Two Pallets, a Bag of Bolts, and a Base Plan on Page Three
An 8 by 12 apex shed arrives as eleven flat packs, a hardware bag and a folded sheet of instructions, and it is on the drive by nine in the morning. A 3.6 metre pergola kit for the patio next door arrives the same week, in two long bundles and a box of brackets. Both booklets open at the same page and say more or less the same thing, in the same flat voice: the structure must stand on a firm, level base built to the dimensions shown. Neither of them tells you how, neither of them knows what the ground is, and both of them have already been paid for.
That is the trade a kit makes. It has settled every decision that used to need a carpenter standing on the site — panel sizes, member sections, fastener spacing, roof pitch, the length of every screw in the bag — and in exchange it has become completely inflexible about three things it cannot see from the factory. Where its load enters the ground. Where its posts are allowed to land. And what holds it down when a gale comes across an open garden at three in the morning in February.
Those three are the whole of this article, and it is written for the day the pallets land rather than for the month before. Which base system to build at all — raft slab, concrete pads, ground screws or a proprietary steel frame — is decided by the fall across the plot, the clay and the trees, and it is settled in full in the garden-room base guide along with the sub-base tonnage. The rafter and purlin grids for a pergola you are designing rather than unpacking belong to the pergola guide. Everything below assumes those calls are made and the kit is lying in the grass.
The Base Plan Is a Specification, and It Is Not the Shed's Size
The commonest error on a kit base is building it to the shed rather than to the floor. A timber apex shed is sold by an overall dimension that usually includes the roof overhang, so a base laid out to the size on the invoice finishes 50 to 75 millimetres proud of the floor on every side. That ledge collects the rain running off the cladding and holds it against the bottom board, which is the one board on the building that cannot be replaced without dismantling the wall. The base wants to finish flush with the floor frame or a whisker inside it, and that number is on the base plan rather than on the order.
Sheet-metal and moulded-resin kits invert the problem and are far less forgiving. Their wall panels bolt into a perimeter base rail or drop into a moulded floor pan, and that rail or pan is the datum for every hole in the building. It has to be fully supported along its whole length, dead square, and exactly the plan dimension — a rail bridging a hollow bends when the first panel is bolted to it, and every hole downstream of the bend moves. Those kits also arrive with their anchor points already punched, which means the anchoring layout has been chosen for you and the only remaining question is whether the base can accept fixings in those positions.
Read the base clause as a specification rather than as advice, because on most kits it is also a condition of the guarantee, and the wording differs between manufacturers in ways that matter: some accept a gravel pad, some require a continuous hard surface, some name a minimum bearing width under each floor bearer. The anchoring requirement usually sits in the same paragraph. Read both before the pallet is broken down, while everything is still returnable.
Then there is square, which on a site-built structure you chase with a string and on a kit you either have or do not. Nothing gets scribed on a flat-pack shed: the panels are pre-drilled, and your whole tolerance is the slack in those holes — a small fixed number you can measure on the parts in front of you, and one no article can supply for your kit. On a 2.4 by 3.6 metre floor the diagonal reads 4.327 metres. Pull both before the pad is finished, while the correction still costs a shovel rather than a saw.
Runners Land Under Joists, Not Under Panel Edges
Turn the floor panel over before you touch the ground. It arrives already framed — a perimeter, a set of joists at whatever centres the manufacturer chose, a sheet deck nailed or stapled over them — and that framing is the entire brief for the base. The runners are not there to hold up a floor. They are there to put a continuous, dry, non-settling bearing under joists that were designed on the assumption that something would be there. A runner that lands halfway between two joists is not supporting the frame at all — it presses on the underside of the deck sheet while the joists either side of it carry on spanning to the next runner that does catch one, and that is how a kit shed floor acquires the permanent dip under the mower.
Orientation comes out of the same inspection. Runners lie along the length of the shed and the joists cross them, so the width in the skid calculator is the dimension the runners are spaced across and the length is the dimension each runner runs end to end. Put those the wrong way round and the arithmetic is still correct — correct about a different building — and the error arrives as a runner order that is too short and too numerous. A 2.4 by 3.6 metre floor returns five runners of 3.6 metres each, which across 2.4 metres places them on 600 millimetre centres: marginally tighter than the two-foot convention the count came from, and that is the direction to err in.
