Rainscreen cladding on battens takeoff
Clad a wall in timber, fibre-cement or composite boards or panels on battens (furring strips) over a breather membrane, with a drained, ventilated gap behind: scaffold, the membrane, battens and counter-battens, cavity barriers where a fire strategy draws them, the boards or panels and their fixings, trims, vented closers with insect mesh, mastic at the frames and the offcuts, with the barriers and the fixings' design flagged and never certified.
- Measurements in
- 8
- Trades out
- 1112
- Calculators
- 10
- Going in
- 1112of 1112
- My Project
- Not in it
No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.
Dimensions
Give the job once
Every figure on the right follows these, in the units you choose.
Choose the build-up
Each layer changes the materials below; the dimensions stay the same.
Calculators behind the other choices:
Calculators behind the other choices:
Every trade, from those dimensions
then change a dimension, and each line shows what moved.
Every trade's quantity · 11 rows
Every trade's quantity · 12 rows
Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.
About this job
A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.
Rainscreen cladding hangs boards or panels off a wall on battens, with an open gap behind them. Rain that passes a joint runs down the back of the boards and out at the foot of the gap, and air moving up it dries what is left; the breather membrane (house wrap, a weather-resistive barrier in North American terms) behind the gap keeps the wall itself dry. Nothing is stuck to the wall, which is what separates it from a rendered insulation system: every layer is screwed or nailed to the one it hangs from, and every board can come off again.
The rows are the layers from the wall outwards. The membrane covers the wall's whole face, taped into each opening rather than cut away. The battens are measured by length at the centres the boards need, and upright boards take two layers, battens across the wall over upright counter-battens, so water always has a way down. The boards are counted along the run; the trims go up each outside corner and round each opening; the vented closers with insect mesh run along the foot and head of the gap and over and under every window; and the mastic (caulk) goes round each frame.
The units pick the cladding. With metric showing, the page opens on upright boards with cover battens, the board-on-board look a British house is clad in, counted by the board; with imperial showing, on horizontal lap siding on upright furring strips, measured in squares (100 sq ft, 9.29 m²). Fibre-cement or composite panels screwed or riveted to rails are the third choice in either, and fibre cement of any shape is cut outside with the dust controls its maker sets.
The fire question lives in the gap. An open cavity running up a wall behind combustible boards can carry fire up the face, which is why a fire strategy may ask for cavity barriers across it, open-state strips that close when heated, and why on some buildings the rules limit what may be fixed to a wall at all. The page measures the barrier along the number of lines you enter and counts where each batten crosses one; where the lines go, which product, and whether any of it is allowed are for the fire strategy and building control, and none of it is signed off here.
How each line reads
- Base
- What the calculator gives for these dimensions, before anything is added.
- Allowance
- Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
- Adjusted
- The base with its allowance on top.
- Order
- What to buy: the adjusted figure in whole boards, bags, rolls or lengths.
The order this happens in
Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.
- Settle the cladding system, the fire strategy's barrier lines and any building control or permit, and have old boards that could contain asbestos sampled before anything is stripped.
- Put the scaffold up, isolate the outside lights and take them off with the downpipes (downspouts), pipes and brackets; strip any old cladding, battens and membrane, and sheet the wall at night while it is open.
- Fix any insulation boards to the wall, then the breather membrane (house wrap) from the bottom up so each course laps over the one below, taped into every opening.
- Fix the battens (furring strips) plumb at the centres the boards need, counter-battened where the boards run upright, and fit the cavity barriers across the gap along their lines, sealed round every batten that crosses.
- Fit the vented closers with insect mesh at the foot of the gap, then the corner trims and the head and sill trims round each opening, and get any boiler flue lengthened by the gas engineer while the gap is still open.
- Hang the boards or panels from the bottom up, gapped as their maker asks, cutting fibre cement outside with its dust controls, and extend the fascia first where the overhang no longer clears; close the head of the gap under the eaves with its vented closer.
- Seal each frame with mastic (caulk), stain or paint boards that are finished on site, and refix the downpipes and lights through the cladding on longer fixings.
- Clear the offcuts and any stripped cladding, check every closer, trim and barrier from the scaffold while it still stands, then pass on the cladding and barrier makers' details.
What this takeoff does not cover
- The fire strategy: which walls need cavity barriers and where their lines go, which product and rating, and whether the boards, the membrane and whatever lies behind them may be used on this building at all. The barrier row measures the lines you enter and signs off none of them.
- The structural fixing of the battens or rails: their section, how they are fixed through whatever lies behind them into the wall, and what the wall holds against the wind. The rows count battens at the page's centres and panel fixings at its opening figure per panel.
- Repairs to the wall behind once old cladding or siding comes off in the strip out: rotten sheathing or studs, loose masonry, damp. They are found when the wall is opened and listed nowhere here.
- The timber's species, grade and treatment, and any fire-retardant treatment a board may need; the rows count boards of the width given.
- Moving a gas or electricity meter or its box, which only the supplier or the network operator does, and the flue's design and certification, which is the registered gas engineer's.
- Whether the new facing needs planning permission, and the consent a conservation area or a listed building needs; in North America, a historic district's approval.
- Insulating the wall to a target: the insulation option counts mineral wool boards over the face at the size its page opens on and chooses no thickness.
