Concrete Stair Calculator (Cast Flight: Concrete, Formwork and Rebar)

Count a cast concrete stair from its rise: the concrete in the steps and waist, the formwork faces, and your drawing's bars by count and weight.

Concrete to order, with the allowance: 1.45 yd³ for Floor-to-floor rise 9 ft, Riser to aim for 7.25 in and Going 10.25 in, the page's opening figures; on the metric page, 2.8 m, 18.5 cm and 26 cm give 1.04 m³. Sources are cited below.

Rebar is reinforcement bar in the UK.

  • Answers as you type
  • 3 sources cited
  • Calculated in your browser
SettingsSettings for this calculationUS
Market
Imperial · sales tax
Who is doing the work?

Waste is set to 5% by hand. Pick a tier above to replace it, or keep your own figure.

Finished floor to finished floor.

The risers share it equally; a screed or tile still to be laid is part of it.

The rise is divided into the whole number of risers nearest this.

The stair rise and run page's division, so both pages count the same risers.

Front of one riser to the front of the next, on plan.

Cast treads have no nosing unless the form gives them one; the going is the step on plan.

Side to side, the concrete's width.

Every volume, form and bar count runs across this width.

The slab under the steps, measured square to the soffit: from your engineer's drawing.

Never chosen here. It sets how far the soffit sits below the steps' roots, and so the concrete and the bars' length.

Its length along the run; 0 when the flight meets the upper floor's edge.

A landing cast with the flight adds its slab, its soffit and an edge form, and carries the main bars on to its end.

Used when there is a landing.

From the drawing; the landing's soffit meets the flight's at the head.

A side against a wall needs no form.

Each side form is the flight's whole section in area.

From the drawing or your exposure rule.

Taken off each side of the width for the bars' length across, and off the landing's end.

The size your drawing calls for.

Its nominal diameter gives its weight per length; nothing here chooses it.

Centre to centre across the width.

From the drawing.

The bars across the flight, on the main bars.

From the drawing.

Centre to centre along the main bars.

From the drawing.

How far each main bar carries past the flight into the floor or landing.

From the drawing; added at both ends of every main bar.

Spill and over-break, as a percentage of the concrete.

Added to the volume ordered; the bars and forms are counted as they are.

The limits the riser and the going are read against.

Limits checked, not compliance; the building official decides.

Concrete to order, with the allowance

1.45 yd³

High confidence

WITHIN THE LIMITS CHECKED — US IRC 2024: riser height 7.20 in (183 mm) and tread depth 10.25 in (260 mm) are inside the limits this calculator checks. That is not a compliance determination: headroom, handrails, guards, nosings and width are not checked, and the building control body or inspector decides. The waist, the bars and the cover are the figures you entered; nothing here says they are adequate.

Risers
15 risers
Rise of each step
7.2 in · 7 3/16 in
Treads
14 treads
Pitch
35.09 °
Concrete, as the section measures
1.38 yd³
Soffit length along the slope
13.55 ft · 13 ft 6 5/8 in
Soffit formwork
47.43 sq ft
Riser forms
31.5 sq ft
Side forms
21.26 sq ft
Formwork in all
100.18 sq ft
Main bars
7 bars
Main bar length, each
15.51 ft · 15 ft 6 1/8 in
Distribution bars
20 bars
Distribution bar length, each
3.33 ft · 3 ft 4 in
Steel in the bars
92.39 lb
Then change the inputs to see how far the answer moves.

Show calculation logic

How this was calculated

Formula source(s)

  • A cast flight's section: the steps' triangles of riser x going / 2 above the line through their roots, and the waist below it measured square to the soffit, so the soffit lies waist / cos(pitch) below the roots; the area by the shoelace formula, times the width, is the concrete
  • Reinforcing bar mass from its nominal diameter, 7850 kg/m³ x π d² / 4: 10 mm 0.617 kg/m, 12 mm 0.888 kg/m (BS 4449 tables); #4 0.668 lb/ft, #5 1.043 lb/ft (ASTM A615 Table 1)
  • US: IRC 2024 R311.7.5 — risers at most 7.75 in and treads at least 10 in; UK: Approved Document K Table 1.1 for a private stair; Australia: NCC Housing Provisions Table 11.2.2a; Canada: NBC 2020 Tables 9.8.4.1 and 9.8.4.2 for a private stair, as the stair rise and run page checks them

