Internal wall removal takeoff

Take out an internal wall, load-bearing or not: the protection, the rubble and the skip (dumpster), the beam casing, and making good the ceiling, the wall ends and the floor along the old wall line.

Measurements in
9
Trades out
13
Calculators
11
Going in
13of 13
My Project
Not in it

No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.

Dimensions

Give the job once

Every figure on the right follows these, in the units you choose.

Step 1 of 3

Choose the build-up

Each layer changes the materials below; the dimensions stay the same.

Wall
Floor
Fire protection to the beam

Calculators behind the other choices:

Every trade, from those dimensions

then change a dimension, and each line shows what moved.

Every trade's quantity · 13 rows

13 of 13 going in
ItemQuantityOrderWaste / allowance
Dust sheets and tape for both rooms5 items5 itemsno pack size recordednone
The wall, broken up2.04 yd³2.04 yd³no pack size recordednone
Ceiling board along the old wall line1 sheet1 sheetalready whole10%
Fire-rated board casing the beam1 sheet1 sheetalready whole10%
Angle bead on the beam casing4 lengths4 lengthsalready wholenone
Backing and finish coat on the wall ends18.5 lb18.5 lbno pack size recorded15%
Skim over the ceiling band12.95 lb12.95 lbno pack size recorded15%
Skim over the beam casing9.72 lb9.72 lbno pack size recorded15%
Levelling compound across the old wall line3.43 gal3.43 galno pack size recordednone
Wall paint for the joined room2.44 gal2.44 galno pack size recordednone
Ceiling paint for the joined room1.38 gal1.38 galno pack size recordednone
Skirting (baseboard) round the joined room70.5 linear ft70.5 linear ftno pack size recorded10%
Skip (dumpster) for the rubble2.04 yd³2.04 yd³no pack size recordednone

Every trade's quantity · 13 rows

13 of 13 going in
ItemQuantityOrderWaste / allowance
Dust sheets and tape for both rooms5 items5 itemsno pack size recordednone
The wall, broken up1.53 m³1.53 m³no pack size recordednone
Ceiling board along the old wall line1 sheet1 sheetalready whole10%
Fire-rated board casing the beam1 sheet1 sheetalready whole10%
Angle bead on the beam casing4 lengths4 lengthsalready wholenone
Backing and finish coat on the wall ends8.18 kg8.18 kgno pack size recorded15%
Skim over the ceiling band5.87 kg5.87 kgno pack size recorded15%
Skim over the beam casing4.89 kg4.89 kgno pack size recorded15%
Levelling compound across the old wall line12.24 L12.24 Lno pack size recordednone
Wall paint for the joined room8.84 L8.84 Lno pack size recordednone
Ceiling paint for the joined room5.04 L5.04 Lno pack size recordednone
Skirting (baseboard) round the joined room21.34 m21.34 mno pack size recorded10%
Skip (dumpster) for the rubble1.53 m³1.53 m³no pack size recordednone

Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.

13 of 13 trades chosenNot pricedNot in project
Kept on this deviceUnitsImperialMetricMy Projectnot in it yetQuantities only · your own rates · not a structural check

About this job

A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.

Taking out a wall is two jobs that look like one. The first is structural, and there is nothing on this page to measure in it: whether the wall holds anything up — a floor, a wall standing on it upstairs, a strut from the roof — and, where it does, the props and needles (temporary shoring) that carry that load while the wall comes out, the beam that carries it afterwards, and the padstones (concrete bearing blocks) its ends sit on. Those are the engineer's figures. They appear here as items, never sized. The second job is everything the opening leaves behind, and that is where the quantities are: the rubble, a band of ceiling torn where the wall met it, the two wall ends, the floor strip where the wall stood, and whatever is built round the beam.

