Job takeoff

Asphalt shingle roof takeoff

Shingles, underlayment, ice-dam membrane, ridge cap and ridge vent from the roof's footprint.

A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.

  • 9Measurements in
  • 5Trades out

Give the job once

Every figure on the right follows these, in the units you choose.

Been given a quote for this job?

Paste it into the asphalt shingle roof quote check: each line is read against these same calculators — what it leaves out, what it adds, and what to ask.

Check the quote

Every trade, from those dimensions

5 of 5 trades chosenNot pricedNot in project

then change a dimension, and each line shows what moved.

TradeQuantity
Roofing Shingle CalculatorShingles from the outline to the drip edge, at the pitch above. The 10% allowance covers cutting on a plain gable: the ridge cap is its own row and starter strip is bought separately, so raise it if you cut starters or caps from field shingles, or for hips and valleys.
Base
11.34 squares
Waste factor
+1.13 squares · 10%, set by this takeoff
Adjusted
12.47 squares
Order
12.47 squares (no pack size recorded)
Why this quantity?
  1. Base quantity11.34 squarescalculatorRoofing Shingle Calculator v1.0.1, headline with the waste factor at 0%
  2. Waste factor1.13 squaresworked outthe adjusted figure less the base, at 10% (set by the Asphalt shingle roof takeoff)
  3. Adjusted quantity12.47 squarescalculatorRoofing Shingle Calculator v1.0.1, headline with the waste factor at 10%
  4. Order quantity12.47 squaresworked out12.47 squares (no pack size recorded)

Resting on

  • Footprint length39 ftgivenyour footprint length
  • Footprint width26 ftgivenyour footprint width
  • Roof pitch (rise per 12)6givenyour roof pitch (rise per 12)
  • Waste Factor (%)10%assumedset by the Asphalt shingle roof takeoff

The waste factor: set by the Asphalt shingle roof takeoff.

Change any other figure on the Roofing Shingle Calculator

12.47 squares
Roofing Underlayment CalculatorUnderlayment over the SLOPED area, less the eave strip the ice-dam membrane covers; it laps onto the membrane rather than doubling it. To leave the membrane out, set the eaves with ice-dam membrane to 0 rather than unticking its row, or this row stays short by the strip. Where each half of the roof is no wider on plan than that strip (1.16 m / 3 ft 10 in at the opening figures), the membrane covers the whole slope and this row does not appear.
Base
1 roll
Overlap allowance
+0 rolls · 10%, trade convention
Adjusted
1 roll
Order
1 roll, already whole
Why this quantity?
  1. Base quantity1 rollcalculatorRoofing Underlayment Calculator v1.1.0, headline with the overlap allowance at 0%
  2. Overlap allowance0 rollsworked outthe adjusted figure less the base, at 10% (the calculator's working figure, a trade convention)
  3. Adjusted quantity1 rollcalculatorRoofing Underlayment Calculator v1.1.0, headline with the overlap allowance at 10%
  4. Order quantity1 rollworked out1 roll, already whole

Resting on

  • Footprint length39 ftgivenyour footprint length
  • Footprint width26 ftgivenyour footprint width
  • Slope factor1.12givenyour slope factor
  • Eaves with ice-dam membrane2givenyour eaves with ice-dam membrane
  • Eave overhang16 ingivenyour eave overhang
  • Exterior wall thickness6 ingivenyour exterior wall thickness
  • Ice-dam reach past the wall's inside face2 ftgivenyour ice-dam reach past the wall's inside face
  • Overlap Allowance (%)10%assumedthe Roofing Underlayment Calculator's default

The overlap allowance: the calculator's working figure, a trade convention.

