Kitchen refit takeoff

Strip out a kitchen and fit a new one: base and wall units by standard width, the worktop (countertop) in stock lengths or as a template area, plinth (toe kick) and cornice, a tiled splashback, the new floor and the decoration, with the plumbing, electrical and gas work listed and never certified.

Measurements in
17
Trades out
16
Calculators
12
Going in
16of 16
My Project
Not in it

No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.

Dimensions

Give the job once

Every figure on the right follows these, in the units you choose.

Step 1 of 5

Choose the build-up

Each layer changes the materials below; the dimensions stay the same.

Worktop (countertop)
Walls after the strip-out
Floor
Before the new floor

Every trade, from those dimensions

then change a dimension, and each line shows what moved.

Every trade's quantity · 16 rows

16 of 16 going in
ItemQuantityOrderWaste / allowance
Dust sheets and tape3 items3 itemsno pack size recordednone
Base units8 units8 unitsalready whole0.75 in
Wall units7 units7 unitsalready whole0.75 in
Cornice (crown), and as much again for a light pelmet2 lengths2 lengthsalready whole0.75 in
Worktop (countertop) lengths2 lengths2 lengthsalready whole0.75 in
Splashback tiles259 tiles259 tilesalready whole10%
Splashback tile adhesive1 bag1 bagalready wholenone
Splashback grout4.89 lb4.89 lbno pack size recorded10%
Tile trim on the splashback's edges22.14 ft22.14 ftno pack size recorded8%
Wall paint1.66 gal1.66 galno pack size recordednone
Ceiling paint0.65 gal0.65 galno pack size recordednone
Underlay1 roll1 rollalready wholenone
Laminate or vinyl plank5 packs5 packsalready whole7%
Threshold strips3.15 ft3.15 ftno pack size recorded5%
Plinth (toe kick)3 lengths3 lengthsalready whole0.75 in
Skip (dumpster) for the strip-out3.39 yd³3.39 yd³no pack size recordednone

Every trade's quantity · 16 rows

16 of 16 going in
ItemQuantityOrderWaste / allowance
Dust sheets and tape3 items3 itemsno pack size recordednone
Base units8 units8 unitsalready whole20 mm
Wall units7 units7 unitsalready whole20 mm
Cornice (crown), and as much again for a light pelmet2 lengths2 lengthsalready whole20 mm
Worktop (countertop) lengths2 lengths2 lengthsalready whole20 mm
Splashback tiles256 tiles256 tilesalready whole10%
Splashback tile adhesive1 bag1 bagalready wholenone
Splashback grout2.11 kg2.11 kgno pack size recorded10%
Tile trim on the splashback's edges6.75 m6.75 mno pack size recorded8%
Wall paint6.05 L6.05 Lno pack size recordednone
Ceiling paint2.4 L2.4 Lno pack size recordednone
Underlay1 roll1 rollalready wholenone
Laminate or vinyl plank5 packs5 packsalready whole7%
Threshold strips0.945 m0.945 mno pack size recorded5%
Plinth (toe kick)2 lengths2 lengthsalready whole20 mm
Skip (dumpster) for the strip-out2.6 m³2.6 m³no pack size recordednone

Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.

16 of 16 trades chosenNot pricedNot in project
Kept on this deviceUnitsImperialMetricMy Projectnot in it yetQuantities only · your own rates · not a structural check

About this job

A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.

A kitchen refit is the one room job where the joinery sets the order for every other trade. The unit plan decides where the waste, the water and the cables come through the wall, so the first fix is marked out from that plan before a carcass arrives; the worktop (countertop) is cut or templated only once the base units stand level; and the splashback, the floor and the plinth (toe kick) each wait on the units in turn. A waste pipe run to the wrong place is found when it comes up behind a drawer pack.

The units are counted rather than measured. Each run is filled with as many units of the main width as fit, 600 mm where units are made to metric sizes and 24 in in the US, then one or two units of other standard widths, and what is left is closed with a filler. Where two runs meet, the second run's units start at the front edge of the first run's worktop, so an L loses a worktop depth from its second leg: dividing the two wall lengths by a unit width buys a unit too many.

