Below grade

Backfilling Against Waterproofing

Filling is the one operation that can destroy a membrane without leaving a mark: board it, place it in lifts, and prove the drain takes what arrives.
  • 17 minReading time
  • 8Sections
  • 5Calculators inline
  • Last reviewed

Four hours of machine time against a fortnight of membrane

The waterproofing crew rolled their last lap on the Thursday, walked the face with the clerk of works on the Friday and demobilised. Monday morning there is a 13-tonne machine parked on the ramp, sixty tonnes of 40 mm clean stone stacked at the top of the dig, and a driver who has been told to close the void before knocking-off time. Nothing that happens over the next four hours can be revisited, and — this is the part that catches crews out — almost none of it produces evidence at the moment it goes wrong.

A sheet gouged by a bucket tooth on the Monday does not leak on the Monday. It leaks in year three, and it leaks at a damp patch four metres away from the gouge, because water that gets behind a bonded membrane tracks along the concrete face until it finds a tie hole or a lift line to come through. By then the wall is buried, the injection contractor is chasing a defect he cannot locate, and everyone involved is arguing about a membrane that was almost certainly installed correctly. That asymmetry — cheap to prevent, close to unfixable, and silent for years — is the whole reason this operation gets its own method statement rather than being a line on the excavation programme.

There is a contractual edge to it as well. The specialist who warrants the membrane has left site; the groundworker who can void that warranty with one bucket movement has never seen it. Below-grade membrane literature is generally explicit that protection is a condition of the installation and not an accessory to it — GCP's Bituthene sheet literature and Carlisle's CCW documentation both treat the protection layer and the timing of backfill as part of the specified system. The practical answer is boring and works: put the pre-backfill walk-round in the programme as an activity with a duration and a named attendee from the waterproofing subcontractor. A hold point with no duration against it is a hold point that gets absorbed into somebody's morning.

Ask the wall before you ask the machine

A basement wall is not designed to be filled against on its own. It spans vertically between the footing at its base and the ground-floor diaphragm at its head, and until that deck is on and connected, filling one side turns a propped wall into a cantilever it was never sized as. The International Residential Code puts this in Section R404.1.7, Backfill placement: fill is not to go against the wall until it has sufficient strength and has been anchored to the floor above or braced well enough that the backfill cannot damage it, with an exception only for walls supporting less than four feet of unbalanced backfill. The failure it is written against is familiar — a horizontal crack near mid-height, or a wall pushed inward off its kicker, discovered later when the ground-floor setting-out will not close.

Strength is two separate questions and site collapses them into one. The strength at which formwork can come off is a formwork question, covered by ACI 347R for the removal of forms and shoring; the strength at which the finished wall may be loaded laterally comes out of the structural design to ACI 318 and is named in the specification. They are not the same number and in cold weather they can be a fortnight apart. Field-cured cylinders taken from the actual pour, kept beside the wall, are what answers it — not the calendar, and not the pour ticket. On a grouted masonry wall the same logic applies to the grout cure and to the bond beam that ties the head of the wall into the deck.

The load itself depends on whether the wall is free to move, and a propped basement box is not. IBC Section 1610.1 draws the line explicitly: walls whose horizontal movement is restricted at the top are designed for at-rest pressure, while a retaining wall free to move and rotate at its head is permitted the active case. The difference is not small. Jaky's relation gives the at-rest coefficient as one minus the sine of the effective friction angle, so a well-graded granular fill at 34 degrees sits at about 0.44, and against a fill weighing 20 kN per cubic metre that is roughly 8.8 kPa of lateral pressure for every metre of depth — near 56 pounds per square foot per foot in the other system. Over 2.7 metres of fill the triangular diagram integrates to about 32 kN on every metre run of wall, close to 2,200 pounds on every foot, acting a third of the way up from the base. Table 1610.1 tabulates minimum design lateral soil loads by soil group with separate active and at-rest columns, subject to a geotechnical investigation under Section 1803 saying otherwise, and AASHTO's LRFD Bridge Design Specifications, Section 3.11, additionally requires compaction-induced pressures to be accounted for.