Inputs used

Floor-to-floor rise
9 ft
Riser to aim for
7.25 in
Going
10.25 in
Width of the flight
3.5 ft
Waist thickness
6 in
Landing at the head
0 ft
Landing slab thickness
6 in
Sides cast against a wall
None: formed both sides
Cover to the bars
1 in
Main bars along the flight
12 mm
Main bar spacing
6 in
Distribution bars across
10 mm
Distribution bar spacing
9.75 in
Anchorage at each end
11.75 in
Allowance on the concrete
5
Code for the readout
US — IRC 2024

Intermediate steps

Risers
15 risers
Rise of each step
7.2 in
Treads
14 treads
Pitch
35.09 °
Concrete, as the section measures
1.38 yd³
Soffit length along the slope
13.55 ft
Soffit formwork
47.43 sq ft
Riser forms
31.5 sq ft
Side forms
21.26 sq ft
Formwork in all
100.18 sq ft
Main bars
7 bars
Main bar length, each
15.51 ft
Distribution bars
20 bars
Distribution bar length, each
3.33 ft
Steel in the bars
92.39 lb
Final result1.45 yd³

Confidence note: WITHIN THE LIMITS CHECKED — US IRC 2024: riser height 7.20 in (183 mm) and tread depth 10.25 in (260 mm) are inside the limits this calculator checks. That is not a compliance determination: headroom, handrails, guards, nosings and width are not checked, and the building control body or inspector decides. The waist, the bars and the cover are the figures you entered; nothing here says they are adequate.

What this calculation does not cover

  • The waist, the bars, their spacing and the cover are yours or your engineer's: this counts the concrete, the formwork and the steel they make, and never says whether the flight is strong enough or the bars are the right ones.
  • One straight flight on a waist slab, with or without a landing at the head. Solid steps cast on the ground are counted on the concrete steps volume page; a flight cast against a wall on one side has that side's form left out.
  • Bars are counted as main bars along the flight and distribution bars across it, each at its spacing, with the anchorage entered at both ends of the main bars; laps, starter bars, chairs, the landing's own top mat and the bending allowance are not added.
  • Formwork is the area of the faces a form touches. Props, ledgers, the nosing form detail and the release agent are not counted, and the form is not designed.

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

6 in3.5 ft8 at 6 in
Schematic, drawn to the proportions you entered — not to scale on screen.

Part of a bigger job

This trade is one line of a job takeoff. Run the whole job and every other trade comes back with it, off the same measurements.

Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.

Sources checked 2026-10-24 · 9 test vectors · v1.0.0

Regulatory standards & verification citations3
  1. A cast flight's section: the steps' triangles of riser x going / 2 above the line through their roots, and the waist below it measured square to the soffit, so the soffit lies waist / cos(pitch) below the roots; the area by the shoelace formula, times the width, is the concrete
  2. Reinforcing bar mass from its nominal diameter, 7850 kg/m³ x π d² / 4: 10 mm 0.617 kg/m, 12 mm 0.888 kg/m (BS 4449 tables); #4 0.668 lb/ft, #5 1.043 lb/ft (ASTM A615 Table 1)
  3. US: IRC 2024 R311.7.5 — risers at most 7.75 in and treads at least 10 in; UK: Approved Document K Table 1.1 for a private stair; Australia: NCC Housing Provisions Table 11.2.2a; Canada: NBC 2020 Tables 9.8.4.1 and 9.8.4.2 for a private stair, as the stair rise and run page checks them

Which documents these citations point at

  • International Residential Code — 2024 R311.7.5 (United States)One- and two-family dwellings and townhouses up to three storeys — structure, fire safety, energy, plumbing, mechanical and electrical in a single document.
  • Approved Documents to the Building Regulations (England) — K (United Kingdom)Practical guidance on meeting the Building Regulations, one lettered part per subject — Part A structure, Part B fire, Part K protection from falling, Part L conservation of fuel and power, and the rest.

Standards referenced: ASTM A615 (ASTM International, United States).

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments. This site holds no adoption data for any authority, so check what is in force with the authority where you build. Any section cited above without an edition should be checked against the edition in force where you build. What it would take to know.

Cite this page

Your workspace

Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.

Tools and safety for this job

To place and finish concrete, erect formwork and saw-cut cured concrete. Generic types, no brands, no prices.

