Earthworks

Balancing Cut and Fill on a Wet Site

A site balances on the drawing long before it balances in the dirt: shrinkage and a formation wet of optimum each take their share of the cut first.
  • 17 minReading time
  • 8Sections
  • 5Calculators inline
  • Last reviewed

A levels drawing is not a materials schedule

The tender is due Friday and the only earthworks note on the levels drawing says the site is to balance. Cut hatched one way, fill hatched the other, a schedule underneath that agrees to within a few cubic metres, and no line anywhere for muck away or for imported fill. On free-draining ground in a dry June that note is close enough to true to price against. On a clay site in February it is a statement about the geometry between two triangulated surfaces, and the material caught between them has opinions of its own.

What the software produced is the difference between an existing ground model and a design surface, in undisturbed measure, taken from levels somebody shot before a machine touched the site. That number is usually reliable. What it carries no information about is density, moisture content, organic content, plasticity, or whether any of the material it counted can be persuaded to hold a specified dry density once it has been dug, carted a hundred metres and rolled.

Two deductions stand between that geometric figure and the fill you can actually build. The first is a density change: the same soil occupies less space compacted than it did in the ground, so the cut buys fewer metres of fill than it measures. The second is an acceptability judgement: part of the cut will not make fill at any density on the day you dig it, either because of what it is or because of how much water is in it. They are fixed by different things and they have to be priced separately, because one is settled by the specification and the other is settled by the weather.

Everything stripped sits outside the sum

Topsoil is the first subtraction and it never re-enters the balance as fill. Organic material is excluded from structural fill by every earthworks specification worth the name — classified out under BS EN 16907-2 Earthworks: Classification of materials, or by the acceptability tables of the Manual of Contract Documents for Highway Works, Volume 1: Specification for Highway Works, Series 600 (Earthworks), and identified in the first place by a classification such as ASTM D2487 Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System). The depth to strip is a measured quantity, logged bucket by bucket in the trial pits, not the round figure written on a note. A hundred millimetres of error across a hectare is a thousand cubic metres of argument.

Behind the topsoil sits everything else that produces spoil without producing fill: the root mat under a hedge line, made ground from a building nobody has drawings for, the hardcore raft under a demolished slab, soft spots over an old pond, and any material a contamination assessment has flagged. Each of these hits the ledger twice. It is a cut that yields no fill, and it leaves a hole that has to be brought back up with something acceptable, so the deficit grows from both ends at once.

The topsoil also comes back at the end, which moves every level you are about to set. Formation has to sit low by the settled thickness of the layer being respread, and a stockpile of wet cohesive topsoil standing through a winter loses fines out of its toe and holds water in its heart. Site it where it drains, off the fill footprint, and off the ground you will later be asked to prove a density on.

Shrinkage is a density ratio, not a property of the soil

The shrinkage percentage in an earthworks estimate is doing one job: converting an in-situ dry density into a specified compacted dry density. One cubic metre in the ground becomes the ratio of those two densities once it is placed and rolled. Which means the factor is not a fixed characteristic of the clay in front of you — it moves the moment the specification moves. A fill written to ninety-five per cent of a maximum obtained by modified effort consumes noticeably more bank metres per compacted metre than one written to ninety per cent of a standard-effort maximum, on the identical material.

The other half of the ratio is what the ground is doing before you dig it. Loose alluvium, soft made ground and anything recently placed and never compacted shrinks heavily, because there is a great deal of air to take out. A dense glacial till that has been consolidated under ice for ten thousand years is already close to the density your roller is trying to achieve, and shrinks very little. Push that far enough and the sign flips: a heavily over-consolidated clay, dug and remoulded, can occupy more space compacted than it did undisturbed, which turns an assumed shortfall into a surplus and a haulage bill nobody bid. The ten to fifteen per cent that gets quoted for ordinary cohesive fill is a planning assumption to open with, not a number to close a tender on.

