Glazing

Spacing Structural Glass Fins and Glazing Bars

A fin count and a bar count both fall out of a spacing somebody else approves — and that one number then fixes the pane, the bite and the lift.
  • 17 minReading time
  • 8Sections
  • 5Calculators inline
  • Last reviewed

Eleven Fins, None of Them Drawn

The request for information lands before anything is ordered and it asks for three things: fin centres, fin makeup, and the setting-out dimension from the west return to the centre of the first fin. The fabricator wants them because a toughening and lamination slot has to be booked and the autoclave does not care that the design is not finished. On the architect's general arrangement the same wall is 14.4 metres of unbroken line between two hairlines, 4.2 metres from finished floor to the underside of the soffit, and there is nothing on the sheet that answers any of the three questions.

That absence is the normal condition, not a failure of the drawing. A glass fin is a beam that has been made invisible on purpose, and the whole point of a frameless wall is that the structure holding it up does not read as structure. What the elevation hides is a plain load path: the panes span horizontally from fin to fin, each fin spans vertically from the slab to the soffit, and the fins deliver the whole wind load of the elevation into two lines of restraint at top and bottom. Take the fins out of the drawing and none of that stops being true; it just stops being visible to whoever is reading the sheet.

The spacing is the hinge every other decision turns on. It sets how wide a pane has to span, which sets the glass makeup; it sets how much wall each fin collects, which sets the fin section and the anchorage; it sets the pane width, which sets what one piece weighs and therefore whether the wall goes in on suckers, on a glazing robot, or on a crane through a hole left in the roof. Change the centres by a hundred millimetres late in the job and all four of those move with it, which is why the number wants settling before anybody prices access.

The Centres Are an Output, and Not Yours

The maximum spacing is a structural result. It comes from a facade or structural engineer working from the site's design wind pressure — the components and cladding provisions of ASCE/SEI 7, Minimum Design Loads and Associated Criteria for Buildings and Other Structures, or BS EN 1991-1-4, Eurocode 1: Actions on Structures — Wind Actions — against a proposed glass makeup and a proposed fin section. The calculator further down this page takes that maximum as an input and does not pretend otherwise. Entering a number you liked the look of produces a count that is arithmetically correct and structurally meaningless.

Two checks fight over the answer. The pane is the first: its load resistance for a given size, thickness, glass type and support condition is established by ASTM E1300, Standard Practice for Determining Load Resistance of Glass in Buildings, or by BS EN 16612, which does the same job by calculation. A pane held on two vertical edges only is a one-way span, and bending stress in a one-way span goes with the square of the clear distance between supports. Widening the centres from 1.5 to 1.6 metres is not a seven per cent change; it is nearer fourteen per cent more stress in a material with no yield and no warning.

The fin is the second check, and it is the awkward one. A deep, thin plate loaded out of plane along one edge is a lateral-torsional buckling problem before it is a bending problem, and the restraint that solves it usually comes from the panes themselves through the joint — which means the fin's capacity depends on the spacing you are trying to derive from it. CEN/TS 19100, Design of Glass Structures, and the Institution of Structural Engineers' Structural Use of Glass in Buildings are where that iteration is set out. It converges quickly, but it converges somewhere the person doing the take-off does not get to choose.

Then there is what happens after something breaks. Fins are laminated so that a fractured ply leaves residual capacity behind it — ASTM C1172, Standard Specification for Laminated Architectural Flat Glass, and BS EN 14449 cover the product. The question the engineer has to answer is whether the wall survives losing one fin, because if the panes are required to bridge two bays in that condition the spacing that governs is the post-breakage one, not the intact one. A wall that can bridge a lost fin at 1.44 metre centres gets accepted with far less argument than one that cannot.

One last thing keeps the number from being single-valued: design pressure is not constant across an elevation. The end zones of a wall and the strips near a roof edge carry higher components and cladding pressures than the field does. That leaves three honest options — tighten the fins at the ends, thicken the glass at the ends, or design the whole wall for the corner value and accept the cost. What is not available is a single field spacing quietly applied to a corner it was never checked for.

