Stormwater

Meeting a Stormwater Runoff Condition on a Tight Site

A condition caps discharge and the plan has no room for a basin. What a vegetated roof is credited with, what stone holds, and which one empties in time.
  • 19 minReading time
  • 9Sections
  • 4Calculators inline
  • Last reviewed

Five Litres a Second, Off a Yard That Makes Thirty

The condition is four lines long and it has already been agreed. Surface water from the development shall discharge to the public surface water sewer at a rate not exceeding 5 litres per second, for all events up to and including the one-in-a-hundred-year storm with an allowance for climate change, and the drainage details shall be submitted to and approved in writing before any development above slab level. There is no negotiation left in it. The applicant took the condition rather than fight it because the permission was already eight months old, and the drainage design is now a discharge-of-conditions submission with a build programme behind it.

The site is a 1,900 m² (about 20,450 sq ft) infill plot, a former builders' merchant, coming back as a single-storey trade counter with a 900 m² (9,700 sq ft) footprint, 700 m² (7,500 sq ft) of yard and turning space, and a thin strip of planting along the boundary. Impermeable area when it is finished: roughly 1,600 m², something over 17,000 sq ft. Put that through a peak-flow sum against a storm the reviewing authority would recognise and the answer comes back near 30 litres per second — about 1.1 cubic feet per second — which is six times the number in the condition.

The plot does not have room for a basin. It does not have room for anything with a footprint, because the only open ground is the yard, the yard is the turning circle for a rigid on a nine-metre swept path, and the delivery bay sits over a live sewer easement that the undertaker will not let anyone excavate above. So the two candidates left are the two surfaces the building already occupies: the roof, and the ground underneath the part of the yard that is not the delivery bay. This is the position most tight-site drainage designs end up in, and the honest way through it starts by admitting that the condition and the thing you have to build are measured in different units.

A Rate Is Not a Volume, and the Condition Only Names One of Them

Q = C i A gives a peak. It is the flow at the top of the hydrograph, and it is the right number to hold against a condition expressed as litres per second, because both are rates and they are directly comparable. What it cannot do — and this is where small submissions lose a fortnight — is tell you how much water is behind that peak. The Rational Method has no time axis. It is a snapshot at the moment of maximum flow, and a snapshot of a flood does not tell you the size of the tank.

The volume comes from routing: an inflow hydrograph for a storm of a given duration, an outflow fixed at the permitted rate, and the difference between them accumulated over time. Run it once and you have the storage for that duration. Run it for a spread of durations and the largest answer is the one you build, which is the whole reason the critical duration for storage is almost never the critical duration for peak flow. The short violent burst makes the biggest instantaneous flow; the two-hour storm makes the biggest tank, because the outflow only drains 5 litres per second no matter how long the rain goes on and a longer storm gives it more to get through. USDA NRCS Technical Release 55, Urban Hydrology for Small Watersheds, and the rainfall-runoff methods published with the Flood Estimation Handbook are two of the routes to the hydrograph; the local ordinance will name one.

The permitted rate itself is worth understanding before it is designed to. Where a condition sets the cap at the greenfield runoff rate, that rate is estimated by a named method — in the United Kingdom, Institute of Hydrology Report No. 124, Flood estimation for small catchments, is the usual one for a plot this size — and on 0.19 hectares it produces a fraction of a litre per second. Nobody builds a flow control that small, because the opening it needs is smaller than the debris that will arrive at it. So sewerage undertakers and lead local flood authorities apply a minimum practicable discharge rate instead, and it is that minimum, not the greenfield estimate, that usually appears in the condition. The 5 litres per second on this site is a floor, not a calculation, and knowing that changes how much argument is available later.

Two things belong in the file before any of the arithmetic. Whether water crosses onto the site from outside it, since offsite catchment has to be carried through the development whether or not the condition mentions it — here the railway embankment behind the yard falls away, which is worth recording as a finding rather than leaving as an assumption. And the discharge hierarchy: Approved Document H, Drainage and waste disposal, puts infiltration first, a watercourse second and a sewer last, so a condition permitting a sewer discharge does not excuse you from showing the ground was tested.

