SettingsSettings for this calculationUS
Waste is set to 5% by hand. Pick a tier above to replace it, or keep your own figure.
Steel flights on stringers, or cast flights and slabs.
The flights and landings are split the same way for both.
Where the stair turns.
A quarter landing is the stair's width square; a half landing twice the width by once.
Finished floor below to finished floor above.
Measured on site with the finishes each floor will carry; the risers share it equally.
The rise per step you want.
Rounded up into whole risers, so none is taller, as the L- and U-shaped page counts them.
The same on every flight.
Your code sets the least it may be.
Width of the flights, and of the landings' sides.
A steel stair's treads span between the stringers' flanges.
Up to the first landing.
The rest go in the flight after it.
Straight sections, or a strip folded up the steps.
A zigzag stringer follows every riser and tread; its developed length and bends are counted.
Your section, never chosen or checked here.
Also frames the steel landings' edges.
Two at the sides; a third under a wide stair.
Your engineer's count.
Checker plate.
Weighed at 7850 kg/m³.
Tread past its riser.
Deepens each tread plate.
At each end, for the connection.
Added to each channel stringer's cut length.
Upper floor to the ceiling below.
Sets the opening with the headroom.
Clear height over the flights.
Opens on the IRC's 6 ft 8 in.
On the steel weight, the concrete and the bars.
Offcuts and over-pour.
The code the flights, landings and headroom are read against.
Figures compared with the code's own, never compliance: the building official or building control body decides. Where this page does not read a code's figures it says so rather than guessing them.
Risers
15 risers
WITHIN THE LIMITS CHECKED — US IRC 2024: riser height 7.20 in (183 mm) and tread depth 10.25 in (260 mm) are inside the limits this calculator checks. That is not a compliance determination: headroom, handrails, guards, nosings and width are not checked, and the building control body or inspector decides. On this page, headroom is read on its own: the opening is worked out for 2032 mm (80.0 in) of headroom over the pitch line, at or above the 6 ft 8 in (2032 mm) of IRC 2024 R311.7.2; the headroom as built is measured on site. Each landing is 1067 mm (42.00 in) long in the direction of travel, at or over the 36 in (914 mm) of IRC R311.7.6.
- Riser height
- 7.2 in · 7 3/16 in
- Flights
- 2 flights
- Landings
- 1 landing
- Steel, all flights and landings, with the allowance
- 1,330.53 lb
- Longest stringer as cut
- 8.33 ft · 8 ft 4 in
- Tread plates
- 13 plates
- Floor opening, plan area
- 46.82 sq ft
They open the calculator with your figures already in it
Steel and Concrete L- and U-Shaped Stair Calculator (Landings, Channel or Zigzag Stringers, Waist and Bars): 15 risers — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Show calculation logicHide calculation logic
How this was calculated
Formula source(s)
- Flights and landings split as this site's L- and U-shaped stair page splits them; each flight worked as its steel stair and concrete stair pages work one (sections from BS EN 10365 and the American standard channel tables, steel at 7850 kg/m³)
- Zigzag stringer: a strip folded riser, tread, riser…, its developed length n x riser + (n - 1) x going and 2n - 1 bends; mass = length x strip depth x thickness x 7850 kg/m³
- US: IRC R311.7.5 (riser at most 7 3/4 in, tread at least 10 in), R311.7.6 (landings at least 36 in in the direction of travel), R311.7.2 (headroom 6 ft 8 in); UK: Approved Document K section 1; Australia: NCC Housing Provisions 11.2.2 and 11.2.5; Canada: NBC 9.8.4 and 9.8.6, as the L- and U-shaped stair page reads them
Inputs used
- Material
- Steel stringers
- Shape
- L — a quarter landing
- Total Rise (floor to floor)
- 9 ft
- Riser You Are Aiming For
- 7.25 in
- Going (nosing to nosing)
- 10.25 in
- Stair width
- 3.5 ft
- Risers in the first flight
- 8
- Risers in the middle flight
- 3
- Stringers (steel)
- Rolled section (channel or flat)
- Stringer section
- PFC 200 × 75 (23.4 kg/m)
- Stringers per flight
- 2
- Zigzag strip depth
- 7.75 in
- Zigzag plate thickness
- 0.31 in
- Tread and landing plate thickness
- 0.25 in
- Nosing
- 1 in
- Stringer end allowance
- 4 in
- Waist (concrete)
- 6 in
- Landing slab thickness
- 6 in
- Cover
- 1 in
- Main bar diameter
- 0.5 in
- Main bar spacing
- 6 in
- Distribution bar diameter
- 0.39 in
- Distribution bar spacing
- 9.75 in
- Anchorage at each end
- 11.75 in
- Floor depth at the opening
- 9.75 in
- Headroom to keep
- 80 in
- Allowance (%)
- 5
- Code for the readout
- US — IRC
Intermediate steps
- Riser height
- 7.2 in
- Flights
- 2 flights
- Landings
- 1 landing
- Steel, all flights and landings, with the allowance
- 1,330.53 lb
- Longest stringer as cut
- 8.33 ft
- Tread plates
- 13 plates
- Floor opening, plan area
- 46.82 sq ft
Confidence note: WITHIN THE LIMITS CHECKED — US IRC 2024: riser height 7.20 in (183 mm) and tread depth 10.25 in (260 mm) are inside the limits this calculator checks. That is not a compliance determination: headroom, handrails, guards, nosings and width are not checked, and the building control body or inspector decides. On this page, headroom is read on its own: the opening is worked out for 2032 mm (80.0 in) of headroom over the pitch line, at or above the 6 ft 8 in (2032 mm) of IRC 2024 R311.7.2; the headroom as built is measured on site. Each landing is 1067 mm (42.00 in) long in the direction of travel, at or over the 36 in (914 mm) of IRC R311.7.6.
