The board in your hand is the right board for the wrong plane
Pull one panel off a sloping ceiling in an old room-in-the-roof and put a tape in the rafter. A nominal 100 measures 97, sometimes 95, and on a roof built before regularised sawing it will change by five millimetres between one bay and the next. The 100 mm sheet of foil-faced board leaning against the dwarf wall was bought to fill that rafter, and it cannot, because fifty of those ninety-seven are already spoken for by moving air. That sheet has a job on this roof. Its job is under the rafters, not between them.
A sloping ceiling is the tightest thermal envelope in a house because both of its faces are pinned. Above it are battens, underlay and a covering nobody is lifting unless the roof is coming off anyway. Below it is a finished line that decides whether the room is legal to stand up in, and where the slope dies into the dwarf wall. Unlike a loft deck, depth cannot be bought here by piling more on: every millimetre added on the warm side is a millimetre taken permanently out of the room, and the person taking it is standing in the room while they do it.
So the job is a subtraction before it is an insulation job - written down in millimetres down the rake before a single sheet is ordered. What the air path takes, what the rafter leaves, what the continuous layer has to make up, what the finish and the services add back. Get that column of figures on paper and every product decision after it becomes obvious. Skip it, buy the thickness that was on offer, and the first thing to go wrong is the thing nobody can see until a winter has been through it.
The subtraction this page is about, run in one pass: the target U-value, a ceiling's upward heat flow, the airway above treated as a well-ventilated layer, the resistance already in the rafter bay and the board's conductivity give the continuous layer's thickness. For the 0.18 target over 50 mm (2 in) of board between the rafters it comes to 68 mm (2.7 in) — the surface films included, which the depth budget further down leaves out.
The U-value the element has to reach, from the regulation or specification for this job.
Sets the internal surface resistance, which depends on which way the heat is flowing.
A well-ventilated cavity counts for nothing, and nor does anything outside it.
Everything in the construction except the new insulation and the two surface films, added together.
The declared conductivity on the product's certificate, at the thickness you are buying.
The thickness you can actually buy, to see the U-value it reaches with the rest of the construction.
Insulation thickness needed
4.232 in
Thickness = (1 ÷ U − the two surface resistances − the other layers) × λ: the layer sum of BS EN ISO 6946 run backwards.
- Total resistance the target asks for (1 ÷ U)
- 31.55 hr·ft²·°F/BTU
- Internal surface resistance
- 0.74 hr·ft²·°F/BTU
- External surface resistance
- 0.23 hr·ft²·°F/BTU
- The other layers
- 2.84 hr·ft²·°F/BTU
- Resistance the insulation has to supply
- 27.74 hr·ft²·°F/BTU
They open the calculator with your figures already in it
Insulation Thickness for a Target U-Value Calculator (BS EN ISO 6946): 4.23 in — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Add the equipment this sizes
This result is a specification — 4.232 in — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.
What this calculation does not cover
- A layer bridged by timber or steel — insulation between rafters, studs or joists — is worth less than its full resistance, because the framing carries heat around it. BS EN ISO 6946 averages the two paths with its upper and lower limit method; enter the bridged layer's reduced figure, or use the thermal bridging calculator for it.
- A floor on the ground loses heat in a way that depends on its exposed perimeter as well as its layers, calculated to BS EN ISO 13370. This page gives the thickness the layers need, not the ground floor's U-value.
- The corrections of BS EN ISO 6946 Annex F — for air gaps in the insulation layer, mechanical fixings through it and rain on an inverted roof — are not applied.
- The target comes from the regulation or specification for the job, and the conductivity from the product's own certificate; neither is supplied here.
The air path is spent before anything else gets any
In a cold roof with a ceiling that follows the pitch, the ventilation gap is not slack in the detail. It is a designed cross-section running from an inlet at the eave, up the full length of every rafter bay, to an outlet at high level, and it does one thing: it carries away moisture that got past the ceiling before that moisture reaches a cold underlay and turns into water. It is the first claim on the rafter depth and it does not trade against a better U-value, because the two failures are not comparable. An under-insulated slope costs money every winter. A blocked one rots the rafter feet and stains the ceiling, and by the time it shows, the plasterboard is on.
What sets the figure is the document adopted at the address, not habit. In the UK, BS 5250, Management of moisture in buildings - Code of practice, is what a building control officer will be working from for a roof where the ceiling follows the pitch; 50 mm free above the insulation, with a continuous inlet at the eave, is the detail most UK roofers have in their hands, and the current edition is where to confirm it. In North America the International Residential Code, Section R806, Roof Ventilation, requires a clear space between the insulation and the roof sheathing in a vented rafter assembly, with a minimum of one inch, and pairs it with a required net free ventilating area for the space as a whole and a split between the low- and high-level openings. Different numbers, same subtraction: whatever the clear dimension is, it comes off the rafter first.
