Wet underfloor heating in an existing floor takeoff

Lay wet underfloor heating (radiant floor heating) into a floor that is already there: dust sheets on the route and tape at the doorways, the insulation or grooved panels, the pipe loops and their leaders at the designer's centres, a levelling compound, a screed or relaid boards over them, the finish, transition strips at the doorways and the skip, with the manifold, the edge strip, the pressure test before anything covers the pipe, the warm-up and the door trimming listed, and the height it adds flagged.

Measurements in
6
Trades out
8
Calculators
8
Going in
8of 8
My Project
Not in it

No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.

Dimensions

Give the job once

Every figure on the right follows these, in the units you choose.

Step 1 of 2

Choose the build-up

Each layer changes the materials below; the dimensions stay the same.

How the pipe goes into the floor
Pipe centres (the designer's)
Floor finish

Every trade, from those dimensions

then change a dimension, and each line shows what moved.

Every trade's quantity · 8 rows

8 of 8 going in
ItemQuantityOrderWaste / allowance
Dust sheets on the route, and tape round the doorways2 items2 itemsno pack size recordednone
Grooved panels (low-profile boards)8 sheets (4x8 ft)8 sheets (4x8 ft)already whole10%
Pipe loops and leaders (PEX)524 linear ft of PEX524 linear ft of PEXno pack size recorded10%
Levelling compound or latex screed (self-leveling underlayment)34.29 gal34.29 galno pack size recordednone
Floor tiles61 tiles61 tilesalready whole10%
Tile adhesive, flexible5 bags5 bagsalready wholenone
Transition strips (door bars, T-moldings) at the doorways6.3 ft6.3 ftno pack size recorded5%
Skip (dumpster) for what is taken up0.4006 yd³0.4006 yd³no pack size recordednone

Every trade's quantity · 8 rows

8 of 8 going in
ItemQuantityOrderWaste / allowance
Dust sheets on the route, and tape round the doorways2 items2 itemsno pack size recordednone
Grooved panels (low-profile boards)8 sheets (2400x1200 mm)8 sheets (2400x1200 mm)already whole10%
Pipe loops and leaders (PEX)156.36 m of pex156.36 m of pexno pack size recorded10%
Levelling compound or latex screed (self-leveling underlayment)120 L120 Lno pack size recordednone
Floor tiles62 tiles62 tilesalready whole10%
Tile adhesive, flexible5 bags5 bagsalready wholenone
Transition strips (door bars, T-moldings) at the doorways1.89 m1.89 mno pack size recorded5%
Skip (dumpster) for what is taken up0.3 m³0.3 m³no pack size recordednone

Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.

8 of 8 trades chosenNot pricedNot in project
Kept on this deviceUnitsImperialMetricMy Projectnot in it yetQuantities only · your own rates · not a structural check

About this job

A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.

Laying wet underfloor heating into an old floor is a problem of height before it is a problem of heat. In a new house the loops are designed into the floor from the start; in an existing room every layer added, the insulation under the pipe, whatever covers it and the new finish, raises a floor whose level the doors, the next room, the kitchen's plinths and the bottom step of the stair were all built to. So the first decision is how the pipe gets into the floor. Grooved low-profile panels laid over the old floor with a thin levelling compound over them add the least; digging out the old screed on a solid floor makes room for insulation, pipe and a new screed at the old level; and on a suspended timber floor the boards come up, the pipe goes between the joists in aluminium spreader plates over insulation, and the boards go back at the height they were. The units do not choose between them; the floor does.

Whatever the build-up adds is flagged here and never answered. At a doorway it becomes a step, which a transition strip ramps and a trimmed door clears. At the foot of a stair it makes the bottom riser shorter than the rest, which is a trip for anybody coming down and a question for the stair rules building control works to; resetting the stair is not in this job. And a screed is heavy: laid over boards on joists, whether they carry it is a structural question for the designer or an engineer, never this page.

Heat goes where the insulation lets it, so the insulation or the panels go over the whole heated floor, with a compressible edge strip round every wall and frame to let the warmed floor expand. The loops run in one unjointed length each from a port on the manifold and back, at the centres the heating designer sets for the heat each room loses, and the leaders between the room and a manifold outside it are pipe as well, counted by the circuits and the route. The manifold, with a pump and a mixing valve where the heat source runs hotter than the floor should, is fixed where it can be reached, and its thermostats and wiring centre are electrical work. Whether the heat source, a boiler or a heat pump, can run at the floor's low water temperature is its own question, excluded here.

