Plot three, the rear boundary, and canes nobody looked at in February
Four houses on a fifth of a hectare, outline consent discharged, groundworks starting in six weeks. Along the rear boundary there is a run of hollow, bamboo-like canes about two and a half metres tall with red-flecked stems, standing in a band roughly fifteen metres by two. Plot three's strip footing runs straight through the middle of it. Rather more than half the stand is on the far side of a lap fence, in a garden that belongs to somebody who has not returned a letter.
Two clocks now run against each other and they keep different time. The build programme is measured in weeks and it wants the corner cleared. A herbicide programme is measured in growing seasons, because it works by getting a translocated chemical down into a rhizome system while the plant is actively moving material into it, and the plant only does that for part of the year. Excavation, by contrast, can happen in January — but a January survey looks at dead canes over frozen ground and cannot tell you where the rhizome stops, so a winter dig is a dig whose extent was guessed.
What makes this unlike every other awkward corner is that the soil is perfectly ordinary. Nothing has leached into it, no laboratory will find anything in it, and a leaching test settles nothing. The control is on a plant, and the entire method — the fence line, the dedicated bucket, the sheeting, the barrier, the named gate — exists because of what a fragment of rhizome does when it is dropped somewhere else. The Environment Agency's code of practice put the regenerating fragment at under a gram. Everything below follows from that one sentence.
The dig line is dug for, not scaled off
Where the canes stand is not where the plant is, and the gap between those two statements has moved a long way in a decade. The Environment Agency's knotweed code of practice, version 3 of 2013, put rhizome extension at up to seven metres laterally and three metres deep, and that pair of figures is still the basis of a great many method statements written today — even though the document was withdrawn in 2016. Work published in PeerJ in 2018 by Fennell, Wade and Bacon found typical rhizome extension very much shorter than the seven-metre planning figure, and the RICS professional standard of January 2022, Japanese knotweed and residential property, dropped the seven-metre rule in favour of a categorised management assessment made on evidence. The practical consequence is that the extent is now argued rather than assumed, and what you argue from is a grid of holes.
The survey is a machine job, not a walk. Inspection pits are dug outward and downward from the last visible cane on a grid, logged with position and depth, and continued until pits come back clean on consecutive lines. The sequence matters as much as the spacing: work from clean ground inward rather than from the stand outward, so the bucket is never carrying rhizome into virgin soil, and backfill each pit with its own arisings rather than tidying them into a heap. A survey done the wrong way round is itself a spreading event, and the pits are usually the first time anyone puts a machine in that corner.
For the corner above, say the pits come back clean 2.4 metres beyond the last cane on the site side and find rhizome down to 1.5 metres in a band that follows an old field drain. The agreed excavation plan comes out at 11 metres by 5.5, taken to 2.2 metres — deeper than the deepest find, because the last 700 millimetres is what you inspect on the way out. That is 133 cubic metres in the ground, and it is worth noticing that the footing on plot three only ever needed 1.1 metres. The plant set the depth, not the structure.
Now put the bank figure through the swell. Loose, that material is around 166 cubic metres, and on this job that number is not about lorries — it is about whether there is anywhere on the plot capable of receiving it. A cell void, a lined and bunded treatment stockpile, or a vehicle body: those are the three destinations, and all three are sized in loose volume. The recompacted figure the calculator returns alongside it is worth reading too, because material placed back into a cell in thin lifts finishes denser than it left the ground, so the void the cell needs is not simply the bank volume with a percentage on it.
| What the pit shows | What that settles | What it leaves open |
|---|---|---|
| A rhizome crown directly beneath a standing cane | That the stand is where it appears to be | How far it runs from there in any direction |
| Clean soil on two consecutive lines beyond the last cane | A defensible outer edge for the dig line | Whether the far side of the boundary behaves the same way |
| Rhizome at 1.5 m under made ground | The excavation depth, independently of any foundation depth | Whether it runs deeper again under the fence line |
| Rhizome tracking along an old drain or service trench | That the dig follows the trench rather than the grid | Where that trench leaves the site and what it passes under |
| Fragments in imported fill spread across the plot | That the source was a soil movement, not a growing stand | How many other loads went to how many other addresses |
| Dead canes in February and nothing identifiable below | Very little | Effectively everything — a winter survey defers the question |
Put the surveyed block — 11 by 5.5 by 2.2 metres — in as the bank volume and read the loose figure as a space requirement rather than a haulage one: it is what a cell void, a treatment bund or a vehicle body has to swallow.
