The slab decides, not the datasheet
Every resinous failure worth arguing about traces back to a decision made before the first pail was cracked. Delamination, blistering, osmotic bubbling, edge peel, telegraphed cracking — none of these are coating defects in origin. They are substrate conditions that the coating faithfully reported some weeks later, when the client was already walking on it.
So the sequence a resin applicator works to is not mix, prime, coat, topcoat. It is: find out what the slab is doing, decide whether it can be made to stop doing it, and only then choose a system that suits the answer. A slab that is still giving up water needs a different specification from one that is bone dry but polished to a closed, glassy skin. A slab contaminated to 4 mm (5/32 in) depth with hydraulic oil needs neither — it needs removal.
Two properties govern nearly all of it. Surface profile determines whether the resin has anywhere mechanical to key into, because on a dense trowelled slab chemical adhesion alone is a coin toss. Moisture — both free water and vapour driving up from below — determines whether that key survives, because hydrostatic and osmotic pressure will lift a perfectly bonded film off a perfectly profiled slab if the drive is high enough and the coating is impermeable enough.
Read those two before pricing, before scheduling, before ordering. A resin job that has been sold on square metres of coating and then discovers a 95 percent RH internal reading is no longer the job that was sold. That conversation belongs at survey stage, not on day two of a shutdown.
Slabs that are still wet: reading the drive, not the surface
Concrete does not dry in the way that word suggests to a client. A ground-bearing slab loses water from its upper surface long before its lower half has equilibrated, and a slab on a well-detailed vapour barrier still holds a large reservoir of mix water that has nowhere to go but up. Touch-dry means nothing. What matters is the relative humidity deep in the slab, because that is what will drive vapour into the underside of a cured film.
In-situ probe testing to ASTM F2170, Standard Test Method for Determining Relative Humidity in Concrete Floor Slabs Using in situ Probes, is the method most resin specifications now call for, and it exists precisely because surface tests are easily fooled. Probes are drilled to a specified fraction of the slab depth — different for slabs drying from one side versus two — sealed, and left to equilibrate before reading. The equilibration period is not optional padding; a probe read too early reads the drilling, not the slab. Where surface-based methods are still specified, ASTM F1869, Standard Test Method for Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride, may appear instead, and in UK and European practice BS 8203 and BS 8204 describe hygrometer-based assessment. Which regime applies is a contractual matter — the specification, the manufacturer's warranty conditions and the local standard between them decide the threshold, and those thresholds genuinely differ.
What the number changes is the system, not the effort. Below a manufacturer's stated limit, a standard primer is fine. Above it, the options narrow to a moisture-tolerant epoxy vapour-suppression primer applied at a film thickness the manufacturer states for that RH band, or a change of specification entirely. Applying a normal primer to a wet slab and hoping is how you buy a re-do at your own cost eighteen months later.
Watch for the localised sources that a probe grid misses. A slab cast against a wall with a failed damp-proof course, a floor duct that sweats, an area under a leaking chiller, a section of slab that had standing water during construction. Blistering that appears as a rash in one bay and nowhere else is almost always a local drive, not a batch fault. Map wet zones on the survey drawing and price them separately.
New slabs bring a second timing problem. A slab that lost surface water too fast during finishing has a weak, crazed upper skin that grinds away to reveal a sound layer beneath — good, if you allowed for the extra removal. Assessing evaporative conditions at the time of the pour, when you are coordinating with the concrete contractor on a fast-track programme, tells you how much of that skin to expect.
Slab temperature, air temperature, humidity and wind together decide whether that crazed skin forms at all, which is worth knowing while the pour is still someone else's problem and not yet your removal cost.
The temperature of the fresh concrete, not the air.
The ambient air temperature at the job site.
The relative humidity at the job site.
The wind speed across the concrete surface during placement and finishing.
Estimated evaporation rate
0.11 lb/ft²/hr
Below the critical threshold under these conditions — standard curing practices should be adequate, though conditions can change during a long pour, so re-check if temperature or wind picks up.
- Critical threshold
- 0.2 lb/ft²/hr
They open the calculator with your figures already in it
Concrete Evaporation Rate Calculator: 0.11 lb/ft²/hr — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Add the equipment this sizes
This result is a specification — 0.11 lb/ft²/hr — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.
What this calculation does not cover
- Solar gain is not in the model. The equation reads concrete temperature, air temperature, humidity and wind only, so a slab in full sun and the same slab in shade return an identical rate from identical readings. If the sun is on the pour, take the concrete temperature off the finished surface rather than off the chute, or the answer comes back low.
