Electrical

Running Power to a Detached Garage

A garage feeder is decided by distance, not by load: terminal temperature, a shared volt budget, and whether a fault can still get home.
  • 18 minReading time
  • 8Sections
  • 6Calculators inline
  • Last reviewed

The String Line Across the Lawn Is the Specification

Somebody has already stretched a line from the meter box to the garage door and paced it off at forty metres. That number, not the tool list inside the garage, is what this job turns on. A detached garage rarely asks for much current — a couple of general-power circuits, some lighting, whatever gets wheeled in — and if the building were bolted to the house you would put a small feeder in and think no more about it. Move it forty metres away, bury the connection, and three separate constraints start pulling in different directions on a conductor size that would otherwise have been obvious.

The first is ampacity at the temperature the terminals are rated for, not the temperature the insulation is rated for. The second is voltage drop, which is proportional to length and is therefore the only one of the three that got worse the moment the garage was sited at the bottom of the garden. The third is the one that almost never gets calculated: whether a fault at the far end can push enough current back through the protective conductor to operate the device at the house. Each of those can force a bigger conductor, none of them can make it smaller, and all three have to be settled before anything goes in the ground.

It also matters that this is a feeder to a separate structure and not a very long branch circuit. Under NFPA 70 National Electrical Code that puts it into Article 225, Outside Branch Circuits and Feeders, which limits a structure to one supply except in defined cases and requires a disconnecting means at the structure, readily accessible and near the point of entry. Under BS 7671 Requirements for Electrical Installations it is a distribution circuit feeding a separate consumer unit, with its own disconnection time and its own earthing question. Whichever document is adopted where you are working, the garage ends up with its own board and its own means of isolation, and the run between the two buildings is a thing that must be recorded, because in ten years nobody will remember where it went.

What a Workshop Draws, and When It Draws It

Add up the nameplates in a working garage and you get a number nobody would pay to bury. A welder, a compressor, a table saw, a dust extractor, a car lift, a heater and a kettle will total well past a hundred amps on paper, and they cannot all be running because there is one person in the building and two hands on the job. Feeder sizing has always dealt with this through demand and diversity — Article 220 in the NEC, the diversity allowances in the IET On-Site Guide to BS 7671, the maximum demand tables of AS/NZS 3000 Electrical Installations — and the outbuilding case is where those allowances earn their keep hardest.

The exceptions are the loads that sit at full value for hours, because diversity is an argument about coincidence and those loads do not care. Electric vehicle supply equipment is the obvious one: it is a continuous load, it is sized at 125 percent of its rating in NEC practice, and it is the single change most likely to arrive after the trench is closed. Resistive space heating in a workshop is the same shape of problem — nobody switches a garage heater on for ten minutes in February. Where those two exist or are plausible, they get added at full value on top of a diversified figure for everything else, and that is usually what decides between a sixty amp feed and a hundred.

Motors are the other special case, and they are special in a way that is easy to get backwards. Conductor sizing for a motor branch circuit works from the tabulated full-load current for its horsepower and voltage rather than from the amps printed on the plate, and the tables exist precisely because plate values vary between manufacturers for the same nominal machine. A compressor or a two-post lift at the end of a long soft feeder is also the load that will expose every millivolt of drop, because its starting current is several times its running current and the drop scales with the current of the moment.

Then there is the question the client will not ask and you should. A trench is dug once. The marginal cost of the next conductor size up, while the ground is open and the duct is being bought anyway, is copper and nothing else; the cost of finding out in three years that the feeder cannot take a charger is the whole garden again. Size the feeder for the building the garage is going to become, write down what you assumed, and let the client decline it in writing if they want the smaller number.

Charging equipment is the load that decides this feeder, because it is the one that runs for hours at its rated current — put the charger's continuous rating in and the breaker it returns is the number that has to sit on top of everything else you diversified.

Minimum breaker size

40 A breaker

Minimum required (125% rule)
40 A

The breaker size also requires correctly-sized wiring for that circuit (see the Wire Gauge Voltage Drop Calculator) — always have the final circuit installed or verified by a licensed electrician and permitted per local code.

The Lug Decides Which Column You May Read

Conductor insulation is rated for a temperature and so is every terminal it lands in, and NEC 110.14(C) settles the argument in favour of the lowest-rated part of the connection. In practice that means equipment rated 100 amperes or less, or marked for conductors 14 AWG through 1 AWG, is treated as a 60 degree Celsius termination unless the device or its instructions are marked otherwise. Most modern breakers and panelboard lugs are marked for 75 degrees; plenty of older ones are not, and an unmarked lug is a 60 degree lug. The 90 degree column exists chiefly so you have something to apply correction and adjustment factors to on the way down — it is almost never the number you finish on.

