Wall Formwork and Shuttering Calculator (Form Area, Ties, Wales and Studs for a Poured Wall)

The form a poured concrete wall takes on both faces: contact area with stop-ends and box-outs, the tie grid, wales, studs and form sheets.

  • Answers as you type
  • Every formula cited
  • Calculated in your browser
SettingsSettings for this calculationUS
Market
Imperial · sales tax
The run of wall poured in one form, end to end.

Measure along the wall between its free ends, or round the whole footprint for a closed ring of foundation wall. Take a corner as the end of one run and the start of the next.

Tools needed: Tape measure

From the top of the footing to the top of the pour.

The height the concrete stands in the form, which is the height both faces are sheathed to and the length of every stud.

The concrete's thickness, from the drawing.

The gap between the two faces, held by the ties' set length. It sizes the stop-ends and the box-outs round openings; the faces themselves do not depend on it. The page never chooses it.

How many ends of the pour need a bulkhead across them: two for a straight wall, none for a closed ring.

A stop-end, or bulkhead, closes the form across the wall's thickness where the pour stops, at a free end or at a construction joint. A ring of foundation wall round a footprint has none.

Window or door openings boxed out of the pour.

Each opening is a box-out fixed between the two faces: its area comes off both faces and its four sides add form across the wall's thickness. Enter openings of several sizes at their average size, or as separate runs.

Each opening's width as poured.

The box-out's outside width, which is the opening the concrete leaves.

Each opening's height as poured.

With the width, the area each box-out takes off both faces and the length of form round its edge.

How far apart the ties stand along the wall, from your form maker.

The MASCO catalogue's common Jahn layouts space snap ties 24 in (610 mm) along the wall on plywood forms; a steel-framed panel system spaces them much wider, Doka's Framax up to 1.35 m (53 in). The spacing that holds your pour is the maker's table or a formwork designer's.

How far apart the rows of ties are up the wall, from your form maker.

Fresh concrete pushes hardest at the bottom of the form, so a table may close the rows up near the foot; the MASCO catalogue's Jahn layouts use 12 or 16 in (305 or 406 mm) rows, and Doka needs only two rows on a Framax panel up to 3.15 m (10 ft 4 in) of pour. Enter the closest spacing your table gives for a count on the safe side.

How far apart the horizontal wales run up each face.

Wales tie the studs into a straight line and carry them to the ties. Quikrete's wall guide puts them on forms more than 4 or 5 ft (1.2 to 1.5 m) high, no further apart than 30 in (760 mm); a form maker's table may set them closer.

One member in each row, or a pair the tie passes between.

A double wale is two members set apart so the tie's end comes through between them and bears on a bracket or washer across both. Your form detail says which.

The vertical studs behind the sheathing on each face; zero for a panel system that has its own.

Quikrete's wall form frames put 2x4 studs on 16 in (406 mm) centres behind the plywood. A steel or aluminium framed panel carries its own ribs, so enter zero and no studs are counted.

Form contact area

533 sq ft

High confidence

Both faces the full height, 2 stop-ends and 1 box-out; 136 ties on the grid you gave, 17 along by 8 up.

Both faces, openings taken off
516.33 sq ft
Stop-ends across the free ends
10.33 sq ft
Box-outs round the openings
6.35 sq ft
Form ties
136 ties
Tie positions along the wall
17 positions
Tie rows up the wall
8 rows
Wale rows on each face
4 rows
Wales, lineal, both faces
264 ft
Studs, both faces
52 studs
Studs, lineal
416 ft
Form sheets for both faces
17 sheets
Then change the inputs to see how far the answer moves.