A gap only exists if something physically holds it open. Rigid chutes stapled to the rafter sides, running from behind the eave inlet up past where the insulation will stop, are the whole of that job, and they have to go in before any insulation, because once a bay is full there is no way to slide one up it. Two details decide whether they survive: they need fixing to the rafter sides rather than to the underlay, and they need to start low enough that the eave inlet is behind them rather than under the first sheet of board. And the path needs somewhere to go at the top. A 50 mm channel that arrives at a sealed ridge, or dies into a collar with the flat ceiling insulated across it, is a stripe of cold air with no exit and it will condense at its top end.
Chutes go in first and get bought first, so the bay count off the eave run is the number that has to be right before anyone is on a ladder with a staple gun. Its spacing field offers 400 and 600 centres only, so a roof that measures neither goes through the second counter further down instead.
The length of the eave line where rafter bays need baffles.
The on-center spacing between rafters.
Baffle vents needed
30 baffles (one per rafter bay)
- Attic width
- 39 linear ft
They open the calculator with your figures already in it
Attic Baffle Vent Calculator: 30 baffles (one per rafter bay) — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- The figure covers one eave line, because that is the only length asked for. A gable roof carries a soffit down each long side and needs the calculation run for each, so the 30 baffles returned for a 12 m eave at 16 in centres is 60 for the pair, and a hipped roof has eave on all four sides.
- The result counts bays, not the number of baffle sections a bay swallows. Rafter baffles are commonly sold in sections of about 1.2 m (4 ft), enough to carry the channel over the top plate and the first stretch of loft insulation, so where the vented channel must continue up the rafter — the vaulted assembly described in the FAQ, running soffit to ridge — a 4 m rafter run takes three or four sections in every bay and the quantity to order is that multiple of the number shown.
- Baffles protect an airflow path; they do not create one. Nothing here tests whether the soffit actually has vents in it, or whether their net free area meets the 1:150 or 1:300 attic rule, and a baffle fitted above a solid soffit or an uncut sheathing panel achieves nothing. Intake area also has to be balanced against ridge or gable exhaust before the channel will draw.
- The count says nothing about the depth of the channel a baffle holds open or its height above the finished insulation. A minimum clear air gap between the baffle and the underside of the sheathing is normally required — one inch is the figure most often quoted, but the clearance that applies is set by the code in force — and at a shallow eave that gap plus full insulation depth may not fit beneath the rafter at all, which is a raised-heel truss or insulation-depth question rather than a baffle-count one.
- Dividing the eave length by the rafter spacing assumes parallel, uninterrupted bays for the whole run. Hip corners with jack rafters, dormers, valleys, chimneys and the bay that dies against a gable wall all break that pattern, and the number neither removes bays with no soffit vent below them nor adds the short jack-rafter bays a hip creates.
Run the target backwards before choosing a thickness
Consent is granted against a U-value. Merchants sell millimetres. Convert once, at the very start, and carry a resistance figure around for the rest of the job instead of a transmittance. The unit trap on that conversion is worth stating flatly, because it is a factor of nearly six rather than a rounding error: a metric U-value in W/m²K and an imperial one in BTU/hr·ft²·°F differ by about 5.678. A target of 0.18 W/m²K is 0.0317 in imperial units, whose reciprocal is about R-31.5 hr·ft²·°F/BTU, the same assembly as 5.56 m²K/W. Divide the metric figure by 5.678 before it goes anywhere near an imperial calculator, or the answer comes back roughly five times too flattering and looks entirely plausible on the way past.
Which target applies is a question with a local answer. In England, Approved Document L, Conservation of fuel and power, Volume 1: Dwellings, sets the standards, and a room in the roof lands in a different row depending on whether the element counts as new, as a change of use, or as a retained element being upgraded, with the edition in force at the date of application deciding all of it. In the United States the International Energy Conservation Code and the IRC set it by climate zone. Take the number off the paperwork for this address, and treat any figure quoted in an article - the 0.18 used as arithmetic above included - as an example rather than as your requirement.
This is the one conversion that has to happen before any product is chosen, and it takes an imperial U-value, so a specification written in W/m²K goes through the 5.678 division first.
The assembly's thermal transmittance, as specified.
Equivalent R-value
20 hr·ft²·°F/BTU
R = 1 ÷ U, the exact inverse relationship. The result is the whole assembly's resistance — subtract the other layers before choosing an insulation thickness.
They open the calculator with your figures already in it
U-Value to R-Value Calculator: 20 hr·ft²·°F/BTU — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Add the equipment this sizes
This result is a specification — 20 hr·ft²·°F/BTU — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.
