Stormwater

Sizing a Soakaway From Three Timed Fills

Three timed water drops in a trial pit give one infiltration rate. Storage volume, crate count and the half-drain check all fall out of it.
  • 21 minReading time
  • 11Sections
  • 8Calculators inline
  • Last reviewed

The Condition Nobody Read Until the Steels Were In

A single-storey rear extension, 46 m² (about 495 sq ft) of new roof on plan, and a full plans approval issued eight weeks earlier with a condition attached to it that nobody had opened since: surface water to be disposed of by soakaway, sized in accordance with BRE Digest 365, calculations to be submitted before the drainage is covered. The builder had run 110 mm pipe from both new downpipes to a point past the patio and left the ends capped in a heap of spoil, on the reasonable assumption that a hole full of stone at the bottom of the garden is a soakaway. The inspector's position was that a hole full of stone is a hole full of stone until somebody has measured how fast the ground takes water, and that the measurement has to happen at the depth the thing will actually be built at.

That is the whole job in one sentence. A soakaway is not sized from its footprint, from the roof area alone, or from what the neighbours put in. It is sized from a rate measured on the plot at the right level, before any of the arithmetic downstream means anything — and that measurement takes a full day of somebody's attention plus a bowser or a standpipe and a great deal of water, which is why it is the step that gets skipped and then has to be done anyway with the trench already open. The choice between a stone-filled trench and a stack of plastic cells is not a preference either; it falls out of the rate you measured and the shape the garden will let you dig.

What sits in the hole, top to bottom

A crate soakaway in section, six layers deep: turf and topsoil over compacted backfill, a geotextile wrapped around a geocellular core, blinding stone across the excavated base, and the undisturbed subgrade that is the only part of the assembly actually taking water away.
  1. Turf and topsoil — the cover that has to be replaced and usually settles twice, bought by area against a stated depth rather than by the bag Topsoil Calculator
  2. Compacted backfill over the core — placed in shallow lifts so the cells below are not crushed, and rarely the same material that came out of the hole Trench Excavation & Backfill Volume Calculator
  3. Geotextile wrap — keeps fines out of the voids from every side and is measured by wrapped surface area with laps, not by plan area Driveway Separation Geotextile Roll Calculator
  4. Geocellular storage core — the storage itself — modular cells at roughly 95% void, counted as whole units and never cut to fit a calculated volume PICP Permeable Pavement Infiltration Storage Calculator
  5. Blinding stone on the base — a clean single-size layer giving the cells a flat bearing without smearing the formation beneath them Gravel Calculator
  6. Undisturbed subgrade — the only surface in the drawing that removes any water at all, and the one the percolation test was measuring Permeable Reservoir Drawdown Time Calculator

One Hole, Three Fills, and the Slowest Answer Wins

The trial pit is dug where the soakaway is going and down to the level its base will sit at, because the horizon that matters is the one the water will actually meet. Topsoil takes water freely and says nothing useful about the clay 1.4 m (4 ft 7 in) beneath it, and a rate measured in the first spit is the commonest way a soakaway ends up half the size it needed to be. A pit long and narrow rather than square gives more wetted side for the same volume of water and behaves more like the finished thing.

BRE Digest 365 fills the pit to a marked effective depth, lets it fall, and times the passage between the levels at 75% and 25% of that depth. The middle half of the drop is used because the ends are the untrustworthy parts: the first minutes are dominated by whatever the excavator smeared onto the sides, the last by the base, which on a real soakaway is assumed to silt up and stop working. What comes out is a soil infiltration rate f in metres per second — the volume that left between the two marks, divided by the pit's wetted area up to half depth, divided by the seconds it took.

The area term is where this method is misapplied more often than anywhere else. For the trial pit the area is taken to half the effective depth including the base; for the finished soakaway it is the side area to half depth with the base written off, on the grounds that the base is where fines end up. Two different definitions, one page apart, and using the pit's figure for the soakaway inflates the answer by whatever fraction of the area the base happened to be. Check the definition against the edition of the Digest you are working to before the arithmetic is worth checking.

Three fills, because one is an anecdote. The first is heavily influenced by how dry the ground was when you started; the third is closer to the wetted condition the soakaway lives in through a wet February. Take the slowest of the three — the longest time, the lowest f — and design on it. On this plot a pit 1.5 m long by 0.5 m wide, filled to 1.0 m, held 0.375 m³ between the two marks against a wetted area of 2.75 m² to half depth, and drained in 9 h 40 min, 11 h and 11 h 50 min. The last of those gives f = 3.2 × 10⁻⁶ m/s, which is 11.5 mm/hr or 0.45 in/hr. That is a sandy clay: not a refusal, but nowhere near free-draining, and it is the number every remaining sum on this page runs on.