The number matters less than what it is attached to: a soil group in a moist condition at its optimum density, which is how the code table states its own basis before adding that actual field conditions govern. The designer picked a value from a row, and the row assumed a material. Turn up with site-won clay because the granular fill did not arrive and you have changed the load case without changing a drawing, in the direction the wall cannot take; let the same fill saturate because the drainage layer was never connected and you have added a water pressure the row never contemplated. Fill evenly around the structure as well — two metres against one elevation and nothing against the return is a net push on a box that was designed for a balanced one, and it is the reason temporary props are designed props rather than a scaffold tube wedged across a corner.

Jaky's coefficient from the fill's friction angle, then the pressure at the base and the thrust along the wall from the fill's weight and height — the working above, for a wall propped at its head. Give it a water table inside the fill and the breakdown shows what a drainage layer that was never connected adds.

The height of soil against the wall, from the base slab to the ground surface behind it.

At rest for a wall held by the floor at its head; an entered value for anything else the designer has set.

The drained friction angle of the retained soil, from the ground investigation.

1 for normally consolidated soil and placed fill; higher for ground that was once under more load.

The weight of the retained soil as it is in service, water in the pores included.

The weight of the soil with its voids full, used below the water table.

How far below the retained surface the design water level sits; the full height or more means no water on the wall.

A load spread over the ground behind the wall — a drive, stored material, a building's floor.

Total thrust on the wall per unit run

3,450 lbf/ft

Medium confidence

At rest: the soil stays where it was placed, which is the state of a wall propped by the floor at its head. A wall genuinely free to lean away could use the lower active coefficient, but only if it can move enough to earn it. Below the water table the soil contributes only its buoyant weight times the coefficient, and the water acts on top of it at full hydrostatic pressure.

At-rest coefficient K0
0.5
Soil pressure at the base
464.55 psf
Water pressure at the base
312.25 psf
Total pressure at the base
776.8 psf
Soil thrust per unit run
2,673.27 lbf/ft
Water thrust per unit run
780.62 lbf/ft
Height of the resultant above the base
3.13 ft

Add the equipment this sizes

This result is a specification — 3,450 lbf/ft — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

10 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • Characteristic, unfactored pressures for a screening check. A design applies the partial or load factors of the code in force, and the structural engineer sets the design water level and the coefficient the wall is designed to.
  • Horizontal ground behind the wall. A slope rising away from the wall increases the at-rest coefficient — Eurocode 7 multiplies it by (1 + sin β) — and is not modelled here.
  • Compacting backfill in layers against a propped wall can lock in pressures above the at-rest figure near the top of the wall. AASHTO LRFD 3.11 and CIRIA C760 set out methods for it; this page does not add them.
  • The water is static and the soil's cohesion is ignored. Seepage towards a drained wall changes the pore pressures, and a line load or strip footing close to the wall adds pressure that a uniform surcharge does not represent.

The board is impact protection, and it is bought in sheets

Protection board exists to take the loads the membrane cannot: point pressure from angular stone bearing on a sheet a millimetre and a half thick, gouging from a bucket working close to the face, and the slow abrasion of a settling fill dragging down a bonded membrane for the next decade. That last one is the quiet killer, because settlement drag pulls at laps rather than at the field of the sheet, and a lap that has been worked loose leaks at the one line nobody photographed. The product is usually an asphaltic core board of the W. R. Meadows PROTECTION COURSE type, extruded polystyrene, or a dimpled drainage composite such as Carlisle CCW MiraDRAIN or GCP Hydroduct doing protection and drainage in one pass. If you are using XPS, check whose drawing set its thickness — an insulation thickness chosen by the thermal model is not automatically the impact protection the membrane manufacturer asked for.

Fixing is where good boards get installed badly. Below the waterproofing termination, nothing is fastened through the membrane plane: not a nail, not a washer, not a hit-and-drive anchor. The board is held by adhesive dabs, by double-sided tape, or by a mechanical fix taken into the wall above the membrane's top edge, and the membrane manufacturer's literature governs which of the three is permitted on their sheet. Take the board right down to the footing rather than stopping where the fill is expected to start, because the base corner is precisely where a bucket arrives when the driver is scraping the last of the stone off the formation.