Order matters more than on most jobs. The pipe is pressure-tested before anything covers it and kept under pressure while a screed goes down, because a leak found under a screed is a floor broken open. A sand and cement screed (a topping, in North America) then dries for weeks, and is warmed up in the steps its maker gives over days, never switched straight to full heat, before any finish goes on; a levelling compound (self-leveling underlayment) over panels is ready far sooner. Tiles pass heat best; boards, their underlay and carpet each have a limit on how much they may hold it back, which the maker of each states. The rows follow the build-up and the finish chosen, and the centres chosen for the pipe: nothing here follows the units, and every row answers in each market's own measures.

How each line reads

Base
What the calculator gives for these dimensions, before anything is added.
Allowance
Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
Adjusted
The base with its allowance on top.
Order
What to buy: the adjusted figure in whole boards, bags, rolls or lengths.

The order this happens in

Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.

  1. Have the heating designer work out each room's heat loss, the loop layout, the pipe centres and the flow temperature, and confirm the heat source can run at it; measure the height the new floor will add at every doorway and at the foot of any stair before a build-up is chosen.
  2. Where the old floor finish, its adhesive or the screed beneath it is old enough, have it checked for asbestos; sheet the route through the house, tape round the doorways against dust, isolate any circuit whose cables run under the floor, and drain down any radiator the floor replaces.
  3. Take up the old finish and the skirting (baseboard), and take off the radiators the floor replaces; on a solid floor being dug out, break out the old screed, and on a timber floor lift the boards.
  4. Fix the edge strip round every wall and frame, lay the insulation or the grooved panels, fix the manifold on its brackets, and run the flow and return from the heat source to it and the thermostats' cables through the holes and chases the builder has made.
  5. Lay each loop in one length from its port and back at the designer's centres, record its length against the port, and pressure-test the floor; keep the pipe under pressure while the levelling compound or the screed goes down, or while the old boards are relaid or a new deck is laid over the plates.
  6. While a screed dries for the time its maker gives, wire the thermostats to the wiring centre and have the heat source set for the floor's cooler water, or commissioned where it is new; then fill and purge each loop, dosing the inhibitor where the loops join a sealed system, set its flow at the manifold and warm the floor up in the maker's steps over days. A levelling compound needs only its own drying time before the fill.
  7. Lay the tiles, boards or carpet chosen for a heated floor, fit a transition strip wherever the raised floor meets the next room's, trim each door to clear the new floor, and refix the skirting at its new height.
  8. Test the new wiring, make good the brackets and pipe holes the radiators left, clear the waste, and hand over the loop record, the pressure test and the warm-up record.

What this takeoff does not cover

  • The heat source itself, a boiler or a heat pump, and whether it can run as cool as the loops ask: that is its own job, and only resetting it is listed.
  • The loop layout, the heat each room's floor gives out and the pipe centres, which the designer sets. The centres here are one of the three the pipe page offers, for the reader to change to the designer's.
  • Whether a suspended timber floor carries a screed's weight, which is flagged: strengthening the floor, or changing to a lighter build-up, is for the designer or an engineer.
  • Raising door frames, the stair, kitchen plinths or fitted furniture to the new floor level. Trimming the doors is listed; the shorter bottom riser the raised floor leaves at the foot of a stair is flagged, and resetting the stair is another job.
  • Whether the chosen tiles, boards or carpet suit being heated, beyond naming the question: how warm each may run and how much each holds the heat back come from its maker.
  • An electric mat or cable system under the floor, which is heated another way; the heated bathroom floor takeoff counts one.
  • Removing asbestos the survey finds in the old floor, which is specialist or licensed work with its own programme.
  • Damp found in the floor once it is opened up, and whatever damp proof layer or damp-proof course it then needs.
  • Redecorating the walls marked where the old emitters hung; making good their brackets and pipe holes is listed.

Labour by trade

Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.

