Damp remediation and replastering takeoff

Carry out the remedy a damp specification names on the walls it names: dust sheets and a taped doorway, the plaster hacked off a band to the height the specification sets, a tanking slurry where that is the remedy, the band skimmed over its backing coat, the skirting (baseboard) refitted along it, the room repainted wall to wall once the wall has dried, and the skip, with the survey, an injected damp-proof course (damp course) or a membrane, the backing coat, the radiator and the sockets listed, and nothing prescribed or promised.

Measurements in
8
Trades out
5
Calculators
5
Going in
5of 5
My Project
Not in it

No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.

Dimensions

Give the job once

Every figure on the right follows these, in the units you choose.

Step 1 of 2

Choose the build-up

Each layer changes the materials below; the dimensions stay the same.

The remedy your specification names

Calculators behind the other choices:

Every trade, from those dimensions

then change a dimension, and each line shows what moved.

Every trade's quantity · 5 rows

5 of 5 going in
ItemQuantityOrderWaste / allowance
Masking and protection materials3 items3 itemsno pack size recordednone
Skim finish coat (plaster)53.59 lb53.59 lbno pack size recorded15%
Skirting (baseboard)28.6 linear ft28.6 linear ftno pack size recorded10%
Painting and decorating (decoration): emulsion to decorate the room, after a mist coat1.94 gal1.94 galno pack size recordednone
Skip (dumpster)0.5617 yd³0.5617 yd³no pack size recordednone

Every trade's quantity · 5 rows

5 of 5 going in
ItemQuantityOrderWaste / allowance
Masking and protection materials3 items3 itemsno pack size recordednone
Skim finish coat (plaster)23 kg23 kgno pack size recorded15%
Skirting (baseboard)8.8 m8.8 mno pack size recorded10%
Painting and decorating (decoration): emulsion to decorate the room, after a mist coat7.01 L7.01 Lno pack size recordednone
Skip (dumpster)0.4 m³0.4 m³no pack size recordednone

Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.

5 of 5 trades chosenNot pricedNot in project
Kept on this deviceUnitsImperialMetricMy Projectnot in it yetQuantities only · your own rates · not a structural check

About this job

A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.

Damp in a wall has more than one cause, and each has its own answer. Moisture can rise from the ground through a wall whose damp-proof course (damp course) has failed or was never built in; rain or ground water can come through from outside where a path or a flower bed is banked above that course, or render or pointing bridges it; a pipe can leak inside the wall; or the air in the room can condense on a cold surface. The salts water carries up a wall stay behind in its plaster and draw moisture out of the air, so an old wall can read wet on a surface meter whether or not damp is still rising. That is why the work begins with a survey into the depth of the wall and a written specification, and why this page lists that survey as the surveyor's and never says which remedy a wall needs.

The page measures what follows from the specification, and asks for the two figures it sets: the length of wall treated and the height the plaster comes off to and goes back up to. The hacking off, a tanking slurry, a membrane, the backing coat and the skim all cover that band, the length times the height, and the skirting runs along its length. The decoration does not: a wall replastered along its foot is painted from the skirting to the ceiling, and round the rest of the room so the new plaster does not show, so the paint row follows the room you give. The remedy is one of three, whichever your specification names, and the page opens on an injected course in every market; that is a starting point for the figures, not a recommendation.

What goes back on a treated wall matters as much as the treatment. Plaster that has held salts comes off rather than being painted over, and a gypsum plaster laid straight onto a treated wall takes the salts up and breaks down again, so the backing coat is the salt-resistant coat, renovating plaster or sand and cement the specification names, with plastic or stainless beads at the corners, and a skim over it. New plaster takes time to dry before it can be decorated, and the wall is read with a meter before any paint goes on. The radiator, the sockets and the switches come off the treated walls and go back on the new plaster; where an injected course is cut into a wall shared with a neighbour in England and Wales, the notice the Party Wall etc. Act 1996 may require is the owner's to serve.

How each line reads

Base
What the calculator gives for these dimensions, before anything is added.
Allowance
Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
Adjusted
The base with its allowance on top.
Order
What to buy: the adjusted figure in whole boards, bags, rolls or lengths.

The order this happens in

Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.

  1. Have the walls surveyed and the cause found, and the specification written down: which walls, which remedy, the height the plaster comes off to, the backing coat, and how long the wall dries before it is decorated; have any old textured coating or boarding on those walls checked for asbestos before it is touched.
  2. Agree who puts right what the survey flags outside, a bed banked against the wall, a leaking gutter or downpipe, render bridging the course or a blocked air brick (foundation vent), since the treatment inside does not answer any of them.
  3. Clear and sheet the room, tape a sheet across the doorway, isolate the circuits feeding the sockets and switches on the treated walls and have the electrician take them off and make the cable ends safe, and drain down and lift off any radiator hanging on those walls.
  4. Take off the skirting, then hack the plaster off the band back to the masonry to the height set and brush the wall down; where salts or damp show higher once the plaster is off, stop and have the extra area agreed before going on.
  5. Lay the remedy specified: drill the bed joint and inject the cream along the treated walls, making good the holes on an outside face; or brush or trowel the slurry onto the masonry in its coats; or plug the membrane to the wall with its joints and every plug sealed as its maker details.
  6. Lay the backing coat the specification names over the band, with plastic or stainless beads at the corners, or dry-line the membrane on its plugs or battens; let it set, then skim it.
  7. Leave the wall to dry for as long as the specification gives, reading it with a meter, then fix the treated skirting along its foot, rehang the radiator and refill the system, and have the sockets and switches refitted and tested.
  8. Decorate the room's walls in the paint the specification names, clear the skip and the sheets, and hand over the survey, the specification, the installer's paperwork and the electrician's certificate.

