The job
Modelled, not recorded. Every figure here is the answer the Concrete Calculator gives for these inputs, written down in both unit systems and re-run whenever the site is built. No job was carried out, so there is no measured overrun on this page.
The job is a freestanding single garage at the back of a suburban block, or a carport being closed in: a square slab, 6 m each way, poured over a compacted crushed-rock base with a sheet of reinforcing mesh lifted on bar chairs in the middle of it. It is a size that is too big to mix by hand and small enough that the order is a single truck, so the volume has to be right the first time.
The thickness is the calculator's opening 10 cm, a common figure for a lightly loaded residential garage slab, and it is kept that way only to show the method. Whether a given slab can be that thin, what grade of concrete it needs and whether it wants thickened edges is decided by the site class of the soil and the engineer's design under AS 2870, the standard an Australian reader's drawings will refer to for house slabs; this page counts what the drawing says and sizes nothing.
The mesh is where the market matters. The calculator offers the sheet sizes sold in the UK, North America and Australia, and an Australian reader's page opens on the local one, 6.0 × 2.4 m (19.7 × 7.9 ft), Australian standard. A merchant sells the sheet in grades such as SL72 or SL82, a designation that names the bar and its spacing; the grade is the engineer's to specify, and every grade in a range comes in the same sheet, so the count below holds whichever is drawn.
Open this job in the calculator
Embed this calculator on your own page
Every figure is worked again by the real calculators, in both unit systems; nothing is priced and nothing is saved until you press Use as my project.
The inputs, exactly as entered
| Input | Value | Why |
|---|---|---|
| Slab Length | 6 m (19.69 ft) | Measured between the inside faces of the formwork, the edge the concrete will actually take, not between the pegs outside the boards. |
| Slab Width | 6 m (19.69 ft) | Taken square to the length, and checked across both diagonals: two equal diagonals are the proof the forms are square before anything is ordered. |
| Slab Thickness | 10 cm (3.94 in) | Left at the calculator's own default. |
| Waste Factor (%) | 10 | Left at the calculator's own default. |
| Sub-base depth (0 for none) | 10 cm (3.94 in) | Left at the calculator's own default. |
| Sub-base compaction allowance (%) | 20 | Left at the calculator's own default. |
| Form board depth (its face width) | 150 mm (5.91 in) | Left at the calculator's own default. |
| Reinforcement to count | Welded mesh sheets | Set to count mesh, so the calculator adds the sheet layout to the volume; with no reinforcement chosen it counts concrete alone. |
| Mesh sheet size | 6.0 × 2.4 m (19.7 × 7.9 ft), Australian standard | The sheet an Australian reader's page opens on, the size a local merchant stocks; a different sheet changes the number of rows and laps, not the concrete. |
| Mesh lap at each join | 200 mm (7.87 in) | Left at the calculator's own default. |
The working, step by step
1. Volume (no waste)
3.6 m³ (4.71 yd³)
Length, width and thickness multiply, each in metres first, to the slab as drawn: 3.6 m³ (4.71 yd³). It is the solid the formwork encloses and nothing more, the number a plan gives before anyone has dug a base or set a board.
2. Volume with waste factor
3.96 m³ (5.18 yd³)
The calculator adds its allowance as a share of that solid, 10 per cent, to reach 3.96 m³ (5.18 yd³). The allowance pays for a base that is a little low in places, boards that bow under wet concrete and what stays in the barrow and the pump line. This is the figure to order against.
3. Edge forms, the run round the slab
24 m (78.74 ft)
Around the slab the formwork runs the full perimeter, 24 m (78.74 ft), and with boards as deep as the calculator's default the edge is one board high. Bought in whole lengths and cut at the corners, that is 8 x 4.8 m boards, a count worth checking against the timber lengths the local yard carries.
4. Rows of mesh sheets across the slab
3 rows
The mesh is laid with the sheet's long side along the slab, so one sheet spans each row here, and the rows are lapped side by side until they cover the width: 3 rows. Each lap uses up part of a sheet's width, which is why the rows add up to more than the slab's width divided by one sheet.
5. Mesh sheets, lapped, cut sheets counted whole
3 sheets
Rows times sheets per row gives the order, 3 sheets, with any sheet that has to be trimmed counted as a whole one, since a merchant sells whole sheets. Trim the last row to the edge with bolt cutters, keeping the cover the engineer asks for between the steel and the formwork.
Estimated concrete needed
3.96 m³
5.18 yd³
Two orders come out of this page. The concrete, 3.96 m³, goes to the batching plant, which delivers in its own increments with a minimum load, so the figure is an estimate of what the slab takes rather than what the docket will show. The mesh, 3 sheets in the local sheet, goes to the steel merchant with the grade the drawing names, along with bar chairs to hold it at its height. The calculator's confidence is high: the inputs are ordinary for a garage, which says nothing about the ground beneath it.