How thick a wall looks, or whether it sounds hollow, does not say whether it carries load. Joists landing on it, a wall above it, or a loft strut bearing down onto it do; and a stud partition can carry a floor as surely as a brick one. So the beam's girth below is a figure to take from the engineer's section once there is one, and a wall that carries nothing is entered with a girth of 0, which takes the casing, its fire protection and its beads off the list. Carrying nothing does not always mean no approval: a wall that encloses the stair or hall, the way out of a house with a floor more than 4.5 m (15 ft) up, protects the escape route, and taking it out is a matter for building control in England and Wales and for a permit in much of North America.

The wall's material decides the waste and the wall ends. Brick or block breaks into rubble that the demolition row bulks up by half and sends to a skip (dumpster) as heavy waste; a stud wall comes out as timber and plasterboard (drywall), light and bulky. Masonry ends cut back to a clean line take a backing coat before the finish, which the stud wall's boarded end does not.

The floor under the old wall is the part a plan of the room hides. On a solid floor there is a strip where the wall stood — often lower than the floors either side, because the wall sat on its own footing — to fill and then level; on a suspended timber floor the joists and boards have to be carried across the gap. And two rooms that had different floor coverings now meet in the middle of one room, where the join takes a threshold strip or one covering laid right through.

How each line reads

Base
What the calculator gives for these dimensions, before anything is added.
Allowance
Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
Adjusted
The base with its allowance on top.
Order
What to buy: the adjusted figure in whole boards, bags, rolls or lengths.

The order this happens in

Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.

  1. Establish what the wall carries, and have the engineer's design and building control's agreement in hand before touching a wall that carries load.
  2. Isolate the cables and pipes in the wall, and sheet both rooms' floors and the route out to the skip.
  3. Set the props and needles where the design puts them, and only then cut the wall away, from the top down.
  4. Build the padstones, set the beam, pack it tight to what it carries, and leave the props in until the engineer says the packing has taken the load.
  5. Case or coat the steel to the fire protection agreed, board the ceiling band, and make good the wall ends.
  6. Skim the new surfaces and let them dry; fill and level the floor strip once the plastering is finished, so no plaster drops onto the new levelling coat.
  7. Decorate the joined room as one room: ceiling, walls and skirting, so the old wall line does not show through in two shades.

What this takeoff does not cover

  • The structural design: whether the wall carries load, the beam's size and grade, its bearings and padstones, and the temporary props. Each is an item here with no quantity, because each is the engineer's figure, and the page sizes none of them.
  • A beam that bears into a party wall, which brings a notice to the neighbour under the rules where you build — in England and Wales, the Party Wall etc. Act 1996.
  • The cables, pipes and any radiator rerouted out of the wall, which are listed as work and not measured.
  • The mortar, concrete or screed that fills a deep floor strip below the finish. The levelling row covers a thin levelling coat across the band, not the fill under it.
  • The corners of any piers left at the ends of the opening, each a length of angle bead; the bead row counts the casing's two arrises only. And on a stud wall, the cut ends boarded over the last stud, a strip of board and skim no wider than the wall.
  • A floor covering laid right through the joined room, and the threshold strip where two coverings meet, which are listed as work and not measured.

Labour by trade

Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.

Metric opening

Length of wall taken out 3.4 m · Floor to ceiling 2.4 m · Wall thickness, finish to finish 125 mm and 6 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer2.5 h (1.3–6.6)half a day
Drywaller1 drywaller + 1 labourer0.6 h (0.4–1.2)under a quarter of a day
Plasterer1 plasterer1.2 h (0.7–2.4)under a quarter of a day
Painter1 painter12 h (6.9–28)1½ days
Carpenter1 carpenter3.8 h (2.1–8.5)half a day
In all21 h (11–47)2½ days

Imperial opening

Length of wall taken out 11 ft · Floor to ceiling 8 ft · Wall thickness, finish to finish 5 in and 6 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer2.6 h (1.3–6.7)half a day
Drywaller1 drywaller + 1 labourer0.6 h (0.4–1.2)under a quarter of a day
Plasterer1 plasterer1.2 h (0.7–2.4)under a quarter of a day
Painter1 painter13 h (7.1–28)1½ days
Carpenter1 carpenter3.9 h (2.1–8.6)half a day
In all21 h (12–47)2½ days

Quote check

Been given a quote for this job?