A better figure costs one lab schedule. Take in-situ dry densities from the trial pits by sand replacement to BS 1377 Part 9 or ASTM D1556 Standard Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method, and take the laboratory maximum from a compaction test at the effort the specification names — ASTM D698 for standard effort, ASTM D1557 for modified, or their AASHTO equivalents T 99 and T 180. The ratio between what the ground has and what the specification demands is your shrinkage factor, derived rather than borrowed, and it belongs in the file with the price.

Running the balance itself is then arithmetic with three careful inputs. Cut goes in as bank measure after the strip has been deducted and after any share of the cut you do not believe will make fill has been taken out. Fill goes in as the compacted design volume, which is what the drawing gives you directly. Shrinkage goes in as a negative percentage, because the convention here treats compaction as a reduction from bank. The sign is a convention and not a limit, though: the field runs from minus twenty-five through to plus thirty-five, so the over-consolidated clay that bulks on remoulding goes in directly as a positive figure and the cut volume stays the honest bank measure its label asks for. Both volumes are plain cubic metres in this one, so convert before typing if your takeoff is in yards.

With the strip off the top and the unacceptable share out of the cut, what is left is a bank volume that has to become a compacted one — and the shrinkage percentage is what decides whether lorries are arriving loaded or leaving loaded.

Net earthwork balance

131 yd³100 m³

Cut volume as compacted fill
1,177.16 yd³900 m³

SURPLUS: approximately 131 yd³ of cut material will be left over after filling — plan for haul-off or on-site stockpiling.

Wet of optimum, and the roller that only polishes

For a given compactive effort, a soil reaches its highest dry density at one moisture content and falls away either side of it. That is the whole of the compaction curve and the reason a wet formation cannot be beaten into specification. Dry of optimum, the particles will not slide past one another; wet of optimum, water occupies the space the roller is trying to close, and no number of passes will remove it because the load path goes into pore pressure rather than into the soil skeleton. The reference tests are ASTM D698 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Standard Effort and ASTM D1557 for modified effort. BS 1377 covers the same ground in UK practice, though check which edition your specification names: the compaction tests moved into BS 1377-2:2022 when the long-standing Part 4 was withdrawn, and specifications written before that still cite the old part.

On site the failure announces itself before any gauge does. A formation that visibly deflects under a loaded lorry and springs back behind the wheels is pumping, and a proof roll that produces that movement is telling you the answer for the whole lift. Get a moisture number rather than a hand assessment: the oven method of ASTM D2216 is the reference but wants overnight, while ASTM D4944 using the calcium carbide gas pressure tester or the microwave method of ASTM D4643 will give you something to act on inside the shift. Where a UK earthworks specification is in force, acceptability may be set as a moisture content limit expressed against the plastic limit from BS 1377 Part 2, or as a band of moisture condition value, and the earthworks specification rather than the estimator decides which.

Field density then confirms what the proof roll suggested, by nuclear gauge to ASTM D6938 or by sand cone. Record moisture alongside every density result without exception. A density failure with no moisture reading beside it is an unexplained failure, and unexplained failures are the ones that become a conversation about competence instead of a conversation about weather.

The gauge gives a field dry density and the laboratory gives a maximum for the same soil at the effort the specification names; what matters is the percentage between them and whether it clears the clause you signed up to.

Percent compaction achieved

94.9 %

Specified minimum
95 %

The compaction at this test point is 94.87%, below the 95% the specification calls for. This needs checking by a qualified person before you proceed. This compares what you measured with the figure specified for the work. Acceptance of the earthwork is the specifying engineer's, not this page's.

Thin lifts as a drying strategy

Lift thickness limits are normally read as a compaction constraint — how deep the roller can reach before the bottom of the layer stops densifying. On a wet cohesive site they are also the only free moisture reduction available. A thin lift exposes its whole depth to wind and sun for the hour between spreading and rolling; a thick one buries its own wet half where nothing can get at it. Halving the lift roughly doubles the surface you are drying per cubic metre placed, and the plant is on site regardless.

