Materials & Quantities

Slope Cut-and-Fill Earthwork Balance Calculator

Check whether a site's cut material (adjusted for shrinkage) covers its fill requirement, or whether you need to import or haul off material.

  • Answers as you type
  • Every formula cited
  • Calculated in your browser
SettingsSettings for this calculationUS
Market
Imperial · sales tax
The in-situ (undisturbed) volume of soil to be cut, in m³.

This is the volume before excavation disturbs it — measured from the original ground survey.

The compacted volume needed to build up the fill areas, in m³.

This is the final, compacted design volume of the fill.

How the compacted fill volume compares with the bank volume it came from. Negative shrinks, positive bulks.

Common earth shrinks 10-15% when excavated and recompacted, because compaction packs the particles tighter than the ground had them. Rock and heavily over-consolidated clay do the opposite: broken up and placed back, they occupy MORE room than they did in situ, which is why earthworks tables publish swell factors alongside shrinkage ones. Take the figure from the geotechnical report for the material in question rather than from a general table.

Net earthwork balance

131 yd³

Medium confidence

SURPLUS: approximately 131 yd³ of cut material will be left over after filling — plan for haul-off or on-site stockpiling.

Cut volume as compacted fill
1,177.16 yd³
Then change the inputs to see how far the answer moves.

Show calculation logic

How this was calculated

Formula source(s)

  • Standard earthwork balance: cut volume (bank/in-situ measure) converts to a smaller compacted fill volume via a shrinkage factor; comparing that to the required fill volume gives a net surplus (haul off-site) or deficit (import fill)

Inputs used

Cut Volume (Bank Measure)
1000
Required Fill Volume (Compacted)
800
Shrinkage or Bulking (%)
-10

Intermediate steps

Cut volume as compacted fill
1,177.16 yd³
Final result130.8 yd³

Confidence note: SURPLUS: approximately 131 yd³ of cut material will be left over after filling — plan for haul-off or on-site stockpiling.

What this calculation does not cover

  • The balance assumes every cubic metre of cut becomes acceptable fill. Topsoil strip, root mat, made ground, soft spots and anything too wet or too contaminated to place yield spoil without yielding fill, and each also leaves a hole that has to be brought back up — so they hit the balance from both ends and neither effect is in this sum.
  • The answer is in compacted measure. Neither muck away nor imported fill is transacted in that measure: convert through a swell factor to get the loose volume lorries actually carry, and through a bulk density to get the tonnage a weighbridge or tip charges on.
  • One shrinkage figure is applied to the whole cut. It does not vary by stratum or by moisture content, and it does not move with the compaction specification — the same soil written to a higher percentage of a modified-effort maximum consumes more bank volume per unit placed. Drying, moisture conditioning and lime or cement treatment are not modelled at all.
  • This is a volume balance, not a mass-haul plan. It carries no haul distances, phasing, sequencing, stockpile space or seasonal working windows, so a site that balances across the whole job can still need imported fill early and export later.
  • This is not a geotechnical assessment or a design. It does not check settlement of the fill or of the ground beneath it, the stability or angle of the cut and fill slopes, or any temporary support the excavation needs — those come from the site investigation and the earthworks specification, and the extra fill that settlement consumes sits outside this calculation.

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.

Sources checked 2026-09-02 · in the site-wide review of 2026-09-06 · v1.0.1

Regulatory standards & verification citations1
  1. Standard earthwork balance: cut volume (bank/in-situ measure) converts to a smaller compacted fill volume via a shrinkage factor; comparing that to the required fill volume gives a net surplus (haul off-site) or deficit (import fill)
Cite this page

Your workspace

Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.

Tools and safety for this job

To excavate by machine. Generic types, no brands, no prices.

Protection this work requires

  • Digging blind strikes gas, water and power every day: get the plans, scan with a cable avoidance tool, and hand-dig trial holes over anything you find.

Excavate by machine: Operating an excavator is a trained and, in most markets, formally certified activity, and hiring one does not include that training. Underground services must be traced before any machine dig. This list covers the tools, not the competence.

Show the 4 tools this job needs

Essential

  • Cable and pipe detector

  • Shovel and spade

Recommended

  • Spirit level

  • String line and pins

what each groundwork tool is for, and the spec that decides which to buy where one does.

Now that you have the number

These guides cover the work this quantity is for — the first ones run this calculator inside the section that raises the question.

Called something else where you work? Bulking and swell — the term in each market, how close the equivalence really is, and the standard that governs it.

Still deciding? Balancing Cut and Fill vs Importing Material — the factors that actually differ, with no invented prices.

The data behind it: Production rates by operation

How to calculate slope cut-and-fill earthwork balance in 4 steps

  1. Cut Volume (Bank Measure)The in-situ (undisturbed) volume of soil to be cut, in m³.
  2. Required Fill Volume (Compacted)The compacted volume needed to build up the fill areas, in m³.
  3. Shrinkage or Bulking (%)How the compacted fill volume compares with the bank volume it came from. Negative shrinks, positive bulks.
  4. Net earthwork balanceThe tool computes the net earthwork balance from those figures and shows the formula, its sources, and a confidence rating alongside it.

Net earthwork balance by cut volume (Bank Measure)

Page defaults, not your figures above.

Cut Volume (Bank Measure)Net earthwork balance (yd³)
100-929
200-811
500-458
1,000131
2,0001,308
5,0004,839
10,00010,725

Frequently asked questions

Why does cut soil 'shrink' when used as fill?
Undisturbed (bank) soil has a natural structure with void spaces; once excavated and recompacted at a controlled density, the same mass of soil typically occupies less volume than it did in its original undisturbed state.
What's the difference between shrinkage and swell?
Swell is loose (hauled or stockpiled) soil taking up MORE volume than in its bank state, and shrinkage is the same soil recompacted into LESS. Loosening causes the swell, and recompaction leaves the soil smaller than its bank state; the Soil Swell & Shrinkage Haul Volume Calculator covers the loose-volume side of this.
What should I do about a deficit?
Source imported fill material, adjust the grading design to reduce fill requirements, or import from a nearby cut site — compare against haul-off costs for other project phases too.
Preliminary estimate, not certified engineering. This tool produces an indicative quantity calculation for planning purposes only — it is not a certified structural analysis, a guaranteed material takeoff, or a substitute for building department approval. Always verify measurements on-site and have a licensed contractor or structural engineer review any load-bearing, code-sensitive, or safety-critical work before purchasing materials or starting construction. Spotted an arithmetic or standards error? Report it to contact@craftquantities.com with your inputs — a confirmed fix gets a permanent check of its own, so the same mistake cannot come back.