Cross-market term

Battens, furring and strapping

A thin strip of timber or metal fixed across a structure to carry a covering, to hold it off the surface behind, or to cover a joint. The word travels across markets; what it is carrying does not.
  • 4Markets
  • NoSame thing everywhere
  • 3Calculators

What it is called, by market

One concept, four markets. Where a name means something else locally, the card says so rather than leaving you to find out on site.

  • United Kingdom

    Same word, different thing

    batten

    also tile batten, counter-batten, roofing batten

    A UK tile batten is a structural component with a graded specification and a gauged spacing set by the covering. A counter-batten runs the other way beneath it to form a drainage and ventilation path.

  • Australia

    Close, not identical

    batten

    also roof batten, top hat batten, ceiling batten

    Frequently a steel top-hat section rather than timber, and in sheet-roofing practice the batten does the job a purlin does elsewhere.

  • United Statesyours

    Same word, different thing

    furring strip

    also furring, batten, 1x3

    Furring is usually about levelling a surface or creating an air gap, not about carrying a tile. And board-and-batten names a cladding pattern where the batten is the visible strip over a board joint.

  • Canada

    Same word, different thing

    strapping

    also furring, batten, 1x3 strapping

    Canadian strapping is the light battens run across joists or studs before boarding. In UK usage strapping means metal restraint straps tying a wall to a floor, which is a structural component.

The governing standard, by market

  • United Kingdom

    BS 5534 / BS EN 15228

    Batten sizes, grading and fixing for slating and tiling, and preservative treatment.

  • United States

    ASTM E2925 / IRC Chapter 7

    Furring and rainscreen assemblies, and requirements for wall covering support.

Calculators for this

Each works in either measurement system, and the terminology on the page follows whichever market you have selected.

Frequently asked questions

Is a roofing batten the same as a furring strip?
No, and the difference is that one is graded structure and the other is packing. A British roofing batten carries the whole weight of the tiles or slates plus anybody walking on the roof, spans between rafters, and resists the uplift trying to pull the covering off — so it has a specified size, a strength grade, a knot and wane limit, and a preservative treatment, and substituting an ungraded strip of the same dimensions is a real reduction in the roof. A furring strip is normally doing none of that: it levels an uneven surface, holds a covering off the wall to create a drained cavity, or gives a fixing line. Both are thin strips of timber, and only one of them is a structural member.
What does the batten gauge mean, and why is it not simply the tile length?
The gauge is the distance from one batten to the next, and it is the tile length MINUS the lap, divided by however many courses cover a given tile. Each course has to overlap the one below by enough to keep water out, so the exposed part of a tile is always shorter than the tile — which is why a 265 mm tile at a 65 mm lap gives a gauge around 100 mm on a double-lap covering rather than anything resembling 265 mm. The lap itself depends on the roof pitch and on the exposure of the site, so the same tile on a shallower roof needs a bigger lap, a tighter gauge, more battens and more tiles. Taking the gauge from a table without checking the pitch it was written for is one of the ways a tile order comes out short.
Why would a roof have battens running in both directions?
Because the second set creates a drainage and ventilation path that the first set blocks. Where an underlay is laid over the rafters and the tile battens go straight onto it, each batten sits tight against the underlay and acts as a small dam: water running down the underlay is held at every batten line, and air cannot move up the slope. Counter-battens fixed along the rafters first, with the tile battens across them, lift the whole grid clear so water runs to the eaves and air passes behind the covering. It matters most on low pitches, on long slopes, and wherever the underlay is vapour-permeable and depends on that air movement to work. It also adds a full extra set of timber and a longer fixing to the material list, which is why it should be identified before pricing rather than discovered on site.