  1. Dig the pit at the soakaway's own position and to its finished base level, and log what the sides show as you go — BS 5930 practice, even on a domestic plot, because the horizon the water meets is the finding.
  2. Treat anything over 1.2 m as an excavation to be entered under HSE HSG185 rather than leaned into: measure from the surface with a tape and a float rather than climbing down to read a mark.
  3. Mark the effective depth on a batten fixed to the side, then mark 75% and 25% of it — the marks, not the pit, define the test — and time the fall between them in seconds, with a watch rather than a memory.
  4. Repeat twice more, refilling as soon as the previous fill has emptied, so the later tests run on progressively wetted ground.
  5. Divide the volume between the two marks by the wetted area to half depth and by the slowest time to get f, and record all three results rather than only the one you used.
  6. Leave the pit open overnight before backfilling and look again in the morning — water standing in it that you did not put there is groundwater, and that is a different conversation entirely.
The three fills on this plot, and what each one is evidence of
FillTime from 75% to 25%Rate impliedWhat it tells you
First9 h 40 min (34,800 s)3.9 × 10⁻⁶ m/sDry ground taking water into unsaturated soil above the wetting front. Optimistic by construction.
Second11 h (39,600 s)3.4 × 10⁻⁶ m/sThe soil is beginning to behave as it will in a wet week. The trend, not the value, is the signal.
Third11 h 50 min (42,600 s)3.2 × 10⁻⁶ m/sWetted condition, and the figure the design is built on. If it were still falling steeply, a fourth fill would be cheaper than a resubmission.
The three fills on this plot, and what each one is evidence of

The pit's length, width and effective depth, and the time each fill took between the two marks: the rate comes back from the slowest fill, with each fill's own rate beneath it — the trend across the three that the table above reads.

The pit's internal length at the level of the test.

The pit's internal width.

The depth of water the pit is filled to, from its base to the marked fill level.

The minutes the level took to fall from the 75% mark to the 25% mark on the first fill.

The minutes the level took to fall from the 75% mark to the 25% mark on the second fill.

The minutes the level took to fall from the 75% mark to the 25% mark on the third fill.

Soil infiltration rate f (slowest fill)

0.44 in/h

High confidence

BRE Digest 365 states the same rate in metres per second, the figure the storage and half-emptying sums take. The design runs on the slowest of the three fills, the one closest to the ground's wet-season condition.

Water lost between the 75% and 25% marks
0.49 yd³
Wetted area to half depth, base included
30.25 ft²
Slowest fill, 75% to 25%
710 min
Rate from fill 1
0.54 in/h
Rate from fill 2
0.47 in/h
Rate from fill 3
0.44 in/h

Add the equipment this sizes

This result is a specification — 0.44 in/h — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

5 ft1.5 ft3.5 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • The trial pit's area is taken to half depth INCLUDING its base; the soakaway's own area in the storage sum is the sides only, because a soakaway's base silts up. Using the pit's figure for the finished soakaway overstates what it will drain.
  • It measures the horizon the pit was dug in. A pit that stops in topsoil above a clay, or a rate measured in the first spit, says nothing about the ground the soakaway will actually sit in.
  • A rate from one location on one day. Ground varies across a site and through the year, a rising water table stops a soakaway working, and building control may ask for a test in the wetter months.

The Storm That Sizes It Is Not the One You Would Guess

Storage is a volume problem, not a flow problem. Water arrives over the duration of a storm and leaves through the sides at f the whole time, and what has to be held is the difference between the two totals. Inflow over a storm of duration D is the impermeable area times the rainfall depth for that duration at the design return period; outflow over the same D is the side area to half depth times f times D. The storage you must provide is the largest value of inflow minus outflow across every duration tested — a search rather than a single sum, because inflow rises fast then flattens while outflow rises in a straight line forever.

Which duration wins depends on the ground. On free-draining sand the outflow term catches up quickly and the critical storm is short and violent. On this plot, at 3.2 × 10⁻⁶ m/s, it does not catch up for the better part of a day, and the critical duration lands somewhere between six and twenty-four hours. Anyone who sized this from a one-hour storm — the instinct, because that is the storm you can picture — would have built roughly two-thirds of what the ground needs. Run the durations the Digest lists and take the worst; do not decide in advance which one it will be.

The rainfall depths belong to the location and to no calculator on this site. BRE Digest 365's own tables are built on the Flood Studies Report rainfall statistics — the M5-60 depth and the ratio r — while current UK practice reads depth-duration-frequency data from the Flood Estimation Handbook, and North American work reads NOAA Atlas 14 or whatever the state manual has adopted in its place. The return period is not yours to choose either: it comes from Approved Document H and from whatever the local authority has adopted alongside it, and a climate-change uplift on top — in England, the Environment Agency's published peak rainfall intensity allowances — is now routine rather than optional. The five depths used below — 12 mm at fifteen minutes, 22 mm at an hour, 40 mm at six hours, 65 mm in a day and 80 mm over two — are placeholders chosen to show which term wins, and they are not data for your postcode.

The duration search for 46 m² of roof at f = 3.2 × 10⁻⁶ m/s, against a 4.0 m × 0.5 m × 1.2 m store
Storm durationInflow (m³)Outflow through the sides (m³)Storage still required (m³)
15 minutes0.550.020.54
1 hour1.010.060.95
6 hours1.840.371.47
24 hours2.991.491.50 — the critical case
48 hours3.682.990.69
The duration search for 46 m² of roof at f = 3.2 × 10⁻⁶ m/s, against a 4.0 m × 0.5 m × 1.2 m store

The duration search above, with the storms' rainfall depths taken from the local data: the impermeable area, the rate from the trial pit and the store's plan, depth and void ratio give the storage the critical storm leaves behind, and the breakdown carries the store's time to empty to half and the plan shape that would do it within the day.

