Paving

Open-Graded Bedding: The Layer That Has to Stay Open

Fifty millimetres of single-sized stone that must never be compacted, walked on, or topped up with anything a quarry has not washed.
  • 16 minReading time
  • 9Sections
  • 3Calculators inline
  • Last reviewed

A Bay That Got Firmed Up First

Somebody runs the plate over the screeded bed before the first block goes down. It is not sabotage and it is not laziness — it is thirty years of muscle memory from sand-bedded work, where a loose bed under a wheelbarrow is a nuisance and a firmed one lays quicker and truer. The stone tightens, the screed marks disappear, the bay goes down beautifully, and the foreman notices nothing because there is nothing to notice.

Two months later the ring test at handover reads a fraction of what the bay beside it reads, and the two bays are indistinguishable to look at. Every joint is full of the right stone. The subbase below is the depth on the drawing. What changed is that a layer whose whole function on a permeable pavement is to pass water at a rate nobody ever specifies — because nobody expects it to be the constraint — was consolidated into the throttle for everything underneath it.

That is the difference worth holding on to. On a conventional pavement the laying course beds the unit and absorbs the compaction, and density in it is a virtue. Here the same fifty millimetres does that job and also sits in the flow path between the aperture and the reservoir, and the two requirements pull in opposite directions. Everything below is about the second one, on the assumption that you can already lay blocks.

Single-Sized Is a Purchase Order, Not a Description

Open-graded means a grading curve with the intermediate and fine sizes deliberately absent, so the particles bear on one another and the space between them stays space. ASTM D448, Standard Classification for Sizes of Aggregate for Road and Bridge Construction, is where the size numbers on your order come from, and the reference bedding material in ASCE/T&DI 68-18, Permeable Interlocking Concrete Pavement, is No. 8 at a nominal fifty millimetres screeded thickness. Some unit manufacturers call for No. 89 or No. 9 instead, usually because their aperture is too narrow for No. 8 to fill reliably and they would rather one stone served both the bed and the joint.

Washed is a separate word from the size number and it has to appear on the order in its own right, because a quarry whose day job is dense-graded road base will happily load you material that meets the No. 8 band and still carries the dust it was crushed in. The number that decides whether a load is fit is the material finer than the 75 micrometre sieve, measured by ASTM C117 alongside a sieve analysis to ASTM C136/C136M. Ask for both per delivery and read them at the gate, because a load rejected on the weighbridge costs an hour and a load rejected after screeding costs a bay.

The size numbers in play across a permeable section, with the nominal ranges the ASTM D448 designations refer to — the grading bands themselves are in the standard, not here
DesignationNominal size rangeWhere it sitsWhat goes on the order beyond the number
No. 9No. 4 to No. 16Apertures on units with a narrow jointWashed; confirm the unit maker accepts it before ordering
No. 893/8 in to No. 16Joints, and bedding where the unit maker specifies itWashed; the same stockpile serves both if the detail allows
No. 83/8 in to No. 8The reference bedding course, and most joint fillWashed; sieve analysis and washed-fines result with each load
No. 571 in to No. 4Choker course immediately under the bedWashed; this layer is the filter, so the fines limit is the point of it
No. 2 or No. 32 1/2 in to 1 1/2 in, or 2 in to 1 inReservoir beneath the chokerWashed; placed in lifts and locked, never rolled to a density figure
The size numbers in play across a permeable section, with the nominal ranges the ASTM D448 designations refer to — the grading bands themselves are in the standard, not here

What the Bed Sits On, and Why It Does Not Vanish Into It

Three gradations meet within about a hundred and fifty millimetres of the surface, and only one of the two interfaces is stable on its own. No. 8 laid straight onto No. 2 has nothing to bear on: the small stone finds the large voids under vibration and under traffic, works down over a season or two, and the surface follows it. You get a pavement that has drained perfectly all along and has still developed wheel-path dishing, and the temptation then is to blame the subgrade, which was never touched.

The choker course of No. 57 is what makes those two stones able to see each other. Its own particles are too large to fall into the reservoir voids and too small to swallow the bedding stone, and that is the entire argument for a layer that adds nothing to storage and costs real money. Formal filter criteria exist for soils against geotextiles and are worth knowing, but between standard aggregate size numbers the answer in practice is the published section rather than a calculation you run on the job — which is a good reason not to improvise the stack when a supplier is short of one designation.