- Bleed rate is not modelled. Plastic shrinkage cracking is evaporation outrunning the bleed water rising to replace it, and this calculates only the evaporation half. Low-bleed mixes - low water-cement ratio, silica fume, heavy fly ash replacement, high-range water reducers - can crack plastically at rates below the threshold this page flags.
- Nothing about the slab itself is an input. Thickness, subgrade moisture and absorption, restraint from reinforcement and edge conditions, finishing timing, and the curing method actually applied all govern whether cracks form, and none of them reach the calculation.
- This is one moment at one spot. Wind, humidity and temperature move across the hours of a placement and vary across a large slab - funnelled between buildings, faster over a hot deck, calmer behind a windbreak. Re-run it against readings taken at slab level during the pour, not against a forecast from the nearest airport.
- The threshold is a screening line, not a pass/fail verdict and not a curing specification. A rate below it is not a guarantee against cracking and a rate above it is not a prediction of it; the number tells you when to have fogging, evaporation retardant and windbreaks ready, and it does not replace the hot- or cold-weather concreting requirements in your project specification or the supplier's guidance for the mix being placed.
Conditions are favorable for a standard cure, but evaporation risk can change quickly if wind picks up or humidity drops during a long pour — recheck this calculator against updated conditions if the placement runs long.
Slabs that are dry but closed: opening the surface
A power-floated slab that passes every moisture test can still reject a coating, because a burnished surface presents almost no mechanical key and often carries residual curing compound. Resin sitting on that surface bonds to a thin, weak layer that shears away under wheel loads. The remedy is mechanical, and there is no chemical shortcut that reliably substitutes for it.
Concrete Surface Profile, as defined by the International Concrete Repair Institute in Guideline No. 310.2R, Selecting and Specifying Concrete Surface Preparation for Sealers, Coatings, Polymer Overlays, and Concrete Repair, is the language to use here. The CSP chips run from a near-smooth acid-etched texture through progressively more aggressive profiles to heavy scarification. Coating manufacturers state a required CSP band against system thickness — thin roller-applied films need a shallower profile, self-smoothing screeds and broadcast systems need a deeper one. Specifying by CSP number rather than by machine type is what makes the requirement enforceable, since two operators with the same grinder can produce very different surfaces.
Method follows the target. Diamond grinding opens a closed surface and removes curing compound with reasonable dust control on a vacuum-shrouded head. Shot blasting produces a more uniform, deeper profile quickly across open floor, and is the workhorse for large industrial areas — but it rides over undulations rather than correcting them, and it will not reach within a hand's width of walls and columns. Scabbling and scarifying go deeper still and bruise the substrate, which then needs a further pass. Whatever the primary method, budget properly for edge work; the hand-ground perimeter strip is where most programmes lose a shift they did not plan for.
Pull-off adhesion testing to ASTM D7234, Standard Test Method for Pull-Off Adhesion Strength of Coatings on Concrete Using Portable Adhesion Testers, applied to a trial patch, settles arguments before they become claims. A cohesive failure in the concrete is the result you want. A clean break at the interface says the preparation was insufficient, and finding that out on a two-square-metre (about 20 sq ft) sample is a good day.
Dust is not a nuisance, it is a bond breaker. Vacuum, then vacuum the vacuum's path, then check by pressing a clean gloved hand to the floor. Compressed air moves dust sideways into the wet edge you are about to work into.
Slabs that are contaminated: what grinding will not fix
Oil, grease, hydraulic fluid, sugars, food acids and silicone all defeat resin adhesion, and unlike laitance they are not confined to the surface. Contaminants migrate down the pore structure and back up again under heat, which is why a workshop floor can look clean after grinding and then show fisheyes and craters within minutes of the primer going down.
Test rather than assume. Water dropped on the prepared surface should darken it and soak in within a short period; beading indicates residual contamination or an unbroken sealer. Do this in a grid across the area, because contamination is patchy and follows the machine positions, drip trays and traffic paths of the previous occupant.
Degreasing precedes preparation, not the other way round. Grinding contaminated concrete drives oil deeper and smears it across clean areas. Alkaline degreasers with hot water and mechanical agitation, followed by thorough rinsing and drying, will handle surface loading. Deep-set oil in a slab that has been soaking for decades may need the top layer physically removed — and where it cannot be removed, the honest answer is a system chosen for its tolerance, or a different floor finish entirely.