Which document settles which number on a supported glass wall
The numberWhat settles itWhere it is written
Design wind pressure on the wallBuilding geometry, height, exposure and the zone the panel sits inASCE/SEI 7 components and cladding provisions, or BS EN 1991-1-4
Pane thickness and makeupPane size, support condition, glass type and the pressure aboveASTM E1300, or BS EN 16612 by calculation
Fin depth, thickness and stabilitySpan, out-of-plane load, and the restraint the panes give the compression edgeCEN/TS 19100, and the IStructE Structural Use of Glass in Buildings
Structural silicone biteThe pane's short span, the design pressure, and the sealant's tested long-term allowableASTM C1401, with ASTM C1184 for the sealant itself
What is permitted overheadWhether the glazing is sloped, what is below it, and the makeup proposedIBC Section 2405, Sloped Glazing and Skylights
Which document settles which number on a supported glass wall

Ten Gaps, Eleven Fins, and the One at the End You May Not Need

With a maximum of 1.5 metres approved and 14.4 metres to cover, the division gives 9.6, which rounds up to ten gaps, and ten gaps need eleven fins. The centres you will actually set out to are then 14.4 divided by ten, or 1.44 metres — not the 1.5 you were given. That distinction is worth writing on the drawing, because the maximum is a limit and the built centre is a dimension, and a site engineer setting out to the limit will run out of wall.

The plus-one assumes a fin standing at each end of the run, and that assumption is wrong often enough to check every time. If the wall dies into masonry returns or steel columns at both ends and those elements restrain the pane edge, the end supports already exist and the order is nine fins, not eleven. One return and one free end gives ten. A run that meets a second glazed run at a corner shares its end fin with that run, and the fin counted twice on two separate schedules is the single most common error on a multi-run job — count each straight run separately, then reconcile the shared fins once before the order goes out.

The other trap is arithmetic rather than judgement. When the spacing divides exactly into the width, the answer is the number of gaps plus one and nothing needs rounding at all: eight metres at a one metre centre is eight gaps and nine fins. A quotient that is already whole must not be rounded up, and the way it gets rounded up anyway is almost never something anyone typed. Two point one metres at three hundred millimetre centres is seven gaps, but in the binary arithmetic a spreadsheet, a script or the field on this page all run on, that division lands a hair above seven — and rounding the hair up hands you a member you do not need and a set-out dimension that no longer meets the return. Exact multiples are the one case to confirm by hand.

Keep the two counts apart on paper as well. Eleven fins bound ten panes, and fins and panes get transposed on schedules with tiresome regularity because both are described as a number of glass pieces from the same fabricator. Label the schedule by member type, not by count.

Feed it the run width and the maximum centre the engineer approved; it returns the fin count for a run with a fin at each end, which is the number to start from before the end conditions on the plan reduce it.

The total horizontal width of the frameless glazed wall.

The maximum allowable spacing between structural glass fins, per the engineering wind-load design.

Glass fins needed

10 glass fins

High confidence
Bays between fins
9
Fin centres across the wall
4.33 ft

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

10 ft2 m39 ft11.89 m4.33 ft1.32 m

What this calculation does not cover

  • Spacing sets the panel width, and glass comes in sizes. The resulting width has to be one the supplier can cut from stock sheet, laminate, heat-treat, ship and lift into position, and the handling and transport limits usually bite before any rating does — so a spacing that divides the wall neatly can still land on a panel that becomes a special or a crane lift. Check the width the count implies before treating the layout as settled.
  • Fins are counted; nothing that holds them is. Each needs a shoe or pocket top and bottom, and the head detail has to let the slab above deflect and shrink without coming to bear on the glass — a movement allowance with a fitting able to take it. Brackets, fixings, the structural silicone between panels and the fin-to-panel connections are separate quantities, and the head allowance is a design decision whose omission is what cracks fins.

What Arrives on One Fin, and What Arrives on the Crane

At 1.44 metre centres and 4.2 metres of storey height, each intermediate fin collects a strip of wall 1.44 metres wide over its full height. At a design pressure of 1.5 kilopascals that is a uniform line load of about 2.16 kilonewtons per metre down the fin, roughly 9.1 kilonewtons in total, arriving as something near 4.5 kilonewtons of reaction into the slab and the same again into the soffit above. Those two reactions are the numbers the base shoe, the head restraint and their fixings have to be designed for, and they scale directly with the spacing — which is the clearest reason not to widen the centres after the anchorage has been signed off.

