³; Wall studs (studwork), 68 studs; Wall sheathing, OSB or plywood, 18 sheets (2440x1220 mm); House wrap (breather membrane) on the walls, 1 roll; Flashing tape round each window opening, 5.94 m; Flashing tape round each side door's opening, 8.36 m; Siding on the walls, 47 m²; Roof trusses, 11 trusses; Roof deck, OSB or plywood, 18 sheets (2440x1220 mm); Roof underlayment, 1 roll; Asphalt shingles, 54.5 m²; Ridge cap, 1 bundle; Fascia boards along both eaves, 5 x 3.6 m boards; Soffit under both eaves, 4.36 m² of soffit board; Gutters and downspouts along both eaves, 4 x 4 m sections; Skip (dumpster) or muck away for the spoil, 11.3 m³; Skip or bags for the offcuts and packaging, 4.5 m³. Opened at Length, along the ridge 20 ft · Width, the garage door's wall 20 ft · Wall height 8 ft · Roof pitch (rise per 12) 6 · Slope factor 1.12 · Eave overhang, each side 11.8 in · Gable overhang, each end 11.8 in · Garage door opening width 16 ft · Garage door opening height 7 ft · Side doors 1 · Windows 1 · Window opening width, each 3 ft · Window opening height, each 3 ft · Dig over the footprint 9.75 in: Topsoil and ground dug out over the footprint, 15 yd³; Slab concrete, with its sub-base and edge forms, 5.43 yd³; Wall studs (studwork), 68 studs; Wall sheathing, OSB or plywood, 18 sheets (4x8 ft); House wrap (breather membrane) on the walls, 1 roll; Flashing tape round each window opening, 19.8 ft; Flashing tape round each side door's opening, 27.5 ft; Siding on the walls, 5.24 squares; Roof trusses, 11 trusses; Roof deck, OSB or plywood, 19 sheets (4x8 ft); Roof underlayment, 1 roll; Asphalt shingles, 6.04 squares; Ridge cap, 1 bundle; Fascia boards along both eaves, 5 x 12 ft boards; Soffit under both eaves, 4 x 12 sq ft panels; Gutters and downspouts along both eaves, 5 x 10 ft sections; Skip (dumpster) or muck away for the spoil, 15 yd³; Skip or bags for the offcuts and packaging, 6.08 yd³. Every figure follows the dimensions you give it.
Which calculators does the detached garage takeoff run?
15 calculators, for 18 lines: Trench Excavation & Backfill Volume Calculator, Concrete Calculator, Framing Stud Calculator, Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof), House Wrap Calculator, Window Opening Flashing Membrane Calculator, Siding Calculator, Roof Truss Spacing & Count Calculator, Roofing Underlayment Calculator, Roofing Shingle Calculator, Roof Ridge Cap Calculator, Fascia Board Calculator, Soffit Panel Calculator, Gutter Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
What does the detached garage takeoff leave out?
9 things, each named on this page: What the slab and the frame must be to carry the garage; The garage door itself, its track, springs and opener, and the side door and windows as products; The top and sole plates, the corner posts and the headers over the openings; Ice-dam membrane at the eaves; Drip edge, starter strip, ridge vent and any roof penetration; Insulation, an inside lining, a floor coating or paint inside; Power, lighting and any circuit to the garage; A driveway or apron in front of the door, and where the downspouts discharge; Zoning, planning and permit decisions.
Can I check a quote for this job against the takeoff?
Yes. The detached garage quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.