What this calculation does not cover
- The conversion is arithmetic and takes the U-value at face value. It does not check that you have the right figure for the element: a window's whole-unit U-factor, its centre-of-glass value and its frame value are three different numbers, and only the whole-unit one describes what the opening actually loses.
- The field is imperial only, and the site's metric/imperial toggle does not convert it. A W/m2K figure typed in unchanged returns the metric resistance in m2K/W, which is about a fifth of the imperial R the result is labelled as. Divide a metric U-value by 5.678 before entering it.
- Thermal bridging is not in the number. A U-value quoted for a clear-wall build-up excludes studs, joists, rim boards, lintels and junctions, so the R returned describes the insulated bay rather than the whole element.
- This is not a code compliance check. It does not test the figure against any energy code's prescriptive U-factor or R-value tables, and it does not perform the area-weighted or trade-off calculation a submission needs.
- Steady-state conduction only: no air leakage, no thermal mass, no moisture. Insulation that is compressed, wind-washed or damp delivers less than its rated R, and a reciprocal cannot show that.
Building regulations and window schedules are written as maximum U-values, while insulation on a merchant's shelf is labelled in R, so specifying to a regulation means crossing between them. The arithmetic is a reciprocal and takes a second. The two traps are unit systems and scope. A metric U-value in watts per square metre kelvin is roughly 5.68 times its imperial counterpart, and mixing them produces an assembly that appears five times better insulated than it is. And the converted R covers the entire build-up, not the insulation alone: sheathing, cladding, internal linings and surface films all contribute, so the product you buy only needs to close the remaining gap.
Writing the depth budget down
With the air path fixed and the target expressed as resistance, the rest is a column of subtractions, written in the order the layers sit down the rake so that the continuous layer stops being the afterthought that gets thinner every time the headroom argument comes up. Two figures feed it and both belong on a document rather than in anyone's memory. The first is the declared thermal conductivity of whatever board or wool is going in: rigid polyisocyanurate is commonly declared around 0.022 W/m·K, mineral wool between roughly 0.032 and 0.044 depending on density and product line, and the value that counts is the one on that product's certificate at that thickness. The second is the rafter, which is timber and conducts like timber - softwood at about 0.13 W/m·K puts a 100 mm rafter near 0.77 m²K/W, or about R-4.4, almost exactly what a 2x4 stud is worth in a wall.
Run those through the assembly and the shape of the problem appears immediately. Fifty millimetres of board at 0.022 is about 2.27 m²K/W. Against a 5.56 target that leaves roughly 3.3 still to find, which is another 72 mm of the same board, and it has to be continuous under the rafters because there is nowhere else for it. Add plasterboard, and a service batten if the specification has one, and the finished ceiling has come down somewhere between 85 and 110 mm from the underside of the rafter. That is the real cost of the job and it belongs in the conversation with the owner before the order is placed, not after the first ceiling is up and somebody notices the door head.
One arithmetic caution when totalling layers: internal and external surface resistances are part of the assembly and are worth having, but they are worth having once. The calculator below adds a combined air film allowance of R-0.85 - about 0.15 m²K/W - on top of the layers entered, so put materials in its three layer fields and let it supply the films rather than spending a field on them. Those three fields are imperial R and do not follow the metric toggle, which makes them the second place the 5.678 factor bites: every metric resistance above goes through it on the way in, so 2.27 m²K/W is typed as 12.9 and a 5.56 target is R-31.5.
| Down the rake | Depth it takes | What fixes that depth |
|---|---|---|
| Ventilated air path | 50 mm in the usual UK detail; 1 in (25 mm) minimum under the IRC | The ventilation provision in force, held open by a chute in every bay |
| Insulation between the rafters | Whatever the rafter has left after the air path | Measured rafter depth minus the gap - not the nominal size |
| The rafters | Full depth, at every centre, plus every trimmer | Timber conducts; this is the parallel path, not part of the insulation |
| Continuous layer under the rafters | The shortfall multiplied by the board's declared conductivity | The target resistance, less whatever the between-rafter layer delivered |
| Service batten or counter-batten | 0 mm, 25 mm or 38 mm | Whether cables, downlights and a shower feed are allowed to cross the vapour layer |
| Plasterboard and skim | 12.5 mm plus 2 to 3 mm | The finish, and the lining the conversion needs in its own right |
Total the layers as a stack rather than judging them one at a time, because the between-rafter board and the continuous board are only meaningful added together against the target.
The R-value of your main insulation layer, printed on the product.
The R-value of a second layer, like exterior sheathing.
The R-value of interior finish material, like drywall (typically about R-0.45 for 1/2 in).
Total assembly R-value
15.8 R-value
- Sum of material layers
- 14.95 R
- Air film allowance
- 0.85 R
They open the calculator with your figures already in it
R-Value Calculator: 15.8 R-value — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Add the equipment this sizes
This result is a specification — 15.8 R-value — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.
