Calculator example · Concrete

A cast-in-place concrete stair rising 2.8 m (9.19 ft) on a waist slab, formed on both sides

The flight takes 1.04 m³ (1.36 yd³) of concrete with the allowance. The page follows the risers into the section, the section into the concrete and the forms, and the drawing's bars into a count and a weight.
  • 1.04 m³The answer
  • 6Steps shown
  • UK, metric firstWritten for

The job

Modelled, not recorded. Every figure here is the answer the Concrete Stair Calculator (Cast Flight: Concrete, Formwork and Rebar) gives for these inputs, written down in both unit systems and re-run whenever the site is built. No job was carried out, so there is no measured overrun on this page.

The rise is 2.8 m (9.19 ft) from the finished lower floor to the upper one, and the stair is cast in place between forms, as a basement or a plant-room stair often is. It stands free of the walls, so both sides are formed. The flight is 1 m (3.28 ft) wide.

The waist, the bars, their spacing and the cover come from the engineer's drawing: a waist of 150 mm (5.91 in), main bars along the flight at 150 mm (5.91 in) and distribution bars across at 250 mm (9.84 in), with 25 mm (0.98 in) of cover. The calculator counts what that drawing makes and never says whether it is strong enough.

The riser count comes from the target riser as the stair rise and run page divides it, so the steps here are the ones that page and its code readout give for the same rise.

Open this job in the calculator

Embed this calculator on your own page

Every figure is worked again by the real calculators, in both unit systems; nothing is priced and nothing is saved until you press Use as my project.

The inputs, exactly as entered

Every input the calculator takes for this job, and why it is what it is
InputValueWhy
Floor-to-floor rise2.8 m (9.19 ft)Finished floor to finished floor, with any screed still to come counted in.
Riser to aim for18.5 cm (7.28 in)A comfortable riser inside the English limits; the count is the whole number nearest it.
Going26 cm (10.24 in)The step on plan; cast treads have no nosing here.
Width of the flight1 m (3.28 ft)The concrete's width, side form to side form.
Waist thickness150 mm (5.91 in)From the engineer's drawing, measured square to the soffit.
Landing at the head0 m (0 ft)No landing: the flight meets the upper floor's edge; the variant adds one.
Landing slab thickness150 mm (5.91 in)Used only when there is a landing.
Sides cast against a wallNone: formed both sidesFree-standing, so both sides are formed.
Cover to the bars25 mm (0.98 in)From the drawing.
Main bars along the flight12 mmFrom the drawing.
Main bar spacing150 mm (5.91 in)From the drawing.
Distribution bars across10 mmFrom the drawing.
Distribution bar spacing250 mm (9.84 in)From the drawing.
Anchorage at each end300 mm (11.81 in)How far the drawing carries each main bar into the floors.
Allowance on the concrete5Spill and over-break on the concrete.
Code for the readoutUK — Approved Document KAn English building, so the readout uses Approved Document K.

The working, step by step

  1. 1. Risers

    15 risers

    The rise into the whole number of risers nearest the target: 15 risers of 186.7 mm (7.35 in), with 14 treads cast on top of the waist and the upper floor as the last step. The pitch is 35.68 °.

  2. 2. Concrete, as the section measures

    0.99 m³ (1.29 yd³)

    The section is the steps' triangles above the line through their roots and the waist below it, measured square to the soffit; its area times the width is 0.99 m³ (1.29 yd³). The allowance on top gives the headline, the figure to order.

  3. 3. Soffit formwork

    4.16 m² (44.82 sq ft)

    The soffit runs 4.16 m (13.66 ft) along the slope, and its form is that times the width: 4.16 m² (44.82 sq ft). A riser form at every step adds 2.8 m² (30.14 sq ft), and the two sides, each the whole section, add 1.98 m² (21.27 sq ft).

  4. 4. Main bars

    7 bars

    Main bars along the flight at the drawing's spacing across the width less the covers: 7 bars, each 4.76 m (15.63 ft) with the anchorage carried into the floors at both ends.