The shape of a critical-duration search, on illustrative intensities only — the real ones come off the site's own depth-duration-frequency data, and the storage answer moves with them
Storm durationRunoff onto the networkReleased at 5 l/sStorage still required
15 minutes54 m³4.5 m³49.5 m³
1 hour86 m³18 m³68 m³
2 hours115 m³36 m³79 m³
3 hours130 m³54 m³76 m³
6 hours156 m³108 m³48 m³
The shape of a critical-duration search, on illustrative intensities only — the real ones come off the site's own depth-duration-frequency data, and the storage answer moves with them

Use this for the number the condition is written in — the peak the finished surfaces will produce, against the rate you are allowed to release. It answers how far over you are, which is the question that decides whether there is a scheme at all; it does not answer how big the tank is, and no peak-flow method does.

Area inside the site boundary that drains to the point being sized.

Fraction of rainfall on the site area that becomes surface runoff.

Area beyond the boundary whose water crosses onto the site and has to be carried through it.

Runoff fraction for the surface beyond the boundary, which is rarely the same as the site's.

Average intensity of the design storm over the catchment's time of concentration (25.4 mm/hr is 1 in/hr).

Peak discharge

1.49 ft³/s

Medium confidence

The Rational Method returns a peak flow and nothing else — no hydrograph, no volume, no timing. It is accepted for small catchments and routinely rejected above a size limit written into the local ordinance, so check that limit before using this figure in a submission.

Total contributing area
34,450 ft²
Area-weighted runoff coefficient
0.63 (C)
Contribution from beyond the boundary
0.31 ft³/s
Share of the peak arriving from offsite
20.79 %

Add the equipment this sizes

This result is a specification — 1.49 ft³/s — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

What this calculation does not cover

  • Assumes uniform rainfall over the whole catchment for the full duration, and a single time of concentration for both areas.
  • Gives no runoff volume, so it cannot size detention or infiltration storage — those need a hydrograph method.

Roughly Eighty Cubic Metres, and Nowhere Obvious to Put It

Call the storage 80 m³ — a shade over 2,800 cubic feet — and hold it loosely, because it will move when the real rainfall data goes in. The useful thing about having the figure early is that it immediately kills options. Eighty cubic metres is a swimming pool. It is not going in a manhole, it is not going in an oversized pipe run, and on a plot where the only spare plan area is 340 m² (3,660 sq ft) of yard outside the delivery bay and the easement, it is going either above the building or below the yard.

Those two are not variants of the same idea, and the table below is the argument in its shortest form. A vegetated roof is a retention device: it removes water from the system permanently, by holding it in pore space until the weather takes it back, and it gives that volume back to you slowly and on nobody's schedule. A stone reservoir is an attenuation device: it holds water briefly and hands it on, either downwards into the subgrade or sideways into a throttled outlet. The reviewer's questions differ, the evidence differs, and the condition's sentence about emptying means something different in each case.

The same five questions put to each of the two routes, and how differently they answer
What the reviewer wants to knowVegetated roofStone reservoir under the yard
Where the water sitsPore space in the growing medium and the cups of the drainage composite, over the vegetated footprint onlyVoid space between clean open-graded aggregate, over whatever plan area is free below ground
What fixes the credited volumeThe product's tested retention at saturation, discounted by whatever the local method allows for antecedent wetnessDepth times void ratio times plan area, with the void ratio the manual permits rather than the one the quarry quotes
How the storage comes backEvapotranspiration over days — a weather outcome, not a design variable, and not something you can put a clock onInfiltration at a measured and factored rate, or through an underdrain, both of which can be timed
What quietly destroys itA roof that has not dried out since the last storm, and outlets nobody has looked at since handoverFines in the voids, a subgrade smeared by tracked plant, and silt arriving from the yard it sits under
Who is holding it in fifteen yearsWhoever maintains the roof, which on a let building is rarely the occupierNobody, unless the inspection well and the maintenance schedule were written into the title
The same five questions put to each of the two routes, and how differently they answer

