Extension shell, one or two storeys takeoff
Build a masonry extension to weathertight: pegging out, footings and the walls below the damp course, the ground floor, cavity walls with ties and insulation, a tiled lean-to or pitched roof, gutters and the openings, with the beam into the house and every structural member listed and never sized.
- Measurements in
- 14
- Trades out
- 25
- Calculators
- 20
- Going in
- 25of 25
- My Project
- Not in it
No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.
Dimensions
Give the job once
Every figure on the right follows these, in the units you choose.
Choose the build-up
Each layer changes the materials below; the dimensions stay the same.
Calculators behind the other choices:
Calculators behind the other choices:
Every trade, from those dimensions
then change a dimension, and each line shows what moved.
Every trade's quantity · 25 rows
Every trade's quantity · 25 rows
Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.
About this job
A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.
An extension shell is priced from the ground up and goes wrong from the ground down. Before a block is laid the footprint is pegged square off the house, the drains, cables and pipes under it are traced, and the trenches are dug to whatever depth the ground and building control accept on the day, which is not always the depth on the drawing. This page builds the shell the way most extensions in Britain and Ireland go up: concrete footings, a cavity wall of block inside and brick or rendered block outside, a ground floor, and a roof tiled on battens, taken as far as a building that keeps the weather out. A timber-framed addition, the usual way in North America, is the framed exterior wall takeoff on the same foundation.
The walls are counted as they are laid rather than as a box with holes cut out on paper. The run is the three new walls, meaning the two returns and the far wall, and the doors and windows are given by number, width and height, so each leaf comes in two rows: the wall clear of any opening at full storey height, and the courses above and below the openings. The ties, the cavity insulation and the render (stucco) follow the same net area. Every run is taken along the walls' outside face, as the footings are, so the inner leaf, the ties and the cavity insulation, which sit further in, come out a little over. Where each return meets the house it is tied in, with a vertical damp course between old and new; that work is listed, and the ties to the house are not counted.
One storey or two changes the roof more than the height. A single storey takes a lean-to, one slope rising to the house wall, where a cavity tray cut into the house above the roof and a flashing dressed over the tiles keep the junction dry. A second storey brings a first floor, a way up to it, a scaffold twice as high, and a pitched roof of its own, gabled at the far end and joined to the main roof with valleys; a hipped end adds a third eave that the rows here do not count.
The brick and block sizes follow the units. Metric opens on the 215 × 65 mm (about 8 1/2 × 2 1/2 in) bricks and 440 × 215 mm (about 17 3/8 × 8 1/2 in) blocks a British extension is built in; imperial opens on the US modular sizes the brick and block pages use, a 7 5/8 × 2 1/4 in (194 × 57 mm) brick and a block with a 15 5/8 × 7 5/8 in (397 × 194 mm) face, which count a fifth to a quarter more to the square metre. The build-up below names the size, and either can be chosen whichever units are showing. Nothing structural is chosen here either way: the footings, the slab, the lintels (headers), the rafters or trusses and the beam into the house come from the designer, the truss maker and the engineer.
How each line reads
- Base
- What the calculator gives for these dimensions, before anything is added.
- Allowance
- Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
- Adjusted
- The base with its allowance on top.
- Order
- What to buy: the adjusted figure in whole boards, bags, rolls or lengths.
The order this happens in
Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.
- Send building control the notice or the plans the work needs, have the footings, lintels, roof and any beam designed, and trace the drains, cables and pipes under the footprint before pegging out.
- Peg out the three walls off the house, square them by the diagonals, dig the trenches, and have the bottoms inspected before any concrete arrives.
- Pour the footings, build both leaves up to the damp-proof course, and lay any drain that has to run under the new floor while the ground is still open.
- Dig out the floor, then lay and compact the hardcore, blind it, lap the membrane up to the damp course, and cast the slab or lay the beam-and-block floor, with the floor insulation.
- Scaffold the walls and raise both leaves together, bedding the ties and the cavity insulation as the courses rise, closing the cavity at every opening, setting a lintel over each and tying the returns into the house.