That distinction is worth a size on a garage feeder. Six AWG copper is 55 amperes in the 60 degree column and 65 in the 75 degree column, so the same cable is either short of a sixty amp device or comfortably over it depending on a marking you can only read by taking the dead front off and looking. Check both ends. The breaker at the house and the main lug or main breaker in the garage board are separate answers, and the lower one governs the whole run. UL 486A-486B Standard for Wire Connectors is the document behind the connector side of that relationship, and the torque value in the equipment instructions is part of the listing rather than a suggestion — a lug tightened by feel is the failure that shows up as a browned insulation tail a decade later.

The wiring method carries its own constraint. Everything inside a buried raceway is a wet location from the first winter, whatever the weather was on the day you pulled it, so the conductors have to be listed for wet locations: the dual-rated THHN/THWN-2 that most suppliers stock, or XHHW-2, or a direct-burial cable such as USE-2 where the design is to bury the cable rather than a duct. Plain THHN is a dry-location rating and has no business in a duct that runs under a lawn. In the United Kingdom the equivalent decision is usually made in favour of steel wire armoured cable buried directly, and its ratings come from Appendix 4 of BS 7671 with an installation-method correction that a duct in the ground and a cable in free air do not share.

Allowable ampacities of copper conductors from NEC Table 310.16, at 30 degrees Celsius ambient with not more than three current-carrying conductors — the column you are entitled to use is set by the lowest-rated termination in the circuit, not by the insulation
Copper conductor60 °C column75 °C column90 °C column
8 AWG40 A50 A55 A
6 AWG55 A65 A75 A
4 AWG70 A85 A95 A
3 AWG85 A100 A115 A
2 AWG95 A115 A130 A
1 AWG110 A130 A145 A
1/0 AWG125 A150 A170 A
Allowable ampacities of copper conductors from NEC Table 310.16, at 30 degrees Celsius ambient with not more than three current-carrying conductors — the column you are entitled to use is set by the lowest-rated termination in the circuit, not by the insulation

Run the size you had in mind and read all three columns at once, then discard the two you are not allowed to use — the marking on the lug is what tells you which one that is.

Use the Wire Gauge to Amperage calculator

One Volt Budget, Spent Twice

Voltage drop on this job is not a single calculation, it is a budget with two claimants. The feeder spends some of it getting to the garage, and every branch circuit inside the garage spends the rest getting from the garage board to a socket at the far wall. The familiar three percent for a branch circuit and five percent overall is informative guidance in the NEC rather than an enforceable rule; BS 7671 sets limits in its appendices that must actually be met — three percent for lighting and five percent for other uses on a supply taken from a public distribution network. Either way the arithmetic is the same, and either way a feeder that eats four and a half percent has left nothing for the circuits it exists to supply.

So set the feeder a target rather than a limit. Somewhere around two percent leaves the inside of the garage a workable allowance, and it also leaves room for the load to grow without the drop growing past what the equipment tolerates. It is a design decision, not a code number, and it is the single most useful thing to fix before pricing conductor.

Measure the path, not the lawn. The line somebody paced off is the shortest distance between two buildings and the conductor will not travel it. Add the climb from the house board down to the point where the duct leaves the wall, the offsets around a soil stack and a bay window, the sweeps at each end of the trench, the slack you leave in the duct so the cable is not stretched, and the rise inside the garage to a board that is mounted at chest height. Forty metres of string line lands somewhere near fifty-five metres of conductor on most gardens, and drop is linear in exactly that number.

Drop is also linear in current, which means the worst case is not the average day. It is the moment the welder strikes while the charger is running and the compressor kicks in, and the voltage at the garage board falls furthest exactly when three things want it most. Motors respond to low voltage by drawing more current and running hotter, which makes the drop worse, which is a loop that ends in a tripped overload or a shortened motor.

When the calculation says upsize, the upsize has consequences beyond the price of copper. The protective conductor is increased in proportion under NEC 250.122(B) where the ungrounded conductors are enlarged for voltage drop, which changes the cable you are buying rather than just one core of it. Larger conductors need a larger duct, a longer bending radius inside both enclosures, and lugs that will physically accept them — check that the garage board's main lug takes the size you have arrived at before it is on a reel in the van. Upsizing for drop is the most common reason a feeder outgrows the enclosure that was picked for it.