The plan area of roof and paving that drains to this soakaway.

The slowest rate from the trial pit, from the soakaway infiltration rate calculator.

The internal length of the store — the crate run or the stone-filled trench.

The internal width of the store.

The depth of the store below the inlet, which is the depth that can hold water.

About 0.95 for geocellular crates and about 0.30 for clean single-size stone.

A storm duration to test, in minutes.

The rainfall depth for that duration at the design return period, from your site's rainfall data.

A storm duration to test, in minutes.

The rainfall depth for that duration at the design return period, from your site's rainfall data.

A storm duration to test, in minutes.

The rainfall depth for that duration at the design return period, from your site's rainfall data.

A storm duration to test, in minutes.

The rainfall depth for that duration at the design return period, from your site's rainfall data.

A storm duration to test, in minutes.

The rainfall depth for that duration at the design return period, from your site's rainfall data.

A storm duration to test, in minutes.

The rainfall depth for that duration at the design return period, from your site's rainfall data.

A storm duration to test, in minutes.

The rainfall depth for that duration at the design return period, from your site's rainfall data.

A storm duration to test, in minutes.

The rainfall depth for that duration at the design return period, from your site's rainfall data.

Storage required at the critical storm

1.91 yd³

Medium confidence

The store as drawn holds more than the critical storm leaves behind. It empties to half within the 24 hours BRE Digest 365 asks for.

Storage the store provides
2.74 yd³
Critical storm duration
1,440 min
Inflow over the critical storm
3.86 yd³
Outflow over the critical storm
1.95 yd³
Side area to half depth (base excluded)
58 ft²
Time to empty to half
16.9 hours
Time the Digest asks for, at most
24 hours
Plan area ÷ perimeter
0.67 ft
Largest plan area ÷ perimeter that half-empties in 24 hours
0.95 ft

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

13 ft1.5 ft4 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • The rainfall depths belong to the site and to the approving authority's design standard — return period, climate-change allowance — and none of the defaults on this page is data for any location.
  • The store is taken as a rectangle with vertical sides, emptying through its sides only; the base is written off because it silts up. A soakaway ring, a sloping-sided pit or a store with a sealed side needs its own side area.
  • The half-emptying time is worked on the storage the store provides, full to its effective depth. A store that is only part-filled by the design storm empties the same fraction in the same time, because the side area and the stored volume fall together.
  • A soakaway is an infiltration device, and it is only the right answer where the ground takes water, the water table stays below it, and it is far enough from buildings and boundaries; building control and the Building Regulations' drainage guidance settle those before the arithmetic starts.

A Box That Is Mostly Gap

The store holds nothing itself; it holds what fits between the bits of it. Clean single-size aggregate to BS EN 13242 gives about 30% voids, and geocellular cells give about 95% — the datasheets across the common systems, Polypipe's Polystorm, Wavin's AquaCell and ACO's StormBrixx among them, all sit around that figure, and the exact number belongs to the product actually bought rather than to a rule of thumb. That single ratio is the entire difference between the two ways of building a soakaway: 1.5 m³ of storage takes 1.6 m³ of crates or 5.0 m³ of stone, and the hole follows the material.

Storage volume itself is the least interesting multiplication on the page — plan area by depth by void ratio — and it is worth doing on a calculator only because it is the one place a unit slip goes unnoticed. What the page below cannot do is model a crate stack: it is a permeable-pavement page, its void-ratio field is bounded to the 0.25–0.45 range open-graded aggregate actually occupies, and 0.95 is outside it. So is the drawdown page in the section after next, which stops at 0.45 for the same reason. Use them for the stone version. The storage page in the section above is the BRE sum itself and accepts either fill, crates or stone, with the manufacturer's void figure in its void field.

Plan area, storage depth and void ratio, for the aggregate version of the store — the same multiplication that decides whether the box you have drawn holds the volume the duration search asked for.

The total surface area of the permeable interlocking concrete pavement.

The depth of the open-graded aggregate reservoir layer beneath the pavement.

The fraction of the aggregate layer's volume that is open void space available for water storage.

Stormwater storage volume

3,160 gal

Medium confidence

Void ratio depends on the specific aggregate gradation used — confirm the actual void ratio for your chosen open-graded base material (commonly tested per ASTM C29) rather than assuming a generic value.