- Replacing the roofline, and the carpentry that brings the eaves or a verge out: extending the fascia, soffit and bargeboards where the overhang no longer clears the new face is listed as work, and the rafter feet or gable ladder behind them are not sized.
- The windows and doors themselves, and the sills under them; the trims and closers round them are counted.
- A line of its own for the cover battens over board-on-board cladding: one over every gap between boards plus one to finish each end of a wall, each cut to the height clad, counted in the board row's working and not compared.
- The starter strip, J-channel and corner posts that plastic siding hangs from: bought by length with the siding, for its own profile, and in no row's count here.
Labour by trade
Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.
Metric opening
Length of wall clad, walls end to end 16 m · Height clad 5.2 m · Windows 6 and 5 more of the page's opening figures
Imperial opening
Length of wall clad, walls end to end 52 ft · Height clad 17 ft · Windows 6 and 5 more of the page's opening figures
Quote check
Been given a quote for this job?
Paste it into the rainscreen cladding quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.
What it leaves out
Every line this takeoff has that nothing on the quote reads as.
What it adds
Labour, removal, hire, fees — each named for what it is.
What to ask
One list of questions, ready to copy. Never a verdict.
More takeoffs
Other job takeoffs
External wall finish
3 tradesWrap, cladding and finish over a measured wall area.
Run this takeoffInsulate a floor
3 tradesInsulation, vapour control and underlayment over a floor area.
Run this takeoffFibre cement siding
5 tradesCourses, cutting waste, corner posts, fasteners and caulk for a lap-sided elevation.
Run this takeoff
Frequently asked questions
- What does the rainscreen cladding takeoff give for a typical job?
- Opened at Length of wall clad, walls end to end 16 m · Height clad 5.2 m · Windows 6 · Window opening width, each 1.2 m · Window opening height, each 1.2 m · Doors 1 · Outside corners 2 · Cavity barrier lines across the gap 1, it orders: Ground sheeting under the clad walls, and tape at the frames, 3 items; Scaffold along the clad walls, 83.2 m² of face; Breather membrane (house wrap, weather or water resistive barrier), 1 roll; Counter-battens, upright over the membrane, 213 m; Cavity barriers or blocking across the ventilated gap, 17.6 m; Horizontal battens carrying the boards, 224 m; Corner and opening trims, 15 sheets; Vented closers (vent closures) with insect mesh, 16 sheets; Cladding boards, board on board (timber, fibre cement or composite), 92 boards; Mastic (caulk) at the frames, 1.26 L; Stain, oil or paint on the boards, 20.8 L; Skip (dumpster) for offcuts, 1.66 m³. Opened at Length of wall clad, walls end to end 52 ft · Height clad 17 ft · Windows 6 · Window opening width, each 4 ft · Window opening height, each 4 ft · Doors 1 · Outside corners 2 · Cavity barrier lines across the gap 1: Ground sheeting under the clad walls, and tape at the frames, 3 items; Scaffold along the clad walls, 884 sq ft of face; Breather membrane (house wrap, weather or water resistive barrier), 1 roll; Furring strips (battens), upright, 680 ft; Cavity barriers or blocking across the ventilated gap, 57.2 ft; Corner and opening trims, 15 sheets; Vented closers (vent closures, vent strips) with insect mesh, 16 sheets; Lap siding or cladding boards (wood, fibre cement or composite), in squares, 8.5 squares; Mastic (caulk) at the frames, 0.38 gal; Stain, oil or paint on the boards, 5.5 gallons; Skip (dumpster) for offcuts, 2.15 yd³. Every figure follows the dimensions you give it.
- Which calculators does the rainscreen cladding takeoff run?
- 10 calculators, for 11 lines: Masking and Protection Materials Calculator, Scaffold Face Area and Hire Quantity Calculator, House Wrap Calculator, Rain-Screen Cladding Furring Strip Calculator, Cavity Barrier Run and Crossing Count Calculator, Exterior Flashing Layout Trim Sheet Calculator, Siding Calculator, Fiber-Cement Siding Caulk Joint Volume Calculator, Exterior Paint Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.10 calculators, for 12 lines: Masking and Protection Materials Calculator, Scaffold Face Area and Hire Quantity Calculator, House Wrap Calculator, Rain-Screen Cladding Furring Strip Calculator, Cavity Barrier Run and Crossing Count Calculator, Exterior Flashing Layout Trim Sheet Calculator, Board and Batten Siding Calculator, Fiber-Cement Siding Caulk Joint Volume Calculator, Exterior Paint Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
- What does the rainscreen cladding takeoff leave out?
- 11 things, each named on this page: The fire strategy; The structural fixing of the battens or rails; Repairs to the wall behind once old cladding or siding comes off in the strip out; The timber's species, grade and treatment, and any fire-retardant treatment a board may need; the rows count boards of the width given; Moving a gas or electricity meter or its box, which only the supplier or the network operator does, and the flue's design and certification, which is the registered gas engineer's; Whether the new facing needs planning permission, and the consent a conservation area or a listed building needs; in North America, a historic district's approval; Insulating the wall to a target; Replacing the roofline, and the carpentry that brings the eaves or a verge out; The windows and doors themselves, and the sills under them; the trims and closers round them are counted; A line of its own for the cover battens over board-on-board cladding; The starter strip, J-channel and corner posts that plastic siding hangs from.
- Can I check a quote for this job against the takeoff?
- Yes. The rainscreen cladding quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.