Change any other figure on the Roofing Underlayment Calculator

1 roll
Roof Eave Ice Dam Protection Membrane FootprintAlong the eaves counted above — both eaves of a gable by default, twice the footprint length — from the drip edge to the reach past the wall's inside face, so its overhang box carries the overhang and the wall thickness together. Where freeze-thaw does not call for it, set the eaves with ice-dam membrane to 0 rather than unticking this row: the underlayment row subtracts this strip whenever that count is above 0. On a roof so narrow that the strip reaches the ridge (the underlayment row then drops out), this row counts the full strip anyway and can come to more than the roof: order no more than the roof area.
Base
334.29 ft²
Allowance
+0 ft² · none added
Adjusted
334.29 ft²
Order
334.29 ft² (no pack size recorded)
Why this quantity?
  1. Base quantity334.29 ft²calculatorRoof Eave Ice Dam Protection Membrane Footprint v1.0.1, headline
  2. Allowance0 ft²worked outnone: the calculator adds no allowance, and none was added
  3. Adjusted quantity334.29 ft²worked outthe base plus the allowance
  4. Order quantity334.29 ft²worked out334.29 ft² (no pack size recorded)

Resting on

  • Footprint length39 ftgivenyour footprint length
  • Eaves with ice-dam membrane2givenyour eaves with ice-dam membrane
  • Eave overhang16 ingivenyour eave overhang
  • Exterior wall thickness6 ingivenyour exterior wall thickness
  • Ice-dam reach past the wall's inside face2 ftgivenyour ice-dam reach past the wall's inside face
  • Roof pitch (rise per 12)6givenyour roof pitch (rise per 12)

Change any other figure on the Roof Eave Ice Dam Protection Membrane Footprint

334.29 ft²
Roof Ridge Cap CalculatorCap shingles along the whole ridge, over the vent where there is one.
Base
2 bundles
Cut-end allowance
+0 bundles · 10%, trade convention
Adjusted
2 bundles
Order
2 bundles, already whole
Why this quantity?
  1. Base quantity2 bundlescalculatorRoof Ridge Cap Calculator v1.1.0, headline with the cut-end allowance at 0%
  2. Cut-end allowance0 bundlesworked outthe adjusted figure less the base, at 10% (the calculator's working figure, a trade convention)
  3. Adjusted quantity2 bundlescalculatorRoof Ridge Cap Calculator v1.1.0, headline with the cut-end allowance at 10%
  4. Order quantity2 bundlesworked out2 bundles, already whole

Resting on

  • Ridge length39 ftgivenyour ridge length
  • Cut-End Allowance (%)10%assumedthe Roof Ridge Cap Calculator's default

The cut-end allowance: the calculator's working figure, a trade convention.

Change any other figure on the Roof Ridge Cap Calculator

2 bundles
Ridge Vent Linear Footage CalculatorRidge vent under the cap, along the slot — an addition to the cap, not a replacement. Skip the row for an unvented ridge.
Base
39 ft
Waste allowance
+1.95 ft · 5%, trade convention
Adjusted
40.95 ft
Order
40.95 ft (no pack size recorded)
Why this quantity?
  1. Base quantity39 ftcalculatorRidge Vent Linear Footage Calculator v1.0.1, headline with the waste allowance at 0%
  2. Waste allowance1.95 ftworked outthe adjusted figure less the base, at 5% (the calculator's working figure, a trade convention)
  3. Adjusted quantity40.95 ftcalculatorRidge Vent Linear Footage Calculator v1.0.1, headline with the waste allowance at 5%
  4. Order quantity40.95 ftworked out40.95 ft (no pack size recorded)

Resting on

  • Ridge length39 ftgivenyour ridge length
  • Waste Allowance (%)5%assumedthe Ridge Vent Linear Footage Calculator's default

The waste allowance: the calculator's working figure, a trade convention.

