Quote check
Check a garage conversion quote
- 25Lines the job needs
- 9Measurements
- QuestionsNever a verdict

How the quote is read
Each line of a garage conversion quote is matched to the line of the job it names, or marked as something the Garage conversion takeoff does not measure — labour, removal, hire, fees, or anything else. Work the takeoff lists as part of the job but gives no quantity for is read as that work, not as something the quote adds.
The job’s own figures come from 9 measurements — garage length, inside, garage width, inside, finished floor to ceiling, garage door opening, width, garage door opening, height, window in the new wall, width, wall under the window, old walls to line and insulate, doors into the room — run through the same calculators as the takeoff, so the two give the same figure for the same job.
Reading a garage conversion quote
A garage conversion quote prices a structure it cannot see yet: the footing under the new wall depends on what is found when the trench is dug, and the floor depends on how far the old slab sits below the house. Worth asking how each quote treats the footing — a fixed sum, a provisional sum, or a figure per metre dug — whether the courses from the footing up to the old slab sit in that figure or in the wall's, and whether it assumes a screed or a timber floor to bring the level up, since the two are not priced alike.
The lining of the old walls is the line a quote can leave vague. Worth seeing named whether the walls are lined on studs with insulation between, or with insulated board fixed to the masonry, how the ceiling is insulated, and where the vapour control layer goes. Whether the building control fees, the new window, the radiator and its connection to the heating, and the door through from the house are inside the price, or left to you, is worth settling before the door comes out.
Three steps
- Give your measurements. The page opens on a typical job so it has something to show.
- Paste the quote's lines as they came, or add them one at a time. Leave the prices in — they are taken out, never read.
- Read the report: what is left out, what is added, what sits outside the range, and one list of questions to send.
Your quote
The garage conversion quote you were given
Paste from an email, or open or drop a PDF, Excel, CSV or text file, or a photo of the quote. Amounts of money are taken out before anything is read — this page compares quantities, never prices.
Nothing you paste or open leaves this device.
The reading
What the quote says, against the job
Garage conversion · Garage length, inside 18 ft · Garage width, inside 10 ft · Finished floor to ceiling 8 ft · Garage door opening, width 8 ft · Garage door opening, height 7 ft · Window in the new wall, width 4 ft · Wall under the window 3.5 ft · Old walls to line and insulate 28 ft · Doors into the room 1Garage length, inside 5.5 m · Garage width, inside 3 m · Finished floor to ceiling 2.4 m · Garage door opening, width 2.4 m · Garage door opening, height 2.1 m · Window in the new wall, width 1.2 m · Wall under the window 1.05 m · Old walls to line and insulate 8.5 m · Doors into the room 1
What it leaves out
Every line the job needs that nothing on the quote reads as, with the quantity your measurements produce.
What it adds
Lines this job's takeoff does not measure — labour, removal, hire, fees, anything else — each named for what it is.
What sits outside the range
Quantities above or below the computed range, by how much, in the quote's unit or converted and shown.
What to ask
One list of questions, in the quote's order, ready to copy and send. Questions, never a verdict.
Paste the quote above, or add its lines one at a time. The reading appears here as each line is read.
Outside what this takeoff measures
8Nothing in the reading measures these. Whether the quote covers each is worth asking in its own right: a scope missing from a quote tends to become a cost after work has started. Why each is left out is on the takeoff.