The undisturbed, in-situ soil volume.
How much the soil expands once excavated and loosened, as a positive percentage.
How much smaller the soil ends up once recompacted, as a negative percentage.
Loose (haul) volume
163 yd³
Swell and shrinkage factors vary significantly by soil type and moisture content — use site-specific values from a geotechnical report or local hauling experience where available, rather than generic averages.
- Bank (in-situ) volume
- 130.75 yd³
- Compacted (recompacted) volume
- 117.68 yd³
They open the calculator with your figures already in it
Soil Swell & Shrinkage Haul Volume Calculator: 163 yd³ — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- The swell and shrinkage percentages are figures you supply, not properties this page derives. Moisture content, fines content, how the material is dug and the compactive effort actually applied all move the real factors, and the same soil at a different moisture will not behave like the number you typed. Take the factors from the site investigation or measured local experience, not from a general table.
- This is a volume conversion, not a haulage calculation. It does not size trucks, count loads, or apply payload limits — wet or dense spoil often reaches a lorry's weight limit before it fills the body, and heap, tailgate profile and further bulking during loading all sit between this loose figure and a load count.
- The compacted figure is not a compaction specification. It assumes the placed fill achieves exactly the shrinkage percentage entered, and says nothing about the density the fill must be tested to, layer thickness, the plant used, or material rejected and reworked. It does not replace field density testing.
- One bank volume with one pair of factors. A mixed excavation — topsoil over clay over rock, or a trench through made ground — has different swell and shrinkage per stratum, and running the whole quantity at a single figure misstates both the haul and the fill. Topsoil stripping and unsuitable or contaminated material that leaves site instead of returning to fill are outside the model entirely.
- The loose volume describes material immediately after excavation. A stockpile consolidates under its own weight and with rain, so a survey of a pile that has stood for weeks comes back below this figure. Nothing here addresses waste classification, tipping, or duty-of-care disposal requirements for spoil going off site.
Five routes out of the same corner, and land is what chooses
There are five honest answers here and they are paid for in three different currencies: growing seasons, land, or money by the tonne. Two of them leave the material broadly where it lies — a herbicide programme run on the standing plant under a written plan, or a horizontal barrier capping it in place under hard standing. Two move it without letting it off the plot, into a lined and bunded treatment stockpile or into a membrane cell. The fifth sends it to a permitted gate and closes the file.
The arithmetic quietly eliminates two of them on most jobs before anyone has a preference. The withdrawn Environment Agency code of practice set out the two burial geometries the industry still designs to: burial at a depth of at least five metres without a barrier, or encapsulation within a root barrier membrane with at least two metres of cover over it. Take the second. One hundred and sixty-six cubic metres of loose arisings under two metres of cap, in a hole with battered sides, is either a hole about five metres deep or a footprint the size of a tennis court — and whichever it is, that land is finished. Nothing structural goes over it, no drain runs through it, and no future owner digs a pond in it. On a fifth of a hectare with open space at the rear, that is a conversation. In a nine-metre town garden it is not an option at all, and saying so early is more useful than pricing it.
Whether the on-site routes are even permissible is a separate gate again, and it is not one to take from a guide. In England the mechanism is the Environment Agency's regulatory position statement on the treatment and disposal of invasive non-native plants, RPS 178, which sets the conditions under which burial or on-site treatment can proceed without an environmental permit. Read the current version of it rather than any summary, including this one: regulatory position statements carry expiry dates, are withdrawn and reissued, and their conditions — depth, containment, cover, records, notification — are the whole of the permission. In Scotland, Wales and Northern Ireland the regulator is different and so is the position.