- Set the wall plate and fix the rafters or trusses, the fascia and the underlay; above a lean-to, cut the cavity tray into the house wall before the flashing, and on a two-storey roof form the valleys into the main roof. Then batten and tile.
- Hang the gutters, fit the windows and doors, and only then open the house wall, under a beam on padstones with the props left in until the packing takes the load, sheeting the opening until the extension is closed in.
- Render a block outer leaf once the roof is on, and clear the spoil and the waste before the scaffold comes down.
What this takeoff does not cover
- Every structural size: the footings, the slab, the lintels, the rafters or trusses, the first floor's joists, and the beam, padstones and props for the opening into the house. Each is listed as work with no quantity, or counted at the design's spacing, and the designer, the truss maker or the engineer sets it.
- A flat roof over a single storey. The flat roof replacement page's deck, insulation, membrane, upstand and trim rows, run over this footprint, are that roof.
- The tiles or slates, and their fixings. The batten rows count the courses up each slope; the tiles are the roof area times the tile maker's number to the square metre (square), which the page that counts roof fixings gives, with the fixings, when it is run over this roof's slope.
- The masonry above the eaves: the raking tops of a lean-to's side walls and the gable of a two-storey roof. The wall rows stop at the eaves; each raking top or gable is a triangle, half its base times its rise.
- The precast beams and infill blocks of a beam-and-block floor, laid to the floor supplier's layout, which sizes them; no operation lists them yet. The insulation over them is counted and the screed is listed.
- Planning permission, a party wall notice or agreement where the extension stands on or near a boundary, and a build-over agreement for, or a diversion of, a public sewer under the footprint.
- Movement joints in the new brickwork, and the detail where a return meets the house, which the designer chooses between a tie system, a toothed bond and a joint.
- Everything after weathertight: the first and second fix, plastering, the insulation in the roof, the floor finish and the decoration.
Labour by trade
Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.
Metric opening
Width along the house 5 m · Projection from the house 4 m · Wall height for each storey 2.5 m and 11 more of the page's opening figures
Imperial opening
Width along the house 16.5 ft · Projection from the house 13 ft · Wall height for each storey 8 ft and 11 more of the page's opening figures
Quote check
Been given a quote for this job?
Paste it into the extension shell quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.
What it leaves out
Every line this takeoff has that nothing on the quote reads as.
What it adds
Labour, removal, hire, fees — each named for what it is.
What to ask
One list of questions, ready to copy. Never a verdict.
More takeoffs
Other job takeoffs
Concrete slab
3 tradesConcrete, reinforcement and formwork for a ground slab from one set of dimensions.
Run this takeoffTimber deck
4 tradesBoards, footings, fixings and finish for a rectangular deck.
Run this takeoffSegmental retaining wall
4 tradesBlocks, levelling pad, drainage stone and reinforcement layers for a block retaining wall.
Run this takeoff
Frequently asked questions
- What does the extension shell takeoff give for a typical job?