Enter the one-way route length you measured rather than the distance somebody paced — the field wants the run in one direction and the arithmetic doubles it for you — together with the design current rather than the average, and the percentage in the breakdown is the share of the budget the feeder has taken before the garage has spent anything. Its gauge list and its current field both run past an ordinary garage feed, so a larger subpanel feeder goes through the same page.

Voltage drop

1.94 V

Voltage drop
1.61 %
Voltage at the load
118.06 V

A Fault at the Far End Has to Get Home

Here is the constraint that separates a competent outbuilding feed from a dangerous one. When a live conductor touches the metal frame of a machine in the garage, the current that operates the protective device has to return to the source through a conductor, and the earth beneath the garden is not that conductor. NEC 250.4(A)(5) says so explicitly: the earth shall not be considered an effective ground-fault current path. The arithmetic is Ohm's law and it is brutal. A driven rod that achieves 25 ohms — a respectable figure in ordinary soil — offers 240 volts divided by 25 ohms, which is under ten amperes. A sixty ampere breaker will sit and watch that indefinitely while the machine frame stays live.

Which is why a feeder to a detached structure runs with an equipment grounding conductor pulled alongside the live conductors and the neutral, and why the neutral is not re-bonded to earth at the garage. NEC editions from 2008 onward removed the old permission to use the grounded conductor as the fault path at a separate building, so the modern arrangement is four wires to a three-wire supply: two ungrounded, one grounded, one equipment grounding conductor, with the bonding screw or strap taken out of the garage board and the neutral bar isolated from the enclosure. The garage still gets a grounding electrode of its own under NEC 250.32 — a rod, or the reinforcement of its slab where that qualifies as a concrete-encased electrode — but that electrode is a reference and a surge path, not a fault path, and it never substitutes for the conductor.

The British framing gets to the same place by a different route and with a number attached. Automatic disconnection of supply requires the earth fault loop impedance at the point of the fault to be low enough that the device operates within the disconnection time — commonly 0.4 seconds for a final circuit and 5 seconds for a distribution circuit on a TN system. A Type B miniature circuit breaker needs somewhere between three and five times its rated current to trip magnetically, and a Type C between five and ten times, so a 40 ampere Type B wants roughly 200 amperes of fault current before it will operate quickly. Fifty-five metres of feeder with an undersized protective conductor adds resistance to both legs of that loop, and the adiabatic check in Section 543 of BS 7671 then has to confirm that the protective conductor survives the current for as long as it takes to clear.

The earthing arrangement itself is a separate decision in the United Kingdom and one worth taking advice on rather than assuming. Exporting a PME earth to an outbuilding is constrained by the distributor's conditions and by the Electricity Safety, Quality and Continuity Regulations 2002, and the common alternative is to earth the garage as a TT island with its own electrode and residual current protection, which changes the disconnection argument from impedance to residual current. Buried cable in a garden attracts a 30 milliampere residual current device in any case, and the NEC reaches the same protective outcome for people through the ground-fault circuit-interrupter requirements that cover garage and outdoor receptacles.

This is the calculation that makes the point: enter the supply voltage and the resistance of the path you were hoping would clear the fault, and read the current it will actually pass.

Ohm's Law Calculator

Current

3 A (current)

Power
36 W
Voltage
12 V

The Trench, and What Is Already In It

Before anything else, find out what is already under the lawn. A garden between a house and a garage is a good place to find a gas service, a water main, a soil drain, a telecom duct and an irrigation line, none of which are on a drawing and at least one of which is shallower than anybody expects. HSE guidance HSG47, Avoiding Danger from Underground Services, sets out the sequence — plans, then a locator, then careful hand digging near anything found — and it is the right sequence whether or not you are working under UK law. Where a locate service exists, use it, and note that a private garden run between two buildings is exactly the case such services do not have records for.

Depth is set by the wiring method and by what is on top, not by preference. NEC Table 300.5 gives different minimum cover for different methods and locations: direct-buried cable deepest at 600 mm, rigid nonmetallic conduit at 450 mm, rigid metal conduit shallowest at 150 mm, with a reduced row for a residential 120 volt branch circuit at 20 amperes with residual protection, and different figures again under a driveway or a building. Read the row for your method in the edition your jurisdiction has actually adopted. BS 7671 prescribes no single depth in Section 522, requiring instead that a buried cable be of a type suitable for the duty, at sufficient depth to avoid damage, and marked — with NJUG Volume 4 giving the positioning and colour coding practice the utilities themselves work to. Frost depth, tree roots and the route of a future patio all argue for going deeper than the minimum rather than exactly to it.