Two placements are worth deciding rather than inheriting. Put a runner directly beneath the door opening: it is the only part of the floor taking a concentrated wheel load, it is where the threshold gets cut for a ramp, and it is the first area to rot because it is the only one rain reaches. And let each runner project 50 to 100 millimetres past the end of the floor frame, so the end grain is clear of the bearing and a bar can get under it when the shed has to be shifted in ten years. Each of those projections is a saw cut through pressure-treated timber, exposing a face the treatment never reached — flood it with a field-applied preservative to the manufacturer's instructions, which is the ground AWPA M4, the Standard for the Care of Preservative-Treated Wood Products, covers.
The pad beneath them runs past the runner grid on every side rather than stopping at it, for the same reason a slab edge is never built at the edge of its sub-base; the tonnage and the compaction that implies are worked through next door in the garden-room guide. The runners sit in ground contact whatever is under them, so they want the ground-contact use category — Use Class 4 under BS EN 335, or its equivalent under AWPA U1 — rather than the above-ground decking timber stacked beside it in the rack, which looks identical and is not.
A shed floor standing on runners
- Sheet floor panel — arrives already fixed to its joists, so its bearing is decided by where the runners land rather than by anything done on the day Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof)
- Floor joists — the members the runners actually have to catch; their centres are set at the factory and are the reason the runner grid is not a free choice Deck Joist Span and Size Calculator
- Pressure-treated runners — spaced across the width and running the full length, with one placed deliberately under the door opening and every cut end re-treated Shed Foundation Skid Calculator
- Compacted gravel pad — placed and compacted in layers a hand-guided plate can reach, and run out past the runner grid rather than stopped at it Gravel Base Layer Tonnage Calculator
- Retaining edge — stops the pad spreading and losing its compaction at the perimeter, which is exactly where the outer runners are standing
- Stripped formation — topsoil, turf and roots taken off down to something that will not keep settling once the pad is compacted onto it
Enter the floor panel's own dimensions — width across the runners, length along them — and then check the count it returns against the joists you can see on the underside of that panel, because the useful answer is a runner under every bearing rather than a runner every two feet.
The width of the shed, across which skids are spaced.
The length of the shed, which sets each skid's length.
Skids needed
6 skids
This assumes a standard 2 ft (0.61 m) skid spacing suitable for typical small-to-mid-size sheds — larger sheds or heavier floor loads may need closer spacing or a different foundation type (concrete piers or a full slab) per your local code.
- Length of each skid
- 12 ft
They open the calculator with your figures already in it
Shed Foundation Skid Calculator: 6 skids — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- The count comes from the Shed Width field alone — width decides how many runners, while length only sets how long each one is — so typing the two dimensions the other way round returns a different number of skids, and the layout takes it for granted that the floor joists cross the runners rather than sitting parallel to them.
- Skid size is never chosen here: there is no entry for a 4x4 against a 4x6, or for species and grade, so the beam depth carrying the floor between its bearing points, and the joist span across the gap between runners, still have to be sized on their own.
- Ground preparation sits outside the answer entirely — the gravel bed beneath the runners, its depth and footprint, the levelling work, and any blocks or pads the skids rest on are none of them counted, and the result behaves as though the ground is already flat and draining.
- Each skid is reported at exactly the shed's length, with no overhang past the floor frame for skidding or blocking, no cutting allowance, and no rounding to a stock beam length, so a runner that lands between sizes is still bought at the next length up and a shed longer than the longest beam available needs a splice this figure does not reveal.
- Nothing in the result holds the building down: the fasteners between the floor frame and the runners, and any tie-down against wind uplift or sliding, are separate from how many skids lie underneath, and a shed on skids rests on the ground rather than being fixed into it.
Level Is Three Points; the Fourth Is Where the Rock Lives
Any three points define a plane, which is why a three-legged stool never rocks and why a base checked at three corners is not checked at all. The fourth corner is the one that either lies in that plane or does not, and a five-runner base has five top surfaces that all have to lie in it. Nothing about this is forgiving on a kit: a site-built shed absorbs a twisted base into its framing and looks slightly odd, while a bolted panel kit transmits the twist straight into the hole pattern and the last panel simply will not meet the first.