Counting it is straightforward arithmetic with one trap in it. The sheet count is the below-grade wall area divided by the area of one sheet, rounded up, because a part sheet still costs a whole sheet. The trap is that the two standard boards are not the same board: 1.2 by 2.4 metres is 2.88 m², and 4 by 8 feet is 32 sq ft, which is 2.97 m² — about 3% apart. On a wall 2.7 m high round a 46 m perimeter, 124 m² of face takes 44 metric boards or 42 North American ones, and counting on the larger imperial sheet while metric boards arrive on the wagon leaves you a full board short at the last elevation on a Friday afternoon. Take the area off each face separately: every side of a pilaster is a face, every step in the footing changes the height, and the return at a light well is real area that a perimeter-times-height figure never sees.

Enter the face area you actually measured and the sheet you are actually buying — the calculator counts whole boards from those two numbers and nothing else, so cuts at penetrations, offcuts at returns and any product that laps rather than butts have to go into the area you type in.

The total below-grade foundation wall area to be protected.

The area of a single protection board sheet.

Protection board sheets needed

17 sheets

High confidence

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

What this calculation does not cover

  • The count is wall area divided by sheet area, with no allowance for cutting waste, offcuts around window wells and pipe penetrations, or the extra coverage some specifications require at corners and footing turn-downs. Rounding up is not that allowance: 50 m² of wall on 2.88 m² boards gives 18 sheets, which is 1.84 m² of spare board across the whole job.
  • Sheet area is the only property of the board this page uses, so a thin asphaltic hardboard, a dimpled polymer sheet and a rigid insulation panel all return the same count for the same wall. Whether the board's thickness and compressive strength survive the backfill material, the lift depth and the compaction plant is a separate judgement the sheet count does not make.
  • Only the boards are counted. The mastic dabs, tape, termination bar and mechanical fixings that hold the board against the wall until backfill is placed are not in the result, and neither is the membrane, the primer or the perimeter drain the board exists to protect.
  • The sheet area field runs from 1 to 6 m² (10.8 to 64.6 sq ft), so a protection course supplied as a roll cannot be entered as a single unit, and the wall area field replaces anything above its 1,000 m² maximum (about 10,760 sq ft) with that maximum. A wall larger than that has to be run in sections and the counts added, which rounds up once per section.

Place it, do not tip it

Lift thickness is decided by the compaction plant, never by how quickly the void needs to close. A hand-guided plate will densify roughly 150 to 200 mm of loose granular material in one go; a rammer in a confined corner does less; a roller does far more but is not allowed anywhere near the wall in the first place. The lift count falls straight out of it — 2.7 metres of fill in 200 mm lifts is fourteen circuits of the whole perimeter, which is a real figure to have in front of you when someone proposes closing the dig in an afternoon. Material matters just as much: well-graded granular fill to the specified grading, with the maximum particle size capped, because one 150 mm cobble bearing on a board in the first lift is the puncture that nobody will ever find.

How the fill arrives at the wall is the difference between a protected membrane and a scarred one. Stone is placed away from the face and worked toward it, or lowered and released at low level; it is never dropped from a raised bucket, and the first lift in particular goes in by hand or with a chute where access allows. Keep tracked plant off the fill inside the standoff the designer sets, and remember that the pressure heavy compaction locks into the backfill does not relax when the machine leaves the site. If people are working in the void as it fills, the excavation is still an excavation, with everything 29 CFR 1926 Subpart P requires of it, right up until the last lift.

  1. Confirm the board or composite is continuous and undamaged across the elevation about to be filled, and photograph it before anything is placed.
  2. Tip the load away from the wall and push or lower it into position, so nothing lands against the protection layer from height.
  3. Spread to the loose lift thickness the plant can actually compact, checking the depth at the wall face rather than out in the middle.
  4. Compact from the wall outward with hand-guided equipment inside the standoff, keeping the number of passes consistent lift to lift.
  5. Test to the specified frequency at the face as well as away from it, and carry the lift number and test result forward on the same record sheet.
  6. Bring the fill up evenly around the whole structure rather than completing one elevation at a time.

