Party wall soundproofing takeoff

Line a party wall (a demising or shared wall) against a neighbour's noise: an independent stud frame clear of it, or resilient bars or sound clips on it, mineral wool in the void, mass-loaded vinyl where the specification has it, two layers of dense plasterboard (drywall) sealed at every edge, a skim in metric or taped joints in imperial, skirting (baseboard) and paint, with the sockets brought forward, their putty pads and a radiator rehung listed, no sound rating claimed and nothing certified.

Measurements in
3
Trades out
9
Calculators
9
Going in
9of 9
My Project
Not in it

No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.

Dimensions

Give the job once

Every figure on the right follows these, in the units you choose.

Choose the build-up

Each layer changes the materials below; the dimensions stay the same.

How the lining is held clear of the party wall
Mass-loaded vinyl in the build-up
The finish on the boards
How the lining is held clear of the party wall
Mass-loaded vinyl in the build-up
The finish on the boards

Every trade, from those dimensions

then change a dimension, and each line shows what moved.

Every trade's quantity · 9 rows

9 of 9 going in
ItemQuantityOrderWaste / allowance
Masking and protection materials2 items2 itemsno pack size recordednone
Studs and plates (independent frame, studwork)13 studs13 studsalready whole10%
Mineral wool batts3 packages3 packagesalready whole5%
Mass-loaded vinyl (MLV, acoustic membrane)109.2 sq ft109.2 sq ftno pack size recorded5%
Dense or acoustic plasterboard (drywall), two layers8 sheets8 sheetsalready whole10%
Acoustic sealant0.2727 gal0.2727 galno pack size recordednone
Joint compound and tape (or a skim coat of compound)1 x 4.5 gal box1 x 4.5 gal boxalready whole10%
Skirting (baseboard)14.3 linear ft14.3 linear ftno pack size recorded10%
Painting and decorating (decoration): two coats, a mist coat apart0.52 gal0.52 galno pack size recordednone

Every trade's quantity · 9 rows

9 of 9 going in
ItemQuantityOrderWaste / allowance
Masking and protection materials2 items2 itemsno pack size recordednone
Studs and plates (independent frame, studwork)13 studs13 studsalready whole10%
Mineral wool batts3 packages3 packagesalready whole5%
Mass-loaded vinyl (MLV, acoustic membrane)10.08 m²10.08 m²no pack size recorded5%
Dense or acoustic plasterboard (drywall), two layers8 sheets8 sheetsalready whole10%
Acoustic sealant0.9216 L0.9216 Lno pack size recordednone
Skim finish coat (plastering)27.6 kg27.6 kgno pack size recorded15%
Skirting (baseboard)4.4 m4.4 mno pack size recorded10%
Painting and decorating (decoration): two coats, a mist coat apart1.92 L1.92 Lno pack size recordednone

Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.

9 of 9 trades chosenNot pricedNot in project
Kept on this deviceUnitsImperialMetricMy Projectnot in it yetQuantities only · your own rates · not a structural check

About this job

A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.

A party wall (a demising or shared wall, to a North American reader) carries a neighbour's noise through its own mass and through the floors and walls joined to it, whether it is solid masonry, two leaves with a cavity, or a frame. The lining built in front of it is a second leaf that touches the first as little as it can. On the frame build-up that is a row of studs standing on the floor and fixed to the ceiling, set a small clear gap off the party wall so no timber bridges it. On the bars build-up the boards hang from sprung resilient bars (resilient channel), or from furring channel (hat channel) pressed into sound clips, fixed to the wall itself. Either way the lining costs the room some width, which is agreed before the line is marked.

Mass is the other half of it. Two layers of dense plasterboard (drywall) with the second layer's joints staggered over the first, mineral wool filling the void, and, where the specification includes it, a limp layer of mass-loaded vinyl between the frame and the boards: the board row counts both layers in one figure, the lining's face twice over, and the vinyl row that face once. None of these rows says how much quieter the room will be. That is a matter of the whole building and of a test in the finished room, and a page that multiplies areas cannot answer it.