- The footing under the new wall and any lintel over its window
- The brickwork and blockwork from the top of the new footing up to the old slab and the damp-proof course
- Whether the conversion needs planning permission or a permit where you are, including any condition on the house that keeps the garage for parking
- The screed, or the sleepers (battens) and the board deck, that raise the floor
- A slab lower than the ground outside, where the membrane, the damp courses and the new floor have to be detailed against water coming in; the page takes the slab as dry
- Moving a gas or electricity meter, or the consumer unit (panel), that sits in the garage
- The heating design
- Fire separation from the house and the way out of the new room, which building control sets for the room's use
The reference
Every line the reading looks for
For Garage length, inside 18 ft · Garage width, inside 10 ft · Finished floor to ceiling 8 ft · Garage door opening, width 8 ft · Garage door opening, height 7 ft · Window in the new wall, width 4 ft · Wall under the window 3.5 ft · Old walls to line and insulate 28 ft · Doors into the room 1Garage length, inside 5.5 m · Garage width, inside 3 m · Finished floor to ceiling 2.4 m · Garage door opening, width 2.4 m · Garage door opening, height 2.1 m · Window in the new wall, width 1.2 m · Wall under the window 1.05 m · Old walls to line and insulate 8.5 m · Doors into the room 1. Each is the calculator linked under it, run with those measurements; a range is that calculator at both ends of one choice, not a margin for error.
Inner leaf blocks, under the window
34–37 blocks
34 at 5% waste factor, 37 at 15%.
Open the Concrete CMU Block Counter & Grout Infill CalculatorInner leaf blocks, beside the window
17–19 blocks
17 at 5% waste factor, 19 at 15%.
Open the Concrete CMU Block Counter & Grout Infill CalculatorFacing bricks, under the window
202–221 bricks
202 at 5% waste factor, 221 at 15%.
Open the Brick CalculatorFacing bricks, beside the window
101–111 bricks
101 at 5% waste factor, 111 at 15%.
Open the Brick CalculatorWall ties across the cavity
at least 16 ties
The fewest ties the area one tie may carry allows across this wall; the extra ties up the sides of an opening come on top, and a closer spacing is a choice.
Open the Brick Veneer Wall Tie Density CalculatorWeep holes along the base
at least 5 weep holes
The fewest weep holes the spacing allows along the base of this wall.
Open the Cavity Wall Weep Hole Spacing CalculatorCavity insulation in the new wall
2 sheets (4x8 ft)
The same at 5% cutting waste and at 15%, once rounded to what is bought.
Open the Foam Board Insulation CalculatorFlashing tape round the window
22.1–24.2 ft
22.1 at 5% waste allowance, 24.2 at 15%.
Open the Window Opening Flashing Membrane CalculatorFloor insulation board
6–7 sheets (4x8 ft)
6 at 5% cutting waste, 7 at 15%.
Open the Foam Board Insulation CalculatorStuds lining the old walls
22–26 studs
Studs are counted at the spacing with nothing spare, and a bowed or split one is set aside rather than used. 22 net, 26 with 15% added.
Open the Framing Stud CalculatorInsulation between the lining studs
3 packages
The same at 5% waste factor and at 15%, once rounded to what is bought.
Open the Insulation Batt CalculatorInsulation between the ceiling joists
2–3 packages
2 at 5% waste factor, 3 at 15%.
Open the Insulation Batt CalculatorSockets (outlets) round the room
at least 5 outlets (minimum)
A starting count for the whole perimeter as one wall space; each doorway or fireplace starts a new space, so the code minimum can be higher.
Open the Outlet Spacing CalculatorPlasterboard (drywall) on the walls
14–15 sheets (4x8 ft)
14 at 5% waste factor, 15 at 15%.
Open the Drywall CalculatorPlasterboard (drywall) on the ceiling
6–7 sheets
6 at 5% waste allowance, 7 at 15%.
Open the Ceiling Plasterboard (Gypsum Board) Sheet CalculatorJoint compound
2 x 4.5 gal boxes
The same at 5% pan and sanding loss and at 15%, once rounded to what is bought.
Open the Drywall Joint Compound CalculatorMist coat or primer on the walls
1.03–1.18 gal
Paint is bought by the tin, and some always stays in the tray and on the roller. 1.03 net, 1.18 with 15% added.
Open the Paint CalculatorMist coat or primer on the ceiling
0.45–0.52 gal
Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 0.45 net, 0.52 with 15% added.