Put the fill height and the loose lift thickness your plant can genuinely handle into it, and treat the answer as a programme figure — fourteen lifts is fourteen spread-and-compact cycles round the building, not one afternoon with a bucket.

The total height of fill to be placed.

The maximum loose lift thickness for your compaction equipment and material.

Number of lifts needed

16 lifts

High confidence
backfill 10 ftbackfill 3.05 mtrench base10 ft3.05 m16 lifts

What this calculation does not cover

  • Lift thickness and fill height have to be measured the same way. This page takes the loose thickness the plant can place in one pass, so where a specification instead states a maximum compacted lift, the finished height gained per lift is less than the figure entered and the true count is higher than the number shown.
  • A lift is one layer of material, and it is not brought to density by a single pass of the roller. Reaching the specified density normally takes several passes over each lift at a set overlap and travel speed, so plant hours come from lifts multiplied by passes, and this page asks for neither.
  • The count assumes every lift is the same thickness across the whole plan area. It does not cover the thinner first lift often required over a soft or yielding subgrade, the bedding and haunching zone around a pipe where lift thickness is reduced and compaction is done by hand, or the depth of cover that must be built up before heavy plant is allowed to track over a buried service.
  • Placing the right number of lifts is not the same as passing compaction testing. Density is checked lift by lift against a laboratory Proctor value, and a lift that fails has to be scarified, moisture-conditioned and recompacted no matter how thin it was placed, with moisture content away from optimum the usual reason a correctly sized lift will not reach density.
  • This is a count of layers and nothing else. It produces no volume, tonnage or delivery quantity for the fill, and the loose material ordered exceeds the compacted volume in the void by the material's bulking, which is a separate calculation.

A number, not an opinion

Percent compaction is field dry density over the laboratory maximum for that material, times a hundred, and every part of that sentence gets abused on site. The laboratory maximum comes from a Proctor test run at a stated compactive effort: ASTM D698 for standard effort, ASTM D1557 for modified. The same soil gives a higher maximum under modified effort, so 95% of one is emphatically not 95% of the other, and a specification that names a percentage without naming the effort has not specified anything. Worse, a Proctor run on the borrow that was in the ground during the site investigation tells you nothing about the material the haulier delivered last week. Classify what actually turned up, to ASTM D2487, and run the Proctor on that.

Field density comes from ASTM D6938 with a nuclear gauge, ASTM D1556 with a sand cone, or ASTM D2937 with a drive cylinder, and each reads only the depth it reaches — a gauge probed to 150 mm is telling you about one lift and not about the three beneath it. Test at the wall face, not three metres out where the plant could get a proper run, because the strip within a metre of the board is the strip that will be under-compacted and it is the strip whose settlement drags on the membrane.

Clean open-graded stone is the exception that gets fudged. Uniformly graded 20 or 40 mm drainage stone has no meaningful Proctor curve, so specifying 95% modified against it writes a requirement that cannot be complied with — and a requirement that cannot be met on site gets quietly waived, which leaves the drainage zone as the one part of the fill under no control at all. Control it by relative density instead, using the index densities from ASTM D4253 and ASTM D4254, or by method: a named machine, a named lift, a named number of passes, agreed before the stone is ordered.

What each named test answers about a backfill, and the question it leaves open. Nothing here substitutes for the project specification's own frequencies.
Question on siteNamed methodWhat it will not tell you
Is this the material the design assumed?ASTM D2487 classification of the delivered fillAnything about how well it has been placed
What density are we measuring against?ASTM D698 standard effort or ASTM D1557 modified effortWhich of the two the specification meant, if it did not say
What density did this lift reach?ASTM D6938 nuclear, ASTM D1556 sand cone, ASTM D2937 drive cylinderAnything below the depth the probe or hole reaches
How do we control clean drainage stone?Relative density via ASTM D4253 and D4254, or method compactionA Proctor percentage, which this material cannot produce
What will the drainage layer pass under load?ASTM D4716 in-plane flow rate per unit widthWhat the collector pipe downstream is able to accept
What each named test answers about a backfill, and the question it leaves open. Nothing here substitutes for the project specification's own frequencies.