Metric opening

Floor to be heated 20 m² · Circuits (loops) off the manifold 2 · Manifold to the heated floor, one way 3 m and 3 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer4.2 h (2.3–12)half a day
Plasterer1 plasterer + 1 labourer4.4 h (2.4–9.0)half a day
Tiler1 tiler12 h (7.0–24)1½ days
Floor layer1 floor layer0.9 h (0.6–1.9)under a quarter of a day
Rated rows22 h (12–46)2½ days

Imperial opening

Floor to be heated 220 sq ft · Circuits (loops) off the manifold 2 · Manifold to the heated floor, one way 10 ft and 3 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer4.3 h (2.4–12)half a day
Plasterer1 plasterer + 1 labourer4.5 h (2.5–9.2)half a day
Tiler1 tiler12 h (7.2–25)1½ days
Floor layer1 floor layer1.0 h (0.6–1.9)under a quarter of a day
Rated rows22 h (13–47)2½ days

Quote check

Been given a quote for this job?

Paste it into the underfloor heating retrofit quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.

  • What it leaves out

    Every line this takeoff has that nothing on the quote reads as.

  • What it adds

    Labour, removal, hire, fees — each named for what it is.

  • What to ask

    One list of questions, ready to copy. Never a verdict.

More takeoffs

Other job takeoffs

All job takeoffs

Frequently asked questions

What does the underfloor heating retrofit takeoff give for a typical job?
Opened at Floor to be heated 20 m² · Circuits (loops) off the manifold 2 · Manifold to the heated floor, one way 3 m · Doorways where the new floor meets another 2 · Floor sheeted along the route through the house 8 m² · Loose waste, as a depth over the heated floor 15 mm, it orders: Dust sheets on the route, and tape round the doorways, 2 items; Grooved panels (low-profile boards), 8 sheets (2400x1200 mm); Pipe loops and leaders (PEX), 156 m of pex; Levelling compound or latex screed (self-leveling underlayment), 120 L; Floor tiles, 62 tiles; Tile adhesive, flexible, 5 bags; Transition strips (door bars, T-moldings) at the doorways, 1.89 m; Skip (dumpster) for what is taken up, 0.3 m³. Opened at Floor to be heated 220 sq ft · Circuits (loops) off the manifold 2 · Manifold to the heated floor, one way 10 ft · Doorways where the new floor meets another 2 · Floor sheeted along the route through the house 86 sq ft · Loose waste, as a depth over the heated floor 0.59 in: Dust sheets on the route, and tape round the doorways, 2 items; Grooved panels (low-profile boards), 8 sheets (4x8 ft); Pipe loops and leaders (PEX), 524 linear ft of PEX; Levelling compound or latex screed (self-leveling underlayment), 34.3 gal; Floor tiles, 61 tiles; Tile adhesive, flexible, 5 bags; Transition strips (door bars, T-moldings) at the doorways, 6.3 ft; Skip (dumpster) for what is taken up, 0.4 yd³. Every figure follows the dimensions you give it.
Which calculators does the underfloor heating retrofit takeoff run?
8 calculators, one to a line: Masking and Protection Materials Calculator, Foam Board Insulation Calculator, Radiant Floor PEX Tubing Calculator, Self-Leveling Underlayment (SLU) Volume Calculator, Floor & Wall Tile Calculator, Thinset & Tile Adhesive Calculator, Floor Transition Strip Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
What does the underfloor heating retrofit takeoff leave out?
9 things, each named on this page: The heat source itself, a boiler or a heat pump, and whether it can run as cool as the loops ask; The loop layout, the heat each room's floor gives out and the pipe centres, which the designer sets; Whether a suspended timber floor carries a screed's weight, which is flagged; Raising door frames, the stair, kitchen plinths or fitted furniture to the new floor level; Whether the chosen tiles, boards or carpet suit being heated, beyond naming the question; An electric mat or cable system under the floor, which is heated another way; the heated bathroom floor takeoff counts one; Removing asbestos the survey finds in the old floor, which is specialist or licensed work with its own programme; Damp found in the floor once it is opened up, and whatever damp proof layer or damp-proof course it then needs; Redecorating the walls marked where the old emitters hung; making good their brackets and pipe holes is listed.
Can I check a quote for this job against the takeoff?
Yes. The underfloor heating retrofit quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.