Turning the material multiplies that effect. A harrow or an agricultural rotavator run through a spread lift breaks the clods that hold water in their centres and exposes new faces, and two passes of a harrow in a drying wind will do more than a day of rolling. Evaporation, not the plant list, sets the rate — which is why cohesive earthworks in a British winter effectively stop, and why the programme has to respect a season even though the specification only ever tests acceptability. Seal the formation before every shift end and ahead of any forecast rain: a pass with a smooth drum and a fall left across the surface sheds a night of rain that would otherwise undo three days of drying.

Match the roller to the material while placing. A padfoot or sheepsfoot kneads cohesive fill from the bottom of the lift upward and walks out as the layer stiffens, which is a visible progress indicator as well as a compaction method. A smooth drum on the same clay during placement seals the top and traps water underneath it, which is exactly what you want at the end of the day and exactly what you do not want at the start of one.

  1. Scarify the surface of the lift below so the new layer keys into it instead of sitting on a rolled plane.
  2. Spread to the loose thickness the specification allows for the plant on site, not the thickness the dozer finds convenient.
  3. Harrow or rotavate the spread lift and give the wind an hour on it before anything rolls.
  4. Take a moisture reading with a field method rather than judging by hand, and stop if it is above the acceptability limit.
  5. Compact with the roller the material wants, padfoot for cohesive fill and smooth drum for granular.
  6. Take density and moisture together at the specified frequency, recorded against lift and chainage.
  7. Seal the surface and leave a fall on it before the shift ends.

Fill it, then add the allowance

Fill height divided by the loose lift thickness gives the number of layers, and that count is what actually sets the aeration cycles, the roller passes and how many density tests the specification will ask for.

Number of lifts needed

16 lifts

Treating it rather than carting it

Every cubic metre of site-won material made acceptable removes two movements from the job, not one: a load out to a tip and a load in from a quarry, each with its own gate charge, its own haul cycle and its own lorry on the road. That arithmetic is why lime turns up on wet cohesive sites at all. It is not being used to build a pavement layer; it is being used to keep the balance the drawing already claimed, and the saving is measured in movements rather than in strength.

The chemistry is worth understanding because it decides what you can promise. Quicklime hydrates on contact with the water in the soil, consuming free moisture and releasing heat as it does, which drops the moisture content immediately. The calcium then exchanges with the cations held on the clay particles, flocculating a dispersed plate structure into crumbs and pulling the plasticity index down — measurable the same day by ASTM D4318 Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils, or by BS 1377 Part 2. That immediate change is modification, and it is what turns an unworkable formation into something a roller can act on. Given enough lime to hold a high pH, plus time and temperature, a slower pozzolanic reaction with the clay's own silica and alumina builds cementitious strength: that is stabilisation, a different job with a different dosage and its own strength testing, commonly a soaked CBR to ASTM D1883.

The dosage is a laboratory output, never a site guess. ASTM D6276 Standard Test Method for Using pH to Estimate the Soil-Lime Proportion Requirement for Soil Stabilization establishes the lime demand for the specific soil, and a full mix design confirms it against whatever performance the specification asks for. Mix designs commonly land between about two and eight per cent by dry weight, which is the band the calculator accepts, but the number for your clay comes from the study. Two things trip people up when converting that percentage into a delivery: the volume to enter is the treated layer only, area multiplied by treatment depth, and not the whole cut; and the dry density is your soil's measured value from the geotechnical report, because it scales the answer directly. Once you have a mass, divide it by the treated area to get the spread rate in kilograms per square metre that the operator actually sets on the spreader.

Sulfate is where lime treatment goes wrong, and it goes wrong late. In sulfate-bearing or sulfide-bearing clays, lime, sulfate and water together form expansive minerals, and the heave shows up weeks or months afterwards under a slab or a road that was signed off as passing. Total sulfate, water-soluble sulfate and oxidisable sulfide all get tested before any decision to treat, and the earthworks specification carries the limits and the mitigation — extended mellowing, a different binder, or a decision not to treat that material at all. BS EN 16907-4 Earthworks: Soil treatment with lime and/or hydraulic binders covers the process; on UK highway work the acceptability limits sit in Series 600 of the Specification for Highway Works.