Show calculation logic

How this was calculated

Formula source(s)

  • Masons Supply Company (MASCO), Concrete Forming and Accessories catalogue, p. 40, Jahn Forming System: the most common snap tie spacings are 12 in vertical x 24 in horizontal, 16 in x 24 in and 12 in x 12 in, the ties 12 in in from the sides of a 4 ft panel and 6 in from the top and bottom of an 8 ft one; based on 3/4 in Plyform Class I and 2x4 S4S studs, normal-weight concrete, slump no more than 4 in
  • QUIKRETE, Project: Concrete Walls: a straight wall form of 1/2, 5/8 or 3/4 in exterior plywood sheathing, studs, spacers, ties and wales; frames of 2x4s with studs on 16 in centres; wales in forms more than 4 or 5 ft high, spaced no more than 30 in on centre; the form run slightly longer than the wall so a stop board closes its end
  • Doka, Framax Xlife framed formwork brochure: panel heights of 1.35, 2.70 and 3.30 m, form ties up to 1.35 m apart, and only two form-tie layers for pouring heights up to 3.15 m with the 3.30 m panel

Inputs used

Wall Length
33 ft
Wall Height
8 ft
Wall Thickness
7.75 in
Free Ends Closed by a Stop-End
2
Openings Through the Wall
1
Opening Width
35 in
Opening Height
24 in
Tie Spacing Along the Wall
24 in
Tie Spacing Up the Wall
12 in
Wale Spacing Up the Wall
30 in
Wales in Each Row
A single wale
Stud Spacing Along the Wall
16 in

Intermediate steps

Both faces, openings taken off
516.33 sq ft
Stop-ends across the free ends
10.33 sq ft
Box-outs round the openings
6.35 sq ft
Form ties
136 ties
Tie positions along the wall
17 positions
Tie rows up the wall
8 rows
Wale rows on each face
4 rows
Wales, lineal, both faces
264 ft
Studs, both faces
52 studs
Studs, lineal
416 ft
Form sheets for both faces
17 sheets
Final result533.02 sq ft

Confidence note: Both faces the full height, 2 stop-ends and 1 box-out; 136 ties on the grid you gave, 17 along by 8 up.

What this calculation does not cover

  • A count of form, not a formwork design. Whether the sheathing, studs, wales and ties hold the wet concrete depends on the rate of pour, the mix, the temperature and each part's rating; the form maker's tables or a formwork designer decide the spacings you enter, and the pressure and tie spacing pages check them.
  • Ties are a full grid over the face, the first a half spacing in from each end and from the top and bottom. Ties are not taken out where an opening interrupts the grid, and a panel system's tie holes fall where its panels put them, so read the count off the maker's layout where the two differ.
  • One straight run of one height. Corners, pilasters, steps in the footing and a wall that changes height are separate runs; at a corner the outside form runs past the inside one by the wall's thickness, which is not added here.
  • With a manufactured panel system the studs and wales are part of the panels. Set the stud spacing to zero and use the contact area and the tie count; the panel count is the maker's layout.
  • Bracing, kickers, stakes, form oil, chamfer strips, the brackets or wedges that lock each tie, and a walkway at the top of the form are not counted.
  • Sheets are bought for both faces gross, as if each were cut from whole sheets with the openings sawn out; a reused form, or sheets ripped to a wall lower than a sheet, changes that.

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

33 ft2.92 ft7.75 in
Schematic, drawn to the proportions you entered — not to scale on screen.

Part of a bigger job

This trade is one line of a job takeoff. Run the whole job and every other trade comes back with it, off the same measurements.

Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.

Sources checked 2026-10-10 · v1.0.0

Regulatory standards & verification citations3
  1. Masons Supply Company (MASCO), Concrete Forming and Accessories catalogue, p. 40, Jahn Forming System: the most common snap tie spacings are 12 in vertical x 24 in horizontal, 16 in x 24 in and 12 in x 12 in, the ties 12 in in from the sides of a 4 ft panel and 6 in from the top and bottom of an 8 ft one; based on 3/4 in Plyform Class I and 2x4 S4S studs, normal-weight concrete, slump no more than 4 in
  2. QUIKRETE, Project: Concrete Walls: a straight wall form of 1/2, 5/8 or 3/4 in exterior plywood sheathing, studs, spacers, ties and wales; frames of 2x4s with studs on 16 in centres; wales in forms more than 4 or 5 ft high, spaced no more than 30 in on centre; the form run slightly longer than the wall so a stop board closes its end
  3. Doka, Framax Xlife framed formwork brochure: panel heights of 1.35, 2.70 and 3.30 m, form ties up to 1.35 m apart, and only two form-tie layers for pouring heights up to 3.15 m with the 3.30 m panel
Cite this page

Your workspace

Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.

Tools and safety for this job

To erect formwork. Generic types, no brands, no prices.