Set the gauge reading beside the laboratory maximum for the material actually in the ground and against the percentage the specification demands — and if the two densities came from different soils, the answer is arithmetic about nothing.

The measured field dry density (from a nuclear density gauge or sand cone test).

The maximum dry density from a laboratory Standard or Modified Proctor test.

The project specification's minimum required compaction percentage.

Percent compaction achieved

94.9 %

ComparisonA comparison, not a check — no result here is an approval.

The compaction at this test point is 94.87%, below the 95% the specification calls for. This needs checking by a qualified person before you proceed. This compares what you measured with the figure specified for the work. Acceptance of the earthwork is the specifying engineer's, not this page's.

Specified minimum
95 %

What this calculation does not cover

  • There is no moisture input. Both boxes take dry density, and nothing here checks the placement-moisture band that specifications normally pair with the density clause, so a lift can hit the percentage while being placed too dry or too wet of optimum. Enter a wet gauge reading in the field box by mistake and the percentage comes out inflated with no warning.
  • The page assumes both densities are on the same basis and does not verify it. It has no way to know whether the laboratory maximum came from a Standard or a Modified Proctor, or whether that curve was run on the material actually in this lift rather than carried over from an earlier borrow face.
  • No oversize correction is applied. A Proctor is run on screened material with the large particles taken out, so a gravelly or coarse fill can measure denser in the field than that curve suggests and read at or above 100% while still short of the compaction the specification intends.
  • The percentage describes one test at one spot, to the depth that gauge or sand cone reaches. It carries no testing frequency, no lot size, and no view of whether acceptance rests on every individual test or on the average of a set with a floor under any single result.
  • Both density boxes are limited to roughly 1,000-2,500 kg/m³ (about 62-156 pcf), and a value outside that is replaced by the nearest bound before the percentage is worked out. Lightweight aggregate and other low-density fills sit below the floor. The comparison shown is the arithmetic on the three numbers you typed, not an acceptance decision and not a check of bearing capacity, settlement or stability; where the fill carries a footing, slab, pavement or retaining structure that call belongs to the geotechnical engineer of record.

The sheet is not the bottleneck, and it never is

A dimpled drainage composite works by holding an open gap against the wall so any water that reaches the face falls under gravity at atmospheric pressure instead of standing against the membrane as head. Its geotextile faces the soil, its dimples face the wall, and it only does its job if it is continuous from the top termination down into the stone at the footing. The single most common installation error is a composite that stops a foot above the drain: water runs down the plane, arrives at the bottom, meets soil, and saturates the very strip of backfill the sheet was installed to keep dry.

The rating on the data sheet comes from ASTM D4716, which measures in-plane flow rate per unit width at a stated normal stress and hydraulic gradient. Read the figure at the stress your fill actually applies, not the headline value, and be aware that transmissivity falls over time as the core creeps and the geotextile intrudes into it. One usage note on the calculator below: its rated-capacity field is expressed per metre of width and stays per metre whichever unit system the page is set to, while the width field follows the metric and imperial toggle — so take the per-metre figure straight off the manufacturer's table and let the width look after itself.

Then run the comparison, because it settles an argument that recurs on every job. A composite rated at 5 litres per second per metre, over a 46 m perimeter, has a nominal capacity of 230 litres per second — roughly 3,600 US gallons a minute. Now look at what has to accept it: a 100 mm perforated collector at a 1% fall, flowing full, with a Manning roughness of 0.010, carries something like 6.7 litres per second, about 105 gallons a minute. That is a thirty-fourth of the sheet's rating, and it is the honest constraint. And what actually arrives is smaller again: the backfill trench round that perimeter is perhaps 46 m² of loose ground open to the sky, so 25 mm of rain in an hour puts a little over a cubic metre into it, an average of about a third of a litre per second even if every drop went straight down the fill.