Excavate-and-cap deserves its own warning, because it looks like the cheap answer. Leaving material in place under a horizontal barrier beneath a slab or a parking court saves the dig, the haulage and the gate, and fixes the layout permanently around something nobody may ever break into. A cap under a driveway sits under the exact surface somebody will one day trench for a charge point.
| Route | What it spends | When it is finished | What it leaves on the land |
|---|---|---|---|
| Herbicide programme, plant left in situ | Growing seasons, and a programme that waits on them | When the management plan says so, not when canes stop appearing | Nothing built over that corner in the meantime |
| Excavate, stockpile on site, treat the heap | Land, a bund, a liner and a fenced compound | After the treatment seasons, when the material can be reused | A reusable soil and a compound to reinstate |
| Bury on site in a lined cell | Land, depth, membrane and imported cap fill | At the cap, in one continuous operation | A sterilised footprint that has to be recorded for good |
| Excavate and cap in place under hard standing | Layout freedom, permanently | At the slab | A barrier under a surface somebody will want to dig up |
| Excavate and remove to a permitted gate | Money, by the tonne, plus haulage and vehicle time | When the last transfer note is signed | A clean plot and a folder |
The cell is a lined box and the lid is the part that fails
A burial cell is not a hole with a sheet in it. It is an envelope: a base and four battered faces in one continuous liner, the arisings placed inside it, a lid closed onto the upstands with a made seam, and clean imported fill capping the lot. Everything about it is decided before the first bucket, because there is no version of this that can be adjusted afterwards.
Siting is the hard part on a developed plot. The cell has to sit clear of every foundation and every drain, clear of the ducts and service runs that do not exist yet but are already on a drawing, above the water table, inside your own boundary, and outside the reach of the next machine that comes here. It also has to be dug with faces that stand — battered to a profile the ground will hold, or supported, which is ground the trench and deep-excavation guides on this site cover properly and which a 2.7 metre face absolutely requires. Battering has a second effect people forget when they order membrane: it makes the wetted area of the box very much larger than its plan area.
On the membrane itself, the number to compare across products is not the thickness in microns that appears in the headline. It is the mechanical performance on the data sheet — static puncture resistance to EN ISO 12236, wide-width tensile to EN ISO 10319, dynamic perforation to EN ISO 13433 — because a liner fails where a bucket tooth, an angular stone in the formation or a rock in the cap finds it, not where it is thin in the abstract. Seams are made by the method that product's own installation instruction specifies, welded or taped; they are not made by lapping generously and hoping. And no service, no marker post and no root of anything penetrates the envelope, ever.
For the area, forget the plan footprint. Take the contained portion of a cell — nine by seven metres at the base and 2.7 metres tall, battered one horizontal to two vertical, with the cap dug above it. That is around 63 square metres of base, something like 113 square metres of sloping face and a lid of roughly 120 once the laps are counted: call it 300 square metres of sheet before any allowance for cutting and waste, against a plan footprint of 63. Enter the developed area, and read the area line in the breakdown rather than the roll count, because the roll count is worked against a 300 square foot garden-fabric roll and a root barrier does not come that way. The built-in overlap allowance is a tenth, which is right for a mulch bed and short for a barrier with made seams; add your own lap into the area you enter rather than trusting it.
- Set the cell out clear of every foundation, drain, duct and future service run, and record the setting-out before a bucket goes in.
- Batter the faces to a profile the ground will stand at, or support them — 2.7 metres of face is not something anyone works beside untouched.
- Trim and blind the formation so nothing angular is left bearing on the liner.
- Lay base and faces as one continuous envelope with the laps running the way the installation instruction says, and turn every edge up well above the finished level of the fill.
- Place the arisings in thin lifts with light plant, keeping the bucket clear of the liner throughout.
- Close the lid onto the upstands, make the seam by the specified method, then cap with clean imported fill in compacted lifts and reinstate.
