A 10 × 8 m two-storey house drawn and counted: footing, slab, two storeys of walls, floor joists, stair and roof

A family house on a compact plot: the shell, storey by storey, ready to divide into rooms.
  • 2 levelsDrawn
  • 42Rows to buy
  • Opens as a new projectIn the canvas

Two storeys from the House Estimator

The walls, openings, slab, footing and roof are the House Estimator's own drawing of a house 10 by 8 m (33 by 26 ft) outside with two storeys. Each storey has the same framed outside walls, two partitions across the plan and seven windows spread along the walls, and the ground floor has the front and back doors. Open it in the estimator or here and the same rows come out.

On top of that drawing the template adds what a second storey needs and the estimator leaves out: the upper floor itself, drawn between the outside walls with its joists running the shorter way, and a straight stair from the ground floor to the upper one along the back wall of the first room.

Reading a list by storey

The list keeps each storey apart. Studs, plates, batts, sheathing, wrap and siding appear once for the ground floor and once for the upper floor, as do the partitions and the windows' flashing and casing, so a framer can order one storey at a time. The roof sits on the upper storey and lists shingles, underlayment, ridge cap, ridge vent and trusses; the footing and the slab belong to the ground floor.

The floor joists come from the floor joist page, counted over the floor's outline at its spacing with rim joists and blocking, and the stair from the stair page as a stringer length for the rise between the storeys.

A hip roof, or fewer windows

The first change hips the roof, which replaces the gable ends with two more slopes and changes the ridge and the cap. The second takes the windows down to five a storey, which gives back wall area to the studs, sheathing and siding while the flashing and casing rows shrink.

A new project with this drawing, in your units; nothing you already have is changed, and nothing is uploaded.

How it is drawn

  1. Start from the House Estimator. A 10 × 8 m (33 × 26 ft) footprint, two storeys, two partitions and seven windows a storey.
  2. Keep its gable roof. Shingles on trusses at 6 in 12, the ridge along the longer side.
  3. Add the upper floor. A floor outline on the upper storey between the outside walls, joists the shorter way.
  4. Add the stair. A straight flight on the ground floor, about 0.9 m (3 ft) wide, climbing to the upper floor.

What a professional decides

The joists' size and spacing for the spans and loads, the headers over every opening, the stair's rise, going and headroom, and how the upper storey is braced against wind are an engineer's or the building code's tables, checked by your building office. The drawing counts what the shell comes to; it does not say any part of it is strong enough.

Plan of the two-storey house, 10 × 8 m template, ground floor, to scale, with imperial lengths.
Ground floor, to scale. The canvas's own SVG export of this drawing.
Plan of the two-storey house, 10 × 8 m template, upper floor, to scale, with imperial lengths.
Upper floor, to scale. The canvas's own SVG export of this drawing.
Plan of the two-storey house, 10 × 8 m template, ground floor, to scale, with metric lengths.
Ground floor, to scale. The canvas's own SVG export of this drawing.
Plan of the two-storey house, 10 × 8 m template, upper floor, to scale, with metric lengths.
Upper floor, to scale. The canvas's own SVG export of this drawing.

Everything to buy

Quantities to order, with each calculator’s own waste. Your own rates go on the lines in My Project.