So the design attention belongs downstream of the sheet and at its two ends. Filtration first — a geotextile chosen against filtration criteria of the kind set out in AASHTO M288, with the apparent opening size to ASTM D4751 and permittivity to ASTM D4491 suited to the soil actually behind it, because a blinded fabric turns a drainage plane into a wall covering. Then the base connection into the stone envelope and the perforated line, whose bedding and backfill follow ASTM D2321; then the fall, the cleanouts and an outfall above the invert it discharges to. IBC Section 1805.4 and IRC Section R405.1 are where the subsoil drainage requirements themselves sit, and BS 8102:2022 makes the same point from the other direction by treating drainage and protection as parts of the design rather than as site accessories.

Scale the product's per-metre rating across the run you are covering, then hold that number against the collector, the outfall and the rain landing on the trench — the point of the exercise is to find out which of the four is smallest, and it is almost never the sheet.

The drainage product's rated flow capacity per unit width, from the manufacturer's data sheet.

The total width of foundation wall covered by the sheet drain.

Total drainage capacity

213 CFM

Medium confidence

Rated flow capacity varies by product and compressive load condition (capacity typically decreases under soil/backfill load) — use your specific sheet drain product's rated capacity under expected field loading, not an uncompressed lab value.

Add the equipment this sizes

This result is a specification — 213 CFM — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

66 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • This is the supply side only. A capacity means nothing until it is set against the flow that actually arrives at the wall, and that comes from the catchment above and around the excavation, the permeability of the backfill and the natural soil behind it, and the design storm — none of which appear on this page. A drain rated at three times the flow it will ever see and one rated at a tenth of it return the same confident number here.
  • Rated flow assumes the drain stays open, and what keeps it open is the filter fabric. Fines migrating out of the backfill blind the geotextile over years, and once it blinds, the core behind it is dry and useless whatever the lab rating says. The fabric's opening size has to be matched to the actual backfill gradation — a silty or fine sand backfill against the wrong fabric is the usual way a drainage plane stops draining.
  • Capacity assumes an unbroken path in and out. The sheet has to start at the footing drain and run continuously up to near grade, with the top terminated so surface water and soil cannot get in behind the fabric, and every joint lapped in the direction of flow. A plane stopped short of the footing, or one torn during backfill, delivers a fraction of this figure regardless of what the product is rated at.

The top 600 millimetres undo or protect everything under them

A granular backfill column open at the top is a funnel aimed at your footing drain, so the last part of the fill is cohesive material capping the granular zone, compacted enough to shed and graded to fall away. The residential code sets the surface requirement in IRC Section R401.3: lots are graded to drain surface water away from foundation walls with a fall of not less than 6 inches within the first 10 feet, drains or swales take over where a lot line, wall or slope makes that fall impossible, and any impervious surface inside that 10 feet is laid to at least 2 percent away from the building. The membrane and the board terminate above finished grade at the height the manufacturer states, sealed at the top edge, with any mechanical fixing sitting above the waterproofing plane rather than through it.

Then tell the truth about settlement. Even a properly compacted column settles through its first wet winter, and the ground round a new basement almost always needs topping up once. Leave a crown rather than a level finish, diarise a return visit before the landscaper arrives, and put in writing to whoever takes the building over that a saucer forming at the wall is a maintenance item to be filled, not a membrane failure to be excavated. The things that arrive after handover — a patio laid to fall the wrong way, an irrigation line trenched through the cap, a downspout emptying into the backfill zone — will otherwise put the water straight back where a fortnight of careful work was spent keeping it out.

The hold point, written down

This is the last look anybody gets at a system that will be inaccessible for the life of the building, so the record is part of the work rather than paperwork about it. Photograph every elevation dated, with something in frame for scale, before the first lift and again at each termination and penetration. Not for the file: for the morning in eleven years when a damp patch appears at an internal corner and the only question worth asking is what was actually built behind it.