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

aggregate reservoir 11.75 inaggregate reservoir 298.45 mmsubgrade

What this calculation does not cover

  • It gives the void volume the stone can hold, not whether that water leaves. Drawdown depends on the subgrade's infiltration rate measured at formation level and on the safety factor your authority applies to it, and neither is an input here. A reservoir that holds the volume but will not empty within the permitted time still fails.
  • There is no demand side to this. Design storm, rainfall depth and run-on from adjacent roof or asphalt sit outside the model, so the number tells you what the section holds, not what it has to hold. A bay taking run-on is asked to store several times its own rainfall, and most manuals cap that run-on ratio.
  • Full depth is assumed available across the whole footprint, level. Sloping subgrade, check dams, and an underdrain invert set above the bottom of the stone all cut usable storage - on a sloped site without check dams only the deep end fills - and none of that is modelled.
  • Only the reservoir layer counts. Bedding and choker courses, a sub-base of a different gradation, and the joint fill contribute nothing to this figure, and there is no allowance for void space lost as sediment works down into the stone over the life of the system.
  • This is a volume estimate, not a stormwater design or a pavement section design. It does not check separation between the reservoir bottom and groundwater or bedrock, does not size the section for traffic, and does not demonstrate compliance with a water quality volume or a discharge rate. The void fraction a reviewer will credit is often lower than what the stone actually holds.

Half Empty in a Day, or the Shape Is Wrong

The second check is the one that fails good-looking designs. A soakaway that holds the design storm but is still half full a week later is not available for the next storm, so BRE Digest 365 asks that it discharges half its stored volume within 24 hours. That is a different sum from the storage one and it can fail while the storage sum passes comfortably — which is exactly what happened here on the first attempt.

The first store drawn was a compact box: 2.0 m by 1.2 m of crates, 1.2 m deep, 2.74 m³ of storage against 1.93 m³ required. Ample. Its half-drain time came out at 30.9 hours, and it was rejected. Re-laid as a 4.0 m by 0.5 m trench — one crate module wide, twelve modules in total, three courses of four — it takes slightly fewer cells, 2.4 m³ of them against 2.88, holds 2.28 m³ of water, still comfortably over the 1.50 m³ that geometry needs, and half-drains in 18.3 hours. It got smaller and it drained faster, because what changed was the perimeter.

There is a clean reason for that, and it is worth deriving once because it kills a lot of wasted redrawing. Half the stored volume is plan area times depth times void ratio, divided by two. The side area to half depth is perimeter times depth, divided by two. Divide one by the other and the depth cancels completely: half-drain time is plan area over perimeter, times void ratio, divided by f. Depth does not appear. Making a failing soakaway deeper does not help it drain, and making it shallower does not either — only making it narrower does. Rearranged, the shape passes when plan area divided by perimeter stays below f × 86,400 ÷ void ratio. On this plot that limit is 0.29 m for crates and 0.92 m for stone: the compact box sat at 0.375 and failed, the trench at 0.222 and passed, and the same box built in stone would have passed on the void ratio alone.

The BRE side-area sum itself is the storage page two sections up, which gives the half-emptying time and the largest plan-area-to-perimeter ratio that meets the day beside the storage. The calculator below is a one-dimensional vertical model — stored water depth over a design rate, with a safety factor on the measured figure and a permitted window to check against — which is how North American stormwater manuals frame the same question and how a permeable pavement reservoir is genuinely assessed. It will not reproduce the numbers above, and like the permeable-pavement page it stops at a void ratio of 0.45, so the stone version is the one you can put through it. Use it for what it is good at: seeing how hard the safety factor pushes the answer around, before committing to a shape with no margin in it.

Drawdown as a permeable-pavement reservoir is assessed — measured rate, safety factor, permitted window — which is the framing to use where the local manual sets a 48- or 72-hour limit rather than BRE's half-drain rule.

Depth of the open-graded storage layer, measured from the subgrade up to the top of the reservoir stone.

Fraction of the reservoir layer that is open void space rather than stone.

Field-measured rate at the excavation bottom, before any safety factor is applied (1 in/hr is 25.4 mm/hr).

Divisor applied to the measured rate to obtain the design rate, as required by the governing manual.

Whether a perforated underdrain relieves the upper part of the reservoir.

The longest drawdown the governing manual allows for this system.

Reservoir drawdown time

30.5 hours

Medium confidence

The reservoir empties with about 17.5 hours in hand against the permitted maximum. That margin is only as good as the infiltration test behind it — a single test on a variable soil is thin evidence for a whole footprint.

Design infiltration rate after the safety factor
0.24 in/hr
Depth of stored water that must infiltrate
7.2 in
Permitted maximum drawdown
48 hours
Margin against the permitted maximum
17.52 hours

What this calculation does not cover

  • One-dimensional vertical infiltration only: no credit is taken for lateral seepage out of the sides of the excavation, and none for evaporation.
  • Assumes the reservoir starts full. A design storm that only part-fills it drains proportionally faster.

Stone Instead: A Longer Trench and a Much Bigger Hole

Stone wins on drawdown and loses on excavation, and on a plot with room at the bottom of the garden that is often the right trade. The same 46 m² of roof, built as a stone soakaway rather than a crate one, needs 6.48 m³ of clean aggregate to provide 1.94 m³ of storage — a trench 6.0 m long by 1.2 m wide at 900 mm (3 ft) of stone, or 9.0 m by 800 mm at the same depth if the garden is a strip rather than a square. It half-drains in 13 hours and 9.6 hours respectively, against 18.3 for the crates, because 30% voids move less water per unit of side area than 95% do.