What a burial cell is made of
- Topsoil and turf reinstated — the only part of the cell anyone ever sees, and the reason it stops being marked on site the week after it is finished
- Clean capping fill — imported, placed and compacted in lifts, and the layer the two-metre cover figure is actually about Fill Dirt Cubic Yards to Tons Calculator
- Barrier lid and made seam — closed onto the upstands of the liner by the method the data sheet specifies, never by lapping and weighting Landscape Fabric Calculator
- Knotweed-bearing arisings — placed in thin lifts with light plant, stopped low enough that the lid closes onto a full upstand Soil Swell & Shrinkage Haul Volume Calculator
- Liner, base and battered faces — one continuous envelope with no penetration of any kind, sized on developed area rather than plan area Driveway Separation Geotextile Roll Calculator
- Trimmed formation in undisturbed ground — blinded so nothing angular is left bearing on the liner, and battered to a face the ground will stand at Excavation Sloping/Benching Setback Calculator
Enter the developed area of the envelope — base, four battered faces, lid, upstands and your own lap allowance added in — and read the area figure in the breakdown, not the roll count, which is worked against a garden-fabric roll size.
The total area to cover with fabric.
Fabric spent where strips lap each other so weeds cannot come up through the seam.
Landscape fabric rolls needed
2 rolls
- Area to cover (with overlap allowance)
- 473 sq ft
They open the calculator with your figures already in it
Landscape Fabric Calculator: 2 rolls — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- The roll count assumes every roll covers 300 sq ft (about 27.9 m²), and there is no field for the roll you are actually buying. Landscape fabric is sold in several width and length combinations, and the answer moves in direct proportion: halve the coverage of the roll and you need twice as many. Take the "area to cover" figure from the breakdown and divide it by the coverage printed on your own roll before you order.
- Overlap is a percentage uplift on the area, not a lap calculation. Roll width, lap width and the number of strips a bed takes are not inputs, so the default 10 per cent only holds where the bed is wide enough that a narrow side lap costs roughly a tenth of the sheet. On a narrow border, on anything run across the roll rather than along it, or where end laps stack up on a long run, the lap fraction rather than the bed area decides the count, and the allowance has to be raised to match.
- Nothing is added for cutting waste. Fabric worked around established shrubs, tree trunks, posts, drain covers, curved bed edges, or any bed narrower than the roll leaves offcuts that will not be used anywhere else, and the allowance here is for overlap rather than for cutting. There is also no allowance for turning the sheet up at edges or tucking it under edging restraint.
- This counts fabric only. Pins or staples, seam tape, edging, the ground preparation underneath and the mulch or gravel that goes over the top are separate quantities, and none of them are in this number.
- The result is a quantity, not a specification or a judgement that fabric is the right answer. A light non-woven and a heavy woven of the same area return the same roll count despite very different permeability, weed resistance and service life, and under mulch the organic debris that collects on top of the sheet becomes its own seed bed whatever grade you buy. The area field also stops at 2,000 m² (about 21,500 sq ft); enter more and the figure is replaced with that limit, and a job at that scale is buying contractor-width rolls this retail-roll model does not describe.
The half you cannot treat is on the other side of the fence
Nothing above helps with the part of the stand growing in someone else's garden, and there is no general right to walk onto their land and treat it. Section 14(2) of the Wildlife and Countryside Act 1981 makes it an offence to plant or otherwise cause Japanese knotweed to grow in the wild — Schedule 9, Part II lists it — but that is not an obligation on your neighbour to do anything about theirs. The civil route exists: in Network Rail Infrastructure Ltd v Williams [2018] EWCA Civ 1514 the Court of Appeal held that encroaching knotweed can be an actionable nuisance through loss of amenity, and the Supreme Court returned to what the recoverable loss actually is in Davies v Bridgend County Borough Council in 2024, where causation defeated the claim. Local authorities have a faster and blunter instrument in the community protection notice regime of the Anti-social Behaviour, Crime and Policing Act 2014. All of these take longer than six weeks.
What you can build on your own land, today, is a vertical root barrier along the boundary. A trench, taken below the depth the survey found rhizome and returned or toed at the base, with the membrane hung against the contained face and the trench backfilled. Along the rear boundary and one return that is 38 metres at 600 millimetres wide, taken to 2.5 metres: about 57 cubic metres of excavation. Run it with the pipe diameter set to its minimum, because there is no pipe in a barrier trench and the calculator will otherwise subtract a void that does not exist.