The worktop is where the two markets part. Laminate sold in metric lengths meets at a corner in a butt joint or a masons mitre, so the second piece is a depth shorter; a US post-form counter meets at a 45 degree mitre, both pieces running into the corner, and a length with a mitred end cannot be shared with another piece. Stone, quartz and solid surface are neither: they are made to a template of the fitted units, which is why that option gives the fabricator an area rather than lengths.

What the page will not count is the work that carries the most risk. The water, the waste, the circuits and any gas are listed as work and never measured, and nothing here says any of it is right: a new circuit, a socket moved near the sink, or a gas hob taken off and put back are each for a person registered or licensed for that work where the kitchen is, and the test that follows is theirs to sign.

How each line reads

Base
What the calculator gives for these dimensions, before anything is added.
Allowance
Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
Adjusted
The base with its allowance on top.
Order
What to buy: the adjusted figure in whole boards, bags, rolls or lengths.

The order this happens in

Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.

  1. Survey the room and draw the unit plan to the millimetre or the eighth of an inch, checking every appliance space against the maker's installation size before anything is ordered.
  2. Isolate the water, the kitchen's circuits and any gas, then strip out the old units, worktop and tiles, protecting the route out to the skip (dumpster).
  3. First fix while the walls are bare: move the waste, the water and the cables to where the new plan puts them, make good, and let any new plaster dry.
  4. Fit the base units from the corner outwards, level on their legs or packers, then hang the wall units to a line and fix the cornice (crown) and pelmet while they are clear.
  5. Cut and joint the worktop, or have stone templated now, off the level base units, and make the sink and hob cut-outs to the appliances in hand.
  6. Tile the splashback up from the worktop, and run silicone rather than grout along the worktop joint, which moves.
  7. Second fix: connect the sink, the appliances and the hood, and have the gas appliance connected and the circuits tested by the people registered for each.
  8. Decorate, then lay the new floor up to the base units and under the appliance spaces, and fit the plinth (toe kick) on the finished floor last.

What this takeoff does not cover

  • Tall units, larders and oven housings. The unit page counts base and wall units only, so a tall housing is listed as work, and its width comes out of the runs before they are entered.
  • What goes inside and onto the units: drawer packs, corner fittings, hinges, handles, the sink, the tap and the appliances themselves.
  • Every service as a quantity. Pipe, fittings, the waste, cable, sockets, the extract duct and the gas pipe are listed as work, not measured, and nothing on the page signs any of that work off.
  • The fabricator's side of a stone, quartz or solid-surface worktop: cut-outs, edge profiles, upstands and fitting are priced from the template, and the template option gives the worktop's area alone.
  • Moving a wall, a window or a door to suit the new plan, and anything structural behind the units.
  • Worktop jointing bolts and strips, end caps, edging, sealant, and the fixings for the units, the plinth and the cornice.

Labour by trade

Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.

Metric opening

Kitchen length 4 m · Kitchen width 3 m · Floor to ceiling 2.4 m and 14 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer3.1 h (1.5–8.8)half a day
Carpenter1 carpenter20 h (6.8–42)2½ days
Tiler1 tiler2.9 h (1.8–5.7)half a day
Painter1 painter7.6 h (4.2–17)1 day
Floor layer1 floor layer3.1 h (1.7–6.0)half a day
Rated rows37 h (16–79)4½ days

Imperial opening

Kitchen length 13 ft · Kitchen width 10 ft · Floor to ceiling 8 ft and 14 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer3.1 h (1.5–8.7)half a day
Carpenter1 carpenter20 h (6.8–42)2½ days
Tiler1 tiler2.9 h (1.9–5.8)half a day
Painter1 painter7.7 h (4.3–17)1 day
Floor layer1 floor layer3.1 h (1.7–6.1)half a day
Rated rows37 h (16–79)4½ days

Quote check

Been given a quote for this job?

Paste it into the kitchen refit quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.

  • What it leaves out

    Every line this takeoff has that nothing on the quote reads as.