It has a second job, and on a wet week it is the more visible one. The choker is the surface you screed off, so it has to be locked before the rails go on it. Single-sized stone has no Proctor curve to chase, so the target is behavioural: run the plate or the roller until the stone stops moving under it and the surface stops printing, then stop. Carry on past that and you are manufacturing the fines you paid the quarry to wash out, and they end up exactly where they do the most harm.

Order it against the same area as the layers below rather than the bedding area, because the choker and everything under it normally run out past the edge restraint while the bed stops dead at it. Density is the other trap: a washed single-sized stone in place is lighter than the crusher-run figure most estimating sheets carry, and using the crusher-run number puts an extra load on the road.

The top hundred and fifty millimetres, taken apart

A permeable block pavement seen close in at the surface: jointing stone standing in the apertures between the units, the units themselves, the screeded single-sized bedding course under them, the choker course that keeps the bed from falling into the reservoir, and the top of the reservoir stone below.
  1. Jointing stone in the apertures — the inlet, filled and refilled through compaction until the joints stop swallowing material, and normally the same designation as the bed Permeable Pavement Joint Fill Stone Calculator
  2. Paving units — set on loose stone and left proud of the finished level, because the bay comes down when the plate goes over it Paver Calculator
  3. Screeded bedding course — placed loose to a constant thickness, never precompacted and never trafficked, since it is both the bed and part of the flow path Open-Graded Bedding Course Stone Calculator
  4. Choker course — the filter between two stones that cannot bear on each other, and the working surface the screed rails are set on Gravel Base Layer Tonnage Calculator
  5. Top of the reservoir stone — coarse single-sized rock whose voids are the storage, and which will accept bedding stone permanently if the choker is left out PICP Permeable Pavement Infiltration Storage Calculator

The choker is the one layer here bought at a compacted thickness rather than a loose one, so it belongs on a straightforward area-by-depth tonnage — enter the quarry's figure for washed single-sized stone rather than the crusher-run default, which will over-order.

The total area to be covered with gravel base.

The target compacted thickness of the base layer.

The in-place density of the base once it is compacted.

Gravel base needed

73.8 tons

Medium confidence

Actual density varies by material gradation and compaction — confirm with your supplier's specific product density for a precise order quantity.

Volume
39.81 yd³
Equivalent in US (short) tons
73.82 tons

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

compacted gravel 6 incompacted gravel 15.24 cmsubgrade

What this calculation does not cover

  • This is a take-off, not a pavement design. It multiplies out whatever compacted thickness you enter; nothing here derives that depth from traffic loading, subgrade strength, drainage or frost depth, which come from a pavement design or your local road authority's standard.
  • Geometry is a flat plan area at one uniform depth. Crown and cross-fall, a formation that steps between thicknesses, a dig that deepens where the subgrade was soft, and edge thickening or haunching at the perimeter all fall outside area x thickness.
  • No waste, spillage or subgrade-loss allowance is applied. The figure is the exact in-place mass, so stone lost into a soft or uneven formation, over-excavation, haul and spread losses, and the tail end of a part-load all sit on top of it.
  • The density field is an in-place compacted density. A supplier's loose bulk density and a weighbridge ticket carrying free moisture are different quantities, and substituting either moves the tonnage: the wetter the delivered material, the less dry stone a given delivered weight puts on the ground.
  • It covers one layer of one material. A base and sub-base of different gradations, a bedding or blinding course, and the geotextile or separation membrane between stone and subgrade are not counted here.

Screeding It Without Consolidating It

Rails first. Steel tube or planed batten laid on the locked choker, spaced so the screed board spans them without any sag in the middle, and set to the underside of the bed — finished block level, less the unit thickness, less the nominal screeded depth, less nothing else. Every millimetre of rail error becomes surface error at a point where the surface can no longer be adjusted, so the rails get levelled off the same datum as the blockwork and checked at both ends and the middle of every run.

The pull is one pass. Tip generously ahead of the board so it is always working into surplus, draw it steadily, and take the surplus away rather than dragging it back over ground you have already screeded. A second pass across a hollow does not fill the hollow; it brings the board down onto the stone either side of it and starts kneading a material that is only doing its job while it is loose. What you are producing is loose stone at a correct thickness, not a smooth stone floor, and a bed that looks slightly unconvincing is usually the right one.