Then read both ends of the answer, because they go to different places. The headline is the loose granular that has to arrive — around 65 cubic metres of it — and it has to arrive because the arisings from a trench dug through the exclusion zone are themselves knotweed-bearing and cannot simply be shovelled back on the clean side of a membrane you have just installed. Meanwhile the excavation line in the breakdown is 57 cubic metres joining the disposal total. A boundary barrier is not a cheap alternative to a dig; it is a second dig with an import attached, and it is the only one of the two that a neighbour's inaction cannot undo.
38 metres at 600 wide and 2.5 deep with the pipe diameter wound down to its minimum: the headline is the clean granular that has to be imported, and the excavation line in the breakdown is more material for the gate.
The total length of the trench.
The width of the trench.
The depth of the trench.
The outer diameter of the pipe being laid; 0 for a trench with no pipe.
Depth of bedding material under the pipe; 0 if the pipe sits on the trench bottom.
Depth of the same bedding material over the top of the pipe; 0 for none.
Extra loose material needed to achieve full compaction in the void.
Loose backfill material needed
50.9 yd³
Assumes the excavated soil itself isn't reused as backfill (e.g. importing clean granular fill) — if reusing native soil, account for its own swell factor separately.
- Excavation volume (the depth entered)
- 48.89 yd³
- Pipe volume (subtracted)
- 4.6 yd³
- Compacted backfill void
- 44.29 yd³
They open the calculator with your figures already in it
Trench Excavation & Backfill Volume Calculator: 50.93 yd³ — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
The pipe is drawn to scale inside the trench. Backfill is everything else in the section, which is why the pipe diameter changes the answer at all.
What this calculation does not cover
- The trench is modelled as a plain rectangular prism — vertical faces, one width and one depth over the whole run. Battered or benched sides, the extra width a trench box needs, over-break outside the drawn line, and a bottom that falls with the pipe's gradient are all outside it. A run cut back to a safe slope holds considerably more than this figure, and the shortfall rises with the square of the depth rather than in proportion to it.
- This is a quantity take-off, not an excavation safety assessment. Nothing here classifies the soil, checks the depth against sloping, benching or shoring requirements, or sizes a protective system — that comes from a competent person on site, and past the depths the rules set, from an engineer.
- Only the single pipe you enter is deducted. A second pipe or duct sharing the trench, cable bundles, manholes, chambers, valve boxes, thrust blocks and concrete surround all displace backfill and are not subtracted. No check is made that the pipe fits the trench you described either: where its volume exceeds the excavation, the answer is floored at zero rather than reported as impossible geometry.
- At most two materials: a bedding and surround zone when you enter a bed or a cover, and one backfill above it at one flat percentage. The bedding row is an in-place volume across the full trench width, capped at the trench depth, with no compaction or waste allowance, so add your own for a graded bedding that is compacted. Marker tape or protective tiles, and the sub-base, blacktop or topsoil at the surface are further materials in further thicknesses and are not split out. The percentage is a loose-volume allowance on the backfill and nothing else — it is not a density or Proctor specification, and it says nothing about lift thickness or how many passes the plant makes.
- Nothing is said about the spoil. The excavation row is a bank volume measured in place, not the loose volume that leaves in the truck, and the calculation does not judge whether the arisings can go back, how much of the void they would fill, or what has to be carted away. Rock, groundwater and dewatering, and over-excavation to remove unsuitable ground are all excluded.
Weighed at the gate, described on the ticket
If it leaves, it leaves by weight. The 133 cubic metres from the main dig is about 174 cubic yards, which at the planning density this catalogue publishes for clay is near 261 short tons — roughly 237 tonnes. Add the barrier trench and another 57 cubic metres becomes about 112 short tons, and the corner of the site has produced something like 373 short tons, near 338 tonnes, before anybody has laid a brick. Feed it the bank volume rather than the bulked one, for the reason set out at length in the guide on getting spoil off a small site.