Open the Ceiling Paint CalculatorWall paint
2.06–2.37 gal
Paint is bought by the tin, and some always stays in the tray and on the roller. 2.06 net, 2.37 with 15% added.
Open the Paint CalculatorCeiling paint
0.9–1.04 gal
Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 0.9 net, 1.04 with 15% added.
Open the Ceiling Paint CalculatorUnderlay
2–3 rolls
Rolls are laid edge to edge, and the last one in each run is cut short. 2 net, 3 with 15% added.
Open the Laminate/Vinyl Plank Floor Underlayment Roll CalculatorLaminate or vinyl plank
9 packs
Room and lay: 9 for Simple rectangular room, 9 for Simple rectangular room.
Open the LVP, Laminate & Engineered Floor CalculatorThreshold strips
3.15–3.45 ft
3.15 at 5% waste allowance, 3.45 at 15%.
Open the Floor Transition Strip CalculatorSkirting (baseboard)
55.7–61 linear ft
55.7 at 5% cutting waste, 61 at 15%.
Open the Baseboard & Trim CalculatorSkip (dumpster) for the strip-out and the footing
at least 3.28 yd³
The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.
Open the Skip & Dumpster Size Calculator
Inner leaf blocks, under the window
27–29 blocks
27 at 5% waste factor, 29 at 15%.
Open the Concrete CMU Block Counter & Grout Infill CalculatorInner leaf blocks, beside the window
14–15 blocks
14 at 5% waste factor, 15 at 15%.
Open the Concrete CMU Block Counter & Grout Infill CalculatorFacing bricks, under the window
157–172 bricks
157 at 5% waste factor, 172 at 15%.
Open the Brick CalculatorFacing bricks, beside the window
79–86 bricks
79 at 5% waste factor, 86 at 15%.
Open the Brick CalculatorWall ties across the cavity
at least 16 ties
The fewest ties the area one tie may carry allows across this wall; the extra ties up the sides of an opening come on top, and a closer spacing is a choice.
Open the Brick Veneer Wall Tie Density CalculatorWeep holes along the base
at least 5 weep holes
The fewest weep holes the spacing allows along the base of this wall.
Open the Cavity Wall Weep Hole Spacing CalculatorCavity insulation in the new wall
2 sheets (2400x1200 mm)
The same at 5% cutting waste and at 15%, once rounded to what is bought.
Open the Foam Board Insulation CalculatorFlashing tape round the window
6.62–7.24 m
6.62 at 5% waste allowance, 7.24 at 15%.
Open the Window Opening Flashing Membrane CalculatorFloor insulation board
7 sheets (2400x1200 mm)
The same at 5% cutting waste and at 15%, once rounded to what is bought.
Open the Foam Board Insulation CalculatorStuds lining the old walls
22–26 studs
Studs are counted at the spacing with nothing spare, and a bowed or split one is set aside rather than used. 22 net, 26 with 15% added.
Open the Framing Stud CalculatorInsulation between the lining studs
3 packages
The same at 5% waste factor and at 15%, once rounded to what is bought.
Open the Insulation Batt CalculatorInsulation between the ceiling joists
2–3 packages
2 at 5% waste factor, 3 at 15%.
Open the Insulation Batt CalculatorSockets (outlets) round the room
at least 5 outlets (minimum)
A starting count for the whole perimeter as one wall space; each doorway or fireplace starts a new space, so the code minimum can be higher.
Open the Outlet Spacing CalculatorPlasterboard (drywall) on the walls
14–15 sheets (2400x1200 mm)
14 at 5% waste factor, 15 at 15%.
Open the Drywall CalculatorPlasterboard (drywall) on the ceiling
7 sheets
The same at 5% waste allowance and at 15%, once rounded to what is bought.
Open the Ceiling Plasterboard (Gypsum Board) Sheet CalculatorJoint compound
34.1–37.4 kg
34.1 at 5% pan and sanding loss, 37.4 at 15%.