What a Vegetated Roof Is Actually Credited With

The roof is 900 m², and about 620 m² (6,700 sq ft) of it can be vegetated once the plant deck, the rooflights, the perimeter fire and access zones and the outlet surrounds are taken out. Take a manufacturer's rated retention of 30 mm at saturation and that footprint holds a little under 19 m³. Against 80 m³ of required storage, the roof on its own is not the answer to this condition and no amount of specification improves that, because the yard is 700 m² of impermeable surface that does not drain across the roof and never will. This is worth establishing in the first hour rather than the third week, and it is the single most common misreading of what a green roof does for a drainage submission.

The 19 m³ is also a ceiling rather than a design value. A rated retention depth is what the medium and the composite hold starting dry and wetted to saturation, and the design storm has no obligation to arrive on a dry roof. In a wet autumn the medium may already be at capacity when the rain starts, at which point the credited storage is zero and the roof behaves as a flat roof with a rougher surface. CIRIA C753, The SuDS Manual, treats interception — the volume lost before any runoff leaves the site at all — as a design objective in its own right, and how much a vegetated roof may claim against it is set there rather than in the product literature. The component testing sits elsewhere again: ASTM E2398/E2398M for water capture and media retention of geocomposite drain layers, the FLL Guidelines for the Planning, Construction and Maintenance of Green Roofing, and BS 8616 for substrate performance parameters.

None of which makes the roof pointless. It reduces the volume that reaches the tank, which shrinks the tank; it delays the roof's contribution so that it arrives after the yard's has passed, which flattens the combined hydrograph; and on a site being assessed against biodiversity or urban greening policy it is doing three jobs at once. What it does not do is give you a discharge rate. A vegetated roof has no throttle in it. Water leaves it when the medium is full, at whatever rate the composite and the outlets pass, and if the condition is a rate cap then something downstream still has to hold the rate — which is the subject of a later section and the thing most often missing from a submission that leads with a green roof.

Put the vegetated area and the manufacturer's rated retention depth in here and read the volume as the best case, not the design case. The number this returns is what the roof holds starting dry; what the reviewer credits is that figure after the local method has taken a view on how wet the roof was when the storm arrived.

The total plan area covered by modular green roof trays.

The manufacturer's rated water retention depth for the tray/media system.

Retained rainwater volume

337 gal

Medium confidence

Retention depth is the manufacturer's rated figure for the specific tray/media system at saturation — actual retention varies with antecedent moisture and rainfall intensity/duration.

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

water retained 1 inwater retained 25.4 mmvegetated tray

What this calculation does not cover

  • This is the ceiling for one storm landing on dry media, not a capacity that resets on demand. The only thing that empties a green roof between storms is evapotranspiration, which runs a few mm (around 0.1 in) on a good summer day and close to nothing in winter, so a second storm twelve hours behind the first meets a full tray and passes straight through. Stormwater credit is assessed against a continuous rainfall record with that drawdown rate built in, and it comes out well below the figure above.
  • The rated depth is a level-tray figure, and slope drains it. Water occupies the tray's reservoir profile only while that profile is level; as pitch increases it migrates to the low side of each module and out, so the depth published for a flat test bed is not what a pitched roof holds. Above the shallow falls these systems are rated at, treat retention as reduced and ask the supplier for a figure at the actual pitch.

The Layer That Decides Whether the Roof Drains At All

Beneath the medium sits a drainage and water-retention composite: a dimpled core that keeps a reservoir standing in its cups and passes everything above that to the outlets, under a filter fabric that stops the fines washing down and blinding it. It is the least visible layer in the build-up and the one that decides whether the roof is a retention device or a bath. Get it wrong and the medium sits permanently saturated, the planting drowns, the dead load climbs to the case the structural engineer was told was the worst case, and the retention volume you claimed in the submission is not available on any storm because it was never empty.

