Canvas template

A 5 × 4 m paver patio drawn and counted: pavers, base, edging, jointing sand and sealer

A level square of pavers outside the back door, and the five things you buy to lay it.
  • One levelDrawn
  • 5Rows to buy
  • Opens as a new projectIn the canvas

One outline, five materials

Outside the kitchen door most gardens want somewhere flat for a table and four chairs, a barbecue and room to walk round them. Five metres by four (16 ft 6 in by 13 ft) seats six without anyone backing onto the lawn. The plan holds only the patio's outline on a Site level; everything listed beneath it is worked from that outline's area and from the length of its edge.

Pavers are counted over the area with a cutting allowance, then the base: crushed stone compacted in layers with a screeded bed of sand on top, which the paver base page gives as one volume. The edge restraint runs round all four sides in sections, polymeric sand fills the joints after the last plate pass, and a sealer goes on once the sand has cured.

Shape it to the garden

Drag a corner and the patio takes the new shape; an L round a corner of the house or a step in plan is still one patio. Its rows are worked over the rectangle that has the same area and the same edge as what you drew, which is how the paver takeoff measures an odd outline, so a long thin patio gets more edging than a square one of equal area.

Where the patio meets the house, the paving should finish at least two brick courses, about 150 mm (6 in), below the damp-proof course or the sill plate, and fall away from the wall so rain runs into the garden. The canvas does not draw falls; set the levels on site with a string line and a spirit level before the base goes down.

Pavers or a poured pad

The first change below pours the same outline as a concrete pad instead, through the room planner's slab: concrete and the steel in it, no base layers and no sand. Comparing the two lists side by side is the quickest way to see which job suits the tools and the help you have; pavers take longer to lay and lift easily for a repair, a poured pad is one day with a mixer and a crew.

A new project with this drawing, in your units; nothing you already have is changed, and nothing is uploaded.

How it is drawn

  1. Add a Site level. A level at ground height for anything outside the walls.
  2. Draw the patio's outline. A 5 × 4 m (16 ft 6 in × 13 ft) rectangle with the site tool, closed on its first corner.
  3. Give it the paver build-up. In Properties, the patio's type is the paver patio: pavers, base, edging, jointing sand and sealer.
  4. Read the list. Five rows, each from its own calculator, worked from the outline's area and edge.

What a professional decides

How deep the base must be for your ground, whether a soft or clay subsoil needs digging out and replacing, and where surface water may drain are decided on site, by a landscaper or a groundworker who has dug a trial hole. A patio that abuts a house wall or crosses a drain run may need your local building office's view before work starts.

Plan of the paver patio, 5 × 4 m template, site, to scale, with imperial lengths.
Site, to scale. The canvas's own SVG export of this drawing.
Plan of the paver patio, 5 × 4 m template, site, to scale, with metric lengths.
Site, to scale. The canvas's own SVG export of this drawing.

Everything to buy

Quantities to order, with each calculator’s own waste. Your own rates go on the lines in My Project.

Outside: drive, patio, deck, fences, walls and beds
Material, and whereQuantity
PaverPV-1, Site236 pavers
Paver Base & SandPV-1, Site2.65 yd³ (gravel base)
Paver EdgingPV-1, Site9 x 8 ft sections
Paver Polymeric SandPV-1, Site3 x 50 lb bags
Paver SealerPV-1, Site3 gallons
Outside: drive, patio, deck, fences, walls and beds
Material, and whereQuantity
PaverPV-1, Site237 pavers
Paver Base & SandPV-1, Site2.03 m³
Paver EdgingPV-1, Site9 x 2.4 m sections
Paver Polymeric SandPV-1, Site3 x 20 kg bags
Paver SealerPV-1, Site11.36 L

What changes if

With a poured concrete pad instead of pavers

  • Paver: 236 pavers → none
  • Paver Base & Sand: 2.65 yd³ (gravel base) → none
  • Paver Edging: 9 x 8 ft sections → none
  • Paver Polymeric Sand: 3 x 50 lb bags → none
  • Paver Sealer: 3 gallons → none
  • Steel in the slab: none → 17 x 20 ft sticks
  • Concrete for the slab: none → 2.92 yd³

With a larger patio, 6 × 4.8 m (19 ft 6 in × 15 ft 6 in)

  • Paver: 236 pavers → 333 pavers
  • Paver Base & Sand: 2.65 yd³ (gravel base) → 3.73 yd³ (gravel base)
  • Paver Edging: 9 x 8 ft sections → 10 x 8 ft sections
  • Paver Polymeric Sand: 3 x 50 lb bags → 4 x 50 lb bags
  • Paver Sealer: 3 gallons → 4 gallons

With a poured concrete pad instead of pavers

  • Paver: 237 pavers → none
  • Paver Base & Sand: 2.03 m³ → none
  • Paver Edging: 9 x 2.4 m sections → none
  • Paver Polymeric Sand: 3 x 20 kg bags → none
  • Paver Sealer: 11.36 L → none
  • Steel in the slab: none → 9 x 12 m sticks
  • Concrete for the slab: none → 2.2 m³

With a larger patio, 6 × 4.8 m (19 ft 6 in × 15 ft 6 in)

  • Paver: 237 pavers → 342 pavers
  • Paver Base & Sand: 2.03 m³ → 2.93 m³
  • Paver Edging: 9 x 2.4 m sections → 10 x 2.4 m sections
  • Paver Polymeric Sand: 3 x 20 kg bags → 4 x 20 kg bags
  • Paver Sealer: 11.36 L → 15.14 L

The calculators behind this list

This page counts materials and does not check strength. The same drawing opens in the Construction Canvas, where every figure can be changed; a house drawn from a form is on the House Estimator. For assistants and scripts: the drawing as JSON, in both unit systems, with a link that opens each.