The classification is the part people get wrong in both directions. Soil carrying knotweed is a controlled waste, so the duty of care in section 34 of the Environmental Protection Act 1990 attaches to it exactly as it does to any other, and in the List of Waste established by Commission Decision 2000/532/EC it sits at 17 05 04, soil and stones, where it comes out with the ground; cut green material on its own falls under 20 02 01. It is not hazardous waste, so there is no consignment note under the Hazardous Waste (England and Wales) Regulations 2005 and no assessment under WM3 to do. What controls it is where it may go and how it is handled on the way. The duty-of-care machinery around that — checking the carrier's registration, what a transfer note has to carry, how long the folder is kept — is set out in the spoil guide and is no different here. What is different is the description you write on the note: a clean-soil description on a knotweed load is not an administrative slip, it is how a receiving site ends up spreading it across its own restoration.
Not every permitted landfill will take it. Sites that do may require pre-notification and place it deep within their own cell, which is why availability, rather than price, quite often decides how far the wagons go. Get the acceptance in writing with the description you intend to use, before the programme is built around a gate that turns out to be forty miles further away than the one you priced.
North American practice has no federal equivalent to lean on: Japanese knotweed is not on the USDA APHIS federal noxious weed list, and control is state by state — restricted in Wisconsin under chapter NR 40 of the Administrative Code, prohibited in New York under 6 NYCRR Part 575, and elsewhere differently again or not at all. Where the state is silent the receiving facility's acceptance policy does all the work, and the question to ask it is the same one: will you take this, described this way, in writing.
The main dig converted at the clay planning density: 174 cubic yards in the ground comes out near 261 short tons, and the barrier trench adds another 112 before the plot is clear.
The volume of clay soil in cubic yards.
Approximate weight
15 short tons
About 1.5 short tons per cubic yard for clay; heavier than loam and highly sensitive to moisture. A planning figure, not a specification. Confirm the density with your supplier before ordering by weight.
- Conversion factor applied
- 1.5 short tons per cu yd
They open the calculator with your figures already in it
Clay Soil Cubic Yards to Tons Calculator: 15 short tons — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- Say which volume you measured. Clay in the ground and the same clay loose in a spoil heap are two different volumes of one material, and this page applies a single planning density to whichever number it is given — so the hole and the heap return different tonnages for the same dig. Settle which of the two you are working from before a load or a charge is planned on the answer.
- An excavation is rarely all clay. Topsoil at the surface, a stone band, old fill or a softer horizon at the base each carry their own weight per cubic yard, and putting the whole excavation volume through one clay density weighs all of it as clay. Split the volume by layer where the difference is large enough to change a load count.
- Treat this as a planning tonnage, not the figure a charge is settled on. Where haulage or disposal is priced by weight the weighbridge ticket governs; where it is sold as a fixed weight allowance per load, this is the number to test that allowance against. For excavated clay the rate per ton also turns on how the material is classified, which no density conversion can tell you.
Clay is the excavated material most likely to complicate a job, and its weight per cubic yard is high enough to matter for haulage. What makes clay difficult is not density but behaviour: it holds water, shrinks and swells with the seasons, and becomes unworkable when wet. Excavated clay also bulks substantially, so the spoil from a trench occupies noticeably more space than the hole it came from — which is why disposal volumes routinely exceed the excavation figure.
Every movement is a chance to plant it somewhere else
Counting loads matters here for a reason that has nothing to do with payload ceilings. At around 166 cubic metres loose against a twelve cubic metre body, the main dig is fourteen movements. Each movement is a sheeted vehicle, a transfer note, a cleaning cycle and several miles of public highway, and a fragment shed off a tailgate onto a verge is a new stand on somebody else's land with your transfer note pointing at it. That is why loads are not part-filled and topped up with clean soil from elsewhere on the plot, and why the vehicle is cleaned before it goes back on a job where nobody is thinking about this.