Legacy coatings deserve their own decision. A sound existing epoxy can sometimes be abraded and overcoated, but only after establishing what it is, whether it is bonded, and whether the new system is compatible with it. Old chlorinated rubber, bitumen or a failing polyurethane comes off. Sample-test in a corner; if the existing film lifts in sheets when scraped, the whole floor is coming up regardless of what the tender allowed.
Sawn joints and cracks need resolving at this stage too. Movement joints must be carried through the resin, not coated over — a resin film bridging a moving joint will crack in a straight line and take a strip of coating with it. Static cracks are opened out, filled with a resin mortar and allowed to cure before the main application.
Opened-out cracks and every joint carried through the finish are a filler volume somebody has to order, and length against the width and fill depth you actually cut is the only honest way to reach it.
The total length of the expansion joint.
The width (gap) of the joint.
The depth of sealant or filler material within the joint.
Filler volume needed
1.929 gal
They open the calculator with your figures already in it
Concrete Expansion Joint Filler Calculator: 1.93 gal — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- No waste allowance. This is the bare geometric volume of the joint - it adds nothing for spillage, tooling loss, part-used cartridges, or offcuts when preformed filler board is cut to length and depth. Order in whole cartridges or boards above this figure.
- It assumes a solid rectangular fill across the full width and depth entered. A sealant bead tooled concave over a backer rod holds less than that, and the backer rod itself is neither counted nor sized here.
- This does not size the joint. Whether the width can absorb the movement expected at that location, and whether the fill depth suits the sealant's movement class, come from the specification and the sealant data sheet - the calculator only multiplies the three dimensions you give it.
- One constant cross-section is assumed over the whole run. There is no allowance for a joint that has opened or closed with the season since it was measured, saw-cut wander, a thickened slab edge, intersections and corners, or blockouts around columns and posts.
- Where the joint crosses a fire-rated floor or wall, the fill is a tested and listed fire-rated joint system with its own materials and fill depth, not a volume of ordinary sealant. Nothing here sizes or substitutes for that listing.
Slabs that are out of tolerance: flatness and falls
Surface regularity is the third condition that gets decided before resin is opened, and it is the one clients notice most. A thin roller-applied coating follows every undulation in the substrate; it does not correct anything. A self-smoothing resin screed evens out small deviations but will not build falls or fix a slab that dishes across a bay.
Where a floor must drain, the falls have to exist in the substrate. Resin cannot be laid to a fall by trowelling in the way a sand-cement screed can, except in the heavier trowel-applied polyurethane screeds, and even those have limits on how much fall they can hold before slumping. If a wash-down area needs a fall to gullies and the slab is flat, that is a screeding operation before the resin trade arrives.
Flatness tolerance classes are set by the relevant national standard and by the specification. In the UK, Concrete Society Technical Report 34, Concrete Industrial Ground Floors, is the usual reference for industrial floor flatness, while ASTM E1155 covers the F-number method used in North American practice. Do not assume the incoming slab meets the class the resin specification wants; survey it, record the deviations, and issue them before you take possession of the area. A resin contractor who coats an out-of-tolerance slab has, in practical terms, adopted the tolerance problem.
Where levelling is needed, an underlayment before the resin adds a further cure period and a further moisture consideration to the programme, since the levelling layer itself has to dry down to the resin manufacturer's limit.
The moment levelling becomes the answer it stops being a tolerance argument and becomes a pour depth, a bag count and a drying period that has to sit inside the shutdown window.
The total subfloor area to be leveled.
The average thickness of the self-leveling compound pour across the floor.
SLU volume needed
42.1 gal
Actual SLU consumption depends on subfloor roughness/low spots — an uneven subfloor will consume more material than this average-depth estimate suggests. Order 10-15% extra for irregular subfloors.
They open the calculator with your figures already in it
Self-Leveling Underlayment (SLU) Volume Calculator: 42.08 gal — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- Litres do not buy anything. SLU is sold by the bag, and turning this volume into a bag count needs the product's own yield — the litres one bag makes at its specified water ratio — which runs roughly 12 to 16 litres (3.2 to 4.2 gal) from a 25 kg (55 lb) bag and varies enough between products to shift the bag count by 10% or more on the same floor. Take the yield off the data sheet rather than assuming a density.
