Materials & Quantities

Soil Swell & Shrinkage Haul Volume Calculator

Convert an in-situ (bank) soil volume into its loose (hauled) volume and its recompacted volume, using swell and shrinkage factors.

  • Answers as you type
  • Every formula cited
  • Calculated in your browser
SettingsSettings for this calculationUS
Market
Imperial · sales tax
The undisturbed, in-situ soil volume.

This is the volume measured before any excavation disturbs the soil.

How much the soil expands once excavated and loosened, as a positive percentage.

Common earth swells roughly 20-30%; rock can swell 40-70% or more.

How much smaller the soil ends up once recompacted, as a negative percentage.

Common earth typically shrinks 10-15% when recompacted relative to its original bank volume.

Loose (haul) volume

163 yd³

Medium confidence

Swell and shrinkage factors vary significantly by soil type and moisture content — use site-specific values from a geotechnical report or local hauling experience where available, rather than generic averages.

Bank (in-situ) volume
130.75 yd³
Compacted (recompacted) volume
117.68 yd³
Then change the inputs to see how far the answer moves.

Show calculation logic

How this was calculated

Formula source(s)

  • Standard earthwork volume states: loose (haul) volume = bank volume x (1 + swell%); compacted volume = bank volume x (1 + shrinkage%), where shrinkage is typically expressed as a negative percentage

Inputs used

Bank (In-Situ) Volume
130.75 yd³
Swell Factor (%)
25
Shrinkage Factor (%)
-10

Intermediate steps

Bank (in-situ) volume
130.75 yd³
Compacted (recompacted) volume
117.68 yd³
Final result163.44 yd³

Confidence note: Swell and shrinkage factors vary significantly by soil type and moisture content — use site-specific values from a geotechnical report or local hauling experience where available, rather than generic averages.

What this calculation does not cover

  • The swell and shrinkage percentages are figures you supply, not properties this page derives. Moisture content, fines content, how the material is dug and the compactive effort actually applied all move the real factors, and the same soil at a different moisture will not behave like the number you typed. Take the factors from the site investigation or measured local experience, not from a general table.
  • This is a volume conversion, not a haulage calculation. It does not size trucks, count loads, or apply payload limits — wet or dense spoil often reaches a lorry's weight limit before it fills the body, and heap, tailgate profile and further bulking during loading all sit between this loose figure and a load count.
  • The compacted figure is not a compaction specification. It assumes the placed fill achieves exactly the shrinkage percentage entered, and says nothing about the density the fill must be tested to, layer thickness, the plant used, or material rejected and reworked. It does not replace field density testing.
  • One bank volume with one pair of factors. A mixed excavation — topsoil over clay over rock, or a trench through made ground — has different swell and shrinkage per stratum, and running the whole quantity at a single figure misstates both the haul and the fill. Topsoil stripping and unsuitable or contaminated material that leaves site instead of returning to fill are outside the model entirely.
  • The loose volume describes material immediately after excavation. A stockpile consolidates under its own weight and with rain, so a survey of a pile that has stood for weeks comes back below this figure. Nothing here addresses waste classification, tipping, or duty-of-care disposal requirements for spoil going off site.

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.

Sources checked 2026-09-06 · in the site-wide review of 2026-09-06 · v1.0.1

Regulatory standards & verification citations1
  1. Standard earthwork volume states: loose (haul) volume = bank volume x (1 + swell%); compacted volume = bank volume x (1 + shrinkage%), where shrinkage is typically expressed as a negative percentage
Cite this page

Your workspace

Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.

Now that you have the number

These guides cover the work this quantity is for — the first ones run this calculator inside the section that raises the question.

Called something else where you work? Bulking and swell — the term in each market, how close the equivalence really is, and the standard that governs it.

Worked examples: Gravel driveway — step 2 of 8 · Paver patio — step 2 of 10 · Brick garden wall — step 6 of 8

How to calculate soil swell & shrinkage haul volume in 4 steps

  1. Bank (In-Situ) VolumeThe undisturbed, in-situ soil volume.
  2. Swell Factor (%)How much the soil expands once excavated and loosened, as a positive percentage.
  3. Shrinkage Factor (%)How much smaller the soil ends up once recompacted, as a negative percentage.
  4. Loose (haul) volumeThe tool computes the loose (haul) volume from those figures and shows the formula, its sources, and a confidence rating alongside it.

Loose (haul) volume by bank (In-Situ) Volume

Page defaults, not your figures above.

Bank (In-Situ) VolumeLoose (haul) volume (yd³)
100 yd³125
150 yd³188
200 yd³250
250 yd³313

Frequently asked questions

Why does the same soil have three different volumes?
Bank volume is the natural undisturbed state; loose volume is what the same soil occupies once excavated and hauled (with extra air gaps from loosening); compacted volume is what it occupies once placed and recompacted — typically denser than even its original bank state.
Why does this matter for truck hauling?
Trucks haul LOOSE volume, not bank volume — sizing your fleet or ordering material based on bank volume alone will underestimate how many truckloads you actually need.
Does rock behave the same way as soil?
Rock typically has a much higher swell factor than soil (blasted rock can swell 40-70%+) since angular rock fragments pack far less efficiently than their original solid rock mass — always use rock-specific factors for rock excavation.
Preliminary estimate, not certified engineering. This tool produces an indicative quantity calculation for planning purposes only — it is not a certified structural analysis, a guaranteed material takeoff, or a substitute for building department approval. Always verify measurements on-site and have a licensed contractor or structural engineer review any load-bearing, code-sensitive, or safety-critical work before purchasing materials or starting construction. Spotted an arithmetic or standards error? Report it to contact@craftquantities.com with your inputs — a confirmed fix gets a permanent check of its own, so the same mistake cannot come back.