What this calculation does not cover
- Layers are summed straight through the insulated cavity. Studs, joists, plates, headers and rim areas conduct several times faster than the insulation between them and are not deducted here, so the real whole-wall or whole-ceiling figure is lower than this total. Run the Thermal Bridging Effective R-Value Calculator on the same wall to see by how much.
- The figures are imperial R-values in hr·ft²·°F/BTU, and so is the fixed R-0.85 air film allowance. Metric RSI values in m²K/W are about 5.68 times smaller, so entering those makes the film allowance alone roughly six times too generous. Convert before you type.
- The air film allowance is one fixed number written for a wall: still indoor air with sideways heat flow, and an outside face exposed to wind. It does not change for heat flowing up or down, for a surface facing a vented attic or an enclosed crawl space, or for a reflective low-emissivity face, all of which shift the film values.
- Product R-values are lab ratings for material at full thickness with no gaps. Batts compressed under wiring, voids at plates and corners, and loose fill that has settled all deliver less than the printed number, and nothing here downgrades the total for installation quality.
- R-value covers conduction only. It says nothing about air leakage, wind washing through the insulation, or moisture in the assembly, and this total is not a code compliance check: the required figure depends on climate zone and on which element you are building, and codes are frequently verified against a whole-assembly U-factor that includes the framing this sum leaves out.
Cutting board into a roof that was never square
Between-rafter board is measured bay by bay and cut bay by bay. Sawn rafters were never a parallel set, they have twisted since, and a roof carrying a purlin or a valley has bays that change width over their own length. Cut one template and repeat it and the slope fills with two-millimetre stripes that are, thermally, slots. Measure top and bottom of each bay, cut two or three millimetres oversize for a friction fit, and seal every piece's perimeter with foam or a compatible tape as it goes in - in a roof this thin the perimeter seal does as much work as the board face.
Ordering surprises people, because this layer is bought as full sheets and used as strips. A sheet ripped into bay-width pieces leaves a last rip that fits nothing, so the waste allowance is meaningfully higher than on a flat wall, and it climbs again on a roof with dormers, a valley or a roof window where a high proportion of pieces are one-offs. Count in sheets, then check the count against the bay schedule rather than against slope area. Rigid polyurethane and polyisocyanurate boards are specified under BS EN 13165, Thermal insulation products for buildings - Factory made rigid polyurethane foam (PU) products - Specification, and ASTM C1289, Standard Specification for Faced Rigid Cellular Polyisocyanurate Thermal Insulation Board; the facer named on that certificate matters twice, once for conductivity and again for vapour resistance.
Foam plastic in an occupied room needs its thermal barrier, and here the plasterboard is that barrier. A slope insulated and left unlined over a weekend is a genuinely different fire risk from one insulated and boarded the same day, which is worth saying out loud to whoever is sleeping in the house during the works. Confirm the lining against the board manufacturer's certificate, which names the thickness and the lining it was tested behind.
The slope, taken apart
- Slates or tiles on battens — the layer nobody is lifting unless the roof is already off, which is exactly why the depth budget starts from the rafter rather than from the outside face Roof Batten Spacing Calculator (Tile Roofing)
- Roofing underlay — an old bitumen felt is a vapour barrier sitting on the cold side, which is the reason the air path beneath it cannot be traded away for thickness
- The ventilated air path — a designed cross-section from the eave inlet to a high-level outlet, existing only for as long as a chute in each bay physically holds it open Attic Baffle Vent Calculator
- Board cut between the rafters — measured and cut bay by bay because sawn rafters are not a parallel set, then perimeter-sealed, and bought as full sheets used as strips Foam Board Insulation Calculator
- The rafters themselves — roughly a tenth of the ceiling area carrying a path of solid timber from the cold side to the warm side at every single centre Thermal Bridging Effective R-Value Calculator
- Continuous board and plasterboard beneath — the only layer that crosses the rafters, which makes it both the shortfall-filler and the bridge repair, and every millimetre of it comes out of the room Ceiling Plasterboard (Gypsum Board) Sheet Calculator
Both board layers get ordered here, in sheets. Its waste allowance is a fixed ten per cent with no field to raise it, so the between-rafter half goes in as an area already inflated for the rips that fit nothing rather than as the measured slope.
SettingsSettings for this calculation
The standard allowance most suppliers and estimating guides assume for ordinary work.
The total wall, foundation, or roof deck area to cover.
Offcuts from fitting boards between framing, around openings and at corners.