  • What it adds

    Labour, removal, hire, fees — each named for what it is.

  • What to ask

    One list of questions, ready to copy. Never a verdict.

More takeoffs

Other job takeoffs

All job takeoffs

Frequently asked questions

What does the kitchen refit takeoff give for a typical job?
Opened at Kitchen length 4 m · Kitchen width 3 m · Floor to ceiling 2.4 m · Doors into the kitchen 1 · Windows 1 · Run 1: base units and appliance spaces 3.4 m · Run 2, round the corner from run 1 (0 if none) 2.4 m · Run 3 (0 if none) 0 m · Integrated appliance spaces under the worktop 0.6 m · Worktop (countertop) depth 0.6 m · Wall units over run 1 2.8 m · Wall units before the hood 1.2 m · Wall units over run 2 (0 if none) 1.2 m · Wall units over run 3 (0 if none) 0 m · Open ends of the base runs 1 · Open ends of the wall-unit runs 2 · Splashback height 450 mm, it orders: Dust sheets and tape, 3 items; Base units, 8 units; Wall units, 7 units; Cornice (crown), and as much again for a light pelmet, 2 lengths; Worktop (countertop) lengths, 2 lengths; Splashback tiles, 256 tiles; Splashback tile adhesive, 1 bag; Splashback grout, 2.11 kg; Tile trim on the splashback's edges, 6.75 m; Wall paint, 6.05 L; Ceiling paint, 2.4 L; Underlay, 1 roll; Laminate or vinyl plank, 5 packs; Threshold strips, 0.95 m; Plinth (toe kick), 2 lengths; Skip (dumpster) for the strip-out, 2.6 m³. Opened at Kitchen length 13 ft · Kitchen width 10 ft · Floor to ceiling 8 ft · Doors into the kitchen 1 · Windows 1 · Run 1: base units and appliance spaces 11 ft · Run 2, round the corner from run 1 (0 if none) 8 ft · Run 3 (0 if none) 0 ft · Integrated appliance spaces under the worktop 2 ft · Worktop (countertop) depth 2 ft · Wall units over run 1 9 ft · Wall units before the hood 4 ft · Wall units over run 2 (0 if none) 4 ft · Wall units over run 3 (0 if none) 0 ft · Open ends of the base runs 1 · Open ends of the wall-unit runs 2 · Splashback height 18 in: Dust sheets and tape, 3 items; Base units, 8 units; Wall units, 7 units; Cornice (crown), and as much again for a light pelmet, 2 lengths; Worktop (countertop) lengths, 2 lengths; Splashback tiles, 259 tiles; Splashback tile adhesive, 1 bag; Splashback grout, 4.89 lb; Tile trim on the splashback's edges, 22.1 ft; Wall paint, 1.66 gal; Ceiling paint, 0.65 gal; Underlay, 1 roll; Laminate or vinyl plank, 5 packs; Threshold strips, 3.15 ft; Plinth (toe kick), 3 lengths; Skip (dumpster) for the strip-out, 3.39 yd³. Every figure follows the dimensions you give it.
Which calculators does the kitchen refit takeoff run?
12 calculators, for 16 lines: Masking and Protection Materials Calculator, Kitchen Unit and Cabinet Run Calculator, Floor & Wall Tile Calculator, Thinset & Tile Adhesive Calculator, Grout Calculator, Tile Edge Profile (Trim Strip) Linear Footage Calculator, Paint Calculator, Ceiling Paint Calculator, Laminate/Vinyl Plank Floor Underlayment Roll Calculator, LVP, Laminate & Engineered Floor Calculator, Floor Transition Strip Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
What does the kitchen refit takeoff leave out?
6 things, each named on this page: Tall units, larders and oven housings; What goes inside and onto the units; Every service as a quantity; The fabricator's side of a stone, quartz or solid-surface worktop; Moving a wall, a window or a door to suit the new plan, and anything structural behind the units; Worktop jointing bolts and strips, end caps, edging, sealant, and the fixings for the units, the plinth and the cornice.