Protection this work requires

  • Cutting or grinding concrete, masonry, screed, tile or fibre-cement board releases respirable silica: cut wet or extract at the tool, and wear a P2/N95 respirator at minimum — a nuisance dust mask does not filter it.
  • Hardwood dust is a recognised carcinogen: extract at the tool and wear a P2/N95 respirator when cutting or sanding indoors.
  • Wet cement and lime burn skin and eyes painlessly until the damage is done: waterproof gloves to EN 374, safety glasses whenever the mix can splash, and never kneel in wet mix in permeable trousers.
  • Saws, grinders and breakers run above 85 dB, where hearing damage accumulates and does not recover: defenders or plugs for every cut, not just the long ones.
  • Breakers and grinders cause permanent nerve damage: limit continuous trigger time, keep hands warm, and stop if fingers tingle or blanch.
  • Boards, blocks and bagged material cause most lasting back injuries on small sites: two people or a lifter for full sheets, and never a bag on one shoulder up a ladder.
Show the 17 tools this job needs

Essential

  • Angle grinder

  • Bull float and edger

  • Circular saw

  • Claw hammer

  • Dust extractor or vacuum with a fine filter

  • Screed bar or rail

  • Shovel and spade

  • Spirit level

  • String line and pins

  • Tape measure

  • Wheelbarrow

Recommended

  • Chalk line

  • Cordless drill/driver

  • Floor or cut-off saw

  • Plate compactor

  • SDS rotary hammer

Optional

  • Power float

Also needed as materials: chalk refill, circular saw blades, cutting and diamond discs, diamond blades, drill and driver bits, SDS bits and chisels.

what each concrete tool is for, and the spec that decides which to buy where one does.

The cast flight drawn and listed

A scaled section and plan of the flight with its waist and bars, and the pour list: the concrete, the soffit, riser and side forms, and the bars by count and weight, with the code readout.

Worked for one job: A cast concrete flight on a waist slab

The data behind it: Bulk densities of construction materials

Every stair type, the planner and the templates: the Stairs hub

How to calculate concrete stair (cast flight: concrete, formwork and rebar) in 17 steps

  1. Floor-to-floor riseFinished floor to finished floor.
  2. Riser to aim forThe rise is divided into the whole number of risers nearest this.
  3. GoingFront of one riser to the front of the next, on plan.
  4. Width of the flightSide to side, the concrete's width.
  5. Waist thicknessThe slab under the steps, measured square to the soffit: from your engineer's drawing.
  6. Landing at the headIts length along the run; 0 when the flight meets the upper floor's edge.
  7. Landing slab thicknessUsed when there is a landing.
  8. Sides cast against a wallA side against a wall needs no form.
  9. Cover to the barsFrom the drawing or your exposure rule.
  10. Main bars along the flightThe size your drawing calls for.
  11. Main bar spacingCentre to centre across the width.
  12. Distribution bars acrossThe bars across the flight, on the main bars.
  13. Distribution bar spacingCentre to centre along the main bars.
  14. Anchorage at each endHow far each main bar carries past the flight into the floor or landing.
  15. Allowance on the concreteSpill and over-break, as a percentage of the concrete.
  16. Code for the readoutThe limits the riser and the going are read against.
  17. Concrete to order, with the allowanceThe tool computes the concrete to order, with the allowance from those figures and shows the formula, its sources, and a confidence rating alongside it.

Concrete to order, with the allowance by floor-to-floor rise

Page defaults, not your figures above.

Floor-to-floor riseConcrete to order, with the allowance (yd³)
4 ft0.54
6 ft0.85
8 ft1.16
10 ft1.47
12 ft1.83
14 ft2.14
16 ft2.46

Frequently asked questions

How much concrete is in a cast stair?
The steps and the waist slab under them. A 2.80 m (9 ft 2 in) flight of 15 risers on a 260 mm (10.24 in) going, 1.0 m (3 ft 3 in) wide on a 150 mm (5.9 in) waist, is about 0.99 m³ (1.29 yd³) as cast, before any allowance for spill.
How much formwork does a concrete stair need?
The soffit under the waist, a riser form at every step and a side form each side that is not against a wall. That same flight takes about 4.2 m² (45 sq ft) of soffit, 2.8 m² (30 sq ft) of riser forms and 2.0 m² (21 sq ft) of side forms.
Does this page size the reinforcement?
No. The waist, the bar sizes, their spacing and the cover are taken from your drawing; the page counts the bars that choice makes and weighs them by their nominal diameter.
Preliminary estimate, not certified engineering. This tool produces an indicative quantity calculation for planning purposes only — it is not a certified structural analysis, a guaranteed material takeoff, or a substitute for building department approval. Always verify measurements on-site and have a licensed contractor or structural engineer review any load-bearing, code-sensitive, or safety-critical work before purchasing materials or starting construction. Spotted an arithmetic or standards error? Report it to contact@craftquantities.com with your inputs — a confirmed fix gets a permanent check of its own, so the same mistake cannot come back.