The exclusion zone is the other half of the same discipline, and it is fenced to the survey line rather than to the canes — which usually surprises whoever has to move the site cabin. One entrance, signed so a delivery driver understands what the fence means. A dedicated bucket and, ideally, a dedicated machine for the duration. A cleaning point inside the line, so nothing crosses it dirty; the compound guide on this site covers how to build one that does not simply wash the problem into a drain. And the vectors nobody fences against are the small ones: barrow wheels, boot treads, the trackway mats, and the length of scaffold board somebody laid across the mud and then carried to plot one.
- Fence to the surveyed line rather than to the visible canes, and sign it so it reads as an instruction rather than as decoration.
- Give the zone a single entrance with the cleaning point inside it, so nothing leaves the line uncleaned.
- Keep one bucket and one machine in the zone for the duration and clean both before they work anywhere else on the plot.
- Sheet every load before it moves and check the tailgate seal — the highway is where a fragment becomes somebody else's problem and your liability.
- Log each load against the excavation plan, so what has left can be reconciled with the block the survey drew before the hole is signed off.
Run the loose volume against the body the haulier is actually sending, and read the bed size printed beside the count rather than assuming the menu opened on it — the fourteen above is 166 cubic metres against a 12 m³ tipper. The count is not a cost line: it is the number of times a loaded vehicle carrying viable rhizome leaves your gate.
The total material volume to haul.
The hauling capacity of the truck being used.
Truck loads needed
5 x 12 yd³ loads
Trucks are also limited by legal weight, not just volume — dense materials like gravel or wet soil may reach a truck's weight limit before filling its full volume capacity, requiring more, partial loads.
They open the calculator with your figures already in it
Dump Truck Load Calculator: 5 x 12 yd³ loads — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- This counts volume only. It does not check payload, axle loading or gross vehicle weight, and a body filled with gravel, sand, wet clay or broken concrete normally reaches its legal weight limit before it is full — so dense material takes more trips than the volume count shows. It is not a legal load check; what the truck may legally carry is the hauler's call.
- The figure you enter is treated as loose, as-loaded volume. Excavated soil and demolition debris swell once they are dug out, and delivered fill loses volume once it is compacted in place, so a bank (in-ground) or compacted-in-place quantity entered here undercounts loads. Convert to a loose volume before using this.
- The three bed sizes are generic fleet sizes, not your truck. Rated capacity moves with body length, sideboard height and whether the quoted figure is struck (level) or heaped, and liners, tailgate gear and a worn body all change what actually goes in. Confirm the number with the hauler or rental yard.
- Nothing here covers getting the truck to the material. Site access and turning room, overhead clearance, tipping space, posted road and bridge weight limits, seasonal load restrictions and permits all change how many trips are actually possible, and none of them are modelled.
- One material, one truck type, and no cost. Loads that cannot be mixed — segregated waste streams, separate stockpiles — need their own counts, and haulage rates, tipping fees and disposal charges (often billed by weight or per ticket rather than per load) sit outside this calculation.
Two prices for the same 338 tonnes
Of the five routes in the table earlier, exactly one resolves into a single figure before anybody starts: the last one. Three hundred and thirty-eight tonnes at whatever the permitted gate quotes is the whole of dig-and-dump, arrived at in one multiplication and final on the day the last wagon leaves. Every other route is a programme, a land take and a set of obligations that outlive the job. So work that one number out first and put it on the table, because until it is there the other four are being argued about in the abstract with a client who only wants the corner cleared by Friday.
Two things to establish before either figure is trusted. Whether landfill tax is inside the quoted rate or added to it, and — more slippery — which rate applies at all: that is decided against the Landfill Tax (Qualifying Material) Order 2011 and HMRC's own guidance on it, and it is a question to put to the operator in writing rather than one to assume from the fact that soil is soil. And whether there is a minimum charge, because on a job that ends with three part loads of inspection-pit arisings, a minimum charge is most of the bill for those three.
Then set the gate figure against the on-site alternative in full: the deeper hole, roughly 300 square metres of membrane, imported cap fill and its compaction, plant standing while the envelope is laid, and a permanent land take disclosed at every future sale. Neither total is a rate this site will print — gate and haulage rates are local, dated and published by somebody else — and both are arithmetic on figures the reader has been quoted. The third column never gets priced at all: what the site costs to hold for the seasons a herbicide programme runs.