How the reading is taken matters as much as where. A 1.2 metre spirit level leapfrogged three times across a 3.6 metre base compounds the instrument's own error three times and adds a fresh setting-down error at each move, always in the direction of travel — which is why a base checked that way comes out reliably wrong along one axis and fine along the other. Bridge the whole dimension with a straightedge and put the level on that, or take every reading from one origin: a water level costs almost nothing and does not care about distance, and a rotary laser does the same job faster above about three metres.
Where a runner has to come up, pack it with something that will still be there in a decade — a slate offcut, a bedded paving fragment, a composite shim — and not with a scrap of the timber you have just cut, which crushes under load and then rots in the wettest position on the site. One or two packers under a bearing point is a repair; a stack of five is a decision to rebuild the pad. Better to build the pad marginally proud everywhere and dress it down, because taking material away is a rake and putting it back is another compaction run.
- Set the two outer runners first, level each along its own length, then level the pair against each other with a straightedge spanning both.
- Bring the intermediate runners up to that plane one at a time, checking each against both outer runners rather than against its neighbour, so no error passes down the line.
- Read the runners against each other diagonally as well as square, since a base can be level in both principal directions and still be twisted.
- Stand on each corner and on the middle of each outer runner and watch for movement — a pad that settles under one person settles further under a shed, and it is cheaper to find now.
- Pull both diagonals across the runner ends and correct before anything is fixed, because the floor panel lands on those ends and inherits whatever they are doing.
- Photograph the finished grid with a tape in frame at two corners; once the floor is down, nobody sees any of it again.
A Pergola Kit Lands on a Surface Somebody Else Built
A pergola kit is drawn for open, level, unobstructed ground and it is almost never delivered to any. The realistic site is a twelve-year-old patio with a fall across it for drainage, an inspection chamber somewhere inconvenient, a gully against the house, a soakaway nobody can locate and a paving edge that stops 150 millimetres from where post three would like to stand. None of that is a reason to abandon the kit. All of it is a reason to set the post positions out on the ground with chalk before a single bracket comes out of the box.
Four things veto a post position, and only one is structural. An inspection chamber cannot be built over — access has to be maintained, and on a public sewer that is a formal matter with the water authority rather than a preference. A post base bolted close to a free slab edge has no concrete around it to develop anything, which is the next section. A base landing across a paving joint bears on two independently bedded units that will not stay coplanar. And a post in the low corner of a patio's drainage fall is standing in the puddle, whatever the timber is treated to.
Move a post and the beam over it gets longer, which is where a kit stops being a kit. The section supplied was sized for the span on the drawing, and a rated span for that beam is the only thing that says whether it can carry more — from the kit's own literature, or failing that from a published span table for the species, grade and section, such as the AWC Span Tables for Joists and Rafters or supplier tables derived from the strength classes in BS EN 338. If the answer is no, the resolution is another post rather than a longer beam. A 6.0 by 3.0 metre run at an 8 ft spacing ceiling returns ten posts: four down each long side, plus one intermediate on each short end.
Two limits on that number are worth stating plainly, because both cut in the reader's favour. The spacing choice tops out at 8 ft, so a kit whose beam is genuinely rated to span 3.6 metres clear sits outside the menu entirely — feed a 3.6 by 3.6 frame in and it reports eight posts where the kit correctly ships four, which is an artefact of the ceiling rather than a verdict on the kit. And the model assumes a beam runs along all four sides, so on a pergola beamed on two sides only, the intermediate posts on the short ends have nothing to support and come out of the count by inspection.
Enter the run you actually have to cover after the obstructions have had their say, with the spacing ceiling your beam section is rated for — the answer is whether the kit's post count survives contact with the patio, not a design for a new one.
The length of the pergola structure.
The width of the pergola structure.
The maximum span your beam size can safely support between posts.
Posts needed
8 posts
This is a general layout planning estimate — final beam sizing and post spacing should be confirmed against your local building code and beam span tables for the actual lumber species, grade, and expected roof/shade structure load.
- Posts along each long side
- 3 posts
- Posts along each short side
- 3 posts
- Post centres down each long side
- 6.5 ft
- Post centres across each short side
- 5 ft
They open the calculator with your figures already in it
Pergola Post Spacing Calculator: 8 posts — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- Every answer describes a freestanding four-sided frame: the total adds the posts on two long sides and two short sides and then subtracts the four shared corners, and there is no input for a pergola attached to a house or garden wall, where one whole run of posts is replaced by a ledger and the count drops.