Lifting the rails leaves troughs, and those get filled by hand with the same stone, tipped a little proud and struck off with the edge of a trowel held vertical so it cuts across the surplus. What must not happen is the flat of the trowel going onto it. A troweled patch is a plate compactor with a small footprint, and it will read as a low block at exactly the spacing of your rails, which is the most diagnosable defect on the whole job and the most embarrassing.

Then nobody goes on it. Barrow runs stay on the laid blockwork with plywood down where the wheel turns, stone comes forward in buckets from the face, and the crew works off the pavement they have already built. Where a bay genuinely has to be crossed — a gully to be reached, a level to be checked — a board goes down and comes straight back up, and the print underneath it is reworked loose before the next unit lands on it. Kneeling boards are worse than boots, because they spread the load over exactly the area you least want densified evenly.

Screed only what will be covered before the crew leaves. An open bed overnight collects whatever the site's surface water is carrying, and on a windy afternoon next to a cut-and-fill operation it collects the site itself. A strip screeded ahead of laying is a working convenience that turns into an exposed filter the moment it rains, and the fines that arrive that way sit in the top of the bed where they are least reachable and most effective.

  1. Lock the choker course until the surface stops moving under the plate, and no further.
  2. Set rails on the choker to the underside of the bed, levelled from the same datum as the blockwork.
  3. Tip ahead of the board and pull the bed in a single pass, carrying the surplus off rather than back.
  4. Lift the rails and refill the troughs loose, striking off with a trowel on edge and never on its flat.
  5. Lay from the face onto the loose bed, keeping all traffic on the units already set.
  6. Fill the joints, compact, top up and compact again until the joints stop taking stone.
  7. Screed no further ahead than the day's laying, and cover or close off any bed left open.

Ordering Loose Stone Against a Finished Thickness

The bed is delivered loose and ends up tighter than it was placed, so the quantity has two conversions in it that a sand bed does not. The first is the loose bulk density of the specific gradation from the specific quarry, which is a measurable property — ASTM C29/C29M, Standard Test Method for Bulk Density (Unit Weight) and Voids in Aggregate, is the method behind the figure on a supplier's data sheet — and which is noticeably lower than the dense-graded number most people carry in their heads. The second is the allowance for the course closing up when the units are plate-compacted, and that one is a rule of thumb rather than a published coefficient. No standard gives it, this site will not invent it, and the honest way to use it is as a starting figure to be corrected.

Take the area between the edge restraints, not the excavation. The bed stops at the restraint; the choker and reservoir below usually run past it, which is why their quantities come off a different figure and why a single area used for all three layers is wrong in both directions at once. Where the section changes thickness — a shallower bed under a footway edge, a deeper one where the unit changes — split it and run each zone on its own, because averaging a thickness across a bay averages a surface level too.

Then reconcile on the first bay before the balance of the order is called off. Measure the area you actually screeded and laid, weigh it against what came off the loads, and adjust the allowance to what the site is really consuming. A quarry ten miles away with a slightly different rock will move that figure, and so will a crew that screeds generously. Nobody is going to give you the right number in advance, and the first bay will.

This is the point in the job where a screeded thickness, an area between restraints and two site-measured figures turn into a delivered tonnage — and the point to write down what the allowance was set at, so the first bay can be measured against it rather than argued about.

Plan area of the permeable surface that this screeded course sits under.

Screeded depth of the bedding course before the units go down — the reference detail is a nominal 50 mm (2 in).

Extra loose stone ordered to cover the course closing up when the units are compacted.

Uncompacted bulk density of the delivered gradation, from the supplier's ticket or data sheet.

Delivered bedding stone

9.73 tons

Medium confidence

Both the loose density and the densification allowance are site figures rather than constants. Order the first delivery against this estimate, screed one bay, and reconcile before the balance is called off.

Screeded stone volume to deliver
7.96 yd³
Course volume once the units are bedded and compacted
6.92 yd³
Volume the course loses to densification
1.04 yd³

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

open-graded bedding stone 2 inopen-graded bedding stone 50.8 mmbase

What this calculation does not cover

  • Covers the bedding course only — the No. 57 choker, the subbase and the joint fill are separate gradations bought separately.
  • Assumes a uniform screeded thickness across the whole area; a section that varies in depth has to be split and run per zone.