Foundation and floor
Material, and whereQuantity
Continuous Footing / Grade Beam VolumeFT-1, Ground floor8.88 yd³
Trench Excavation & Backfill VolumeFT-1, Ground floor16.81 yd³
RebarFT-1, Ground floor23 x 20 ft sticks
ConcreteSL-1, Ground floor11.7 yd³
RebarSL-1, Ground floor68 x 20 ft sticks
Concrete FormworkSL-1, Ground floor17 x 8 ft boards
Floors
Material, and whereQuantity
Floor joists, rim joists and blockingFJ-1, Upper floor26 joists
Walls
Material, and whereQuantity
Studs, 2×4 (38 × 89 mm) at 16 in (400 mm) centresEW-1, Ground floor, 4 walls144 studs
Plates, headers, sills, cripples, corner and junction studsEW-1, Ground floor, 4 walls531.48 ft
Fibreglass batts, 3 1/2 in (89 mm), for 2×4 cavitiesEW-1, Ground floor, 4 walls9 packages
Wall sheathing, OSB 7/16 in (11 mm)EW-1, Ground floor, 4 walls28 sheets (4x8 ft)
House WrapEW-1, Ground floor, 4 walls1 roll
Vinyl sidingEW-1, Ground floor, 4 walls8.69 squares
Framing StudIW-1, Ground floor, 2 walls64 studs
Outlet SpacingIW-1, Ground floor, 2 walls6 outlets (minimum)
Drywall Joint CompoundIW-1, Ground floor, 2 walls2 x 4.5 gal boxes
Studs, 2×4 (38 × 89 mm) at 16 in (400 mm) centresEW-1, Upper floor, 4 walls136 studs
Plates, headers, sills, cripples, corner and junction studsEW-1, Upper floor, 4 walls530.9 ft
Fibreglass batts, 3 1/2 in (89 mm), for 2×4 cavitiesEW-1, Upper floor, 4 walls9 packages
Wall sheathing, OSB 7/16 in (11 mm)EW-1, Upper floor, 4 walls29 sheets (4x8 ft)
House WrapEW-1, Upper floor, 4 walls1 roll
Vinyl sidingEW-1, Upper floor, 4 walls9.15 squares
Framing StudIW-1, Upper floor, 2 walls64 studs
Outlet SpacingIW-1, Upper floor, 2 walls6 outlets (minimum)
Drywall Joint CompoundIW-1, Upper floor, 2 walls2 x 4.5 gal boxes
Doors and windows
Material, and whereQuantity
Flashing tape round the opening, for a timber-framed wallDR-1, Ground floor, 2 openings57.2 ft
Architrave (casing) inside, two legs and a headDR-1, Ground floor, 2 openings37.4 linear ft
Mastic (caulk) round the frame, outside and insideDR-1, Ground floor, 2 openings4 tubes
Paint for the door and frame, both faces: undercoat and glossDR-1, Ground floor, 2 openings0.5269 gal
Window Opening Flashing MembraneWN-1, Ground floor, 7 openings171.95 ft
Door & Window CasingWN-1, Ground floor, 7 openings123.18 linear ft
Window Opening Flashing MembraneWN-1, Upper floor, 7 openings171.95 ft
Door & Window CasingWN-1, Upper floor, 7 openings123.18 linear ft
Interior doors, 800 × 2000 mm (31 1/2 × 78 3/4 in)counted on the drawing8 each
Outside doors, 914 × 2134 mm (36 × 84 in)counted on the drawing2 each
Windows, 1219 × 1219 mm (48 × 48 in)counted on the drawing14 each
Stairs
Material, and whereQuantity
Stringer lengthStair t1, Ground floor to Upper floor12.06 ft
Roof
Material, and whereQuantity
Roofing ShingleRF-1, Upper floor12.32 squares
Roofing UnderlaymentRF-1, Upper floor2 rolls
Roof Ridge CapRF-1, Upper floor2 bundles
Ridge Vent Linear FootageRF-1, Upper floor36.7 ft
Roof trussesRF-1, Upper floor18 trusses
Foundation and floor
Material, and whereQuantity
Continuous Footing / Grade Beam VolumeFT-1, Ground floor6.73 m³
Trench Excavation & Backfill VolumeFT-1, Ground floor12.28 m³ (loose)
RebarFT-1, Ground floor12 x 12 m sticks
ConcreteSL-1, Ground floor8.8 m³
RebarSL-1, Ground floor35 x 12 m sticks
Concrete FormworkSL-1, Ground floor17 x 2.4 m boards
Floors
Material, and whereQuantity
Floor joists, rim joists and blockingFJ-1, Upper floor26 joists
Walls
Material, and whereQuantity
Studs, 2×4 (38 × 89 mm) at 16 in (400 mm) centresEW-1, Ground floor, 4 walls144 studs
Plates, headers, sills, cripples, corner and junction studsEW-1, Ground floor, 4 walls162.59 m
Fibreglass batts, 3 1/2 in (89 mm), for 2×4 cavitiesEW-1, Ground floor, 4 walls9 packages
Wall sheathing, OSB 7/16 in (11 mm)EW-1, Ground floor, 4 walls28 sheets (2440x1220 mm)
House WrapEW-1, Ground floor, 4 walls1 roll
Vinyl sidingEW-1, Ground floor, 4 walls81.29 m²
Framing StudIW-1, Ground floor, 2 walls64 studs
Outlet SpacingIW-1, Ground floor, 2 walls6 outlets (minimum)
Drywall Joint CompoundIW-1, Ground floor, 2 walls41.97 kg
Studs, 2×4 (38 × 89 mm) at 16 in (400 mm) centresEW-1, Upper floor, 4 walls136 studs
Plates, headers, sills, cripples, corner and junction studsEW-1, Upper floor, 4 walls162.27 m
Fibreglass batts, 3 1/2 in (89 mm), for 2×4 cavitiesEW-1, Upper floor, 4 walls9 packages
Wall sheathing, OSB 7/16 in (11 mm)EW-1, Upper floor, 4 walls29 sheets (2440x1220 mm)
House WrapEW-1, Upper floor, 4 walls1 roll
Vinyl sidingEW-1, Upper floor, 4 walls85.54 m²
Framing StudIW-1, Upper floor, 2 walls64 studs
Outlet SpacingIW-1, Upper floor, 2 walls6 outlets (minimum)
Drywall Joint CompoundIW-1, Upper floor, 2 walls41.97 kg
Doors and windows
Material, and whereQuantity
Flashing tape round the opening, for a timber-framed wallDR-1, Ground floor, 2 openings17.25 m
Architrave (casing) inside, two legs and a headDR-1, Ground floor, 2 openings11.26 m
Mastic (caulk) round the frame, outside and insideDR-1, Ground floor, 2 openings4 tubes
Paint for the door and frame, both faces: undercoat and glossDR-1, Ground floor, 2 openings1.93 L
Window Opening Flashing MembraneWN-1, Ground floor, 7 openings51.59 m
Door & Window CasingWN-1, Ground floor, 7 openings36.96 m
Window Opening Flashing MembraneWN-1, Upper floor, 7 openings51.59 m
Door & Window CasingWN-1, Upper floor, 7 openings36.96 m
Interior doors, 800 × 2000 mm (31 1/2 × 78 3/4 in)counted on the drawing8 each
Outside doors, 920 × 2100 mm (36 1/4 × 82 3/4 in)counted on the drawing2 each
Windows, 1200 × 1200 mm (47 1/4 × 47 1/4 in)counted on the drawing14 each
Stairs
Material, and whereQuantity
Stringer lengthStair t1, Ground floor to Upper floor3.64 m
Roof
Material, and whereQuantity
Roofing ShingleRF-1, Upper floor114.72 m²
Roofing UnderlaymentRF-1, Upper floor2 rolls
Roof Ridge CapRF-1, Upper floor2 bundles
Ridge Vent Linear FootageRF-1, Upper floor11.13 m
Roof trussesRF-1, Upper floor18 trusses