- Only two maximum spans exist in the dropdown, 6 ft and 8 ft, and whichever you choose is divided into both dimensions at once, so a heavier beam that clears more than 8 ft between posts, or a layout that runs a long beam one way and lighter members the other, cannot be described here.
- Each side rounds its bays up on its own, so the two sets of centres above are usually different from each other and both sit under the maximum you picked — a 4 m side at the 8 ft setting is two bays of roughly 6.6 ft. That is the frame set out square. What it is not is a beam layout: the centres are post positions, and a beam carrying them still has to be checked against its own span.
- The metric option labels are rounded while the arithmetic is not — the option shown as 1.8 m divides by 6 ft (1.829 m) and the one shown as 2.4 m divides by 8 ft (2.438 m) — so on some footprints the bays behind the answer run a few centimetres wider than the metric figure you thought you had selected.
- The length and width you type are treated as the post run itself, so no allowance is made for the beam and rafter tails that normally cantilever past the corner posts, nothing distinguishes an overall outside dimension from centre-to-centre post positions, and only true rectangles are handled — an L-shaped or angled footprint has to be split and each part run separately.
- What comes back is a count of posts and nothing more: no post height or section size, no footing depth or embedment, no diagonal or knee bracing against racking, and no post bases, brackets or fixings.
Bolting to a Slab You Did Not Pour
The hardware bag says the fixings are for concrete, and that is the sum of what the kit knows about the thing it is bolted to. Three facts decide whether they hold, and all three are unknown when the box is opened: how thick the slab is, what is underneath it, and how far the fixing sits from a free edge. A base rail bolted to a 100 millimetre unreinforced garden slab is a reasonable detail. The same rail bolted to a 50 millimetre paving flag on five mortar dabs is not a fixing at all — it is a flag with a bolt through it, and the flag comes up with the shed.
Finding out is a ten-minute job and worth doing before the first real hole. Drill one exploratory hole with a masonry bit in a corner nobody will see, and feel and measure where the resistance stops; the change from concrete to bedding sand or sub-base is unmistakable through the machine, and the depth at which it happens is the number you needed. Where the surface is flags rather than a slab, lift one. On the BS 7533 series of pavements built from precast concrete flags or natural stone slabs, the bedding under them is a construction layer and not a structural one, and no post-installed anchor changes that.
The arithmetic that follows catches people out because a catalogue length reads generously and then loses most of itself before it reaches concrete. A fixed-length wedge or screw anchor gives up the base plate, any shim pack or levelling grout under it, and the washer, nut and thread projection above; only what is left is embedment. Mechanical anchors also want a hole deeper than the embedment so drilling dust falls clear of the tip, tabulated as a minimum hole depth rather than assumed. Between the two, the anchor in the bag frequently cannot reach the embedment its capacity was published at — and the slab is frequently not deep enough for it to try.
The documents that govern this are worth naming rather than paraphrasing. Anchoring to concrete is designed under ACI 318 Chapter 17 in the United States and under BS EN 1992-4, Eurocode 2 Part 4, Design of fastenings for use in concrete, in Europe. Any one product's capacity belongs to one qualified embedment and one installation procedure: mechanical anchors are qualified under ACI 355.2 and adhesive anchors under ACI 355.4, with the values in the product's ICC-ES evaluation report or its European Technical Assessment and the method in the manufacturer's printed installation instructions. Edge distance, spacing and whether the concrete is assumed cracked or uncracked all move those numbers, and the mechanism behind the edge-distance limit — the breakout cone — is worked through in the anchoring-into-concrete guide rather than here.
One structural point about pergola post bases, because it is routinely misread. A flat plate bolted to a slab is not a moment connection: it locates the foot of the post and resists uplift, and that is all it is honestly good for. What stops a freestanding pergola racking is the frame above — the beam-to-post joints, the knee braces, the rafters and purlins acting as a plane — so a kit with no braces and four flat plates is relying on those joints entirely. Worth knowing before somebody decides the braces are ugly and leaves them in the box.
Work the embedment the fixing needs against the anchor length actually in the bag, with the base plate and any packing under it subtracted — then compare the hole depth that produces with the slab thickness your exploratory hole found.
Whether the anchor comes at a fixed length or is cut from stock rod on site.
The embedment the design calls for, measured from the concrete surface.
The extra depth the evaluation report asks for beyond the embedment itself.
