Garden room or backyard office takeoff
Build a detached, insulated timber-framed garden room (a backyard office or studio): the base on ground screws, concrete piers or a slab, a framed and sheathed shell under a flat EPDM roof, clad walls, the door and windows, a lined and decorated room and the power supply from the house, with the base and the frame listed and never sized.
- Measurements in
- 15
- Trades out
- 3130
- Calculators
- 2523
- Going in
- 3130of 3130
- My Project
- Not in it
No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.
Dimensions
Give the job once
Every figure on the right follows these, in the units you choose.
Choose the build-up
Each layer changes the materials below; the dimensions stay the same.
Calculators behind the other choices:
Calculators behind the other choices:
Every trade, from those dimensions
then change a dimension, and each line shows what moved.
Every trade's quantity · 31 rows
Every trade's quantity · 30 rows
Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.
About this job
A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.
A garden room is a small building standing on its own at the end of a garden, and it has to do everything a house wall does with no house to lean on: shed rain driven at all four sides, stay warm enough to work in through a winter, and bring power a long way from the house. Nothing is shared with the house, so every layer from the ground to the roof membrane is part of the job, and the base is decided before anything else is ordered.
The base follows the units shown. With metric showing it opens on ground screws (screw piles, or helical piles in North America): steel screws the supplier designs, drives to a depth and a torque and levels to take the frame, so this page lists them and measures nothing of them. With imperial showing it opens on concrete piers poured in round cardboard forms (tubes), no more than 1.8 m (about 6 ft) apart each way with one at each end of every row. A slab on a stone bed is the third choice in either. Under each, the turf and topsoil come off the footprint and stone goes back into the dig, over a weed membrane under a raised base so that nothing grows beneath the floor and the air gap under it stays open to the outside.
The walls are timber studs sheathed in OSB or plywood and wrapped in a breather membrane (house wrap), then battened out (furred out) so the cladding has a drained, ventilated gap behind it. The units pick the cladding as well: upright boards with cover battens, on battens across the wall and upright counter-battens, in metric, and horizontal siding on upright furring strips in imperial. The roof is flat or falls gently to its back edge, decked and covered in one sheet of EPDM, as a warm roof with rigid boards over the deck or a cold roof with batts between the joists and air moving over them.
Inside, the floor is insulated between its joists and the walls between their studs, with a vapour control layer on the warm side before the board goes up. The finish follows the units: board skimmed in plaster in metric, taped and finished drywall in imperial. Power comes from the house through a buried cable (steel-wire armoured in the UK, direct-burial cable or wire in conduit in North America) in a trench this page measures; the cable, its protection at each end and its earthing are the electrician's work, listed here and signed off by nobody on this site.
How each line reads
- Base
- What the calculator gives for these dimensions, before anything is added.
- Allowance
- Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
- Adjusted
- The base with its allowance on top.
- Order
- What to buy: the adjusted figure in whole boards, bags, rolls or lengths.
The order this happens in
Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.
- Settle the room's size and where it stands against permitted development or a planning application, and building control or a permit; have the screws, piers or slab chosen by their supplier or the designer; and trace any drain, pipe or cable under the footprint and along the cable's route to the house.
- Peg the footprint out square by its diagonals, strip the turf and topsoil, and set the base: the screws driven and levelled, the piers dug and poured in their tubes, or the slab's stone bed compacted, its membrane laid and the concrete cast in its formwork.
- Lay the weed membrane and the stone under a raised base, then build the floor frame on a strip of damp-proof course over each bearing, insulate between the joists and deck it.
- Frame and sheathe the walls, lift the roof joists on and set the fall, deck the roof and, for a warm roof, lay the vapour control layer and the boards; fix the edge trims, bond the EPDM and dress it down over them, then put the gutter up along the low edge and take its downpipe to a water butt, a drain or a soakaway.
- Wrap the walls, fit and tape the door and windows, batten out, hang the cladding with its trims and the insect mesh closers at its foot and head, seal round every frame, and stain or paint the boards unless they are left to weather.
- Dig the cable trench from the house, lay the cable or its duct with warning tape over it and backfill, and run the first-fix cables inside the room.
- Insulate between the studs and, on a cold roof, between the joists with the eaves vents clear; fix the vapour control layer, board the ceiling and the walls, and skim or tape them, letting a skim dry before any paint.
- Paint the walls and ceiling, lay the floor, fix the skirting and the architraves, connect the lights and sockets, have the circuits tested, and take away the spoil and the offcuts.
What this takeoff does not cover
- What the base and the frame must be to carry the room: the ground screws' number, length and rating, the piers' size, depth and spacing, the slab's thickness, and the size of the bearers, floor joists, studs and roof joists. Each appears as work, or as a count at the page's spacing, never with a size; the ground screws are their supplier's design.
- Planning: whether a room this tall, this near a boundary and covering this much of the plot stays within England's permitted development or needs an application, and whether the building regulations' exemption for a small detached outbuilding applies, which the local authority answers. In the US and Canada, the setback, height and lot-coverage rules for an accessory structure, and whether it needs a permit, are the local zoning and building department's.