Foam board sheets needed
15 sheets (4x8 ft)
- Area to cover (with waste)
- 473 sq ft
They open the calculator with your figures already in it
Foam Board Insulation Calculator: 15 sheets (4x8 ft) — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- This counts sheets to cover an area. It does not choose a thickness or R-value, check your climate zone's requirement for continuous insulation, or confirm the board's compressive strength grade suits a load-bearing position under a slab or screed.
- The count is for a single layer. A staggered two- or three-layer build-up is a separate full-area order for each layer, so run the area through once per layer rather than entering the combined thickness.
- The waste allowance is a flat uplift on area, not a cutting layout. Rafter bays, hips, curved walls and dense penetrations throw off more offcuts than that, and offcuts from one bay are often unusable in the next. A wall whose window and door openings you did not deduct is over-ordered by roughly their area.
- It assumes every board is the market's standard full sheet. It does not cover the 2 ft wide XPS or 1200 x 600 mm half boards some ranges are sold in, and it does not deduct the overlap on tongue-and-groove or shiplap edges, which cover less than the board's nominal face area.
- Nothing beyond the boards is counted: seam tape, adhesive or foam, fixings and washers sized to the board thickness, furring, and any separate vapour or air control layer. Rigid foam is also combustible, and building codes generally require a thermal or ignition barrier between it and an occupied space. This calculator neither sizes nor includes that.
What the timber takes back
Nothing installed between the rafters improves the rafters. At 400 centres a 47 mm rafter is a little under twelve per cent of the ceiling area; at 600 centres, closer to eight. Those are the clean numbers, and a conversion is rarely clean: add trimmers around a roof window, valley timbers, a dormer's cheeks, the purlin and its struts, the collar and the doubled rafters either side of an opening, and the timber fraction climbs back towards what a stud wall carries. Count the timber on the actual slope, from the survey.
Put representative figures through the parallel-path arithmetic and the size of it stops being arguable. Fifty millimetres of board between the rafters is about R-13 in imperial terms, the 100 mm rafter beside it about R-4.4, and at twelve per cent framing the two together come out near R-10.5 rather than R-13. Close to a fifth of the between-rafter layer is handed back by the timber, and it is handed back regardless of which board went in the bay - which is the argument for the continuous layer stated as a number instead of as a principle. Parallel path is a simplification and says so; the version to defend a submission with is the combined method in BS EN ISO 6946, Building components and building elements - Thermal resistance and thermal transmittance - Calculation methods, with junction losses handled under BS EN ISO 10211.
One practical note on the calculator below: its framing fraction floors at 0.10, and a disciplined 600-centre roof with nothing in it genuinely sits under that. Check whether the slope really is that clean before taking the benefit - a single valley usually spends it.
This is the number that decides how thick the under-rafter layer has to be, because the shortfall it exposes is the shortfall that layer exists to cover.
The R-value of the insulation filling the stud cavity.
The R-value of solid wood at the stud's thickness.
The percentage of the wall's area taken up by studs, headers, plates, and other framing rather than insulated cavity.
Effective assembly R-value
8.73 R (effective)
This parallel-path method is a widely used simplification — it doesn't account for more complex heat flow effects like point thermal bridges at intersections, which a full 2D/3D heat transfer model would capture more precisely.
- Nominal cavity-only R-value
- 13 R
They open the calculator with your figures already in it
Thermal Bridging Effective R-Value Calculator: 8.73 R (effective) — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Add the equipment this sizes
This result is a specification — 8.73 R (effective) — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.
What this calculation does not cover
- This is the framed insulation layer only. Drywall, sheathing, cladding, air gaps, interior and exterior air films, and any exterior continuous insulation are not in the arithmetic, so the figure is not the wall's total R-value and should not be read against a target stated for a whole assembly.
- The parallel-path split describes timber. Steel studs, Z-furring, spacer bars and brackets, and masonry ties spread heat sideways into the surrounding material, so the bridged area behaves larger than its geometric fraction and this method will not give you the right penalty. For metal, use a steel-specific method or the system supplier's tested U-value.
- One framing fraction is applied evenly over the whole wall. Corners, headers over openings, rim joists, the wall-to-floor and wall-to-roof junctions, and anything penetrating the envelope lose more heat than a plain stud bay, and none of them are resolved here.
- The cavity is assumed filled to its rated R-value everywhere. Gaps at the edges, batts compressed behind wiring and pipework, settled blown insulation, and air moving through the framed layer all put real performance below this number, and none of them are inputs.
- Not a compliance calculation. An energy code submission or a declared U-value needs a whole-assembly figure produced by the method your code names, with junction losses handled separately. Use this to see how much of the batt's label the framing takes back, not as the document you submit.