Change any other figure on the Ridge Vent Linear Footage Calculator

40.95 ft
Roofing Shingle CalculatorShingles from the outline to the drip edge, at the pitch above. The 10% allowance covers cutting on a plain gable: the ridge cap is its own row and starter strip is bought separately, so raise it if you cut starters or caps from field shingles, or for hips and valleys.
Base
107.33 m²
Waste factor
+10.73 m² · 10%, set by this takeoff
Adjusted
118.06 m²
Order
118.06 m² (no pack size recorded)
Why this quantity?
118.06 m²
Roofing Underlayment CalculatorUnderlayment over the SLOPED area, less the eave strip the ice-dam membrane covers; it laps onto the membrane rather than doubling it. To leave the membrane out, set the eaves with ice-dam membrane to 0 rather than unticking its row, or this row stays short by the strip. Where each half of the roof is no wider on plan than that strip (1.16 m / 3 ft 10 in at the opening figures), the membrane covers the whole slope and this row does not appear.
Base
1 roll
Overlap allowance
+0 rolls · 10%, trade convention
Adjusted
1 roll
Order
1 roll, already whole
Why this quantity?
1 roll
Roof Eave Ice Dam Protection Membrane FootprintAlong the eaves counted above — both eaves of a gable by default, twice the footprint length — from the drip edge to the reach past the wall's inside face, so its overhang box carries the overhang and the wall thickness together. Where freeze-thaw does not call for it, set the eaves with ice-dam membrane to 0 rather than unticking this row: the underlayment row subtracts this strip whenever that count is above 0. On a roof so narrow that the strip reaches the ridge (the underlayment row then drops out), this row counts the full strip anyway and can come to more than the roof: order no more than the roof area.
Base
31.12 m²
Allowance
+0 m² · none added
Adjusted
31.12 m²
Order
31.12 m² (no pack size recorded)
Why this quantity?
31.12 m²
Roof Ridge Cap CalculatorCap shingles along the whole ridge, over the vent where there is one.
Base
2 bundles
Cut-end allowance
+0 bundles · 10%, trade convention
Adjusted
2 bundles
Order
2 bundles, already whole
Why this quantity?
2 bundles
Ridge Vent Linear Footage CalculatorRidge vent under the cap, along the slot — an addition to the cap, not a replacement. Skip the row for an unvented ridge.
Base
12 m
Waste allowance
+0.6 m · 5%, trade convention
Adjusted
12.6 m
Order
12.6 m (no pack size recorded)
Why this quantity?
12.6 m

Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance on the row, or open its reasoning to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.

Labour and programme

Person-hours for the rows going in, from trade rules of thumb: a range for each piece of work, never a price.

  • Roofing Shingle14 h (8.1–32)
  • Roofing Underlayment3.7 h (2.2–7.4)
  • Roof Eave Ice Dam Protection Membrane Footprint1.6 h (0.9–3.1)
  • Ridge Vent Linear Footage2.4 h (1.2–4.8)

About 22 person-hours in all, between 12 and 48.

Trade by trade

  1. Roofer2 roofers1½ days

About 1½ days, one trade after another at eight hours a day. Left out: drying and curing, deliveries, inspections, trades overlapping.

1 row carries no hours of its own
  • Roof Ridge Cap: counted with Roofing Shingle

Labour and programme

Person-hours for the rows going in, from trade rules of thumb: a range for each piece of work, never a price.

  • Roofing Shingle14 h (8.3–33)
  • Roofing Underlayment3.8 h (2.3–7.6)
  • Roof Eave Ice Dam Protection Membrane Footprint1.6 h (0.9–3.1)
  • Ridge Vent Linear Footage2.4 h (1.2–4.8)

About 22 person-hours in all, between 13 and 49.

Trade by trade

  1. Roofer2 roofers1½ days

About 1½ days, one trade after another at eight hours a day. Left out: drying and curing, deliveries, inspections, trades overlapping.

1 row carries no hours of its own
  • Roof Ridge Cap: counted with Roofing Shingle

Setups you have saved

The build-up, the dimensions and any allowance you changed — kept on this device, and reusable on any job. Your prices are not copied in: they stay in your price book, so a setup never holds a stale one.

How far does a budget go?

At your own prices, with this build-up unchanged.

About this job

A roof is bigger than the building it sits on, and that is the first thing an estimate has to get right. The footprint here is the roof's outline on plan measured to the drip edge, overhangs included, not the wall line you can tape from the ground; the roof area is that outline multiplied by a slope factor, which at a 6:12 pitch is about 1.12 and at 12:12 is over 1.41. The shingle and ice-dam rows take the pitch you enter and apply the slope themselves. The underlayment row cannot — it takes an area, so the slope factor here must be the one for that same pitch.

The ice-dam row is a climate question wearing a quantity's clothing. Where the winter produces freeze-thaw, the membrane has to reach far enough up the slope to pass the inside face of the exterior wall, which is a depth measured from the eave rather than a percentage of the roof. In a warm climate the row is not needed at all, and the honest thing is to exclude it rather than to order it: set the eaves with ice-dam membrane to 0, rather than unticking the row, and it drops out with the underlayment made whole again.