The Bed and the Joints Are the Same Stone Twice

On most permeable details the bedding and the jointing carry the same size number, which is a convenience and a hazard in the same breath. The convenience is one stockpile, one washed specification and one set of delivery paperwork. The hazard is that a stockpile serving two purposes runs out at the wrong moment, and the joint is the part that gets filled with whatever is nearest when it does. Joints are consumed in rounds rather than in one fill — the first pass, the top-up after the plate, and another after that until they stop taking anything — so the joint quantity is not a footnote to the bedding order and should not be treated as one.

What must never enter those apertures is the shortlist every paving crew already knows and every follow-on trade does not: masonry sand, kiln-dried jointing sand, polymeric sand, stone dust, screenings, sweeping compound. Any of them fills the aperture with a graded fine that will not vacuum back out, and the pavement then weeps instead of draining while looking entirely normal. Say it on the handover sheet, and say it again to whoever is coming back to snag the edges, because the person with the bag of sand is usually trying to help.

Joint fill is a recurring quantity rather than a one-off, so size the first fill, the compaction top-up and the replenishment together here — it is the same stone as the bed, and running short of it mid-bay is how the wrong material gets into the joints.

The plan area of permeable surfacing being laid.

The proportion of the surface made up of joints and apertures.

How deep the stone sits in the joint or aperture.

The delivered bulk density of the jointing aggregate.

Extra stone the joints take as the pavement is vibrated and refilled.

Proportion of the joint volume replaced at each cleaning cycle.

Jointing stone for the first fill

1,940 lb

Medium confidence

Joint fill is the working part of a permeable pavement — it is where the water goes in, and a pavement whose joints have not been kept topped up stops infiltrating long before anything else in the build-up fails. Order the first fill with the pavers, and put the replenishment quantity into the maintenance plan rather than discovering it later.

Loose stone volume in the joints
0.67 yd³
Stone before the compaction allowance
1,685.55 lb
Stone for each replenishment round
84.28 lb
First fill plus one replenishment round
2,022.67 lb

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

What this calculation does not cover

  • Jointing and aperture stone only. The bedding course, the open-graded base and subbase, geotextiles and edge restraints are separate quantities on their own gradations.
  • Does not size the pavement hydraulically. Whether the joints and the reservoir beneath them accept the design storm is an infiltration and storage calculation.

Everything That Can Close the Voids Between Screeding and Compaction

The most concentrated source of fines on the whole job is generated on the pavement, by your own crew, after the bed is down. Wet-saw slurry is rock flour in suspension, and it is produced within a metre of open joints and a screeded bed at the exact moment both are most vulnerable. Cut off the pavement — a bench, a board, a bunded tray, water taken away rather than allowed to find its own level — and never let cut water run back across laid units. A dry-cut station has the same problem in airborne form and needs to sit downwind of the bay, not on it.

Stockpiling is the quiet one. Washed stone tipped onto bare ground is washed stone plus the ground, and the last bucket out of a pile is mostly what was underneath it. Tip on a hardstanding, a sheet or a bay of clean boards, keep the last few hundred millimetres of every pile out of the job, and do not use a bucket that has been in topsoil that morning without washing it. The same applies to the loader ramp: mud tracked onto laid blockwork gets swept into the joints by the next person tidying up.

Neighbouring work is the third route, and it is the one nobody on the paving crew controls. Topsoil placed against the edge, render or brick washings running off a wall above, a wheel wash draining across the corner, an unstabilised slope upslope of the bay. One storm across bare soil delivers more fines than years of service traffic, and it puts them below the surface where sweeping cannot reach. If the pavement has to be built before the surrounding areas are stabilised, it needs a physical barrier or a sacrificial cover, and someone has to own that decision in writing.

Weather sits across all of it. A screeded bed in heavy rain is a filter running at full flow with nothing above it to intercept anything, and a bed that has taken a storm is not repaired by drying out. Plan the day so that stone placed is stone covered, and accept a shorter laying face in poor weather rather than an open bed and a longer one.

Compaction, and the Level You Cannot Get Back

The sequence is fixed and the reason for it is the bed. Units are set on the loose course, joints are filled, and only then does the plate go on — over the units, transmitting through them, closing the bed once with the load spread across the whole block face rather than into a bare stone surface. The bay comes down as that happens, which is why it is laid proud, and how proud is a number confirmed on a trial area against a string line rather than carried in from the last job. A neoprene or rubber-faced pad on the plate protects the block surface and the chamfers, and costs nothing next to a bay of scuffed units.