Long, narrow stone soakaways usually carry a perforated distribution pipe along their length so the inflow is spread rather than dumped at one end, and that pipe displaces stone you would otherwise have ordered. Over 9 m of 150 mm perforated pipe — 160 mm across the outside, which is the dimension that displaces stone — it is about 0.18 m³: small, but it is a real deduction and it is on the same order as the delivery shortfall people usually blame on the supplier.

Trench length, width and depth with the distribution pipe's own volume taken out — the stone-filled form of the same store, sized as the linear trench it usually wants to be. Its width field stops at 900 mm, so it will take the 9.0 m by 800 mm version above and not the 6.0 m by 1.2 m one; and its headline adds a fixed 10% waste you cannot switch off, which for the reasons in the next section you do not want here — take the trench and pipe lines from its breakdown and use the difference.

The total length of the drain trench.

The width of the trench, typically wide enough to work in comfortably.

The depth of the trench, below the frost line in cold climates if the drain must run year-round.

The outer diameter of the perforated drain pipe.

Gravel backfill needed

2.758 cubic yards

High confidence
Trench volume
2.67 yd³
Pipe volume (subtracted)
0.16 yd³

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

The pipe is drawn to scale inside the trench, because the gravel quantity above is the trench volume minus that circle. On a narrow trench with a big pipe the subtraction is a large share of the answer, and this is where you see that.

Perforated pipe — 4″Drainage gravel1′ 6″1′4″

What this calculation does not cover

  • The trench is modelled as a constant-depth rectangular prism, so a run laid to fall is only covered if the depth entered is the average depth over the whole length. A 15 m (49 ft) run at the usual 1 per cent fall finishes 150 mm (6 in) deeper than it starts, and a trench entered at its shallow upstream depth actually holds about 16 per cent more gravel than the figure returned.
  • Gravel is taken as filling the trench to the full depth entered, from the trench floor to ground level. Any soil or turf cap placed over the stone has to come off the depth before it is entered — a 100 mm (4 in) topsoil cap on a 460 mm (18 in) trench is more than a fifth of the volume this page returns.
  • The answer is a volume, not a tonnage, and the 10 per cent added covers ragged trench walls and settlement rather than compaction to a stated density. A quarry weighs stone out rather than measuring it, so converting needs the bulk density of the material actually supplied; clean drainage gravel is commonly quoted near 1.5 tonnes (1.7 tons) per cubic metre, which puts the default 2.81 yd³ order at roughly 3.2 tonnes (3.5 tons).
  • No check is made that the pipe fits the trench. A 200 mm (8 in) pipe entered against a 100 mm (4 in) trench width is accepted and answered normally at 0.31 yd³, and where the pipe would displace more than the trench holds, the result is floored at zero rather than reported as impossible geometry.
  • Pipe diameter enters this calculation only as displaced gravel, never as capacity. Whether the drain carries the water depends on the catchment area feeding it, rainfall intensity, the gradient and the infiltration rate of the surrounding soil — stepping from a 100 mm to a 150 mm pipe over 15 m moves this order by about 0.21 yd³ and settles none of those questions.

Ordering Aggregate Whose Whole Value Is What Is Missing

Two things go wrong when a soakaway's stone is ordered off a general aggregate calculation, and both come from the same place: a soakaway wants an open-graded, single-size, washed stone with the fines taken out, and most gravel sums are written for a base course that wants exactly the opposite.

The first is the compaction allowance. Every driveway and base-course calculation adds 15–25% because loose stone finishes compacted, and every one of those percentage points is a void you are paying to destroy. A soakaway's stone is placed, not rolled. Set the allowance to zero and order the volume you actually want to end up with.

The second is bulk density. The usual default of 1,600 kg/m³ describes a well-graded crushed stone whose small particles have filled the spaces between the large ones. A clean 20/40 single-size — the material a soakaway is built from precisely because it does not do that — comes in lighter, commonly nearer 1,350–1,500 kg/m³, and the honest figure is the loose bulk density on the supplier's own test data for that grade, determined under BS EN 1097-3 or ASTM C29/C29M. On the 6.48 m³ trench above, assuming 1,600 rather than being told 1,400 is 10.4 tonnes against 9.1 — more than a tonne you either paid for or did not get, depending which way round the mistake ran. The page below has 1,600 built into its tonnage and no field to change it, so it will hand you the 10.4: take the loose-volume line out of its breakdown instead and multiply by the density on the supplier's ticket.

Volume converted towards the tonne the aggregate is sold in — with the compaction allowance driven to zero, because compacting a soakaway's stone destroys the storage you bought it for, and with its fixed 1,600 kg/m³ replaced by the supplier's own figure for a single-size grade.

Gravel Calculator

Length of the area to cover.

Width of the area.

Depth of the gravel layer.

Extra to order because loose gravel compacts down.

Gravel required

6.59 US short tons

Medium confidence

Weighs the loose load at a typical loose bulk density of 1600 kg/m³ (100 pcf) for crushed stone or gravel as delivered. Ask your supplier for the loose density of the specific grade — a dense basalt and a light limestone differ by 15%.