- Whether the house's main board (service panel) has the capacity for the room's circuit, the cable's size and protection, and the earthing arrangement at the room: the electrician's decisions. The supply is listed as work and only its trench is measured.
- A water supply, a toilet, a sink or a shower in the room, and any foul drainage from it.
- Whether a soakaway (a dry well) will drain in the ground and how big it must be, where the downpipe runs to one; the drain run to it is listed as work, not measured.
- Decking, a veranda, steps up to the door, and a path from the house.
- Choosing the door set and the windows: a French, bifold or sliding door set, timber, uPVC (vinyl) or aluminium frames, their glazing and their locks. The page takes their openings as entered and counts the tape, the mastic and the trims that fit them.
- Heating, cooling or mechanical ventilation for the room.
- Architraves (casings) round the door set and the windows, and any window boards (stools): fixed with the skirting as its work, and not counted.
- The roof's fall: firring pieces (tapered strips) on the joists, or joists set to a slope, are listed as work, and the roof rows are measured on plan.
- A roof covered in anything but a single EPDM sheet: torch-on felt, GRP, or a pitched roof in tiles or shingles has rows of its own on the flat roof replacement and pitched roof pages.
Labour by trade
Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.
Metric opening
Length, along the front 4 m · Depth, front to back 3 m · Height clad outside 2.4 m and 12 more of the page's opening figures
Imperial opening
Length, along the front 13 ft · Depth, front to back 10 ft · Height clad outside 8 ft and 12 more of the page's opening figures
Quote check
Been given a quote for this job?
Paste it into the garden room quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.
What it leaves out
Every line this takeoff has that nothing on the quote reads as.
What it adds
Labour, removal, hire, fees — each named for what it is.
What to ask
One list of questions, ready to copy. Never a verdict.
More takeoffs
Other job takeoffs
Concrete slab
3 tradesConcrete, reinforcement and formwork for a ground slab from one set of dimensions.
Run this takeoffTimber deck
4 tradesBoards, footings, fixings and finish for a rectangular deck.
Run this takeoffSegmental retaining wall
4 tradesBlocks, levelling pad, drainage stone and reinforcement layers for a block retaining wall.
Run this takeoff
Frequently asked questions
- What does the garden room takeoff give for a typical job?
- Opened at Length, along the front 4 m · Depth, front to back 3 m · Height clad outside 2.4 m · Room height, floor to ceiling 2.2 m · Wall thickness, sheathing to lining 120 mm · Roof overhang, each edge 150 mm · Door opening width 1.5 m · Door opening height 2 m · Windows 2 · Window opening width, each 0.9 m · Window opening height, each 1 m · Supply cable route, house to room 15 m · Cable trench depth 0.6 m · Dig over the footprint 100 mm · Membrane turned over each roof edge 100 mm, it orders: Turf, topsoil and ground dug out over the footprint, 1.5 m³ (loose); Weed membrane and stone laid in the dig (gravel or hardcore), 2.64 metric tons; Floor insulation boards, cut between the joists, 5 sheets (2400x1200 mm); Wall studs, the walls' frame (studwork), 53 studs; Sheathing on the walls, OSB or plywood, 13 sheets (2440x1220 mm); Roof deck, OSB or plywood, 6 sheets (2440x1220 mm); Rigid insulation boards, warm roof, 6 sheets (2400x1200 mm); EPDM membrane over the roof, 1 roll; Gutter and downpipe (downspout) along the eaves, 2 x 4 m sections; Breather membrane (house wrap) on the walls, 1 roll; Flashing tape round the door set's opening, 9.68 m; Flashing tape round each window opening, 12.3 m; Counter-battens, upright, 86.4 m; Battens across the wall, for the upright boards, 98 m; Cladding boards and cover battens (board-and-batten siding), 80 boards; Trims outside: corners, heads and reveals, 8 sheets; Mastic (caulk) round the openings, 0.53 L; Exterior stain or paint on the clad walls, 9.46 L; Trench for the supply cable, dug and backfilled, 3.1 m³ (loose); Insulation batts, walls, 6 packages; Vapour control layer on the walls, 1 roll; Ceiling board (plasterboard or drywall), 4 sheets; Board on the walls inside (plasterboard or drywall), 10 sheets; Skim coat over the boards, walls and ceiling, 98.5 kg; Paint on the walls inside, 4.78 L; Paint on the ceiling, 2.08 L; Laminate or vinyl plank floor, 6 packs; Skirting (baseboard) round the room; architraves (casings) not counted, 13.4 m; Skip (dumpster) or muck away for the spoil, 1.5 m³; Skip or bags for the offcuts and packaging, 1.5 m³. Opened at Length, along the front 13 ft · Depth, front to back 10 ft · Height clad outside 8 ft · Room height, floor to ceiling 7 ft · Wall thickness, sheathing to lining 4.75 in · Roof overhang, each edge 6 in · Door opening