What to buy
| Quantity | Figure | What it is for |
|---|---|---|
| Estimated concrete needed | 3.96 m³ (5.18 yd³) | The concrete to order from the batching plant, in cubic metres, at the grade the drawing calls for. |
| Mesh sheets, lapped, cut sheets counted whole | 3 sheets | Sheets of mesh in the Australian size, in the grade the engineer specifies; buy the bar chairs to support them at the same time. |
The allowance, and what it does here
The 10 per cent allowance belongs to the concrete only, and it is applied once to the whole volume, which takes 3.6 m³ as drawn to 3.96 m³ to order. The mesh has no percentage on it, and should not have one: its spare material is already inside the count, in the laps between rows and in the sheets that are trimmed at the edge and counted whole. The bag rows the calculator prints, 339 bags of the larger metric bag, are worth reading once as a warning; a slab this size is a truck job, not a mixer job.
The common mistake
Laying the sheets edge to edge with no lap
Mesh only works as one sheet if neighbouring sheets overlap, so that the wires of one lie over the wires of the next and share the load across the join. A count made by dividing the slab's area by a sheet's area assumes the sheets butt together, and it comes up short by roughly the laps, so the last strip of the slab is left with no steel, or the sheets are pulled apart on the day to make them reach. The calculator counts with the lap it is given; the lap itself, and how many cross-wires it must cover, is set by the engineer and the reinforcement standard the drawing cites, so read it off the drawing rather than guessing it.
Change the job, and see what moves
The same slab, poured thicker
Slab Thickness: 12.5 cm (4.92 in) → 4.95 m³ (6.47 yd³)
Pour the same slab at 12.5 cm, as a drawing might for a heavier vehicle or a softer site class, and the concrete rises to 4.95 m³. The mesh count stays at 3 sheets: thickness changes the volume and the height of the chairs, never the area of steel the sheets cover.
The same slab, with a smaller allowance
Waste Factor (%): 5 → 3.78 m³ (4.94 yd³)
Trim the allowance to 5 per cent on a base that has been laser-levelled and boxed in steel forms, and the order drops to 3.78 m³. It is a modest saving and a real risk: the shortfall, if the base was not as flat as it looked, is found with the truck already gone.
What to run next
- Welded Wire Mesh Calculator — Reinforcing Mesh Sheets for a Slab
For a slab that is not square, or a lap other than the one used here, the mesh calculator lays the sheets both ways and reports the cuts.
- Gravel Base Layer Tonnage Calculator
The crushed-rock base under the slab is ordered by the tonne, compacted to the depth the drawing gives, on the same day as the concrete.
- Concrete Formwork Calculator
The edge boards, pegs and braces that hold the pour are counted around the same perimeter, and they decide whether the allowance was enough.
Sources
The method and every constant behind these figures belong to the Concrete Calculator, version 1.2.0, last verified 2026-10-31. It rests on:
- Standard formula: cubic yards = length (ft) x width (ft) x thickness (ft) / 27
- An 80 lb bag of pre-mixed concrete yields approximately 0.6 cubic feet once mixed; 60 lb about 0.45 and 40 lb about 0.30 cubic feet — 0.0075 cubic feet per pound of dry mix, which puts 20, 25 and 30 kg bags at about 9.4, 11.7 and 14.0 litres
- Reinforcing bar mass from its nominal diameter, 7850 kg/m³ x π d² / 4: 10 mm 0.617 kg/m, 12 mm 0.888 kg/m (BS 4449 tables); #4 0.668 lb/ft, #5 1.043 lb/ft (ASTM A615 Table 1); bars counted as floor(clear span / spacing) + 1 each way
- Sub-base stone weighed loose at 1,550 kg/m³ (97 lb/ft³), crushed stone in the site's bulk-density table (lib/materials/bulk-density.ts); compaction allowances of 15 to 25% are common supplier and specification practice for crushed stone and hardcore
Frequently asked questions
- How much concrete does a 6 by 6 m garage slab need?
- At 10 cm thick the slab is 3.6 m³, and with the calculator's 10 per cent allowance the order is 3.96 m³. The batching plant rounds that to its own increments; the thickness itself is the engineer's.
- How many sheets of mesh does the slab take in Australia?
- In the Australian sheet, 6.0 × 2.4 m (19.7 × 7.9 ft), Australian standard, lapped as the calculator counts it, 3 sheets: 3 rows of 1 sheet each, with a trimmed sheet counted whole.
- Does a thicker slab need more mesh?
- Not more sheets. The sheets cover the slab's area, so a thicker pour of 12.5 cm still takes 3 sheets; it may take a heavier grade or taller chairs, which the engineer decides.