The overall length of the anchor or rod you have, tip to head.
The combined thickness of everything the anchor passes through before the concrete.
What has to stand above the fixture: washer, nut, and thread run-out past it.
Required drilled hole depth
3.34 in
The anchor entered leaves 3.36 in of embedment, which covers the 2.75 in required. Drill and clean the hole to the depth above, not to the anchor. Hole depth, diameter and cleaning regime are all part of the qualification — an uncleaned hole in an adhesive anchor loses a large fraction of its bond, and no arithmetic here recovers it.
- Embedment available from the anchor entered
- 3.36 in
- Anchor length needed for this embedment
- 3.89 in
- Shortfall against the required embedment
- 0 in
- Drilled depth beyond the embedment
- 0.59 in
They open the calculator with your figures already in it
Post-Installed Concrete Anchor Drill Depth Calculator: 3.34 in — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Add the equipment this sizes
This result is a specification — 3.34 in — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.
What this calculation does not cover
- Does not check capacity. Whether the embedment is adequate for the load is an ACI 318 Chapter 17 calculation involving concrete breakout, pryout, edge distance, spacing and whether the concrete is cracked.
- Does not check that the base material is thick enough. Most reports set a minimum member thickness well above the hole depth, and drilling through a slab is a different problem entirely.
Three Different Things Get Called Anchoring
A light building in an open garden can fail three separate ways in wind, and a bagged anchor kit is usually designed for one of them. Uplift takes the whole box off the base. Sliding translates it sideways off its runners. Overturning rotates it about the downwind bottom edge. They want different restraints in different places, and the reason a shed is sometimes found twenty metres down the garden with its anchors still in the ground is that the anchors held and the thing they were strapped to did not.
| What the wind does | What has to resist it | What the kit usually supplies | Where it lets go first |
|---|---|---|---|
| Uplift — the whole structure lifts clear of its base | A continuous tension path from the roof down to the ground | Ground anchors and straps at the base only | The wall-to-floor joint, which was detailed to locate a panel rather than to carry tension |
| Sliding — the building translates off the runners | Shear between frame and base, and between base and ground | Nothing directly; a taut strap resists sliding only incidentally | The runner, which slides on a gravel pad long before the pad itself moves |
| Overturning — the box rotates about its downwind edge | Hold-down at the windward side, where the leverage is | A perimeter spacing rule that knows nothing about leverage | The two or three windward anchors, which take the whole restoring couple between them |
The Count Is a Budget; the Positions Come From the Frame
Run the convention on the 2.4 by 3.6 metre shed — a 12.0 metre perimeter at roughly six-foot spacing — and it returns seven anchors. Seven does not map onto a rectangle. Four are corners, leaving three intermediates to share between four sides, and every way of doing that leaves one side longer than the rule allows. Build eight: a corner at each corner and one intermediate at the midpoint of every side, which puts the longest unsupported run at 1.8 metres. The count is a budget to buy against and a check on the kit's own hole pattern; the positions come from the geometry, and where they disagree the geometry wins.
The positions also have to land on something structural, which quietly removes most of the perimeter from consideration. On a sheet-metal or resin kit the anchor points are the pre-punched rail holes and there is nowhere else to put them. On a timber shed the strap has to reach a runner, a floor bearer or a wall stud — never the cladding and never the sheet deck, both of which tear out around the fixing long before the anchor moves in the soil. An anchor sitting 100 millimetres off the even spacing for that reason is the correct outcome, not a compromise.
As for how much any of it holds: an auger or screw-in ground anchor's capacity is a strongly soil-dependent figure published by its own manufacturer, and no general number could honestly be printed here for it. What can be said is where the chain usually breaks, and it is almost never the soil. It is the strap, the buckle, or the fixing through the strap into the timber — a single screw through a galvanised strap into a runner has a withdrawal capacity that is a published property of the fastener and the timber, and it is routinely the smallest number in the assembly. Design wind actions come from ASCE/SEI 7 or BS EN 1991-1-4 with its National Annex, and neither produces an anchor count for a shed; the manufacturer's instruction does, and a local requirement for accessory structures overrides both.
Enter the base perimeter and the spacing you intend, then hold the count it returns against the anchor points the kit has already punched into its base rail — what you want out of it is whether the kit's own pattern is tighter or looser than the convention, not a fresh layout.
The total perimeter of the shed's base.