- Opened at Width along the house 5 m · Projection from the house 4 m · Wall height for each storey 2.5 m · Cavity wall thickness 300 mm · Doors and windows in the new walls 3 · Opening width, each 1.5 m · Opening height, each 2.1 m · Footing width, from the design 0.6 m · Footing concrete depth, from the design 0.75 m · Trench depth 1 m · Damp-proof course above the ground 150 mm · Dig over the floor 300 mm · Roof slope factor 1.06 · Eaves overhang 300 mm, it orders: Setting-out diagonals, 6.4 m; Footing trenches, dug, 9.75 m³ (loose); Dig over the floor, 6.11 m³ (loose); Footing concrete, 6.14 m³; Blocks below the damp-proof course, both leaves, 108 blocks; Hardcore under the slab, 5.37 metric tons; Floor insulation boards, 7 sheets (2400x1200 mm); Floor slab concrete, 1.79 m³; Scaffold round the new walls, 32.5 m² of face; Inner leaf blocks, clear of the openings, 221 blocks; Inner leaf blocks, above and below the openings, 19 blocks; Facing bricks, clear of the openings, 1,386 bricks; Facing bricks, above and below the openings, 118 bricks; Wall ties across the cavity, 93 ties; Cavity boards, 9 sheets (2400x1200 mm); Weep holes at the damp course, 23 weep holes; Lean-to rafters, 10 trusses; Fascia along the eaves, 2 x 3.6 m boards; Underlay over the lean-to, 1 roll; Batten courses up the slope, 15 rows; Flashing where the roof meets the house, 4 sheets; Gutter along the eaves, 2 x 4 m sections; Gutter brackets, 10 hangers; Flashing tape round the openings, 29.7 m; Skip (dumpster) loads for the spoil, 15.9 m³. Opened at Width along the house 16.5 ft · Projection from the house 13 ft · Wall height for each storey 8 ft · Cavity wall thickness 11.8 in · Doors and windows in the new walls 3 · Opening width, each 5 ft · Opening height, each 7 ft · Footing width, from the design 2 ft · Footing concrete depth, from the design 2.5 ft · Trench depth 3.5 ft · Damp-proof course above the ground 6 in · Dig over the floor 11.8 in · Roof slope factor 1.06 · Eaves overhang 11.8 in: Setting-out diagonals, 21 ft; Footing trenches, dug, 13.8 yd³; Dig over the floor, 7.92 yd³; Footing concrete, 8.26 yd³; Blocks below the damp-proof course, both leaves, 151 blocks; Hardcore under the slab, 6 tons; Floor insulation boards, 7 sheets (4x8 ft); Floor slab concrete, 2.37 yd³; Scaffold round the new walls, 340 sq ft of face; Inner leaf blocks, clear of the openings, 260 blocks; Inner leaf blocks, above and below the openings, 18 blocks; Facing bricks, clear of the openings, 1,660 bricks; Facing bricks, above and below the openings, 114 bricks; Wall ties across the cavity, 89 ties; Cavity boards, 9 sheets (4x8 ft); Weep holes at the damp course, 23 weep holes; Lean-to rafters, 10 trusses; Fascia along the eaves, 2 x 12 ft boards; Underlay over the lean-to, 1 roll; Batten courses up the slope, 15 rows; Flashing where the roof meets the house, 2 sheets; Gutter along the eaves, 2 x 10 ft sections; Gutter brackets, 10 hangers; Flashing tape round the openings, 99 ft; Skip (dumpster) loads for the spoil, 21.7 yd³. Every figure follows the dimensions you give it.
- Which calculators does the extension shell takeoff run?
- 20 calculators, for 25 lines: Court Diagonal and Squaring Triangle Calculator, Trench Excavation & Backfill Volume Calculator, Continuous Footing / Grade Beam Volume Calculator, Concrete CMU Block Counter & Grout Infill Calculator, Gravel Base Layer Tonnage Calculator, Foam Board Insulation Calculator, Concrete Calculator, Scaffold Face Area and Hire Quantity Calculator, Brick Calculator, Brick Veneer Wall Tie Density Calculator, Cavity Wall Weep Hole Spacing Calculator, Roof Truss Spacing & Count Calculator, Fascia Board Calculator, Roofing Underlayment Calculator, Roof Batten Spacing Calculator (Tile Roofing), Exterior Flashing Layout Trim Sheet Calculator, Gutter Calculator, Gutter Hanger Spacing Calculator, Window Opening Flashing Membrane Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
- What does the extension shell takeoff leave out?
- 8 things, each named on this page: Every structural size; A flat roof over a single storey; The tiles or slates, and their fixings; The masonry above the eaves; The precast beams and infill blocks of a beam-and-block floor, laid to the floor supplier's layout, which sizes them; no operation lists them yet; Planning permission, a party wall notice or agreement where the extension stands on or near a boundary, and a build-over agreement for, or a diversion of, a public sewer under the footprint; Movement joints in the new brickwork, and the detail where a return meets the house, which the designer chooses between a tie system, a toothed bond and a joint; Everything after weathertight.
- Can I check a quote for this job against the takeoff?
- Yes. The extension shell quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.