What this calculation does not cover
- This counts and draws a steel or cast stair that turns; it does not approve it. The riser, going, landings and headroom are read against your code by the L- and U-shaped page's own readout; your building official decides.
- Sections, plate and zigzag thicknesses, waists and bars are your engineer's: entered here, never chosen or checked, and nothing here says a member, a weld, a connection or a bar is adequate.
- A zigzag stringer's length is its folded strip along its line; the bend allowance at each fold is the fabricator's, and the plate it is cut from is the strip's depth wide.
- Landings are flat plates or slabs the stair's width square (a half landing twice the width by once); posts, hangers and the landing's bearing on walls are not counted.
Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.
Sources checked 2026-11-14 · 9 test vectors · v1.0.0
Regulatory standards & verification citations3
- Flights and landings split as this site's L- and U-shaped stair page splits them; each flight worked as its steel stair and concrete stair pages work one (sections from BS EN 10365 and the American standard channel tables, steel at 7850 kg/m³)
- Zigzag stringer: a strip folded riser, tread, riser…, its developed length n x riser + (n - 1) x going and 2n - 1 bends; mass = length x strip depth x thickness x 7850 kg/m³
- US: IRC R311.7.5 (riser at most 7 3/4 in, tread at least 10 in), R311.7.6 (landings at least 36 in in the direction of travel), R311.7.2 (headroom 6 ft 8 in); UK: Approved Document K section 1; Australia: NCC Housing Provisions 11.2.2 and 11.2.5; Canada: NBC 9.8.4 and 9.8.6, as the L- and U-shaped stair page reads them
Which documents these citations point at
- International Residential Code — R311.7.5 (United States)One- and two-family dwellings and townhouses up to three storeys — structure, fire safety, energy, plumbing, mechanical and electrical in a single document.
- Approved Documents to the Building Regulations (England) — K (United Kingdom)Practical guidance on meeting the Building Regulations, one lettered part per subject — Part A structure, Part B fire, Part K protection from falling, Part L conservation of fuel and power, and the rest.
Standards referenced: BS EN 10365 (European Committee for Standardization, as published in the UK by BSI, European (EN)).
A code or standard has force only where a jurisdiction has adopted it, usually with local amendments. This site holds no adoption data for any authority, so check what is in force with the authority where you build. Any section cited above without an edition should be checked against the edition in force where you build. What it would take to know.
Cite this page
Your workspace
Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.
Tools and safety for this job
To place and finish concrete, erect formwork and saw-cut cured concrete. Generic types, no brands, no prices.
Protection this work requires
- Cutting or grinding concrete, masonry, screed, tile or fibre-cement board releases respirable silica: cut wet or extract at the tool, and wear a P2/N95 respirator at minimum — a nuisance dust mask does not filter it.
- Hardwood dust is a recognised carcinogen: extract at the tool and wear a P2/N95 respirator when cutting or sanding indoors.
- Wet cement and lime burn skin and eyes painlessly until the damage is done: waterproof gloves to EN 374, safety glasses whenever the mix can splash, and never kneel in wet mix in permeable trousers.
- Saws, grinders and breakers run above 85 dB, where hearing damage accumulates and does not recover: defenders or plugs for every cut, not just the long ones.
- Breakers and grinders cause permanent nerve damage: limit continuous trigger time, keep hands warm, and stop if fingers tingle or blanch.
- Boards, blocks and bagged material cause most lasting back injuries on small sites: two people or a lifter for full sheets, and never a bag on one shoulder up a ladder.
Show the 17 tools this job needsHide tools
Essential
Angle grinder
Bull float and edger
Circular saw
Claw hammer
Dust extractor or vacuum with a fine filter
Screed bar or rail
Shovel and spade
Spirit level
String line and pins
Tape measure
Wheelbarrow
Recommended
Chalk line
Cordless drill/driver
Floor or cut-off saw
Plate compactor
SDS rotary hammer
Optional
Power float
Also needed as materials: chalk refill, circular saw blades, cutting and diamond discs, diamond blades, drill and driver bits, SDS bits and chisels.
what each concrete tool is for, and the spec that decides which to buy where one does.
The stair drawn, its flights and landings listed