Basement or cellar conversion takeoff

Turn a cellar or basement into a habitable room: strip it out, keep water out with a drained cavity membrane, a barrier coating or both, insulate and line the walls on studs or with boards, board the ceiling as a fire separation, finish and decorate, with any underpinning, lowering, new slab and escape window listed and never sized.

Measurements in
6
Trades out
1312
Calculators
1211
Going in
1312of 1312
My Project
Not in it

No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.

Dimensions

Give the job once

Every figure on the right follows these, in the units you choose.

Step 1 of 2

Choose the build-up

Each layer changes the materials below; the dimensions stay the same.

Floor
Keeping water out
Wall lining
Walls and ceiling finish
Floor finish
Floor
Keeping water out
Wall lining
Walls and ceiling finish
Floor finish

Every trade, from those dimensions

then change a dimension, and each line shows what moved.

Every trade's quantity · 13 rows

13 of 13 going in
ItemQuantityOrderWaste / allowance
Skip (dumpster) for the strip-out4.62 yd³4.62 yd³no pack size recordednone
Drainage channel round the room's edge (interior drain tile)7 segments7 segmentsalready wholenone
Floor insulation boards, under the finished floor9 sheets (4x8 ft)9 sheets (4x8 ft)already whole10%
Studs or battens for the stand-off wall62 studs62 studsalready whole10%
Insulation batts between the studs9 packages9 packagesalready whole5%
Ceiling board, the fire separation (plasterboard or drywall)8 sheets8 sheetsalready whole10%
Drywall (plasterboard) on the new walls15 sheets15 sheetsalready whole10%
Joint compound (mud) over the new board2 x 4.5 gal boxes2 x 4.5 gal boxesalready whole10%
Joint tape over the new board375.98 ft375.98 ftno pack size recorded10%
Paint on the walls2.14 gal2.14 galno pack size recordednone
Paint on the ceiling1.14 gal1.14 galno pack size recordednone
Laminate or vinyl plank floor11 packs11 packsalready whole7%
Skirting (baseboard)64.77 linear ft64.77 linear ftno pack size recorded10%

Every trade's quantity · 12 rows

12 of 13 going in
ItemQuantityOrderWaste / allowance
Skip (dumpster) for the strip-out3.6 m³3.6 m³no pack size recordednone
Drainage channel round the room's edge (interior drain tile)7 segments7 segmentsalready wholenone
Floor insulation boards, under the finished floor10 sheets (2400x1200 mm)10 sheets (2400x1200 mm)already whole10%
Studs or battens for the stand-off wall62 studs62 studsalready whole10%
Insulation batts between the studs10 packages10 packagesalready whole5%
Ceiling board, the fire separation (plasterboard or drywall)9 sheets9 sheetsalready whole10%
Drywall (plasterboard) on the new walls16 sheets16 sheetsalready whole10%
Skim (finish plaster) over the new board178.54 kg178.54 kgno pack size recorded15%
Paint on the walls8.09 L8.09 Lno pack size recordednone
Paint on the ceiling4.33 L4.33 Lno pack size recordednone
Laminate or vinyl plank floor11 packs11 packsalready whole7%
Skirting (baseboard)19.95 m19.95 mno pack size recorded10%

Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.

1312 of 13 trades12 trades chosenNot pricedNot in project
Kept on this deviceUnitsImperialMetricMy Projectnot in it yetQuantities only · your own rates · not a structural check

About this job

A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.

Turning a cellar into a room is first a question of water. Its walls and floor sit below the ground outside, the soil against them is often damp and after heavy rain can be wet, so how the room is kept dry is decided before any lining is bought. In the UK that decision follows BS 8102, which names three kinds of protection: a barrier bonded to the walls and floor (Type A, tanking), a structure watertight in itself (Type B), and a drained cavity that lets water through the wall and carries it away (Type C). In North America the same choice is between a waterproofing coating and an interior drain tile behind a dimple membrane, draining to a sump.

This page offers the two a conversion can add from inside, and both together, and opens on the drained cavity. The studded membrane goes over the walls and floor on sealed plugs, a channel round the floor's edge carries what it collects to a sump, and a pump lifts it out: the channel is counted, and the membrane, the sump and the pump are listed as work, because their layout and the pump's duty are the designer's. A barrier coating is laid on masonry cleaned back to the bare wall, so hacking off the old plaster is part of it, and it is counted by the litre over the walls and the floor. Which of these a given cellar needs, and the grade of protection its use calls for, the page flags for the designer and never chooses.

Headroom comes next. Where the floor has to go down to give it, the walls are underpinned and the floor dug out in the order an engineer's scheme sets, which this page lists as provisional work and never sizes, stopping at the formation level; a new slab on a stone bed is then one choice in the build-up. A cellar with height enough keeps its slab and gives a little of that height to the new floor instead.