  1. Walk the full face with the waterproofing installer present, and record their sign-off before any plant is started.
  2. Confirm the specified strength for loading the wall has been demonstrated on field-cured cylinders, and that the deck or the designed props are in place.
  3. Check the protection board or composite is continuous, tight down to the footing, and that no fastener has been driven through the waterproofing below its termination.
  4. Confirm the composite's geotextile faces the soil and that its base discharges into the stone envelope instead of stopping short above it.
  5. Verify the top termination height, its seal and its fixings against the membrane manufacturer's detail, not against the general arrangement drawing.
  6. Check the delivered fill against the material named in the specification and against the borrow the Proctor was actually run on.
  7. Agree the standoff for tracked and heavy compaction plant with the designer and mark it on the ground where the driver can see it.
  8. Record lift numbers, plant used and density results elevation by elevation, so a future investigation has something to read other than a completion certificate.

Settle these before the stone is tipped

Six figures that decide whether the membrane survives the fill, all of them cheaper to argue about with the void still open than with the wall buried.

  • Below-grade face area — Measured face by face, counting pilaster sides, footing step-downs and light-well returns rather than perimeter times height.
  • Protection board sheet count — Face area divided by the sheet you are buying — the metric and imperial boards differ by about 3%, so fix which one before ordering.
  • Lift thickness and lift count — Set the thickness from the compaction plant that is allowed near the wall, then read the count as a programme figure.
  • Specified density and its effort — The percentage, whether it is against standard or modified Proctor, and the borrow the laboratory maximum was run on.
  • Drainage composite rating under load — The ASTM D4716 flow per unit width at the normal stress your backfill applies, not the unloaded headline value.
  • Collector and outfall capacity — Pipe diameter, fall and outfall level — this is the number that limits the system, so establish it before the sheet is praised for its rating.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • International Residential Code Section R404.1.7, Backfill placement
  • International Residential Code Section R401.3, Drainage
  • International Residential Code Section R405.1, Foundation drainage
  • International Building Code Section 1610 and Table 1610.1, Soil Lateral Load
  • International Building Code Section 1803, Geotechnical Investigations
  • International Building Code Section 1805.4, Subsoil drainage system
  • ACI 318 Building Code Requirements for Structural Concrete
  • ACI 347R Guide to Formwork for Concrete, on the removal of forms and shoring
  • AASHTO LRFD Bridge Design Specifications, Section 3.11, Earth Pressure
  • ASTM D2487 Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
  • ASTM D698 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Standard Effort
  • ASTM D1557 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort
  • ASTM D6938 Standard Test Methods for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
  • ASTM D1556 Standard Test Method for Density and Unit Weight of Soil in Place by Sand-Cone Method
  • ASTM D2937 Standard Test Method for Density of Soil in Place by the Drive-Cylinder Method
  • ASTM D4253 Standard Test Methods for Maximum Index Density and Unit Weight of Soils Using a Vibratory Table
  • ASTM D4254 Standard Test Methods for Minimum Index Density and Unit Weight of Soils and Calculation of Relative Density
  • ASTM D4716 Standard Test Method for Determining the (In-plane) Flow Rate per Unit Width and Hydraulic Transmissivity of a Geosynthetic Using a Constant Head
  • ASTM D4751 Standard Test Methods for Determining Apparent Opening Size of a Geotextile
  • ASTM D4491 Standard Test Methods for Water Permeability of Geotextiles by Permittivity
  • ASTM D2321 Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications
  • AASHTO M288 Geotextile Specification for Highway Applications
  • BS 8102:2022 Protection of below ground structures against water ingress — Code of practice
  • 29 CFR 1926 Subpart P — Excavations (US Occupational Safety and Health Administration)
  • W. R. Meadows PROTECTION COURSE asphaltic protection board product literature
  • Carlisle Coatings & Waterproofing CCW MiraDRAIN drainage composite product literature
  • GCP Applied Technologies Bituthene sheet waterproofing and Hydroduct drainage composite product literature

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.