width 5 ft · Door opening height 6.5 ft · Windows 2 · Window opening width, each 3 ft · Window opening height, each 3.5 ft · Supply cable route, house to room 49 ft · Cable trench depth 2 ft · Dig over the footprint 4 in · Membrane turned over each roof edge 4 in: Turf, topsoil and ground dug out over the footprint, 2.01 yd³; Concrete for the piers, 1.1 yd³; Weed membrane and stone laid in the dig (gravel or hardcore), 2.98 tons; Floor insulation boards, cut between the joists, 5 sheets (4x8 ft); Wall studs, the walls' frame (studwork), 53 studs; Sheathing on the walls, OSB or plywood, 13 sheets (4x8 ft); Roof deck, OSB or plywood, 6 sheets (4x8 ft); Rigid insulation boards, warm roof, 6 sheets (4x8 ft); EPDM membrane over the roof, 1 roll; Gutter and downpipe (downspout) along the eaves, 2 x 10 ft sections; Breather membrane (house wrap) on the walls, 1 roll; Flashing tape round the door set's opening, 31.9 ft; Flashing tape round each window opening, 41.8 ft; Furring (battens) fixed upright on the walls, 288 ft; Siding (cladding): lap or plank, vinyl, wood or fibre cement, 3.49 squares; Trims outside: corners, heads and reveals, 8 sheets; Mastic (caulk) round the openings, 0.16 gal; Exterior stain or paint on the clad walls, 2.5 gallons; Trench for the supply cable, dug and backfilled, 4.11 yd³; Insulation batts, walls, 6 packages; Vapour control layer on the walls, 1 roll; Ceiling board (plasterboard or drywall), 4 sheets; Board on the walls inside (plasterboard or drywall), 9 sheets; Joint compound (mud), walls and ceiling, 1 x 4.5 gal box; Joint tape, walls and ceiling, 228 ft; Paint on the walls inside, 1.23 gal; Paint on the ceiling, 0.56 gal; Laminate or vinyl plank floor, 6 packs; Skirting (baseboard) round the room; architraves (casings) not counted, 43.9 linear ft; Skip (dumpster) or muck away for the spoil, 2.01 yd³; Skip or bags for the offcuts and packaging, 1.97 yd³. Every figure follows the dimensions you give it.
- Which calculators does the garden room takeoff run?
- 25 calculators, for 31 lines: Trench Excavation & Backfill Volume Calculator, Circular Pier / Cylinder Concrete Calculator, Gravel Base Layer Tonnage Calculator, Foam Board Insulation Calculator, Framing Stud Calculator, Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof), EPDM Single-Ply Roofing Roll Calculator, Gutter Calculator, House Wrap Calculator, Window Opening Flashing Membrane Calculator, Rain-Screen Cladding Furring Strip Calculator, Siding Calculator, Exterior Flashing Layout Trim Sheet Calculator, Fiber-Cement Siding Caulk Joint Volume Calculator, Exterior Paint Calculator, Mineral Wool Insulation Batt Calculator, Vapor Barrier Calculator, Ceiling Plasterboard Calculator (Gypsum Board Sheets), Drywall Joint Compound Calculator, Drywall Joint Tape Calculator, Paint Calculator, Ceiling Paint Calculator, LVP, Laminate & Engineered Floor Calculator, Baseboard & Trim Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.23 calculators, for 30 lines: Trench Excavation & Backfill Volume Calculator, Gravel Base Layer Tonnage Calculator, Foam Board Insulation Calculator, Framing Stud Calculator, Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof), EPDM Single-Ply Roofing Roll Calculator, Gutter Calculator, House Wrap Calculator, Window Opening Flashing Membrane Calculator, Rain-Screen Cladding Furring Strip Calculator, Board and Batten Siding Calculator, Exterior Flashing Layout Trim Sheet Calculator, Fiber-Cement Siding Caulk Joint Volume Calculator, Exterior Paint Calculator, Mineral Wool Insulation Batt Calculator, Vapor Barrier Calculator, Ceiling Plasterboard Calculator (Gypsum Board Sheets), Skim Coat Plaster Calculator, Paint Calculator, Ceiling Paint Calculator, LVP, Laminate & Engineered Floor Calculator, Baseboard & Trim Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
- What does the garden room takeoff leave out?
- 11 things, each named on this page: What the base and the frame must be to carry the room; Planning; Whether the house's main board (service panel) has the capacity for the room's circuit, the cable's size and protection, and the earthing arrangement at the room; A water supply, a toilet, a sink or a shower in the room, and any foul drainage from it; Whether a soakaway (a dry well) will drain in the ground and how big it must be, where the downpipe runs to one; the drain run to it is listed as work, not measured; Decking, a veranda, steps up to the door, and a path from the house; Choosing the door set and the windows; Heating, cooling or mechanical ventilation for the room; Architraves (casings) round the door set and the windows, and any window boards (stools): fixed with the skirting as its work, and not counted; The roof's fall; A roof covered in anything but a single EPDM sheet.
- Can I check a quote for this job against the takeoff?
- Yes. The garden room quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.