Dead load usually travels a different route, and it is worth being explicit about which route this wall uses before anything is sized. In the common arrangement the panes bear on setting blocks in a base channel and their weight goes straight into the slab, leaving the fin carrying its own self-weight plus wind. In a suspended wall hung from the structure above, the panes hang from the head and the fin carries them in tension with the slab detail there only to restrain, not to support. The two walls look identical in elevation and have opposite load paths.

The pane weight is where the spacing stops being an engineering abstraction and starts being a logistics problem. A pane of 1.42 by 4.2 metres in laminated glass of two 12 millimetre plies comes to roughly 358 kilograms. That is not a manual lift under any threshold anyone publishes; it is a vacuum lifter or a glazing robot, which brings its own floor loading, its own route through the building, and its own minimum door width. A fin of the same height, 300 millimetres deep and made of three 15 millimetre plies, is about 142 kilograms and is handled quite differently again. Weigh both before committing to an access method, because a spacing chosen purely for wind can produce a pane that will not fit through anything on the ground floor.

Run it twice — once for a typical pane at the centres you have landed on, once for the fin itself — since the two pieces are the same order and are lifted by completely different means.

The width of the glass panel.

The height of the glass panel.

The thickness of a single glass ply/lite, before lamination.

The number of glass layers laminated together in the panel.

Glass panel weight

230.8 lb

High confidence

This calculates WEIGHT ONLY, for handling and rigging planning — it is NOT a structural adequacy calculator. Never select glass thickness or lamination for a load-bearing application (walkways, guards, floors) from this or any generic calculator — structural glass design requires ASTM E1300/E2751/E2752 and a licensed engineer using the specific manufacturer's certified glass strength data.

3.5 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • The panel weight is not the lifting weight, and a vacuum lifter's headline rating is not its rating for this pick. Add the lifter head, spreader beam, slings and any carrier frame into the gross load, then check the manufacturer's derating for the number of pads actually in contact and for the panel's ORIENTATION — a cup set rated at one figure with the glass horizontal is commonly rated far lower once it is tilted to vertical, which is the position it goes into the opening in.
  • Weight tells you nothing about where it lands. All of that mass sits on two setting blocks, so the sill, lintel or slab edge underneath takes it as a pair of concentrated loads over a short bearing, and the head above has to hold a glazing deflection limit — typically on the order of span over 175 with an absolute cap — because a frame that sags onto the glass edge is what cracks the pane. Check the support, not just the glass.

The Joint Is the Connection

Wind gets from the pane into the fin through one of two things: a structural silicone bond onto the fin face, or bolted patch and countersunk fittings through the glass. Silicone is the more common answer on a fin wall and the more misunderstood, because it looks like the weather seal beside it. It is not a caulk; it is a designed adhesive joint whose width is calculated, whose substrates are qualified, and whose product is specified against ASTM C1184, Standard Specification for Structural Silicone Sealants. The design method sits in ASTM C1401, Standard Guide for Structural Sealant Glazing, and where the pane is an insulating unit the secondary seal has its own requirement in ASTM C1249.

The bite width is sized by the tributary method — half the pane's short span carried by each edge joint, divided by the sealant's long-term allowable stress. On a fin wall the pane's short span is very often the fin spacing itself, so the number this whole page is about walks straight into the glue line. Take a 1.42 metre pane at 1.5 kilopascals against the widely used 138 kilopascal long-term allowable: the required bite comes out near 7.7 millimetres, before the sealant manufacturer's own minimum and their own tested allowable are applied on top. Those two always govern over the arithmetic, and the manufacturer's adhesion and compatibility testing has to be done on the actual glass, the actual interlayer edge and the actual fin.

What silicone will not do is carry the pane. Weight belongs on setting blocks, and a joint asked to hold a pane up in shear for twenty years is a joint that will creep and then let go. Bolted fittings avoid that argument and introduce a different one: every hole is a stress concentration in a material with no ductility, the hole positions are fixed in the factory, and there is no site adjustment left once the glass arrives. Choosing between the two is a design decision, but it is one the spacing constrains, because the wider the bay the larger the reaction each connection has to take.

The bite comes off the pane's short span, which on a two-edge-supported fin wall is the spacing you just fixed — so run it again whenever the centres move, and treat the sealant manufacturer's minimum as the floor.