Most of what separates a lining that works from one that disappoints is in details no area shows. Each layer of board stops just short of the floor, the ceiling and the side walls, and that gap is filled with a sealant that never sets hard (an acoustic mastic, or caulk); every socket and switch brought forward into the lining gets a putty pad round its back box (the electrical box); and a radiator that hung on the party wall goes back on the lining, on a line of noggins (blocking) set in the frame or where the bar system's maker allows a heavy fixing, never through the boards into the old wall. In England and Wales the Party Wall etc. Act 1996 can apply to work on the wall itself, and its notices are the owner's.

How each line reads

Base
What the calculator gives for these dimensions, before anything is added.
Allowance
Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
Adjusted
The base with its allowance on top.
Order
What to buy: the adjusted figure in whole boards, bags, rolls or lengths.

The order this happens in

Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.

  1. Mark the line of the lining on the floor, measured off the party wall, agree how much of the room it takes, and read the floor and ceiling along that line for level so the frame or the bars can be packed true.
  2. Lay dust sheets, isolate the circuits feeding any socket or switch on the party wall, take off the skirting, the coving (crown molding) and anything fixed to the wall, and drain down and lift off a radiator that hangs there, capping its pipes.
  3. Scan the plate lines in the floor and ceiling, or the party wall where bars or clips are fixed, for cables and pipes; then fix the independent frame clear of the wall with a line of noggins (blocking) where the radiator comes back, or fix the battens and bars, or the clips and their channel, at the system's centres.
  4. Have the electrician bring each socket and switch forward into an extended or deeper back box, and mould a putty pad round every box with the circuit still isolated.
  5. Friction-fit the mineral wool through the void, and hang the vinyl across the frame where the specification puts it there; then fix the first layer of board stopped short of the floor, the ceiling and the side walls, and fill its edges, and round every box and pipe through it, with acoustic sealant while they can still be reached.
  6. Where the vinyl goes between the layers, hang it over the first; then fix the second layer with its joints staggered over the first's, stopped short and sealed at every edge, box and pipe in the same way.
  7. Skim the outer boards, or tape and finish their joints, and leave the finish to dry; refit the skirting along the foot of the lining over the sealed gap.
  8. Decorate the lining, its first coat thinned on plaster or a primer on taped board, before the radiator goes back; then rehang it on its noggins with its tails sealed through the lining, refill and bleed the system, refit the sockets and switches and have them tested, clear the offcuts, and hand over the lining's specification and the electrician's certificate.

What this takeoff does not cover

  • Flanking sound through the rest of the structure, which this job leaves as it is.
  • Sound tests of any kind, before the work or after it, the pre-completion test in England and Wales among them.
  • Notice to the neighbour, and any surveyors' award under the 1996 Act, where the shared structure is touched at all: the owner's to serve and settle.
  • Strengthening a floor for the added mass (flagged).
  • Ventilating the sealed room.
  • A heater moved elsewhere, or its pipe runs rerouted.
  • Crown molding (coving) put back along the new lining.
  • A fire rating: no row here makes a fire-resisting claim.
  • Green Glue or another damping compound between the layers.
  • Damping compound between the layers, which no row here measures.

Labour by trade

Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.

Metric opening

Floor protected 12 m² · Length of the party wall lined 4 m · Height of the lining, floor to ceiling 2.4 m

TradeCrewPerson-hoursWorking days
Labourer1 labourer1.4 h (0.7–3.1)under a quarter of a day
Carpenter2 carpenters3.0 h (1.6–6.2)under a quarter of a day
Drywaller1 drywaller + 1 labourer5.2 h (2.8–11)half a day
Plasterer1 plasterer1.6 h (1.0–3.4)under a quarter of a day
Painter1 painter1.7 h (1.0–3.8)under a quarter of a day
In all13 h (7.1–28)1 day

Imperial opening

Floor protected 130 sq ft · Length of the party wall lined 13 ft · Height of the lining, floor to ceiling 8 ft