What this takeoff does not cover

  • Diagnosing the cause and choosing what answers it: the surveyor's, listed as its own item.
  • Ground and path levels, gutters, downpipes and render that bridge the DPC, and their repair.
  • Leaking pipes, and condensation and its causes in the room's air.
  • Decay in joists, lintels, floors or timber grounds (flagged).
  • A drained channel and sump at the foot of the floor.
  • Moving a socket to a new place.
  • Any promise that the wall stays dry.
  • The party structure notice to a neighbour, and any award or agreement under the 1996 Act, which are the owner's to serve and settle.
  • Dehumidifiers and temporary heaters beyond the job's own.

Labour by trade

Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.

Metric opening

Room length 4.5 m · Room width 3.5 m · Wall height, floor to ceiling 2.4 m and 5 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer1.0 h (0.5–2.5)under a quarter of a day
Plasterer1 plasterer1.4 h (0.8–2.8)under a quarter of a day
Carpenter1 carpenter1.6 h (0.9–3.5)under a quarter of a day
Painter1 painter6.3 h (3.5–14)1 day
In all10 h (5.7–23)1½ days

Imperial opening

Room length 15 ft · Room width 11.5 ft · Wall height, floor to ceiling 8 ft and 5 more of the page's opening figures

TradeCrewPerson-hoursWorking days
Labourer1 labourer1.1 h (0.5–2.6)under a quarter of a day
Plasterer1 plasterer1.4 h (0.8–3.0)under a quarter of a day
Carpenter1 carpenter1.6 h (0.9–3.5)under a quarter of a day
Painter1 painter6.5 h (3.6–14)1 day
In all11 h (5.9–23)1½ days

Quote check

Been given a quote for this job?

Paste it into the damp proofing and replastering quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.

  • What it leaves out

    Every line this takeoff has that nothing on the quote reads as.

  • What it adds

    Labour, removal, hire, fees — each named for what it is.

  • What to ask

    One list of questions, ready to copy. Never a verdict.

More takeoffs

Other job takeoffs

All job takeoffs

Frequently asked questions

What does the damp proofing and replastering takeoff give for a typical job?
Opened at Room length 4.5 m · Room width 3.5 m · Wall height, floor to ceiling 2.4 m · Length of the walls treated 8 m · Height of the strip-out and replastering, as the specification sets it 1 m · Doors 1 · Windows 1 · Loose waste, as a depth over the band 50 mm, it orders: Masking and protection materials, 3 items; Skim finish coat (plaster), 23 kg; Skirting (baseboard), 8.8 m; Painting and decorating (decoration): emulsion to decorate the room, after a mist coat, 7.01 L; Skip (dumpster), 0.4 m³. Opened at Room length 15 ft · Room width 11.5 ft · Wall height, floor to ceiling 8 ft · Length of the walls treated 26 ft · Height of the strip-out and replastering, as the specification sets it 3.5 ft · Doors 1 · Windows 1 · Loose waste, as a depth over the band 2 in: Masking and protection materials, 3 items; Skim finish coat (plaster), 53.6 lb; Skirting (baseboard), 28.6 linear ft; Painting and decorating (decoration): emulsion to decorate the room, after a mist coat, 1.94 gal; Skip (dumpster), 0.56 yd³. Every figure follows the dimensions you give it.
Which calculators does the damp proofing and replastering takeoff run?
5 calculators, one to a line: Masking and Protection Materials Calculator, Skim Coat Plaster Calculator, Baseboard & Trim Calculator, Paint Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
What does the damp proofing and replastering takeoff leave out?
9 things, each named on this page: Diagnosing the cause and choosing what answers it; Ground and path levels, gutters, downpipes and render that bridge the DPC, and their repair; Leaking pipes, and condensation and its causes in the room's air; Decay in joists, lintels, floors or timber grounds (flagged); A drained channel and sump at the foot of the floor; Moving a socket to a new place; Any promise that the wall stays dry; The party structure notice to a neighbour, and any award or agreement under the 1996 Act, which are the owner's to serve and settle; Dehumidifiers and temporary heaters beyond the job's own.
Can I check a quote for this job against the takeoff?
Yes. The damp proofing and replastering quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.