Finished volume
4.07 yd³
Loose volume to order
4.89 yd³
Cubic yards
4.89 yd³
US short tons
6.59 tons

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

Plan of the slab, 33′ by 10′.33′10′

What this calculation does not cover

  • Length × width × depth is a single rectangle at a single thickness, so a drive that curves, splays at the entrance or opens out into a parking bay has to be measured as several rectangles and the answers added, and nothing is deducted for a manhole, a kerb line or a planted island sitting inside the area.
  • That thickness is then spread evenly over the whole footprint, which assumes ground already graded true — ruts, hollows and the first load that disappears into a soft patch are material the product of three numbers cannot see, and there is no separate term for a levelling course under the stone.
  • The compaction allowance is one flat percentage of the finished volume, applied to the whole job at once and stopping at 40%, rather than a figure derived from the grading or the moisture of what you are actually buying; it is also added to the finished volume rather than divided out of it, so 20% here means 1.20 times the finished figure, not the 1.25 that losing a fifth of a loose load to settlement would call for.
  • The weight and the loose volume are the same load: the tonnage is the loose volume to order, compaction allowance included, at one fixed loose bulk density of 1600 kg/m³ (100 pcf), with no field to change it. That suits stone delivered loose and spread or lightly rolled; a dense-graded base (crusher run, DGA, Type 1) specified by its compacted thickness weighs about 2200 kg/m³ (137 pcf) in place and is better worked on the gravel base tonnage page, which takes a compacted density.
  • Nothing in the arithmetic asks what will drive over the surface or what lies beneath it: any depth from 10 mm (0.39 in) to a metre is accepted without a check on wheel loads or subgrade strength, and a build that puts a coarse base course under a finer wearing course is two separate runs of this page rather than one.
  • What comes back is an exact arithmetic tonnage, not an order quantity — it is not rounded up to whole bulk bags, to the minimum load a tipper will bring out, or to the increment your yard sells in, so the last step of rounding upward is yours once you know how the material is sold.

The Hole, the Muck Away and the Run From the Downpipe

The excavation is bigger than the store in all three directions. The crate trench above is 4.0 m by 0.5 m of cells, but the dig is nearer 4.6 m by 1.1 m to give working space for wrapping the geotextile and for someone to stand while the cells are placed, and it goes 1.5 m deep to take 1.2 m of cells plus blinding and cover — around 7.6 m³ out of the ground. In a sandy clay that arises at roughly 1.25 times its in-situ volume once it is loose, so 9.5 m³ of spoil is looking for somewhere to go on a garden the extension has already occupied.

Almost none of it goes back. Cohesive spoil packed around a soakaway is the material the geotextile exists to keep out, and cover to a cell stack is normally a specified granular fill placed in shallow lifts, which means importing one load and carting another away — two vehicle movements down a domestic street, and the line most often missing from the quote.

The carrier trench from the downpipes is the other excavation and the more predictable one: 14 m of 110 mm pipe at 600 mm wide by 800 mm deep is 6.7 m³ out, about 7.6 m³ of loose granular back in once the pipe's own volume is deducted and a compaction factor applied. The calculator below reports the backfill as its headline; for the soakaway pit itself, take the total excavation figure from its breakdown and ignore the backfill line, since the pit is filled with cells and stone rather than with fill.

The dig and the fill for the carrier run, with the pipe's own volume deducted and a compaction factor on the loose material — and the excavation line in its breakdown for the soakaway pit itself.

The total length of the trench.

The width of the trench.

The depth of the trench.

The outer diameter of the pipe being laid; 0 for a trench with no pipe.

Depth of bedding material under the pipe; 0 if the pipe sits on the trench bottom.

Depth of the same bedding material over the top of the pipe; 0 for none.

Extra loose material needed to achieve full compaction in the void.

Loose backfill material needed

50.9 yd³

Medium confidence

Assumes the excavated soil itself isn't reused as backfill (e.g. importing clean granular fill) — if reusing native soil, account for its own swell factor separately.

Excavation volume (the depth entered)
48.89 yd³
Pipe volume (subtracted)
4.6 yd³
Compacted backfill void
44.29 yd³

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

The pipe is drawn to scale inside the trench. Backfill is everything else in the section, which is why the pipe diameter changes the answer at all.