Paste it into the wall removal quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.

  • What it leaves out

    Every line this takeoff has that nothing on the quote reads as.

  • What it adds

    Labour, removal, hire, fees — each named for what it is.

  • What to ask

    One list of questions, ready to copy. Never a verdict.

More takeoffs

Other job takeoffs

All job takeoffs

Frequently asked questions

What does the wall removal takeoff give for a typical job?
Opened at Length of wall taken out 3.4 m · Floor to ceiling 2.4 m · Wall thickness, finish to finish 125 mm · Joined room, across the old wall line 7 m · Joined room, along the old wall line 3.6 m · Doors in the joined room 2 · Windows in the joined room 2 · Band made good along the wall line 0.6 m · Beam girth to finish 0.5 m, it orders: Dust sheets and tape for both rooms, 5 items; The wall, broken up, 1.53 m³; Ceiling board along the old wall line, 1 sheet; Fire-rated board casing the beam, 1 sheet; Angle bead on the beam casing, 4 lengths; Backing and finish coat on the wall ends, 8.18 kg; Skim over the ceiling band, 5.87 kg; Skim over the beam casing, 4.89 kg; Levelling compound across the old wall line, 12.2 L; Wall paint for the joined room, 8.84 L; Ceiling paint for the joined room, 5.04 L; Skirting (baseboard) round the joined room, 21.3 m; Skip (dumpster) for the rubble, 1.53 m³. Opened at Length of wall taken out 11 ft · Floor to ceiling 8 ft · Wall thickness, finish to finish 5 in · Joined room, across the old wall line 23 ft · Joined room, along the old wall line 12 ft · Doors in the joined room 2 · Windows in the joined room 2 · Band made good along the wall line 2 ft · Beam girth to finish 1.5 ft: Dust sheets and tape for both rooms, 5 items; The wall, broken up, 2.04 yd³; Ceiling board along the old wall line, 1 sheet; Fire-rated board casing the beam, 1 sheet; Angle bead on the beam casing, 4 lengths; Backing and finish coat on the wall ends, 18.5 lb; Skim over the ceiling band, 13 lb; Skim over the beam casing, 9.72 lb; Levelling compound across the old wall line, 3.43 gal; Wall paint for the joined room, 2.44 gal; Ceiling paint for the joined room, 1.38 gal; Skirting (baseboard) round the joined room, 70.5 linear ft; Skip (dumpster) for the rubble, 2.04 yd³. Every figure follows the dimensions you give it.
Which calculators does the wall removal takeoff run?
11 calculators, for 13 lines: Masking and Protection Materials Calculator, Demolition Bulk Volume Swell Calculator, Ceiling Plasterboard Calculator (Gypsum Board Sheets), Plaster Angle and Stop Bead Calculator, Float and Set Plaster Calculator, Skim Coat Plaster Calculator, Self-Leveling Underlayment (SLU) Volume Calculator, Paint Calculator, Ceiling Paint Calculator, Baseboard & Trim Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
What does the wall removal takeoff leave out?
6 things, each named on this page: The structural design; A beam that bears into a party wall, which brings a notice to the neighbour under the rules where you build; The cables, pipes and any radiator rerouted out of the wall, which are listed as work and not measured; The mortar, concrete or screed that fills a deep floor strip below the finish; The corners of any piers left at the ends of the opening, each a length of angle bead; the bead row counts the casing's two arrises only; A floor covering laid right through the joined room, and the threshold strip where two coverings meet, which are listed as work and not measured.
Can I check a quote for this job against the takeoff?
Yes. The wall removal quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.