- The high spot sets the datum for the whole floor, and this takes an average instead. Every SLU has a minimum thickness it will flow and cure at, and you cannot pour thinner than that over the highest point — so nothing on the floor ends up thinner than that minimum and the low corner takes the minimum plus the whole deviation. There is also a maximum lift, above which the pour must be split or extended with aggregate, and adding aggregate changes the yield again.
- Primer is a separate material with its own coverage rate, and skipping it is how a pour fails rather than how it saves money. A porous slab pulls water out of the compound and pinholes; a sealed or non-porous substrate gives it nothing to grip. Porous slabs often take two coats, and the primer rate per square metre has no relationship to the pour depth calculated above.
Coverage on a real profile, not a flat plane
The moment preparation is signed off, the quantity question changes shape. Manufacturers quote coverage against a theoretical smooth surface, and the surface you have just created is deliberately not smooth. A CSP band opened for a broadcast system has substantially more real area than its plan area, and the primer coat fills that texture before it builds any film at all. Under-ordering here is one of the most common commercial errors on a resin package.
Porosity compounds it. A ground slab that has been opened up drinks the first coat, particularly in areas that were weaker to begin with, and a single primer pass over a thirsty substrate can leave dry patches that show through the finish as dull, absorbent shadows. Plan for the possibility of a second primer application on porous zones and price it as a contingency rather than discovering it mid-shift.
Estimating the base and build coats against the actual area, the stated wet film thickness and a realistic wastage allowance is what keeps the last bay from being coated out of a different batch. Batch variation in pigmented resins is real, and running short on a continuous pour is worse than over-ordering by a pail.
Five layers between the slab and the sheen
- Seal coat — the wearing surface and the only layer anybody sees; gloss level and chemical resistance are bought here, in kits sized by area and pass count Epoxy Floor Coating Calculator
- Body coat — the pigmented build that holds broadcast aggregate and does the film-thickness work, ordered against a coverage rate and a number of coats Epoxy Flooring Coating Coverage Calculator
- Primer — vanishes into the open profile before any film starts to build, and that is precisely what makes datasheet coverage under-predict it on freshly ground concrete Epoxy Primer Coverage Over a Profiled Slab Calculator
- Levelling layer — present only where the incoming slab misses its flatness class, and it brings a pour depth, a volume and a drying period of its own Self-Leveling Underlayment (SLU) Volume Calculator
- Prepared slab — ground or blasted to the profile band the system requires; every moisture and contamination decision taken earlier lives in this surface
Coverage rates quoted on a datasheet assume a smooth plane, so run the numbers against the area and profile you actually created before the order goes in.
The total floor area to be coated.
The floor area one unit of the product covers, per coat.
The total number of coats to be applied.
Epoxy coating needed
2.65 gal
Epoxy coverage is governed by the substrate's profile and porosity, not by the nominal film thickness. A shot-blasted concrete floor with an open profile absorbs far more than the theoretical rate, and it must — that profile is what the coating grips.
They open the calculator with your figures already in it
Epoxy Flooring Coating Coverage Calculator: 2.65 gal — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- Excludes the primer, which most systems require and which is the coat that actually bonds to the concrete.
- Does not include broadcast aggregate for a slip-resistant finish, or the additional topcoat that a broadcast system needs to lock it in.
- Moisture in the slab must be tested before coating. A slab passing vapour will lift an impermeable coating regardless of how well it was applied.
Working the pot life: conditions inside the film
With the substrate resolved, the remaining risks move into the material itself and the air around it. Epoxy and polyurethane systems are exothermic; once mixed, they generate heat, and heat shortens working time non-linearly. A batch that gives twenty-five minutes at one temperature may give half that on a warm afternoon, and a full pail left standing after mixing will run away far faster than the same material spread out on the floor.
Mix to the stated ratio by weight or volume as the manufacturer specifies, at the stated speed, for the stated time, scraping sides and base. Under-mixed resin cures soft in streaks. Over-fast mixing entrains air that surfaces as pinholes in a self-smoothing layer. Decant into a second clean container and remix briefly if the system calls for it — unmixed material clinging to the original pail wall is a recurring source of soft spots.
Substrate temperature must sit above the dew point by the margin the manufacturer states, and that margin exists to stop condensation forming on the surface immediately ahead of the wet edge. A slab is thermally massive and lags air temperature by hours; measuring air temperature and assuming the slab matches it is how amine blush and adhesion failures happen on a cold morning in an unheated warehouse. Take slab temperature directly and calculate dew point from measured air temperature and relative humidity.
