Basement or foundation wall (poured concrete) takeoff

Concrete, a reinforcement grid, the outside waterproofing, its protection board and the footing drain for a new poured basement or foundation wall, from its length, height and thickness.

Measurements in
4
Trades out
5
Calculators
5
Going in
5of 5
My Project
Not in it

No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.

Dimensions

Give the job once

Every figure on the right follows these, in the units you choose.

Every trade, from those dimensions

then change a dimension, and each line shows what moved.

Every trade's quantity · 5 rows

5 of 5 going in
ItemQuantityOrderWaste / allowance
Concrete for the wall27.36 yd³27.36 yd³no pack size recorded10%
Reinforcement grid across the wall face85 x 20 ft sticks85 x 20 ft sticksalready whole15%
Forms for both faces of the wall2080 sq ft2,080 sq ftno pack size recordednone
Waterproofing on the outside face45.5 gal45.5 galno pack size recordednone
Footing drain pipe13 segments13 segmentsalready wholenone

Every trade's quantity · 5 rows

5 of 5 going in
ItemQuantityOrderWaste / allowance
Concrete for the wall21.12 m³21.12 m³no pack size recorded10%
Reinforcement grid across the wall face44 x 12 m sticks44 x 12 m sticksalready whole15%
Forms for both faces of the wall192 m²192 m²no pack size recordednone
Waterproofing on the outside face168 L168 Lno pack size recordednone
Footing drain pipe14 segments14 segmentsalready wholenone

Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.

5 of 5 trades chosenNot pricedNot in project
Kept on this deviceUnitsImperialMetricMy Projectnot in it yetQuantities only · your own rates · not a structural check

About this job

A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.

A basement wall is a retaining wall with a house on top of it, and the quantities follow three faces of it. The concrete is the wall's length by its height by its thickness. The waterproofing and the board that protects it cover only the part below the finished ground, the outside face from the footing up to grade, which is why the page asks for that depth separately from the wall's height. The drain runs along the foot, round the whole footprint.

The thickness and the steel are not choices this page makes. A basement wall holds back the soil's pressure, which grows with depth and with wet or heavy ground, and its thickness and reinforcement come from the engineer's drawing or the code's tables for your height of backfill. The rebar row here is one grid across the face at the page's opening spacing, a figure to order against when the drawing calls for that grid, never a design.

Waterproofing and damp-proofing are different jobs. A coating that only damp-proofs slows moisture through the wall; a waterproofing system resists water under pressure, and wet ground or a high water table calls for it. The coating row counts the product at its coverage and coats; which product the ground needs is the specification's.

How each line reads

Base
What the calculator gives for these dimensions, before anything is added.
Allowance
Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
Adjusted
The base with its allowance on top.
Order
What to buy: the adjusted figure in whole boards, bags, rolls or lengths.

The order this happens in

Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.

  1. Set out the wall on the footing and check the footing's level and line before the forms go up.
  2. Fix the reinforcement on its chairs and spacers, to the drawing's laps and cover.
  3. Erect and brace the forms, ties at the maker's spacing, and check them plumb.
  4. Pour in lifts, vibrating each, and leave the forms on for the cure the specification asks for.
  5. Strip the forms, make good the tie holes, and let the face dry before the waterproofing goes on.
  6. Apply the waterproofing to the outside face from the footing to grade, in the coats the product asks for.
  7. Protect the waterproofing before any backfill touches it.
  8. Lay the footing drain round the foot of the wall, falling to its outlet, in its gravel and filter fabric.
  9. Backfill in layers, compacting each, once the floor above is in or the wall is braced.

What this takeoff does not cover

  • The wall's design: its thickness, its reinforcement and the backfill height it may carry are the engineer's or the code's figures, and this page takes them as entered.
  • The forms' bracing, brackets and form oil, and the box-out for any window or door in the wall, which the wall formwork page adds when you enter the openings there.
  • The footing under the wall, which the strip footing page counts.
  • The dig, the over-dig and the backfill, whose volumes are the ground's and the working space's, and the gravel round the drain.
  • Insulation on the wall's face, inside or out, and the damp-proof course where a wall above sits on it.
  • The drain's outlet: a sump, a soakaway or a connection to a sewer, each a decision for the ground and the local rules.
  • The board that protects the waterproofing from the backfill. The protection board page counts its sheets from the same face, the wall's length by its depth below ground.

Labour by trade

Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.

Metric opening

Wall length, round the footprint 40 m · Wall height, footing to top 2.4 m · Wall thickness (from the drawing) 200 mm and 1 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer2 labourers + 1 mason + 1 plant operator46 h (23–96)1½ days
Carpenter1 carpenter + 1 labourer192 h (115–480)12 days
Waterproofing operative1 waterproofing operative + 1 labourer132 h (35–288)8½ days
Rated rows370 h (173–864)21½ days

Imperial opening

Wall length, round the footprint 130 ft · Wall height, footing to top 8 ft · Wall thickness (from the drawing) 7.75 in and 1 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer2 labourers + 1 mason + 1 plant operator46 h (23–95)1½ days
Carpenter1 carpenter + 1 labourer193 h (116–483)12 days
Waterproofing operative1 waterproofing operative + 1 labourer132 h (35–288)8½ days
Rated rows371 h (174–866)22 days

Quote check

Been given a quote for this job?

Paste it into the basement wall quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.

  • What it leaves out

    Every line this takeoff has that nothing on the quote reads as.

  • What it adds

    Labour, removal, hire, fees — each named for what it is.

  • What to ask

    One list of questions, ready to copy. Never a verdict.

More takeoffs

Other job takeoffs

All job takeoffs

Frequently asked questions

What does the basement wall takeoff give for a typical job?
Opened at Wall length, round the footprint 40 m · Wall height, footing to top 2.4 m · Wall thickness (from the drawing) 200 mm · Depth below finished ground 2.1 m, it orders: Concrete for the wall, 21.1 m³; Reinforcement grid across the wall face, 44 x 12 m sticks; Forms for both faces of the wall, 192 m²; Waterproofing on the outside face, 168 L; Footing drain pipe, 14 segments. Opened at Wall length, round the footprint 130 ft · Wall height, footing to top 8 ft · Wall thickness (from the drawing) 7.75 in · Depth below finished ground 7 ft: Concrete for the wall, 27.4 yd³; Reinforcement grid across the wall face, 85 x 20 ft sticks; Forms for both faces of the wall, 2,080 sq ft; Waterproofing on the outside face, 45.5 gal; Footing drain pipe, 13 segments. Every figure follows the dimensions you give it.
Which calculators does the basement wall takeoff run?
5 calculators, one to a line: Concrete Calculator, Rebar Calculator, Wall Formwork and Shuttering Calculator (Form Area, Ties, Wales and Studs for a Poured Wall), Basement Wall Waterproofing Coating Coverage Calculator, Perimeter Weeping Tile Pipe Segment Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
What does the basement wall takeoff leave out?
7 things, each named on this page: The wall's design; The forms' bracing, brackets and form oil, and the box-out for any window or door in the wall, which the wall formwork page adds when you enter the openings there; The footing under the wall, which the strip footing page counts; The dig, the over-dig and the backfill, whose volumes are the ground's and the working space's, and the gravel round the drain; Insulation on the wall's face, inside or out, and the damp-proof course where a wall above sits on it; The drain's outlet; The board that protects the waterproofing from the backfill.
Can I check a quote for this job against the takeoff?
Yes. The basement wall quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.