Where wool is the better answer
Rigid board wins the between-rafter contest on conductivity and loses it on tolerance. Mineral wool will take up a bay that changes width over its length, close around a twisted rafter, and pack into the awkward triangle where a valley board meets a common rafter, all of which are places a rigid sheet leaves a gap that then has to be foamed. On a hundred-year-old sawn roof there are usually several such bays per slope, and the sensible answer is not to pick one product for the whole job.
It also has the better argument on the parts of the room that are not the slope. The dwarf wall behind the eaves, the flat ceiling between the collars, a dormer's cheeks and the studwork around the stair are standard framed cavities at standard centres, and they are where the room's fire lining and acoustic separation are being formed at the same time. Batts specified under BS EN 13162, Thermal insulation products for buildings - Factory made mineral wool (MW) products - Specification, or ASTM C665 in North America, and installed to the practice in ASTM C1320, cover those elements in one pass. Friction fit them, split them around cables rather than compressing over them, and never squeeze a batt into a narrower bay to save a cut.
The trade-off is depth, and depth is this roof's currency. Wool at 0.037 needs roughly two-thirds more thickness than board at 0.022 for the same resistance, so with 50 mm left after the air path it usually loses the slope and wins everywhere else. Order it against the coverage printed on the pack at the thickness actually being used, since coverage per package moves with both thickness and product line.
The dwarf walls, collar ceiling, dormer cheeks and stair studwork are a separate area from the slope and get ordered as packages against the coverage on the pack.
SettingsSettings for this calculation
Waste is set to 5% by hand. Pick a tier above to replace it, or keep your own figure.
The total cavity area to be insulated with mineral wool batts.
The area covered by a single package of mineral wool batts.
Extra material to allow for cutting around obstructions and fitting irregular bays.
Mineral wool packages needed
10 packages
They open the calculator with your figures already in it
Mineral Wool Insulation Batt Calculator: 10 packages — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- Counts thermal batt only. Mineral wool is equally specified as a listed component — safing at slab edges, curtain wall perimeter firestop, head-of-wall joints, and the exact density and facing named in a tested acoustic or fire-rated partition — and those are different products at different densities, often sold by the piece or the linear run. Dropping a general-purpose thermal batt into any of them voids the tested rating while the area sheet still balances.
Which side of the insulation the vapour control belongs on
A room in the roof generates more moisture than the space it replaced and has less ventilation to deal with it. It is usually a bedroom, frequently with an en-suite, sitting at the top of a stair that carries warm humid air up from the whole house, with windows on one plane only. All of that arrives at a ceiling made of thin insulation with cold timber running through it, so a vapour control layer here is doing a harder job than the same membrane on a wall.
The placement rule is what the calculator below tests: keep the control layer warm enough that its own surface never falls to the dew point of the air arriving at it, which means most of the assembly's resistance sits outboard of it and only a small share inboard. Push it too far out - above the between-rafter board, say, or by relying on the foil facer of a board that has another insulating layer inside it - and the membrane becomes the coldest surface in the assembly with warm wet air pressed against it. The method is set out in BS EN ISO 13788, Hygrothermal performance of building components and building elements - Internal surface temperature to avoid critical surface humidity and interstitial condensation - Calculation methods; the psychrometrics behind the dew point are standard ASHRAE Handbook - Fundamentals material.
Two site conditions dominate the outcome and neither is on the drawing. The first is what is already sitting on the cold side. A roof with an old bitumen felt underlay has a vapour barrier outboard of the insulation, which is exactly why that roof must stay ventilated and why its air path cannot be traded for thickness. A vapour-permeable underlay changes the argument, but only where its own certificate says so and only where the eaves detail matches what was tested.
The second is the service zone. Every downlight, cable and shower feed that crosses a vapour layer is a hole in it, and a battened void beneath the membrane is what stops the electrician undoing a week of careful work. BS 5250 and BRE Report BR 262, Thermal insulation: avoiding risks, are the two documents to have open while deciding both of these.
Foil facers deserve their own line. A foil-faced board is already a high-resistance vapour layer, so an assembly with foil-faced board between the rafters, foil-faced laminate under them and a polythene sheet under that has three vapour checks with cold voids trapped between them. Pick which layer is the control layer, make that one continuous and sealed at every perimeter and penetration, and let the others be what they are.
Test the position the membrane will actually occupy against the site's winter design temperature, since the same membrane passes under the plasterboard and fails above the between-rafter board.
The assumed indoor air temperature.
The outdoor winter design temperature for the site's climate zone.
The full wall assembly's total thermal resistance, interior surface to exterior surface.
The portion of the total R-value between the interior face and where the vapor barrier sits.
The dew point temperature of the interior air, based on its temperature and relative humidity.
Temperature at vapor barrier location
55.9 °F
The temperature at this location stays above the interior dew point shown below, so condensation is not predicted under the design conditions entered. No risk predicted under these conditions is not the same as none. The conditions are the ones you entered, and one surface is not the assembly.