Inside the waterproofing, the walls are lined either with a stud wall standing clear of the membrane, insulated between its studs, or with insulation boards fixed to the wall, and the floor is insulated under a screed or a floating board floor. The ceiling is boarded as the fire separation from the rooms above, and the units pick the finish: board skimmed in plaster in metric, taped and finished drywall in imperial. A room below ground that people use also needs a way out in a fire, an escape (egress) window with a well outside it or a protected route up the stair, smoke alarms, and a carbon monoxide alarm where the rules ask for one; each is listed as work.

How each line reads

Base
What the calculator gives for these dimensions, before anything is added.
Allowance
Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
Adjusted
The base with its allowance on top.
Order
What to buy: the adjusted figure in whole boards, bags, rolls or lengths.

The order this happens in

Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.

  1. Have the waterproofing designed and any underpinning or lowering schemed by an engineer, serve the party wall notices where a wall is shared, notify building control or take out the permit, and have old lagging, pipe insulation or boarded linings surveyed for asbestos before they are touched.
  2. Protect the way down through the house, isolate the circuits and water that run through the cellar, and strip out the shelving, coal bunkers, old linings and redundant pipes and cables into the skip.
  3. Where the floor goes down, prop and underpin the walls in the engineer's sequence, dig out to formation, and lay the stone bed and the new slab.
  4. Cut the escape window's opening and set its lintel while the walls are bare; then hack off the old plaster and coat the walls and floor where the design has a barrier, and cut the drainage channel round the floor's edge, sink the sump chamber and fix the cavity drain membrane where it has a drained cavity.
  5. Insulate the floor and lay the screed or the floating floor over it, then build the stand-off stud walls clear of the membrane, or fix the insulation boards to the walls, with every fixing through the membrane sealed as its maker details.
  6. Run the first-fix cables and pipes, fire-stop every service through the ceiling, insulate between the studs, fix the vapour control layer where the design calls for one, then board the ceiling and the walls and skim or tape them.
  7. Let the room dry with air moving through it, decorate, lay the floor, fit the skirting, the doors and the stair's handrail, and connect the extract, the radiator and the alarms; wire the pump, fill its chamber and watch it start, discharge and raise its alarm.
  8. Test the electrics, commission the extract, have the completion inspection, and hand over the waterproofing guarantee with the pump's test record and the instructions for keeping the drainage clear.

What this takeoff does not cover

  • Choosing the system and the grade: which kind of protection the room needs, and the grade its use calls for under BS 8102 in the UK or the code's dampproofing provisions in North America, are the designer's to decide. The page offers each system as a build-up, chooses none, and counts what the chosen one asks for.
  • Underpinning, lowering the floor and the new slab's design: the engineer's scheme, the depth dug, the spoil from it and the old slab broken out are part of a provisional item, and the page stops at the formation level the new slab is laid on. A wall shared with a neighbour brings a party wall award in England and Wales.
  • Anything done to the walls' outside face from a dig in the garden, such as a sheet bonded to it under a protection board: every row here works from inside the cellar.
  • Radon. Where the house is in a radon-affected area in the UK, or a test under US EPA guidance finds a raised level, a barrier or a sump and fan beneath the floor is needed; no row covers it.
  • Flood protection, and the pump's duty, a second pump or battery backup, and where the discharge goes, beyond listing the sump and pump as work.
  • The stair's geometry, headroom and guarding, and the fire separation's specification: the stair, the handrail and guarding and the fire doors are listed as work where they are needed, and building control or the code sets each.
  • Heating a room below ground: whether the boiler or heat pump can serve a circuit carried down the stair, and how large a radiator on a lined wall must be for a room with earth behind two or more of its walls, which the heating engineer works out.
  • Moving a gas or electricity meter, the boiler or the consumer unit (service panel) out of the cellar.
  • The floor's screed or floating board floor as a quantity, and where any vapour layer is placed: each follows the build-up the designer sets, and is listed as work.

Labour by trade

Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.