  5. 5. Distribution bars

    20 bars

    Distribution bars across, at their spacing along the main bars: 20 bars of 0.95 m (3.12 ft). By their nominal diameters the bars weigh 41.32 kg (91.1 lb) in all.

  6. 6. Formwork in all

    8.94 m² (96.24 sq ft)

    All the faces a form touches come to 8.94 m² (96.24 sq ft): the figure to set the form ply and the release agent against, before the props and ledgers, which are the form's own design.

Concrete to order, with the allowance

1.04 m³

1.36 yd³

The headline is the concrete to order, 1.04 m³, the section's volume with the allowance. The bars and the forms are counted as the drawing and the section give them, with nothing added, because both are ordered to a cutting list rather than by the load.

What to buy

The quantities this job comes to, and what each is for
QuantityFigureWhat it is for
Concrete to order, with the allowance1.04 m³ (1.36 yd³)Ready-mix to order for the flight, with the allowance.
Formwork in all8.94 m² (96.24 sq ft)Form faces in contact with the concrete; props and ledgers are extra.
Steel in the bars41.32 kg (91.1 lb)Bar to order by weight before laps, chairs and bending allowance.

The allowance, and what it does here

The 5 per cent allowance goes on the concrete only, for spill and for the over-break where a form bows. The bars and the forms are counted as they are, because a bar schedule and a form list are cut to length rather than poured.

The common mistake

Ordering the steps' volume and forgetting the waist

A flight of steps looks like a stack of triangles, and the triangles alone are well under half the concrete in a cast stair: the waist slab under them carries the rest. An order worked from the steps alone runs out with the soffit half full and a cold joint across the flight. Order from the section, not from the steps, and check the waist on the drawing before the truck is booked.

Change the job, and see what moves

  • The same flight, with a landing cast at the head

    Landing at the head: 1 m (3.28 ft) → 1.23 m³ (1.61 yd³)

    Cast a landing at the head as well and the order rises to 1.23 m³, with the main bars running on to 5.81 m each. The landing adds its slab, its own soffit and an edge form.

  • The same flight, cast between two walls

    Sides cast against a wall: Both sides between walls → 1.04 m³ (1.36 yd³)

    Cast the same flight between two walls and the concrete stays at 1.04 m³, but the side forms go: the formwork falls to 6.96 m².

What to run next

Sources

The method and every constant behind these figures belong to the Concrete Stair Calculator (Cast Flight: Concrete, Formwork and Rebar), version 1.0.0, last verified 2026-10-24. It rests on:

  • A cast flight's section: the steps' triangles of riser x going / 2 above the line through their roots, and the waist below it measured square to the soffit, so the soffit lies waist / cos(pitch) below the roots; the area by the shoelace formula, times the width, is the concrete
  • Reinforcing bar mass from its nominal diameter, 7850 kg/m³ x π d² / 4: 10 mm 0.617 kg/m, 12 mm 0.888 kg/m (BS 4449 tables); #4 0.668 lb/ft, #5 1.043 lb/ft (ASTM A615 Table 1)
  • US: IRC 2024 R311.7.5 — risers at most 7.75 in and treads at least 10 in; UK: Approved Document K Table 1.1 for a private stair; Australia: NCC Housing Provisions Table 11.2.2a; Canada: NBC 2020 Tables 9.8.4.1 and 9.8.4.2 for a private stair, as the stair rise and run page checks them

Frequently asked questions

How much concrete does a cast stair rising 2.8 m take?
On a waist of 150 mm and 1 m wide, 0.99 m³ as the section measures, or 1.04 m³ to order with the allowance.
How much formwork does it need?
The soffit, a form at every riser and the two sides: 8.94 m² of form faces in all, 1.98 m² of it on the sides.
How much reinforcement is in it?
The bars the drawing calls for: 7 bars main bars and 20 bars distribution bars, 41.32 kg by their nominal diameters, before laps and chairs.