Trench safety scales with depth faster than people expect, and the point at which a garden trench becomes an excavation with rules attached is lower than the point at which it looks dangerous. OSHA 29 CFR 1926 Subpart P, Excavations, governs that in the United States: spoil set back from the edge, a means of getting out, and a protective system where the depth demands one. A collapse in a metre and a half of wet clay is enough to kill someone kneeling in it, and a domestic job is exactly where the discipline slips.

  1. Establish and mark the existing services across the whole route before the first spit is turned, then hand dig within the safe distance of anything located.
  2. Set the route to avoid tree root plates, soakaways and the footprint of any structure the client has mentioned wanting, and record where you moved it to.
  3. Excavate to a consistent formation level, keeping spoil back from the edge and off the reinstatement material.
  4. Bed the duct on screened fill, lay it with long sweeps rather than elbows, and leave a draw rope in it whether or not you intend to pull that day.
  5. Bring the surround up over the duct by hand, lay the warning tape well above it rather than on it, and photograph the open trench with a tape measure in shot.
  6. Backfill in lifts and compact each one, then reinstate the surface proud of finished level to allow for the settlement that is coming anyway.

What is actually in the trench

A buried feeder trench in section, from the reinstated turf down: compacted backfill, warning tape at half depth, a sand surround holding the duct, the duct and the conductors inside it, the bedding the duct is laid on, and the undisturbed trench floor beneath.
  1. Reinstated turf and topsoil — the only part of the job the client will ever inspect, and the part that reads as a settled scar across the lawn all winter if the fill below it went in loose Topsoil Calculator
  2. Compacted backfill — returned in lifts and compacted as it goes, because excavated soil bulks on the way out and a trench filled in one push becomes a trench-shaped hollow by spring Trench Excavation & Backfill Volume Calculator
  3. Warning tape — the only warning the next person with a spade is going to get, and worth nothing at all if it is laid on the duct instead of well above it
  4. Sand surround — screened material with no sharp stone in it, brought up around and over the duct so that nothing point-loads it while the backfill above is being compacted
  5. Duct and feeder conductors — sized for the pull and the fill rather than for the copper alone, and a wet location on the inside from its first winter whatever the weather was on pull day Conduit Fill Calculator
  6. Bedding — a level bed of the same fine material so the duct is carried along its whole length rather than bridging between two stones with a span in between
  7. Undisturbed trench floor — cut to a consistent grade with no sumps left in it, and battered or supported wherever the depth and the ground condition call for it Trench Sloping & Excavation Width Calculator

Fill it, then add the allowance

Excavated ground does not go back in the hole it came out of — the volume you dug and the volume of imported surround are different numbers, and this is where the difference gets ordered.

Loose backfill material needed

50.9 yd³38.9 m³ (loose)

Excavation volume (the depth entered)
48.89 yd³37.38 m³
Pipe volume (subtracted)
4.6 yd³3.52 m³

Assumes the excavated soil itself isn't reused as backfill (e.g. importing clean granular fill) — if reusing native soil, account for its own swell factor separately.

Pulling It Through

A long duct pull fails at the bends, not along the straights. Tension builds through friction on every straight section and then multiplies through each change of direction, so two ninety degree elbows in an otherwise easy run can turn a comfortable pull into one that stretches the conductor or strips the jacket. Use long sweeps, keep the total angular content of the run down, and put a pit or a pull point in wherever the geometry demands it rather than trusting to lubricant and effort. Cable-pulling lubricant is not optional on a long feeder, and the manufacturer's guidance — the Southwire Power Cable Installation Guide is the usual reference for the tension and sidewall pressure arithmetic — states a maximum tension for the conductor and a maximum sidewall bearing pressure at a bend, both of which are exceedable by hand with a rope and two willing people.

Feed from the end with the awkward bends and pull from the end with the room. Let the conductors come off the reel in the direction the reel wants to turn, keep them off the ground and out of the spoil, and pull all of the conductors at once including the protective one — the equipment grounding conductor belongs in the same raceway as the conductors it protects, and pulling it separately later is both a nuisance and a mistake if it ends up in another route. Leave enough tail at each end to dress the conductors properly into the boards, because a feeder cut short at the garage end is a joint in a box you did not plan.

Cable weight, run length and the friction of the duct give you a straight-run tension figure to sanity-check before somebody puts a winch on it — the bends push the real number above this one.

Estimated pulling tension

67 lbf300 N

Tension in kgf
30.18 kgf

This covers a STRAIGHT run only — pulls with bends require adding capstan-equation tension multipliers for each bend, and the calculated tension must be checked against the cable manufacturer's maximum allowable pulling tension (often based on conductor cross-section) before pulling. Consult a qualified installer for multi-bend or long/complex pulls.