Ordering it is the simplest arithmetic on the page and still gets undercooked. At 620 m² of vegetated roof against a common roll coverage near 9.3 m² (about 100 sq ft), the base count is 67 rolls before a single lap or cut. Manufacturer laps between rolls, cuts around every outlet, upstand, rooflight kerb and inspection chamber, and the trim at the perimeter all come off the top of that, so the delivered figure is always higher than the area sum and the product's own installation guide is what sets by how much. Two site details are worth fixing at the same time: the falls have to be confirmed on the deck rather than assumed from the drawing, and the waterproofing under all of it gets a flood test to ASTM D5957, Standard Guide for Flood Testing Horizontal Waterproofing Installations, before a single roll goes down — because it is the one layer nobody can reach again once the overburden is placed.

This is the buying number for the composite: net roll coverage against vegetated area. Treat what it returns as the floor, then add the manufacturer's lap allowance and a cut allowance taken off the actual outlet and upstand count, not off a percentage.

The total green roof area to receive the drainage layer.

The area covered by a single roll of drainage/water-retention mat.

Drainage layer rolls needed

10 rolls

High confidence

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

What this calculation does not cover

  • Counts rolls as bare area divided by the coverage figure you enter. Manufacturer-required side and end laps, cuts around drains, vents, upstands and edge trim, and offcut waste on a narrow or irregular roof all add material this number does not include — unless the coverage you typed was already the lapped net figure rather than the roll's own dimensions.
  • Takes the area exactly as typed and makes no adjustment for slope. On a pitched green roof the surface the mat has to cover is larger than the plan area scaled off the drawing.
  • This is a material take-off, not a roof drainage design. It does not check that the drainage layer can move the design storm across the roof to the outlets, and it does not size drains, scuppers or overflows — those stay with the drainage design and the code requirements that apply to it.
  • Does not choose or verify the product. Required core thickness, reservoir depth and in-plane flow capacity follow from roof slope, the drainage path length to the outlets and the specified water retention. Enter a roll whose performance has already been confirmed against the specification; this only counts it.
  • Covers one layer of the build-up. Root barrier, protection mat, filter fleece above the drainage layer, gravel and edge margins and the growing medium are separate take-offs, and the water this layer is designed to hold adds saturated dead load that a structural engineer has to verify against the roof's capacity.

A Roof That Attenuates Is a Different Roof

If what the reviewer actually wants is roof-based attenuation — storage that fills during the storm and empties at a controlled rate afterwards — then the device is a blue roof, not a green one, and the distinction is not pedantry. A blue roof holds water above the waterproofing in a void former or a restricted drainage layer and releases it through flow-restricting outlets, so it has a discharge rate you can specify and a drawdown you can calculate. A green roof holds water in pore space and releases it to the atmosphere. The two are frequently built as one assembly, and they are still two separate claims in a submission.

The moment water is deliberately ponded on a roof, three other disciplines acquire an interest. The structure has to carry the ponded depth as a load case, on top of the saturated medium; BS 6229, Flat roofs with continuously supported flexible waterproof coverings, sets out the design considerations for the roof itself, and BS EN 12056-3, Gravity drainage systems inside buildings, covers the roof drainage layout and its calculation, including the overflow provision that has to work when the restrictor is blocked. And the restrictor will block eventually, which is why an unrestricted emergency overflow at a level the structure can tolerate is not an optional refinement — it is the thing standing between a maintenance failure and a collapse. Any roof attenuation proposal that does not show its overflow on a section has not been designed yet.