Handling comes with its own constraints. Quicklime is caustic and reacts exothermically with moisture, including moisture on skin and in eyes, so it is handled to the supplier's safety data sheet and, in the UK, assessed under the Control of Substances Hazardous to Health Regulations 2002 with the PPE that assessment names. Spreading fine quicklime in wind puts dust on the operator and on the neighbours; shrouded spreaders and granulated products exist for that reason. Mellowing between mixing and final compaction is part of the design rather than slack in the programme — the material is re-mixed and compacted inside the window the specification gives, and a lift left mellowing over a wet weekend is a lift you are treating twice. The lime itself is specified: ASTM C977 Standard Specification for Quicklime and Hydrated Lime for Soil Stabilization in the US, BS EN 459-1 Building lime: Definitions, specifications and conformity criteria in Europe, and the class delivered has to match the class designed.

Once the mix design has settled a target percentage by dry weight, the treated layer's volume and the soil's dry density turn it into a delivered mass — and from there into a spread rate the operator can set.

Lime needed

14,100 lb6,400 kg

The correct lime percentage for your soil must be determined by a geotechnical lab mix-design study (e.g. per ASTM D6276) — this calculator only converts a known target percentage into a material quantity, it does not determine the required percentage itself.

What still leaves, leaves loose and heavy

A surplus is a bank figure and lorries do not carry bank measure. Excavated soil bulks the moment the bucket lifts it, so the loose volume going up the ramp is meaningfully larger than the hole it came out of, and the swell factor between them varies with soil type, moisture and how the machine is loading. Wet cohesive spoil then fails the other way as well: it reaches the vehicle's weight limit while the body still looks capable of taking more, because gross vehicle and axle limits under road traffic law bind before the cube does. Every percentage point of moisture you did not drive off is water you are paying to lift, cart and tip.

Disposal is usually priced by the tonne while your takeoff is in cubic metres, and the bridge between them is a bulk density that moves with moisture. Convert the weighbridge dockets back through a density for that stream and compare them against the volume you predicted; a gap that runs consistently one way is your factor needing correction, not the haulier needing an argument. Do that reconciliation while the job is live, because the same clay is likely to be in the next tender.

The regulatory position is separate from the arithmetic and settles first. Material leaving the site is waste unless it moves under a recovery framework — in England, the CL:AIRE Definition of Waste: Development Industry Code of Practice provides one route, with classification and consignment otherwise following the regime in force. Anything a contamination assessment has flagged goes to a different gate at a different rate, and the classification has to be established before the disposal line is priced rather than discovered when the first load is turned away.

Convert the surplus to its loose volume first, then divide by the rated body capacity of the lorries actually assigned — the load count is what the haulage quote, the wheel-wash and the traffic management plan are all built on.

Truck loads needed

17 truck loads

Price the band and keep the evidence

Run the balance twice. Once on the optimistic set — the strip depth on the note, the textbook shrinkage, all the cut acceptable — and once on the pessimistic set, with a deeper strip, a shrinkage factor derived from a specification written to modified effort, and a realistic share of the cut classed unacceptable in February. The interesting output is not the two volumes. It is the difference expressed as lorry movements and programme days, because that is the shape the money takes and the shape a client can be shown.

That band then has to land somewhere in the contract. Unsuitable material needs a written definition tied to a criterion someone can test on site, and a rate attached to dealing with it, or every wet lorry becomes a negotiation. Whether a formation that has gone soft under rain is a risk you priced or an event you claim for is a question the contract answers, and it is cheaper to answer it before the topsoil comes off than after the first week is lost.

Evidence is what makes any of that collectable. Keep dated survey pairs at every stage — pre-strip, post-strip and formation — because the difference between the first two is the bank volume every later argument is measured against. Keep trial pit logs with in-situ densities and moisture contents, keep every density and moisture result against its lift and chainage, keep the lorry tickets and weighbridge dockets, and photograph the proof rolls that failed as well as the ones that passed.