What changes if

With a hip roof instead of the gable

  • Roofing Shingle: 12.32 squares → 12.57 squares
  • Roof Ridge Cap: 2 bundles → 4 bundles
  • Ridge Vent Linear Footage: 36.7 ft → 7.35 ft

With five windows a storey instead of seven

  • Studs, 2×4 (38 × 89 mm) at 16 in (400 mm) centres: 144 studs → 136 studs
  • Plates, headers, sills, cripples, corner and junction studs: 531.48 ft → 505.95 ft
  • Wall sheathing, OSB 7/16 in (11 mm): 28 sheets (4x8 ft) → 29 sheets (4x8 ft)
  • Vinyl siding: 8.69 squares → 9.04 squares
  • Studs, 2×4 (38 × 89 mm) at 16 in (400 mm) centres: 136 studs → 127 studs
  • Plates, headers, sills, cripples, corner and junction studs: 530.9 ft → 505.37 ft
  • Fibreglass batts, 3 1/2 in (89 mm), for 2×4 cavities: 9 packages → 10 packages
  • Wall sheathing, OSB 7/16 in (11 mm): 29 sheets (4x8 ft) → 30 sheets (4x8 ft)
  • Vinyl siding: 9.15 squares → 9.5 squares
  • Window Opening Flashing Membrane: 171.95 ft → none
  • Door & Window Casing: 123.18 linear ft → none
  • Window Opening Flashing Membrane: 171.95 ft → none
  • Door & Window Casing: 123.18 linear ft → none
  • Window Opening Flashing Membrane: none → 122.82 ft
  • Door & Window Casing: none → 87.99 linear ft
  • Window Opening Flashing Membrane: none → 122.82 ft
  • Door & Window Casing: none → 87.99 linear ft
  • Windows, 1219 × 1219 mm (48 × 48 in): 14 → 10

With a hip roof instead of the gable

  • Roofing Shingle: 114.72 m² → 116.88 m²
  • Roof Ridge Cap: 2 bundles → 4 bundles
  • Ridge Vent Linear Footage: 11.13 m → 2.1 m

With five windows a storey instead of seven

  • Studs, 2×4 (38 × 89 mm) at 16 in (400 mm) centres: 144 studs → 136 studs
  • Plates, headers, sills, cripples, corner and junction studs: 162.59 m → 154.72 m
  • Wall sheathing, OSB 7/16 in (11 mm): 28 sheets (2440x1220 mm) → 29 sheets (2440x1220 mm)
  • Vinyl siding: 81.29 m² → 84.45 m²
  • Studs, 2×4 (38 × 89 mm) at 16 in (400 mm) centres: 136 studs → 127 studs
  • Plates, headers, sills, cripples, corner and junction studs: 162.27 m → 154.4 m
  • Fibreglass batts, 3 1/2 in (89 mm), for 2×4 cavities: 9 packages → 10 packages
  • Wall sheathing, OSB 7/16 in (11 mm): 29 sheets (2440x1220 mm) → 30 sheets (2440x1220 mm)
  • Vinyl siding: 85.54 m² → 88.7 m²
  • Window Opening Flashing Membrane: 51.59 m → none
  • Door & Window Casing: 36.96 m → none
  • Window Opening Flashing Membrane: 51.59 m → none
  • Door & Window Casing: 36.96 m → none
  • Window Opening Flashing Membrane: none → 36.85 m
  • Door & Window Casing: none → 26.4 m
  • Window Opening Flashing Membrane: none → 36.85 m
  • Door & Window Casing: none → 26.4 m
  • Windows, 1200 × 1200 mm (47 1/4 × 47 1/4 in): 14 → 10

The calculators behind this list

This page counts materials and does not check strength. The same drawing opens in the Construction Canvas, where every figure can be changed; a house drawn from a form is on the House Estimator. For assistants and scripts: the drawing as JSON, in both unit systems, with a link that opens each.