The Yard as a Tank, and the Clock Running Underneath It

Which leaves the ground. Eighty cubic metres of water in clean open-graded stone at a permitted void ratio of 0.35 needs about 230 m³ of stone, and spread over the 340 m² of yard that is actually available that is a reservoir roughly 675 mm (26.5 in) deep below the pavement construction. Stone is not the only way to build a void — geocellular units are rated by their manufacturers near 95 per cent void against roughly a third for clean aggregate, and CIRIA C737, Structural and geotechnical design of modular geocellular drainage systems, is where the loading and long-term serviceability of that choice are dealt with. Either way the depth is buildable on this site, and either way compliance turns on a number nobody has yet measured: what the subgrade at the bottom of that excavation will take.

The measurement has to happen at the elevation the excavation will finish at, not at the surface, because the horizon two feet down owes nothing to the topsoil above it. ASTM D3385, Standard Test Method for Infiltration Rate of Soils in Field Using Double-Ring Infiltrometer, is one accepted route; in the United Kingdom the soakage pit procedure in BRE Digest 365, Soakaway design, is the conventional one, and it is worth knowing that the two methods are not interchangeable in what they credit. BRE 365 sizes on the internal surface area up to half the effective storage depth and conventionally takes no credit for the base, on the reasonable ground that the base is where the silt ends up; the drawdown check below is a one-dimensional vertical sum that credits only the base and takes nothing from the sides. They are different conservatisms, not different accuracies, and a submission that mixes them without saying so invites the reviewer to pick whichever is worse.

Whatever the test returns, it gets divided before it is designed to. Every manual applies a safety factor to a measured infiltration rate, and the factor is larger where the testing was thin, where the soil is variable, or where the contributing area is large relative to the infiltrating footprint — which on this site it is, because 1,600 m² of hard surface is draining into a 340 m² reservoir. Suppose the test comes back at 8 mm/hr on a silty clay and the manual asks for a factor of three on a single test. The design rate is 2.7 mm/hr, the water depth to be lost is 675 mm at 0.35 voids, which is 236 mm (9.3 in), and the drawdown runs to something close to 88 hours. Against a permitted maximum of two days, that is not a marginal fail; it is not a scheme.

There are two ways out and only two. Spread the reservoir shallower over a bigger footprint, which this site does not have. Or fit a perforated underdrain at a raised invert, so that only the stone below the pipe has to infiltrate and everything above it leaves through the pipe — at which point the depth on the clock is 200 mm (8 in) of stone rather than 675, the water in it is 70 mm, and the drawdown comes back around 26 hours. That is the standard remedy for a marginal soil and it is a legitimate one, but it converts the scheme from full infiltration to partial infiltration, and the underdrain now needs an outfall that is itself throttled to the 5 litres per second in the condition. The check has not gone away. It has moved to a different part of the section, and a different part of the submission.

  1. Fix the formation level on a section before testing, and test at that level — a rate measured at 300 mm down describes soil you are going to dig out.
  2. Test more than one location across the footprint, and record the coordinates and the date with each result rather than reporting a single averaged figure.
  3. Note the depth to the seasonally highest groundwater table at each hole; the vertical separation the manual requires below the reservoir is a hard constraint on depth, independent of drawdown.
  4. Apply the safety factor the governing manual specifies for the number of tests you actually did, not the one that applies to a full investigation.
  5. Protect the formation once it is exposed: keep tracked plant off it, excavate the last lift with a toothless bucket, and accept that a smeared subgrade is not recovered by scarifying it afterwards.

This is the compliance check the condition's emptying clause turns into: stored water depth, which is reservoir depth times void ratio, divided by the design rate after the safety factor. Run it once as a full-infiltration section, then again with the underdrain invert raised, and the difference between the two answers is the whole partial-infiltration argument.

Depth of the open-graded storage layer, measured from the subgrade up to the top of the reservoir stone.

Fraction of the reservoir layer that is open void space rather than stone.

Field-measured rate at the excavation bottom, before any safety factor is applied (1 in/hr is 25.4 mm/hr).

Divisor applied to the measured rate to obtain the design rate, as required by the governing manual.