The maximum spacing between anchors.
Ground anchors needed
8 anchors
Wind exposure, shed size, and local code all affect the actual required anchor count and spacing — check your specific anchor kit's manufacturer instructions and your local building code before finalizing.
- Shed perimeter
- 43 ft
- Anchor centres round the shed
- 5.38 ft
They open the calculator with your figures already in it
Shed Anchor Kit Calculator: 8 anchors — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- The count is the perimeter cut into equal bays and rounded up, with no floor under it and no anchor set aside for the corners where uplift concentrates: at the default 6 ft spacing, a shed of 18 ft perimeter or less comes back as three anchors, fewer than the building has corners.
- Rounding up tightens the real interval rather than leaving a short last bay, and that finished figure is never shown — the default 13.2 m perimeter at 6 ft spacing returns eight anchors sitting about 5 ft 5 in apart, while the only line under the answer repeats the perimeter in feet.
- Perimeter arrives as a single number, so a long narrow shed and a square one of the same girth get an identical answer, and there is no input for the door opening or a ramp — an anchor point that lands on a threshold has to be shifted by eye.
- Nothing about the anchor or what it goes into reaches the division: auger length, rated withdrawal capacity, the strap or cable that ties the anchor back to the frame, and whether the ground is soft clay, loose sand or backfill all leave the number unchanged.
- The answer is loose anchors rather than packs, so it is not divided into the kit sizes these are sold in and it carries no spare for an anchor that meets a rock or a root and has to be relocated.
- The spacing box stops at 3 m, a little under 10 ft, and the perimeter box at 100 m, so a kit rated for wider intervals or a building bigger than that cannot be entered as it stands.
When the Base Is Wrong and the Kit Is Already Open
By early afternoon the base is built, the first panel is standing against the fence, and there is a defect. There are only three, and they are not equally serious. Out of square is recoverable on a timber shed whose floor overhangs, because the building can be assembled square on a base that is not; it is fatal on a rail-and-panel kit, where the rail is the square. Out of level in one plane is a packing job. Twisted is the one to stop for, because every subsequent operation makes it harder to find and the panel that finally refuses to bolt up is the last one, four hours later.
The fourth defect is not in the base at all: the base is right and it is in the wrong place. A shed set 200 millimetres off a boundary fence can never be re-felted, treated or repaired on that side, and the gap that matters is the one a person can work in rather than the one the plan shows. It is cheaper to fix while the runners are still loose on a pad than at any later moment in the building's life, so walk all four sides with the tape before the floor goes down.
One code point genuinely belongs to this kind of structure, and it is worth knowing before somebody insists on frost-depth footings. IRC Section R403.1.4.1 sets frost protection for footings and carries an exception releasing small freestanding accessory buildings of light-frame construction from it, subject to limits on construction type, floor area and eave height that differ between adopted editions — read them in the edition your jurisdiction has adopted rather than from a summary. What the exception releases is the footing depth, not the consequence: a skid base in a freezing climate will move seasonally, and it survives because it moves as one raft. What damages a shed is differential movement, one corner rising against three, and that is a compaction and drainage problem rather than a depth one. Whether the structure needs permission or building control at all is a separate local question, covered for garden buildings and for pergolas in the two guides linked below.
What to have measured before the pallets are opened
Five numbers decide whether a kit goes up in a day or comes back down in a fortnight, and every one of them is taken off the delivered parts and the actual ground rather than off the order confirmation.
- Floor panel dimensions and its joist centres — Measured on the panel itself with it turned over, not taken from the shed's advertised size — the advertised size usually includes a roof overhang the base must not follow.
- Runner count and orientation against those joists — Runners along the length, spaced across the width, with one deliberately under the door opening and every one landing beneath a joist rather than mid-bay.
- Both diagonals, before and after — 4.327 m on a 2.4 by 3.6 base. Read them on the pad and again on the finished runner ends, because the panel lands on the ends and inherits whatever they are doing.
- Slab thickness and edge distance at every post base — From one exploratory drilled hole per bearing area, with the distance to the nearest free edge written next to it — the two numbers that decide whether the supplied fixings can be used at all.
- Anchor positions on the frame, not on the perimeter — Each hold-down mapped to a runner, bearer, stud or pre-punched rail hole, with the fastener into it named — the strap into the timber is usually the weakest link in the whole assembly.
Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.