Protection this work requires

  • Hardwood dust is a recognised carcinogen: extract at the tool and wear a P2/N95 respirator when cutting or sanding indoors.
  • Saws, grinders and breakers run above 85 dB, where hearing damage accumulates and does not recover: defenders or plugs for every cut, not just the long ones.
  • Boards, blocks and bagged material cause most lasting back injuries on small sites: two people or a lifter for full sheets, and never a bag on one shoulder up a ladder.
Show the 6 tools this job needs

Essential

  • Circular saw

  • Claw hammer

  • Spirit level

  • String line and pins

  • Tape measure

Recommended

  • Cordless drill/driver

Also needed as materials: circular saw blades, drill and driver bits.

what each concrete tool is for, and the spec that decides which to buy where one does.

The data behind it: Production rates by operation

How to calculate wall formwork and shuttering (form area, ties, wales and studs for a poured wall) in 13 steps

  1. Wall LengthThe run of wall poured in one form, end to end.
  2. Wall HeightFrom the top of the footing to the top of the pour.
  3. Wall ThicknessThe concrete's thickness, from the drawing.
  4. Free Ends Closed by a Stop-EndHow many ends of the pour need a bulkhead across them: two for a straight wall, none for a closed ring.
  5. Openings Through the WallWindow or door openings boxed out of the pour.
  6. Opening WidthEach opening's width as poured.
  7. Opening HeightEach opening's height as poured.
  8. Tie Spacing Along the WallHow far apart the ties stand along the wall, from your form maker.
  9. Tie Spacing Up the WallHow far apart the rows of ties are up the wall, from your form maker.
  10. Wale Spacing Up the WallHow far apart the horizontal wales run up each face.
  11. Wales in Each RowOne member in each row, or a pair the tie passes between.
  12. Stud Spacing Along the WallThe vertical studs behind the sheathing on each face; zero for a panel system that has its own.
  13. Form contact areaThe tool computes the form contact area from those figures and shows the formula, its sources, and a confidence rating alongside it.

Form contact area by wall length

Page defaults, not your figures above.

Wall LengthForm contact area (sq ft)
20 ft320
30 ft478
40 ft635
50 ft793
60 ft950

Frequently asked questions

How much formwork does a concrete wall need?
Both faces of the wall, the full height, plus a stop-end across each free end and a box-out round each opening. A 10 m wall 2.4 m high (33 by 8 ft) is 48 m² (517 sq ft) of faces before anything is taken off; one opening 900 by 600 mm (35 by 24 in) takes 1.08 m² (11.6 sq ft) off the two faces and adds 0.6 m² (6.5 sq ft) of box-out in a wall 200 mm (8 in) thick. The total touching the concrete is the contact area, the figure formwork is planned and ordered by.
How many form ties will I need?
One at every point of the grid your form maker gives, starting half a spacing in from each end, the top and the bottom. On the MASCO catalogue's common Jahn layout of 24 in along by 12 in up, an 8 ft high wall has eight rows and a tie every 2 ft along it: 128 ties on a 32 ft run. A framed panel system ties far wider apart, so its own layout governs.
Does the page decide the tie spacing?
No. The spacing that holds the wet concrete depends on its pressure, which grows with the rate of pour and falls with temperature and setting time, and on the sheathing, studs and tie rating. Work the pressure out on the formwork pressure page, check the tie grid on the tie spacing page, and take the maker's table over either; this page only counts the grid.
What are wales and studs?
Studs stand upright behind the sheathing and stop it bowing between ties; wales run along the wall across the studs, keeping the face straight and carrying the studs to the ties. On a site-built plywood form both are timber you buy by length, which is why the page gives them in lineal metres or feet. A manufactured panel has them built in.
Preliminary estimate, not certified engineering. This tool produces an indicative quantity calculation for planning purposes only — it is not a certified structural analysis, a guaranteed material takeoff, or a substitute for building department approval. Always verify measurements on-site and have a licensed contractor or structural engineer review any load-bearing, code-sensitive, or safety-critical work before purchasing materials or starting construction. Spotted an arithmetic or standards error? Report it to contact@craftquantities.com with your inputs — a confirmed fix gets a permanent check of its own, so the same mistake cannot come back.