Open the Drywall Joint Compound CalculatorMist coat or primer on the walls
3.74–4.31 L
Paint is bought by the tin, and some always stays in the tray and on the roller. 3.74 net, 4.31 with 15% added.
Open the Paint CalculatorMist coat or primer on the ceiling
1.65–1.9 L
Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 1.65 net, 1.9 with 15% added.
Open the Ceiling Paint CalculatorWall paint
7.49–8.61 L
Paint is bought by the tin, and some always stays in the tray and on the roller. 7.49 net, 8.61 with 15% added.
Open the Paint CalculatorCeiling paint
3.3–3.8 L
Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 3.3 net, 3.8 with 15% added.
Open the Ceiling Paint CalculatorUnderlay
2–3 rolls
Rolls are laid edge to edge, and the last one in each run is cut short. 2 net, 3 with 15% added.
Open the Laminate/Vinyl Plank Floor Underlayment Roll CalculatorLaminate or vinyl plank
9 packs
Room and lay: 9 for Simple rectangular room, 9 for Simple rectangular room.
Open the LVP, Laminate & Engineered Floor CalculatorThreshold strips
0.95–1.03 m
0.95 at 5% waste allowance, 1.03 at 15%.
Open the Floor Transition Strip CalculatorSkirting (baseboard)
16.9–18.5 m
16.9 at 5% cutting waste, 18.5 at 15%.
Open the Baseboard & Trim CalculatorSkip (dumpster) for the strip-out and the footing
at least 2.48 m³
The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.
Open the Skip & Dumpster Size Calculator
How the ranges are taken
Where the choice is cutting waste, the ends are the site’s own allowances: 5%, the tight buffer of a crew with a planned set-out, and 15%, the wider one a first-timer orders. Where the calculator decides between patterns or materials, the ends are the options it offers. Where it adds nothing for loss, the range runs from the net quantity to 15% over it.
A minimum — the fewest hangers a spacing allows, the least airflow a room needs — has no upper end. A single figure carries an allowance the material itself needs, such as a lap, and names it.
What a reading like this cannot see
- It does not know your prices, your market, or what the work ought to cost.
- It does not know the building — the access, the condition of what is there, or what has to happen first.
- It cannot check a lump sum, because there is no quantity in one.
- A line it reads as missing may be priced under another name. A quantity outside the range is not evidence of anything. Each is a reason to ask a question.
- Two quotes are not comparable until their scopes are.
- It is not advice, and it is no substitute for a second quote.
The full takeoff
Every quantity for this job, with its working
The Garage conversion takeoff runs the same calculators on the same measurements and shows what sits under each line here.
Base, allowance, order
Each line's quantity before and after its allowance, and what to buy.
Every allowance editable
Change a waste figure and the order follows, with its source named.
Into a project
Add the whole job to a workspace with your own prices.
Frequently asked questions
- What quantities does a garage conversion job need?