Metric opening

Length, wall to wall 6 m · Width, wall to wall 4 m · Height, floor to the joists above 2.3 m and 3 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer12 h (6.2–32)1½ days
Waterproofing operative1 waterproofing operative + 1 labourer24 h (5.0–60)1½ days
Carpenter2 carpenters14 h (7.7–29)1 day
Drywaller1 drywaller + 1 labourer8.0 h (4.5–15)half a day
Plasterer1 plasterer11 h (6.2–22)1½ days
Painter1 painter11 h (6.2–25)1½ days
Floor layer1 floor layer6.1 h (3.2–12)1 day
In all86 h (39–194)8 days

Imperial opening

Length, wall to wall 19.5 ft · Width, wall to wall 13 ft · Height, floor to the joists above 7.5 ft and 3 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer12 h (6.1–31)1½ days
Waterproofing operative1 waterproofing operative + 1 labourer24 h (5.0–59)1½ days
Carpenter2 carpenters14 h (7.6–29)1 day
Drywaller1 drywaller + 1 labourer7.4 h (4.1–14)half a day
Taper1 taper + 1 labourer9.8 h (5.5–20)half a day
Painter1 painter11 h (6.1–24)1½ days
Floor layer1 floor layer5.9 h (3.2–12)half a day
In all83 h (38–189)7 days

Quote check

Been given a quote for this job?

Paste it into the basement conversion quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.

  • What it leaves out

    Every line this takeoff has that nothing on the quote reads as.

  • What it adds

    Labour, removal, hire, fees — each named for what it is.

  • What to ask

    One list of questions, ready to copy. Never a verdict.

More takeoffs

Other job takeoffs

All job takeoffs

Frequently asked questions

What does the basement conversion takeoff give for a typical job?
Opened at Length, wall to wall 6 m · Width, wall to wall 4 m · Height, floor to the joists above 2.3 m · Lining depth, old wall to new face 120 mm · Doors 1 · Windows 1, it orders: Skip (dumpster) for the strip-out, 3.6 m³; Drainage channel round the room's edge (interior drain tile), 7 segments; Floor insulation boards, under the finished floor, 10 sheets (2400x1200 mm); Studs or battens for the stand-off wall, 62 studs; Insulation batts between the studs, 10 packages; Ceiling board, the fire separation (plasterboard or drywall), 9 sheets; Drywall (plasterboard) on the new walls, 16 sheets; Skim (finish plaster) over the new board, 179 kg; Paint on the walls, 8.09 L; Paint on the ceiling, 4.33 L; Laminate or vinyl plank floor, 11 packs; Skirting (baseboard), 20 m. Opened at Length, wall to wall 19.5 ft · Width, wall to wall 13 ft · Height, floor to the joists above 7.5 ft · Lining depth, old wall to new face 4.75 in · Doors 1 · Windows 1: Skip (dumpster) for the strip-out, 4.62 yd³; Drainage channel round the room's edge (interior drain tile), 7 segments; Floor insulation boards, under the finished floor, 9 sheets (4x8 ft); Studs or battens for the stand-off wall, 62 studs; Insulation batts between the studs, 9 packages; Ceiling board, the fire separation (plasterboard or drywall), 8 sheets; Drywall (plasterboard) on the new walls, 15 sheets; Joint compound (mud) over the new board, 2 x 4.5 gal boxes; Joint tape over the new board, 376 ft; Paint on the walls, 2.14 gal; Paint on the ceiling, 1.14 gal; Laminate or vinyl plank floor, 11 packs; Skirting (baseboard), 64.8 linear ft. Every figure follows the dimensions you give it.
Which calculators does the basement conversion takeoff run?
12 calculators, for 13 lines: Skip & Dumpster Size Calculator, Perimeter Weeping Tile Pipe Segment Calculator, Foam Board Insulation Calculator, Framing Stud Calculator, Mineral Wool Insulation Batt Calculator, Ceiling Plasterboard Calculator (Gypsum Board Sheets), Drywall Joint Compound Calculator, Drywall Joint Tape Calculator, Paint Calculator, Ceiling Paint Calculator, LVP, Laminate & Engineered Floor Calculator, Baseboard & Trim Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.11 calculators, for 12 lines: Skip & Dumpster Size Calculator, Perimeter Weeping Tile Pipe Segment Calculator, Foam Board Insulation Calculator, Framing Stud Calculator, Mineral Wool Insulation Batt Calculator, Ceiling Plasterboard Calculator (Gypsum Board Sheets), Skim Coat Plaster Calculator, Paint Calculator, Ceiling Paint Calculator, LVP, Laminate & Engineered Floor Calculator, Baseboard & Trim Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
What does the basement conversion takeoff leave out?
9 things, each named on this page: Choosing the system and the grade; Underpinning, lowering the floor and the new slab's design; Anything done to the walls' outside face from a dig in the garden, such as a sheet bonded to it under a protection board; Radon; Flood protection, and the pump's duty, a second pump or battery backup, and where the discharge goes, beyond listing the sump and pump as work; The stair's geometry, headroom and guarding, and the fire separation's specification; Heating a room below ground; Moving a gas or electricity meter, the boiler or the consumer unit (service panel) out of the cellar; The floor's screed or floating board floor as a quantity, and where any vapour layer is placed.
Can I check a quote for this job against the takeoff?
Yes. The basement conversion quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.