Closing Out the Garage End

The garage board is where every decision made in the trench becomes visible. It needs a means of isolation at the structure, a neutral bar floating clear of the enclosure with the bonding link removed, an earth bar bonded to the enclosure and carrying both the incoming protective conductor and the electrode conductor, and a directory that states what feeds it and where that feed is isolated. Site it where the working space required by NEC 110.26 actually exists — around 900 mm of depth, 750 mm of width and 2 m of headroom for the ordinary case — which in a real garage means not behind where the car parks, not above the bench, and not in the corner that will be racking within a year.

Seal the raceway where it enters the building. A duct that runs from a cold trench into a warm garage is a condenser, and an unsealed one delivers water into the bottom of the board over a few seasons; the NEC's raceway sealing requirement in Article 300 exists for exactly that mechanism. Where the duct rises out of the ground into sunlight, rigid PVC expands and contracts enough over a season to need an expansion fitting, and Article 352 covers that for nonmetallic conduit. Neither of these is expensive at first fix and both are miserable to retrofit.

Look for metallic paths running in parallel with your feeder. A steel water pipe, a gas line or a telecom cable running between the two buildings creates a second route between the earthing systems, which is capable of carrying neutral current and of putting a difference of potential across two things somebody can touch at once. That is a bonding question with a real answer, and the answer depends on the earthing arrangement, so it belongs on the design rather than in a discovery at second fix. NECA 1 Standard for Good Workmanship in Electrical Construction is a reasonable yardstick for the standard of the terminations and supports you leave behind.

Then write it down. Photograph the open trench with a tape in it against two fixed features of the property, record the route on a sketch that goes to the client, label both boards with the size and type of the feeder and the fact that its neutral is not bonded at the garage, and test and record the loop impedance or the fault path continuity at the far end rather than assuming it from the calculation. Everything else on this job is buried within a day. The record is the only part of it that is still accessible to the next person, and on a private garden run between two buildings there is no utility drawing that will ever fill in the gap.

Try the calculation

Fix these before the digger arrives

Everything on this list is cheap while the ground is open and expensive afterwards. Work down it in order; each line can only push the conductor size up, never down.

  • Diversified demand, plus continuous loads at full value — Charging equipment and resistive heating do not diversify — add them on top of the diversified figure rather than into it.
  • Termination temperature marking at both boards — The lower of the house breaker lug and the garage main lug decides which ampacity column the whole feeder may use.
  • Measured conductor path, not the paced distance — Include both risers, every offset, the sweeps at each end of the trench and the slack left in the duct.
  • Feeder share of the voltage drop budget, set as a target — Leave the branch circuits inside the garage a workable allowance instead of spending the whole five percent on the run.
  • Four conductors: two live, neutral, and a protective conductor — Pulled in the same duct, with the bonding link removed at the garage board and the neutral bar isolated.
  • Duct, surround, warning tape and reinstatement material — Order the surround as imported screened fill; excavated spoil bulks and rarely goes back as the bedding layer.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • NFPA 70 National Electrical Code — Table 310.16 allowable ampacities, 110.14(C) temperature limitations at terminations, and 240.4(D) small-conductor overcurrent limits
  • NFPA 70 National Electrical Code — Article 225 Outside Branch Circuits and Feeders, 250.4(A)(5) effective ground-fault current path, 250.32 Buildings or Structures Supplied by a Feeder, 250.122(B) increased grounding conductors, Table 300.5 Minimum Cover Requirements, and 110.26 working space
  • BS 7671 Requirements for Electrical Installations (IET Wiring Regulations) — Chapter 41 automatic disconnection of supply, Section 522 buried cables, Section 543 protective conductors, Appendix 4 current-carrying capacity and voltage drop
  • IET On-Site Guide to BS 7671
  • The Electricity Safety, Quality and Continuity Regulations 2002 (United Kingdom)
  • HSE HSG47 Avoiding Danger from Underground Services
  • NJUG Volume 4, Guidelines on the Positioning and Colour Coding of Underground Utilities' Apparatus
  • OSHA 29 CFR 1926 Subpart P, Excavations
  • CSA C22.1 Canadian Electrical Code, Part I
  • AS/NZS 3000 Electrical Installations (Wiring Rules)
  • UL 486A-486B Standard for Wire Connectors
  • Southwire Power Cable Installation Guide
  • NECA 1 Standard for Good Workmanship in Electrical Construction

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.