- It depends on the measurements, so this page asks for yours. At the size it opens on — Garage length, inside 5.5 m · Garage width, inside 3 m · Finished floor to ceiling 2.4 m · Garage door opening, width 2.4 m · Garage door opening, height 2.1 m · Window in the new wall, width 1.2 m · Wall under the window 1.05 m · Old walls to line and insulate 8.5 m · Doors into the room 1 — the lines come to: Inner leaf blocks, under the window, 27–29 blocks; Inner leaf blocks, beside the window, 14–15 blocks; Facing bricks, under the window, 157–172 bricks; Facing bricks, beside the window, 79–86 bricks; Wall ties across the cavity, 16 ties; Weep holes along the base, 5 weep holes; Cavity insulation in the new wall, 2 sheets (2400x1200 mm); Flashing tape round the window, 6.62–7.24 m; Floor insulation board, 7 sheets (2400x1200 mm); Studs lining the old walls, 22–26 studs; Insulation between the lining studs, 3 packages; Insulation between the ceiling joists, 2–3 packages; Sockets (outlets) round the room, 5 outlets (minimum); Plasterboard (drywall) on the walls, 14–15 sheets (2400x1200 mm); Plasterboard (drywall) on the ceiling, 7 sheets; Joint compound, 34.1–37.4 kg; Mist coat or primer on the walls, 3.74–4.31 L; Mist coat or primer on the ceiling, 1.65–1.9 L; Wall paint, 7.49–8.61 L; Ceiling paint, 3.3–3.8 L; Underlay, 2–3 rolls; Laminate or vinyl plank, 9 packs; Threshold strips, 0.95–1.03 m; Skirting (baseboard), 16.9–18.5 m; Skip (dumpster) for the strip-out and the footing, 2.48 m³. In imperial units — Garage length, inside 18 ft · Garage width, inside 10 ft · Finished floor to ceiling 8 ft · Garage door opening, width 8 ft · Garage door opening, height 7 ft · Window in the new wall, width 4 ft · Wall under the window 3.5 ft · Old walls to line and insulate 28 ft · Doors into the room 1 — they come to: Inner leaf blocks, under the window, 34–37 blocks; Inner leaf blocks, beside the window, 17–19 blocks; Facing bricks, under the window, 202–221 bricks; Facing bricks, beside the window, 101–111 bricks; Wall ties across the cavity, 16 ties; Weep holes along the base, 5 weep holes; Cavity insulation in the new wall, 2 sheets (4x8 ft); Flashing tape round the window, 22.1–24.2 ft; Floor insulation board, 6–7 sheets (4x8 ft); Studs lining the old walls, 22–26 studs; Insulation between the lining studs, 3 packages; Insulation between the ceiling joists, 2–3 packages; Sockets (outlets) round the room, 5 outlets (minimum); Plasterboard (drywall) on the walls, 14–15 sheets (4x8 ft); Plasterboard (drywall) on the ceiling, 6–7 sheets; Joint compound, 2 x 4.5 gal boxes; Mist coat or primer on the walls, 1.03–1.18 gal; Mist coat or primer on the ceiling, 0.45–0.52 gal; Wall paint, 2.06–2.37 gal; Ceiling paint, 0.9–1.04 gal; Underlay, 2–3 rolls; Laminate or vinyl plank, 9 packs; Threshold strips, 3.15–3.45 ft; Skirting (baseboard), 55.7–61 linear ft; Skip (dumpster) for the strip-out and the footing, 3.28 yd³.
- Which line on a garage conversion quote varies the most?
- The Insulation between the ceiling joists: 2–3 packages for a job measured Garage length, inside 5.5 m · Garage width, inside 3 m · Finished floor to ceiling 2.4 m · Garage door opening, width 2.4 m · Garage door opening, height 2.1 m · Window in the new wall, width 1.2 m · Wall under the window 1.05 m · Old walls to line and insulate 8.5 m · Doors into the room 1, depending on the waste factor allowed, from 5% to 15%.
- What does a garage conversion quote often leave out?
- The reading names every line of the job that nothing on the quote reads as — any of the 25 lines the takeoff measures. The takeoff also lists 8 things it does not measure, shown under the reading, and each is worth asking about: a scope missing from a quote tends to become a cost after work has started.
- Can I paste the quote exactly as it came?
- Yes — from an email, a PDF or a spreadsheet, one item to a line. Amounts of money are taken out before anything is read, headings and totals are skipped, and each line is shown with what it was read as, so a misreading is one correction. Quantities in the other unit system are converted and the conversion is shown; a count of boxes is never compared with a count of tiles.
- Does this check the price as well?
- No. It reads quantities, never prices, and this site publishes none: an installed price moves with the market, the season, the access and the specification, so a figure for what the work ought to cost would give you confidence in a number nobody can defend. A quantity against your own measurements is checkable, and every figure here links to the calculator that produced it.