Wet film thickness is checked as you go, with a comb, at a frequency that lets you correct before an entire bay is wrong. Applied too thin, an epoxy will not develop its stated chemical resistance and may cure with a patchy sheen. Applied too thick, a fast system can exotherm, discolour, wrinkle or crack. The gauge takes a moment; the remedy for a mis-gauged bay does not.
Ventilation matters for cure and for the people doing the work. Solvent-free systems still demand air movement in enclosed spaces, and confined-space rules apply in pits, tanks and basements regardless of what the resin label says about VOC content.
With slab temperature, film thickness and area now fixed by site conditions, this is the point to convert them into the mixed volume each bay will actually consume.
The total floor area to coat.
2 coats is standard for most DIY epoxy systems.
Epoxy kits needed
2 x 250 sq ft kits
Coverage varies by brand and whether you're adding decorative flakes or a non-slip additive — check your specific kit's coverage rating before buying.
- Area to coat
- 430 sq ft
They open the calculator with your figures already in it
Epoxy Floor Coating Calculator: 2 x 250 sq ft kits — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
What this calculation does not cover
- Assumes one generic kit coverage rating for a two-coat system, and gives you no field for the rating printed on the product you are actually buying. Water-based, solvent-based and 100%-solids kits differ enough that the count can be out by a kit or more — read the label and scale the answer if it disagrees.
- Treats every square foot as taking the same material. Bare, ground, shot-blasted or acid-etched concrete drinks far more on the first coat than a smooth or previously coated slab, and cracks, spalls and open control joints take more again. Patching compound, crack filler and joint sealant are not counted.
- Counts base kits only. A separate primer, a clear topcoat, decorative flakes and non-slip aggregate are bought as their own products, and raising the coat count here simply adds more of the same pigmented kit rather than a topcoat product.
- Carries no waste allowance. This is the bare arithmetic with nothing for material left in the tray and roller, for touch-ups, or for a mixed batch that gels before it reaches the floor — pot life shortens sharply as the slab and the air warm up.
- Says nothing about whether the slab should be coated at all. Epoxy is close to impermeable, so a slab passing moisture vapour will lift the coating off in sheets whatever quantity you buy. A moisture test, and a check for existing sealer or paint, come before this arithmetic; this is a quantity estimate, not a film-thickness or specification check.
Cure, handover and the first six weeks
Resin floors are handed over long before they are fully cured, and that gap causes more disputes than any application defect. Light foot traffic, full foot traffic, wheeled traffic and full chemical resistance each arrive at different times, and every one of those times stretches in cold conditions. A client who parks a loaded forklift on a floor at the light-traffic stage will print the tyres into it permanently, and the argument afterwards is unwinnable without a written handover schedule.
Protect the floor during the cure window as though it were a finished product, because it is. Sheet it against dust and drips from following trades, keep doors closed against wind-driven grit, and hold the temperature — a floor left to cure in an unheated building through a cold snap may never reach its stated hardness.
Inspect and record before demobilising. Photograph the prepared substrate, log moisture readings with their dates and probe locations, keep batch numbers against areas, and file the adhesion test results. When a blister appears in nine months, that file is the difference between a defect investigation and an argument.
Set the maintenance expectation explicitly. Resin floors are chemically resistant, not indestructible; the wrong cleaning chemistry will dull a gloss finish and aggressive scrubbing pads will burnish it unevenly. A short written regime handed to the facilities team, naming what to use and what to avoid, keeps the floor looking like the sample the client approved.
Before the first pail is opened
Six checks that decide whether the system on the specification is still the right system. Complete them at survey, not on the morning of the pour.
- In-situ RH readings, dated and mapped — Probe depth and equilibration period per the governing standard; record probe locations on a drawing so later blistering can be traced.
- Concrete Surface Profile against the system requirement — Compare the prepared floor to ICRI CSP chips, not to a memory of the last job; thicker systems need deeper profile.
- Water-drop absorption grid — Beading means residual oil, sealer or curing compound — degrease before grinding, never after.
- Trial-patch pull-off test — Look for cohesive failure within the concrete; a clean interfacial break means preparation is not finished.
- Slab temperature and dew point, taken together — Slab lags air by hours; the manufacturer's stated margin above dew point applies to the concrete, not the room.
- Movement joints identified and marked — Joints carry through the finish; anything coated over will crack in a straight line and lift the surrounding film.
Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.