- Interior air dew point
- 50 °F
They open the calculator with your figures already in it
Vapor Barrier Dew-Point Condensation Risk Calculator: 55.85 °F — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
What this calculation does not cover
- Air leakage, not diffusion, is what usually wets a wall, and there is nothing about it here. The gradient gives the temperature at the plane; it cannot say how much moisture arrives there. A wall that passes this check and leaks warm interior air through a top plate, a service penetration or an unsealed electrical box deposits far more water at that plane than vapor diffusion through an intact assembly ever could.
- The R-values entered describe the clear field of the wall, between the framing. The path through every stud, plate and header is colder than this straight line says, and at a steel stud or an uninsulated slab edge much colder — so an assembly that passes in the middle of a bay can be sitting below dew point on the back of the sheathing at every framing member, which is exactly where mold turns up.
- It is one snapshot at one pair of temperatures, and it totals nothing. What damages an assembly is how many hours a year it spends below dew point and whether it dries out in between. A wall that dips below on a few cold nights and recovers is not the same wall as one that stays below for a month, and this returns the identical verdict for both.
- The obvious fix for a failing result can produce a wall that cannot dry. Moving the barrier inboard is right only if the outboard side is open to vapor. Where a low-perm layer already sits outside — exterior foam, a self-adhered membrane, an impermeable sheathing — a second one inside traps whatever gets past either of them, and the assembly then passes this temperature check with no drying path in either direction.
The bays that are not the standard bay
The straight run of a slope is the easy part of the take-off. What generates the callbacks is everything the run is interrupted by - trimmers around a roof window, the cheeks and front plate of a dormer, the valley where a dormer or an extension meets the main roof - each of which creates bays narrower than the standard, bays blind at one end, and bays whose ventilation path is cut off partway up. So measure the centres rather than assuming them: a sawn roof drifts, an extension is often framed to a different spacing than the original, and a re-covered roof may have had rafters sistered. Take the run in sections between the interruptions and count each section separately, because a single division across the whole eave assumes a continuity this roof does not have. The two baffle counters on this site answer that division slightly differently - one takes the run over the spacing, the other adds one for the bay that closes the run. On a straight uninterrupted eave the first is fine; where a section is terminated at both ends by a cheek or a valley the closing bay is real, and the higher figure is the one to buy against.
Then handle the paths that are blocked rather than narrow. A bay that runs into a valley board has no route to the ridge and needs its own outlet, usually a tile or slate vent above the obstruction. A dormer roof is a small separate roof with its own inlet and outlet requirement. Neither is solved by ordering more chutes, and both are cheaper to solve while the slope is open than after it has been skimmed.
Use this for the sections between the interruptions, where the spacing was measured rather than assumed and the bay that closes the run is a bay somebody has to buy a chute for.
The total length of the eave run where baffles are needed.
The on-center spacing between rafters.
Baffles needed
25 baffles
They open the calculator with your figures already in it
Attic Rafter Baffle/Chute Count Calculator: 25 baffles — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- Putting a baffle in every rafter bay is not the same as ventilating the roof. The count says nothing about whether the soffit intake and the ridge or high-level outlets together provide enough net free vent area for the insulated ceiling area below, a ratio fixed by your local code, nor whether the soffit vents behind the baffles are actually open. A baffle keeps a path clear; it cannot create intake.
- The count assumes a baffle physically fits at the wall plate. It does not check that the rafter depth there leaves room for the full insulation thickness plus the clear air channel required above it, which is the pinch point on a standard-heel truss. Where it does not fit, the fix is a raised heel, a deeper rafter or a tapered insulation edge, not more baffles.
- The result is a count of bays, not of packs or of running length. Baffles are sold as fixed pieces, commonly around 1.2 m long and pre-sized for 400 mm or 600 mm bays, so any bay baffled further up the slope, such as deep loft insulation or a vaulted section vented to the ridge, takes two or more pieces. No allowance is added here for cut-offs, staples or the edge sealing that stops blown insulation being driven behind the baffle.
- The figure covers one straight eave run. A gable roof has two eaves and has to be worked out and added run by run, and every bay in the run entered is counted whether or not it can be ventilated, including bays closed off by a chimney, a party or fire wall, or a stretch of eave with no soffit vent beneath it.
- Every bay is assumed identical and the spacing box stops at 0.61 m (2 ft), so roofs framed at wider centres cannot be entered, and the trimmed short bays around a rooflight or a hip are not represented — split such a roof into uniform runs and count the odd bays by hand.
When the depth simply will not stretch
Some roofs cannot get there from inside. A 75 mm rafter, a fixed ceiling line in a listed building, or a room already at the limit of usable head height will not accept 90 mm of continuous board underneath however the arithmetic is arranged. Three honest ways out, each buying the depth from somewhere different.