Enter the whole pile — 373 short tons, which is the same 338 tonnes — and then settle which ton the gate quoted in before you believe the total, because the fee field here is read as a rate per SHORT ton and the two tons differ by about a tenth. That one figure is the dig-and-dump row of the route table, and every other route on it has to be argued against that number rather than against a feeling.
The total weight of the debris load.
The disposal facility's rate charged per ton.
Debris weight
24,000 lb
Figures that depend on a rate wait for yours — this page does not assume one.
They open the calculator with your figures already in it
Landfill Tipping Fee Cost Calculator: 24,000 lb — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
What this calculation does not cover
- Weight times rate is the marginal cost, not the invoice. Most facilities set a minimum gate charge and many price pickups and small trailers at a flat per-load rate whatever is on them, so a half-full load does not cost half what a full one costs — it costs the minimum. On small loads the rate by weight stops describing what you will be billed.
- Nothing here covers what the gate adds or refuses. State and county disposal taxes, host-community fees and fuel surcharges are levied on top of the posted rate, and prohibited items — tires, mattresses, appliances holding refrigerant, treated timber, gypsum, anything suspected of containing asbestos — carry their own per-unit charges or turn the whole load away at the scale with the round trip already spent.
- The tip fee is often the smaller half of disposal. Getting the material there is truck, fuel and driver hours each way, and a job that fills more loads than planned multiplies that leg without moving the per-ton rate at all — which is why the debris's bulk density, not just its weight, is what really drives disposal cost.
What has to survive the handover
The excavation is not the deliverable. What a lender's valuer, a purchaser's solicitor and a warranty provider ask for is a written management plan from a contractor with the right accreditation, backed by an insurance-backed guarantee that outlives the job, and read against the RICS professional standard on Japanese knotweed and residential property. The Property Care Association's invasive weed control group publishes the code of practice most of those plans are written to. A dig with no plan behind it and no paperwork after it is, to a valuer, indistinguishable from a stand nobody touched.
A burial cell is a permanent feature of the land and has to be recorded as one. The as-built setting out, the depths, the membrane specification and a plain statement of what is inside it belong in the health and safety file that the Construction (Design and Management) Regulations 2015 require, because the person it is written for is the groundworker who comes back in fifteen years to put a garage in the corner. It belongs in the sale pack for the same reason. A cell nobody wrote down is not contained; it is merely hidden, and a bucket is how it gets out again.
Last, the monitoring. Every credible plan carries a monitoring period running across growing seasons after the works, with a defined response if anything reappears — and that is invariably the line deleted when the budget is squeezed, which is also the line the guarantee depends on. Excavation removes the material you found. The monitoring is what deals with the material the survey did not.
Settle these before the exclusion zone is fenced
Six things that fix the quantity, the containment and the destination on a knotweed corner. The workspace opens on the boundary barrier trench above — 38 metres at 600 wide, 2.5 deep, no pipe in it — with the cell and disposal calculators stacked underneath.
- A dig line taken from inspection pits — Drawn from where the rhizome stops on consecutive clean lines, plus an agreed margin — not from where the canes stop and not from where the footing happens to run.
- Depth set by the plant, not by the foundation — Where the survey finds rhizome below formation level the excavation goes deeper than the drawing, and the extra volume is real material with a real destination.
- Bank, loose and placed kept as three separate columns — Loose is what a cell void, a treatment bund or a vehicle body has to receive; placed is what the void actually ends up holding once it is compacted in lifts.
- Developed membrane area, never plan area — Base, four battered faces, lid, upstands and made-seam laps. A battered cell needs several times the sheet its footprint suggests.
- Somewhere the cell can legally and physically sit — Clear of foundations, drainage and future services, inside your own boundary, above the water table, and recorded before it is covered over.
- A named gate that will accept it, in writing — Not every permitted landfill takes knotweed-bearing soil, and availability sets the haul distance far more often than the rate does.
Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.