Whether a perforated underdrain relieves the upper part of the reservoir.

The longest drawdown the governing manual allows for this system.

Reservoir drawdown time

30.5 hours

Medium confidence

The reservoir empties with about 17.5 hours in hand against the permitted maximum. That margin is only as good as the infiltration test behind it — a single test on a variable soil is thin evidence for a whole footprint.

Design infiltration rate after the safety factor
0.24 in/hr
Depth of stored water that must infiltrate
7.2 in
Permitted maximum drawdown
48 hours
Margin against the permitted maximum
17.52 hours

What this calculation does not cover

  • One-dimensional vertical infiltration only: no credit is taken for lateral seepage out of the sides of the excavation, and none for evaporation.
  • Assumes the reservoir starts full. A design storm that only part-fills it drains proportionally faster.

Neither Option Throttles Anything By Itself

Storage and rate control are two different jobs, and a tank with a small hole in it appears to do both. The tank fixes how much you hold; the hole fixes how fast you let go; a condition written in litres per second is enforced entirely at the hole. Neither candidate contains one. The roof releases at whatever the composite and outlets pass, and the reservoir with an underdrain releases at whatever that pipe carries under the head available — on a full reservoir, a good deal more than 5 litres per second.

So the scheme needs a flow control device at the outfall, sized against a head-discharge relationship rather than a pipe diameter. A plain orifice will do it arithmetically, but the opening needed to pass 5 litres per second under a metre of head is small enough that sewerage undertakers commonly refuse to adopt one, on the straightforward ground that it will block — and a blocked orifice on a tank under a yard announces itself by flooding the yard. Vortex flow controls exist for exactly this reason: they pass the same design flow through a substantially larger opening by making the water spiral rather than by making the hole small, and their head-discharge curves are tested product data. Hydro International's Hydro-Brake range is the one most people have seen on a UK drawing; whichever product is used, the curve that goes in the submission is the manufacturer's, for the specific unit reference, and not a generic orifice equation.

Then there is the storm bigger than the one you designed for, which will arrive. An exceedance route is a drawing showing where water goes when the storage is full and the control is passing all it can — over which threshold, across which levels, out of which gate — and reviewers increasingly ask for it as a plan with spot levels rather than as a paragraph. On this site the answer is that the yard floods to a controlled depth and spills at the vehicle entrance towards the road, which is defensible, and it is defensible only because the finished floor level of the trade counter sits above that depth. BS EN 752, Drain and sewer systems outside buildings, and BS 8582, Code of practice for surface water management for development sites, are the documents that frame this; the levels are the argument.

What Goes In the Pack, and Who Owns It Afterwards

A discharge-of-conditions submission is refused far more often for missing evidence than for wrong arithmetic, and the missing evidence is almost always the same short list. The calculations are the easy part; the infiltration test records, the flow control product data, the exceedance plan and the maintenance arrangement are the parts assembled last and therefore the parts that go in thin. Build the pack as the design proceeds rather than at the end, and every one of them exists as a by-product of work that had to happen anyway.

The last item is the one with the longest tail. A stone reservoir under a trade counter yard has no visible parts, which means that in fifteen years its existence depends on a document rather than on anyone noticing it. Adoption is the cleanest outcome where it is available — in England the route runs through the sewerage undertaker's adoption arrangements under the Water Industry Act 1991 and the Water UK sewerage sector guidance, and in Wales the SuDS Approving Body regime under Schedule 3 of the Flood and Water Management Act 2010 changes both the approval and the adoption picture, so which applies is a question of jurisdiction and date, not preference. Where the system stays private, the maintenance obligation belongs in the title or in a management company's schedule with the inspection well marked on a plan, because a maintenance regime that lives only in a handover file has an expected life of one change of ownership.