Work the whole bay including right up to the restraint, and keep back from the leading edge by a course or two so that nothing is compacted while it is still free to move sideways. Then top the joints up and go again, and keep going until the joints stop swallowing material and the surface stops settling under the machine. Blocks that were bedded on a course with a thick patch in it will show themselves during this, not before, because a thick spot closes further than a thin one and the difference only appears once the load has been applied.

None of it can be corrected from above. A block sitting low against a kerb, a threshold or a gully cannot be lifted and packed, because the packing under one unit will behave differently from the screeded bed under its neighbours and the difference reappears within a winter. The correction is to lift the affected area back to the bed, re-screed it and relay, and the argument about whether it needs doing belongs to the surface tolerance in the specification — which is worth reading before laying rather than after, since it is also what the ring test locations will be chosen around.

Proving the Bed Is Still Open

Test the finished pavement and write the result down. ASTM C1781/C1781M, Standard Test Method for Surface Infiltration Rate of Permeable Unit Pavement Systems, is the ring test for this surface, and a new pavement will return a number far above any design intensity, which is the point: the value is not the pass mark, it is the baseline everything later gets compared against. Take it at several locations, mark them on a plan, and include the bay that was laid in the worst weather rather than only the one that looks best.

That baseline is also the diagnostic. When a reading is low, the first question is whether the blockage is in the joint or below the units, and there is a cheap way to find out: replace the top of the joint fill in the test location and retest. If the rate comes back, the fines were surface-bound and a vacuum or regenerative-air sweeping regime will manage them. If it does not, the restriction is below the blocks — a bed that was compacted, contaminated, or laid without a choker under it — and no maintenance regime reaches it. That distinction is worth establishing while the installer is still on site.

So the paperwork is part of the work. Record the designation and the quarry, the washed specification and the delivery tickets that went with it, the screeded thickness and the allowance the order was built on, the baseline readings with their locations, and the prohibition on sand in the joints. A bay that was firmed up with a plate before laying looks exactly like the bay next to it for the rest of its life, and the only evidence that ever distinguishes them is the record you kept and the number you took on the day.

Settle these before the first load of No. 8 is called off

The bedding order is small, and it is the one on a permeable job most likely to be got wrong twice — once on the gradation and once on the conversion from loose stone to a finished thickness. Fix the material and the area first; the tonnage follows.

  • Size number, washed, one source — Order by the ASTM D448 designation the unit manufacturer and the section call for, with washed stated separately, and keep the bed and the joints on the same stockpile.
  • Sieve analysis and washed fines with each load — ASTM C136/C136M for the grading and ASTM C117 for the material finer than 75 micrometres; read them at the gate, because rejection after screeding is an excavation.
  • Area between the edge restraints — The bed stops at the restraint while the choker and reservoir run past it, so the three layers do not share one area figure.
  • Screeded thickness, and the datum the rails are set from — Nominal fifty millimetres in the ASCE/T&DI 68-18 reference detail; rail level is finished block level less unit thickness less that depth, checked at both ends and mid-run.
  • Loose bulk density and the closing-up allowance — Density to ASTM C29/C29M from the quarry supplying the actual gradation; the allowance is a rule of thumb that gets corrected against what the first bay consumed.
  • Cutting station, stockpile stand and barrow route — All three are decisions about where fines are produced and where they land, and all three are far cheaper to fix on the plan than on the pavement.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • ASTM D448, Standard Classification for Sizes of Aggregate for Road and Bridge Construction
  • ASTM C136/C136M, Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates
  • ASTM C117, Standard Test Method for Materials Finer than 75-µm (No. 200) Sieve in Mineral Aggregates by Washing
  • ASTM C29/C29M, Standard Test Method for Bulk Density (Unit Weight) and Voids in Aggregate
  • ASTM C1781/C1781M, Standard Test Method for Surface Infiltration Rate of Permeable Unit Pavement Systems
  • ASTM C936/C936M, Standard Specification for Solid Concrete Interlocking Paving Units
  • ASCE/T&DI 68-18, Permeable Interlocking Concrete Pavement
  • CIRIA C753, The SuDS Manual

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.