Then close the loop for your own benefit. Write the shrinkage factor you actually achieved, the treatment dosage that actually worked and the moisture contents you were fighting into a record against soil type, specification and season. Three of those records and the next tender on the same clay is priced from your own ground rather than from a range in a textbook, which is the only durable advantage available in earthworks pricing.

Where the balance moves, which direction it goes, and what settles the question
What changesEffect on the ledgerWhat settles it
Strip depth deeper than the drawing noteCut falls, fill unchanged, deficit growsTrial pit logs and a post-strip survey
Specification written to a higher percentage of a modified-effort maximumMore bank metres consumed per compacted metreThe density clause in the earthworks specification
Material placed wet of optimumLift rejected and reworked, cost lands in programme rather than volumeMoisture and density taken together at every test point
Part of the cut classed unacceptableAn export and an import created by the same materialThe acceptability limits in the earthworks specification
Wet cohesive material dried or treated back to acceptableCut re-enters the balance, two movements removedMix design, mellowing window and the sulfate testing
Over-consolidated clay dug and remouldedLittle shrinkage, occasionally bulking, surplus growsIn-situ dry density measured against the laboratory maximum
Where the balance moves, which direction it goes, and what settles the question

Try the calculation

Pinning the balance down before the price goes in

Six things that decide whether the drawing's note about balancing survives contact with the ground, each of them cheaper to establish now than to argue about in week three.

  • Pre-strip and post-strip survey pair — The difference between them is the bank volume every later claim, variation and reconciliation is measured from.
  • Strip depth logged pit by pit — Topsoil, root mat and made ground recorded where they were found, not averaged from a note on the levels drawing.
  • In-situ dry density and natural moisture content — Taken from the trial pits; the first gives you a derived shrinkage factor, the second tells you how far from optimum you are starting.
  • The density clause and the acceptability limits — Which compaction effort, what percentage of it, and what moisture or plasticity criteria class material out — all read off the specification, not assumed.
  • Acceptable, treatable and unacceptable split of the cut — Three quantities rather than one, because each carries a different rate and only the first two stay on site.
  • Treated layer area and depth — Kept separate from the cut volume; lime is proportioned against the layer being mixed, never against the whole excavation.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • ASTM D2487 Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
  • ASTM D4318 Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils
  • ASTM D698 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Standard Effort
  • ASTM D1557 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort
  • ASTM D2216 Standard Test Methods for Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass
  • ASTM D4944 Standard Test Method for Field Determination of Water (Moisture) Content of Soil by the Calcium Carbide Gas Pressure Tester
  • ASTM D4643 Standard Test Method for Determination of Water Content of Soil and Rock by Microwave Oven Heating
  • ASTM D1556 Standard Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method
  • ASTM D6938 Standard Test Methods for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
  • ASTM D6276 Standard Test Method for Using pH to Estimate the Soil-Lime Proportion Requirement for Soil Stabilization
  • ASTM C977 Standard Specification for Quicklime and Hydrated Lime for Soil Stabilization
  • ASTM D1883 Standard Test Method for California Bearing Ratio (CBR) of Laboratory-Compacted Soils
  • AASHTO T 99 Moisture-Density Relations of Soils Using a 2.5 kg Rammer and a 305 mm Drop, and AASHTO T 180 Using a 4.54 kg Rammer and a 457 mm Drop
  • BS 1377 Methods of test for soils for civil engineering purposes (Part 2:2022 Classification tests and determination of geotechnical properties, which absorbed the compaction tests of the withdrawn Part 4; Part 9 In-situ tests)
  • BS EN 16907-2 Earthworks: Classification of materials
  • BS EN 16907-4 Earthworks: Soil treatment with lime and/or hydraulic binders
  • BS EN 459-1 Building lime: Definitions, specifications and conformity criteria
  • Manual of Contract Documents for Highway Works, Volume 1: Specification for Highway Works, Series 600 (Earthworks)
  • CL:AIRE Definition of Waste: Development Industry Code of Practice
  • Control of Substances Hazardous to Health Regulations 2002 (COSHH)

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.