  1. The peak-flow comparison: what the finished surfaces produce against what the condition permits, with the coefficients attributed to the manual they came from.
  2. The storage calculation across a range of storm durations, showing the critical one rather than only the answer.
  3. Infiltration test records with locations, depths, dates and the method named, plus the safety factor applied and the clause of the manual requiring it.
  4. The drawdown check against the permitted window, run for the section as built — full infiltration or partial, with the underdrain invert dimensioned.
  5. The flow control device by manufacturer reference, with its tested head-discharge curve and the design head marked on it.
  6. An exceedance plan with spot levels, showing where the water goes when the storage is full, and the finished floor levels it has to stay below.

Working the submission back from the number in the condition

The order matters more than the arithmetic. The permitted rate is fixed, so everything else is derived from it: peak first to see the size of the gap, storage second, then the depth that the available footprint allows, and only then whether that depth empties in time.

  • Impermeable area as built, split by surface — Roof, yard, access and hard landscape are separate coefficients. A single blended figure with no working behind it is the first thing a reviewer asks to see broken out.
  • Permitted discharge rate, and where it came from — Greenfield estimate by a named method, or the undertaker's minimum practicable rate — knowing which one the condition used tells you whether there is any argument left.
  • Storage volume at the critical duration, not at the critical peak — Route several durations and take the largest. The duration that produces the biggest flow and the one that produces the biggest tank are rarely the same storm.
  • Available plan area below ground, after easements and swept paths — Deduct the delivery bay, the service corridors and anything over a live sewer easement before dividing storage by area, or the depth that comes out is fiction.
  • Design void ratio the manual permits, per layer — The credited fraction is a jurisdictional figure, not the quarry's. Moving from 0.40 to 0.30 adds a third to the excavation for the same stored volume.
  • Measured infiltration rate at formation level, and the factor on it — Recorded per test hole with coordinates and dates. One test on a variable soil usually attracts a larger factor, which is where a marginal drawdown becomes a failing one.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • CIRIA C753, The SuDS Manual
  • CIRIA C737, Structural and geotechnical design of modular geocellular drainage systems
  • Defra, Non-statutory technical standards for sustainable drainage systems
  • BS 8582, Code of practice for surface water management for development sites
  • BS EN 752, Drain and sewer systems outside buildings
  • BS EN 12056-3, Gravity drainage systems inside buildings — Roof drainage, layout and calculation
  • BS 6229, Flat roofs with continuously supported flexible waterproof coverings — Code of practice
  • BRE Digest 365, Soakaway design
  • Approved Document H, Drainage and waste disposal (England and Wales)
  • Water Industry Act 1991, and the Water UK sewerage sector guidance on adoption
  • Flood and Water Management Act 2010, Schedule 3 (SuDS Approving Bodies, Wales)
  • Institute of Hydrology Report No. 124, Flood estimation for small catchments
  • Flood Estimation Handbook, and its rainfall-runoff and depth-duration-frequency methods
  • USDA NRCS Technical Release 55, Urban Hydrology for Small Watersheds
  • NOAA Atlas 14, Precipitation-Frequency Atlas of the United States
  • FHWA HEC-22, Urban Drainage Design Manual
  • ASTM D3385, Standard Test Method for Infiltration Rate of Soils in Field Using Double-Ring Infiltrometer
  • ASTM D448, Standard Classification for Sizes of Aggregate for Road and Bridge Construction
  • ASTM D5957, Standard Guide for Flood Testing Horizontal Waterproofing Installations
  • ASTM E2398/E2398M, Standard Test Method for Water Capture and Media Retention of Geocomposite Drain Layers for Vegetative (Green) Roof Systems
  • ASTM E2397/E2397M, Standard Practice for Determination of Dead Loads and Live Loads Associated with Vegetative (Green) Roof Systems
  • FLL, Guidelines for the Planning, Construction and Maintenance of Green Roofing
  • BS 8616, Specification for performance parameters and test methods for green roof substrates
  • Hydro International, Hydro-Brake vortex flow control product literature and head-discharge curves

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.