Perforated pipe — 1′Backfill4′2′1′ 8″

What this calculation does not cover

  • The trench is modelled as a plain rectangular prism — vertical faces, one width and one depth over the whole run. Battered or benched sides, the extra width a trench box needs, over-break outside the drawn line, and a bottom that falls with the pipe's gradient are all outside it. A run cut back to a safe slope holds considerably more than this figure, and the shortfall rises with the square of the depth rather than in proportion to it.
  • This is a quantity take-off, not an excavation safety assessment. Nothing here classifies the soil, checks the depth against sloping, benching or shoring requirements, or sizes a protective system — that comes from a competent person on site, and past the depths the rules set, from an engineer.
  • Only the single pipe you enter is deducted. A second pipe or duct sharing the trench, cable bundles, manholes, chambers, valve boxes, thrust blocks and concrete surround all displace backfill and are not subtracted. No check is made that the pipe fits the trench you described either: where its volume exceeds the excavation, the answer is floored at zero rather than reported as impossible geometry.
  • At most two materials: a bedding and surround zone when you enter a bed or a cover, and one backfill above it at one flat percentage. The bedding row is an in-place volume across the full trench width, capped at the trench depth, with no compaction or waste allowance, so add your own for a graded bedding that is compacted. Marker tape or protective tiles, and the sub-base, blacktop or topsoil at the surface are further materials in further thicknesses and are not split out. The percentage is a loose-volume allowance on the backfill and nothing else — it is not a density or Proctor specification, and it says nothing about lift thickness or how many passes the plant makes.
  • Nothing is said about the spoil. The excavation row is a bank volume measured in place, not the loose volume that leaves in the truck, and the calculation does not judge whether the arisings can go back, how much of the void they would fill, or what has to be carted away. Rock, groundwater and dewatering, and over-excavation to remove unsuitable ground are all excluded.

What Happens on the Day It Fills

Every number so far has been a volume. Two things on the job are flows, and neither comes out of a storage sum: the pipe carrying the roof to the soakaway, and the route the water takes on the day a storm larger than the design one arrives — because one will, and the only question is whether it runs across a lawn or into an air brick. For both, the Rational Method is the right tool and storage is the wrong one. Peak discharge from a small catchment is runoff coefficient times intensity times area, and it sizes a pipe, a gully or a channel. It will not size the soakaway, and the calculator below says so itself: it returns a peak with no hydrograph and therefore no volume behind it. Keep the two apart in the submission as well as in your head, because a peak flow quoted as though it justified a storage volume gets an otherwise sound calculation sent back.

The exceedance route is a drawing, not a sum, and it is the cheapest insurance on the job: an overflow at the top of the store, a level threshold it discharges to, and a fall away from the building rather than towards it. Approved Document H's minimum separation between a soakaway and a building exists in part for this — the widely applied figure is 5 m, and it is a floor rather than a target. On a shrinkable clay, or where the extension's foundations are shallow, or where the ground falls towards the house, further is the answer and the geotechnical advice governs rather than the round number.

Peak flow for the carrier pipe and the overflow route, with the land beyond the boundary kept separate from the roof — and explicitly not for the storage volume, which needs a duration search rather than a peak.

Area inside the site boundary that drains to the point being sized.

Fraction of rainfall on the site area that becomes surface runoff.

Area beyond the boundary whose water crosses onto the site and has to be carried through it.

Runoff fraction for the surface beyond the boundary, which is rarely the same as the site's.

Average intensity of the design storm over the catchment's time of concentration (25.4 mm/hr is 1 in/hr).

Peak discharge

1.49 ft³/s

Medium confidence

The Rational Method returns a peak flow and nothing else — no hydrograph, no volume, no timing. It is accepted for small catchments and routinely rejected above a size limit written into the local ordinance, so check that limit before using this figure in a submission.

Total contributing area
34,450 ft²
Area-weighted runoff coefficient
0.63 (C)
Contribution from beyond the boundary
0.31 ft³/s
Share of the peak arriving from offsite
20.79 %

Add the equipment this sizes

This result is a specification — 1.49 ft³/s — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

What this calculation does not cover

  • Assumes uniform rainfall over the whole catchment for the full duration, and a single time of concentration for both areas.
  • Gives no runoff volume, so it cannot size detention or infiltration storage — those need a hydrograph method.

Five Metres, a Metre of Clearance, and the Ground That Says No

Position is checked before geometry, because a soakaway with nowhere legal to go is not a sizing problem. Separation from buildings comes from Approved Document H and is reinforced by BRE Digest 365; distance from a boundary, a highway, an existing drain run and anything with a tree on it are all live constraints. The tree is the one people forget: roots find the wettest thing in the garden, and the cells are it.

Groundwater rules out more sites than slow soil does. BRE Digest 365 wants the base of the soakaway clear of the highest expected groundwater level by a margin — a metre is the figure usually applied — and the percolation test tells you nothing whatever about that unless the pit was left open long enough for water to come back into it. A single dry-summer test on a plot with a winter water table at 1.5 m is a design that works beautifully until November. So is a test done in made ground on a plot where the natural horizon is 600 mm further down.

Then there is the case where the answer is simply no, and the shape rule above is what tells you. At f = 1 × 10⁻⁶ m/s the limit on plan area over perimeter falls to about 0.09 m for cells and 0.29 m for stone — a crate run under 200 mm wide, or a stone trench under 600 mm, before the storage volume is even considered. That is not a soakaway anyone is going to build in a garden. Past that point, CIRIA C753 and BS 8582 describe the same escalation the Building Regulations do: infiltrate if you can; discharge to a watercourse at a restricted rate with attenuation storage if you cannot; go to a surface water sewer with the undertaker's agreement if there is no watercourse; and treat a combined sewer as the last option, which most undertakers now refuse for new impermeable area. An attenuation tank with a flow control is a different design with a different governing document — CIRIA Report 156 and C753 rather than the Digest alone — and recognising that early is much cheaper than discovering it after the crates have been delivered.