TradeCrewPerson-hoursWorking days
Labourer1 labourer1.4 h (0.7–3.1)under a quarter of a day
Carpenter2 carpenters3.0 h (1.6–6.1)under a quarter of a day
Drywaller1 drywaller + 1 labourer5.3 h (2.8–11)half a day
Taper1 taper + 1 labourer1.5 h (0.9–3.1)under a quarter of a day
Painter1 painter1.7 h (1.0–3.9)under a quarter of a day
In all13 h (7.0–27)1 day

Quote check

Been given a quote for this job?

Paste it into the party wall soundproofing quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.

  • What it leaves out

    Every line this takeoff has that nothing on the quote reads as.

  • What it adds

    Labour, removal, hire, fees — each named for what it is.

  • What to ask

    One list of questions, ready to copy. Never a verdict.

More takeoffs

Other job takeoffs

All job takeoffs

Frequently asked questions

What does the party wall soundproofing takeoff give for a typical job?
Opened at Floor protected 12 m² · Length of the party wall lined 4 m · Height of the lining, floor to ceiling 2.4 m, it orders: Masking and protection materials, 2 items; Studs and plates (independent frame, studwork), 13 studs; Mineral wool batts, 3 packages; Mass-loaded vinyl (MLV, acoustic membrane), 10.1 m²; Dense or acoustic plasterboard (drywall), two layers, 8 sheets; Acoustic sealant, 0.92 L; Skim finish coat (plastering), 27.6 kg; Skirting (baseboard), 4.4 m; Painting and decorating (decoration): two coats, a mist coat apart, 1.92 L. Opened at Floor protected 130 sq ft · Length of the party wall lined 13 ft · Height of the lining, floor to ceiling 8 ft: Masking and protection materials, 2 items; Studs and plates (independent frame, studwork), 13 studs; Mineral wool batts, 3 packages; Mass-loaded vinyl (MLV, acoustic membrane), 109 sq ft; Dense or acoustic plasterboard (drywall), two layers, 8 sheets; Acoustic sealant, 0.27 gal; Joint compound and tape (or a skim coat of compound), 1 x 4.5 gal box; Skirting (baseboard), 14.3 linear ft; Painting and decorating (decoration): two coats, a mist coat apart, 0.52 gal. Every figure follows the dimensions you give it.
Which calculators does the party wall soundproofing takeoff run?
9 calculators, one to a line: Masking and Protection Materials Calculator, Framing Stud Calculator, Mineral Wool Insulation Batt Calculator, Mass-Loaded Vinyl (MLV) Soundproofing Barrier Calculator, Ceiling Plasterboard Calculator (Gypsum Board Sheets), Acoustic Sealant Bead Volume Calculator, Drywall Joint Compound Calculator, Baseboard & Trim Calculator, Paint Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.9 calculators, one to a line: Masking and Protection Materials Calculator, Framing Stud Calculator, Mineral Wool Insulation Batt Calculator, Mass-Loaded Vinyl (MLV) Soundproofing Barrier Calculator, Ceiling Plasterboard Calculator (Gypsum Board Sheets), Acoustic Sealant Bead Volume Calculator, Skim Coat Plaster Calculator, Baseboard & Trim Calculator, Paint Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
What does the party wall soundproofing takeoff leave out?
10 things, each named on this page: Flanking sound through the rest of the structure, which this job leaves as it is; Sound tests of any kind, before the work or after it, the pre-completion test in England and Wales among them; Notice to the neighbour, and any surveyors' award under the 1996 Act, where the shared structure is touched at all; Strengthening a floor for the added mass (flagged); Ventilating the sealed room; A heater moved elsewhere, or its pipe runs rerouted; Crown molding (coving) put back along the new lining; A fire rating; Green Glue or another damping compound between the layers; Damping compound between the layers, which no row here measures.
Can I check a quote for this job against the takeoff?
Yes. The party wall soundproofing quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.