The ice-dam row also runs along every eave, not one. A gable has two, one down each long side, so the row below takes the footprint length once for each; a hip roof has eaves on all four sides, the whole perimeter, which this gable takeoff does not model. The underlayment starts where the membrane stops, so its row is the sloped area less the membrane strip rather than both over the same eave.

The ridge is two products, and the vent does not replace the cap. A ridge vent goes down first, over a slot cut back from the ridge board; the cap shingles go on last and cover the whole ridge, over the vent where there is one. Choosing a vent adds a line to the order rather than swapping one, and because the slot stops short of the ridge ends, a vent row sized to the full ridge carries a little spare.

How each line reads

Base
What the calculator gives for these dimensions, before anything is added.
Allowance
Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
Adjusted
The base with its allowance on top.
Order
What to buy: the adjusted figure in whole boards, bags, rolls or lengths.

The order this happens in

Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.

  1. Strip to the deck and check it — a re-roof over rot is a re-roof done twice.
  2. Fit the drip edge at the eave, then the ice-dam membrane, then the drip edge at the rake over the top of it.
  3. Lay the underlayment up the slope, lapped so water runs over each joint rather than into it.
  4. Snap the course lines rather than trusting the shingle's own alignment marks.
  5. Cut the ridge slot before capping, and only where the vent will run.
  6. Cap the ridge last, working away from the prevailing wind.

What this takeoff does not cover

  • The deck below, its condition and any repair to it.
  • Valleys, hips, step flashing, chimneys, pipe boots and every other penetration — each is a detail rather than an area.
  • Drip edge, starter strip (the shingle row's allowance covers cutting only) and hip and ridge accessories other than the cap counted here.
  • Intake ventilation at the soffit, which a ridge vent needs and without which it can pull air from the house.
  • Tear-off, disposal and whatever the deck turns out to need.

Quote check

Been given a quote for this job?

Paste it into the asphalt shingle roof quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.

  • What it leaves out

    Every line this takeoff has that nothing on the quote reads as.

  • What it adds

    Labour, removal, hire, fees — each named for what it is.

  • What to ask

    One list of questions, ready to copy. Never a verdict.

More takeoffs

Other job takeoffs

All job takeoffs

Frequently asked questions

What does the asphalt shingle roof takeoff give for a typical job?
Opened at Footprint length 12 m · Footprint width 8 m · Roof pitch (rise per 12) 6 · Slope factor 1.12 · Ridge length 12 m · Eaves with ice-dam membrane 2 · Eave overhang 0.4 m · Exterior wall thickness 0.15 m · Ice-dam reach past the wall's inside face 0.61 m, it orders: Roofing Shingle, 118 m²; Roofing Underlayment, 1 roll; Roof Eave Ice Dam Protection Membrane Footprint, 31.1 m²; Roof Ridge Cap, 2 bundles; Ridge Vent Linear Footage, 12.6 m. Opened at Footprint length 39 ft · Footprint width 26 ft · Roof pitch (rise per 12) 6 · Slope factor 1.12 · Ridge length 39 ft · Eaves with ice-dam membrane 2 · Eave overhang 16 in · Exterior wall thickness 6 in · Ice-dam reach past the wall's inside face 2 ft: Roofing Shingle, 12.5 squares; Roofing Underlayment, 1 roll; Roof Eave Ice Dam Protection Membrane Footprint, 334 ft²; Roof Ridge Cap, 2 bundles; Ridge Vent Linear Footage, 40.9 ft. Every figure follows the dimensions you give it.
Which calculators does the asphalt shingle roof takeoff run?
5 calculators, one to a line: Roofing Shingle Calculator, Roofing Underlayment Calculator, Roof Eave Ice Dam Protection Membrane Footprint, Roof Ridge Cap Calculator, Ridge Vent Linear Footage Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
What does the asphalt shingle roof takeoff leave out?
5 things, each named on this page: The deck below, its condition and any repair to it; Valleys, hips, step flashing, chimneys, pipe boots and every other penetration; Drip edge, starter strip (the shingle row's allowance covers cutting only) and hip and ridge accessories other than the cap counted here; Intake ventilation at the soffit, which a ridge vent needs and without which it can pull air from the house; Tear-off, disposal and whatever the deck turns out to need.
Can I check a quote for this job against the takeoff?
Yes. The asphalt shingle roof quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.