One failure mode belongs here because it happens after everything above has been done correctly. The soakaway is finished, the calculation accepted, and then the site's own construction runoff — silt-laden water off a stripped garden — is allowed to find it. Fines in an open-graded void do not wash out: the infiltration surface you measured and the storage you paid for are both consumed in a wet fortnight, with no remedy short of digging it up. Keep dirty water out until the ground above is grassed or paved, capping the inlet and flooding somewhere harmless in the meantime if that is what it takes.

The Sheet That Closes the Condition

What discharges the condition is short, and it is almost never what gets sent first. It needs: the pit location and depth with a note of what the sides showed; the three timed fills with the volume and area terms written out, not just the resulting f; the design rainfall source, return period and any climate uplift, named; the duration search with the critical case marked; the store's dimensions, void ratio and the product it is built from; the storage provided against the storage required; and the half-drain time against 24 hours. Eight lines and a sketch. An inspector who can follow the arithmetic will accept it; one who is handed a single number and a product brochure will ask for all of the above anyway.

Keep the working, and not for the inspector. The day this house is extended again, or the drive is block-paved and another 30 m² of impermeable area appears, the whole question reopens — and its expensive part, a day with a bowser and an open pit, is already answered on ground that has not changed. A rate measured once and recorded properly outlives the calculation it was used for.

Settle these before the pit is backfilled

The workspace opens on the stone version of the store worked above — a 6.0 m by 1.2 m trench at 900 mm of clean aggregate at 30% voids — because the void-ratio field on that page is bounded to graded aggregate and will not take a crate's 95%. Replace the geometry with yours, then carry the same numbers through the drawdown, aggregate and excavation pages stacked beneath it.

  • Trial pit position, depth and what the sides showed — Dug where the soakaway goes and down to its base level. A rate measured in topsoil describes topsoil, and the horizon 1.4 m down is the one that will be doing the work.
  • Three timed fills, with the volume and area terms written out — Slowest of the three governs. Record all three: a rate still falling steeply on the third fill is an argument for a fourth, not for submitting the third.
  • Which area definition you used, and for which sum — The pit's wetted area to half depth includes its base; the finished soakaway's does not. Using one figure for both is the most common arithmetic error in the method.
  • Design rainfall source, return period and climate uplift — Named dataset and named document — FEH or NOAA Atlas 14 depths, return period from Approved Document H and the local authority's adopted standard, uplift stated rather than assumed.
  • Every storm duration tested, not just the one that won — Storage required is the maximum of inflow minus outflow across durations. On slow ground the critical storm runs for hours, and a one-hour design undersizes it badly.
  • Void ratio from the product datasheet, not from memory — About 0.95 for geocellular cells and about 0.30 for single-size aggregate. It sets the excavation, the delivery weight and the half-drain time all at once.
  • Plan area divided by perimeter, against f × 86,400 ÷ void ratio — The half-drain check reduced to a shape test. Depth cancels out of it entirely, so a failing soakaway is fixed by making it narrower, never by making it deeper.
  • Groundwater clearance and separation distances — Base clear of the highest expected water table by the margin the Digest asks for, and at least the Approved Document H separation from the building — more on shrinkable clay or shallow foundations.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • BRE Digest 365, Soakaway Design (Building Research Establishment)
  • Building Regulations for England, Approved Document H: Drainage and Waste Disposal — Section H3, Rainwater Drainage
  • BS 8582:2013, Code of Practice for Surface Water Management for Development Sites
  • BS EN 752, Drain and Sewer Systems Outside Buildings
  • CIRIA C753, The SuDS Manual
  • CIRIA Report 156, Infiltration Drainage — Manual of Good Practice
  • BS 5930, Code of Practice for Ground Investigations
  • BS EN 13242, Aggregates for Unbound and Hydraulically Bound Materials for Use in Civil Engineering Work and Road Construction
  • BS EN 1097-3, Tests for Mechanical and Physical Properties of Aggregates — Determination of Loose Bulk Density and Voids
  • ASTM D3385, Standard Test Method for Infiltration Rate of Soils in Field Using Double-Ring Infiltrometer
  • ASTM C29/C29M, Standard Test Method for Bulk Density (Unit Weight) and Voids in Aggregate
  • NERC Flood Studies Report, rainfall frequency statistics (the M5-60 depth and ratio r on which BRE Digest 365's tables are built)
  • Centre for Ecology and Hydrology, Flood Estimation Handbook depth-duration-frequency rainfall data
  • Environment Agency, Peak Rainfall Intensity Allowances for Climate Change
  • NOAA Atlas 14, Precipitation-Frequency Atlas of the United States
  • HSE HSG185, Health and Safety in Excavations: Be Safe and Shore
  • Construction (Design and Management) Regulations 2015
  • Polypipe Polystorm, Wavin AquaCell and ACO StormBrixx geocellular system datasheets, for module dimensions, void ratio and load class

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.