Insulating over the rafters buys it from outside. Board over the rafter tops with counter-battens above it, then underlay, battens and covering, leaves the whole rafter depth available beneath and removes the bridge entirely - the best-performing option by a wide margin. It costs a re-roof and it raises the roof line, which at an eaves or a party wall is a planning and party-wall conversation before it is a building one. Deepening the rafters with a ripped timber screwed to the underside buys the depth from the room exactly as a continuous layer does, keeps the bridge, and raises a load-path question, so it is the weakest of the three unless it is happening for structural reasons anyway. Going unvented buys it from the air path, and that is the option to get right rather than merely decide.
An unventilated pitched roof is a legitimate assembly and a specific one. In North America the IRC's unvented enclosed rafter assembly provisions permit it with conditions on air-impermeable insulation and on the minimum resistance placed outboard of the condensing surface by climate zone. In the UK the route runs through BS 5250 and depends on a genuinely vapour-permeable underlay, a continuous and tested air and vapour control layer on the warm side, and confirmation from the underlay manufacturer's certificate that the product is approved without a ventilated void in that build-up. What is never legitimate is filling the gap under an old bitumen felt and hoping: that felt is a vapour barrier on the cold side, and closing the void beneath it turns a working roof into a sealed cavity with a cold surface in it.
Fixings, and the order the slope closes
The fixing schedule is the detail most likely to be improvised, and it is manufacturer's territory rather than rule-of-thumb territory. A screw passing through plasterboard, then an insulated laminate, then into the rafter has to reach a stated penetration into the timber, and the board maker publishes both the length and the pattern for each laminate thickness - centres that usually tighten on a slope compared with a flat ceiling. Long drywall screws are the wrong fastener: they flex in the insulation and the board creeps off the rafter over the following year.
The sequence below assumes the covering is staying on and the work is from inside. Photograph where marked, because what the camera records at step five is buried by step six and stays buried for the life of the building.
- Strip back and survey: measured rafter depth at several points, actual centres section by section, condition of the underlay and rafter feet, and every trimmer, purlin and valley located.
- Fix chutes in every bay, starting behind the eave inlet and running past where the insulation will finish, stapled to the rafter sides rather than to the underlay.
- Settle the interruptions while the slope is open: dormer cheeks, valley bays and any bay whose path to high level is blocked get their own outlet decided now.
- Cut and fit the between-rafter layer bay by bay, oversize for a friction fit, sealing each piece's perimeter as it goes in rather than at the end of the run.
- Photograph every bay, with something in frame identifying where on the roof it is.
- Fit the continuous layer across the rafters, staggering and taping its joints against the between-rafter joints, then form the service void if one is specified.
- Line, seal every perimeter and penetration of the control layer, skim, and file the board, laminate and underlay certificates with the completion paperwork.
Leaving something the next person can check
This assembly cannot be inspected once it is skimmed, so the record is made while it is open: the bay photographs, plus the declared conductivity and thickness of each product actually installed rather than the ones originally specified. A substitution at the merchant is the commonest reason a finished roof does not match the calculation submitted for consent.
Then verify on a cold morning. A thermal image across a decent temperature difference will show the rafters as warm stripes on the inside face, and that is not a fault - it is the parallel path doing what the arithmetic said it would. What should not appear is a bay darker than its neighbours, a cold band along the eave where insulation was run past the wall plate and closed the inlet, or a bright patch at a dormer cheek. Any of the three is a bay to open, and opening one bay in February costs a fraction of the ceiling that otherwise comes down in three winters' time.
The column of figures to settle before ordering
Every line here is a subtraction from the rafter or an addition beneath it, and the order matters because the first line is the one that cannot be traded.
- Measured rafter depth, at several points on each slope — Nominal sizes lie on a sawn roof, and the whole budget is built on this figure. Note where it varies, because the thin bays govern.
- Clear air path dimension from the provision in force — Comes off the rafter before anything else. Confirm the inlet at the eave and a real outlet at high level for every bay, including the interrupted ones.
- Target U-value, converted once into resistance — Off the paperwork for this address. If the specification is in W/m²K and the calculator is imperial, divide by 5.678 before anything else happens.
- Declared conductivity for each product, at the thickness being bought — From the certificate, not from memory, and re-checked if the merchant substitutes a product line.
- Timber fraction from the actual slope — Rafters at measured centres plus trimmers, valley timbers, dormer cheeks, purlin and collar. It sets how much the continuous layer has to recover.
- Finished depth below the rafter, agreed with whoever will live in it — Continuous layer plus service void plus board and skim. This is where the headroom goes, and it is a conversation to have before the order, not after the first ceiling.
Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.