The design wind pressure acting on the glass lite.

The shorter of the glass lite's two edge dimensions.

The long-term allowable tensile stress for the structural silicone sealant — the GANA consensus standard is 138 kPa (20 psi).

Required silicone bite width

0.255 in

Medium confidence

This is the standard ASTM C1401/GANA tributary-load simplification (ignoring two-way plate action and aspect ratio) — a licensed structural/facade engineer should verify final bite width, especially for high-aspect-ratio lites where FEA-based methods may justify a different allowable stress.

Add the equipment this sizes

This result is a specification — 0.255 in — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

What this calculation does not cover

  • Bite is one of two dimensions in the joint, and only the wind-resisting one is sized here. The glueline THICKNESS — the gap between glass and frame — is what absorbs the differential movement as the metal grows and the glass does not, and practice keeps the bite to no more than about three times it, with neither dropping much below 6 mm (0.24 in) however small the arithmetic comes out. Correct bite in too thin a glueline does not fail in a storm; it tears quietly through the first hot summer.
  • Nothing here carries the weight of the glass. Structural silicone's allowable stress under permanent load is a small fraction of the 138 kPa (20 psi) used for wind — of the order of 7 kPa (1 psi) — so on all but the smallest lites the dead load belongs on setting blocks, and a lite genuinely hung in sealant needs its own, far larger, calculation.
  • The pressure entered should be the SUCTION peak for the lite's zone, not the positive one. The bite goes into tension when wind pulls the glass off the frame, and negative pressures at corners, parapets and the upper storeys of a tall building run well above the field figure quoted for the wall. Take the wrong line out of the wind schedule and the bite is undersized precisely where the building is worst loaded.

Lay the Wall Flat and the Load Stops Balancing

A vertical wall is loaded by something that pushes and pulls in roughly equal measure and then goes away. Turn the same assembly horizontal and nothing about the load case survives. Gravity is now permanent and one-directional: the dead weight of every unit, whatever snow arrives, and an access load wherever anyone can reach or fall onto the glass. Wind uplift still acts, but upward, in the opposite direction to everything else. The governing combination changes, and so does the spacing that comes out of it — bars under a glass roof sit closer together than fins in a wall of comparable pane thickness, and that is why.

Snow is the load that catches designs out, because the site figure is not the roof figure. Ground snow load is converted to a flat roof design load through exposure, thermal and importance factors under the snow provisions of ASCE/SEI 7, or through the equivalent shape and exposure coefficients of BS EN 1991-1-3, Eurocode 1: Actions on Structures — Snow Loads. The thermal factor is where a glazed roof over a heated hall genuinely differs from a metal deck over a warehouse, and the value belongs to the code table rather than to judgement. Then there is drift: a rooflight in the reentrant between two blocks, or one running up to a taller parapet, collects a surcharge that the flat-roof figure does not contain at all, and that is exactly the position most glass roofs occupy.

Load duration matters here in a way it does not on a wall. A laminated pane behaves as a composite section only to the degree its interlayer transfers shear, and that shear stiffness falls with rising temperature and with lengthening load duration. A pane checked against a three-second gust and the same pane checked against a month of lying snow are two different sections. BS EN 16613 is the standard for determining those interlayer properties, and the interlayer manufacturer's tabulated data at the relevant temperature and duration is the input the check actually needs.

Finally, two documents can veto the makeup that made a spacing work. IBC Section 2405, Sloped Glazing and Skylights, governs what is permitted over occupied space and where retention is required beneath it. In the United Kingdom the separate question of whether a roof assembly is non-fragile is settled by test, under ACR[M]001, Test for Non-Fragility of Roofing Assemblies, published by the Advisory Committee for Roofsafety, and it is a whole-assembly result rather than a property of the glass alone. Neither document sets a bar spacing. Both can rule out the pane that let you widen one.

Start from the ground snow load on the site's map and convert it before it goes anywhere near a bar spacing — and treat drift against a parapet or an adjoining wall as a separate addition, not as something this conversion already contains.

The site's ground snow load, from your local building code's ground snow load map.

Accounts for wind exposure and terrain, which affects how much snow accumulates on the roof versus blows off.

Accounts for heat loss through the roof that can melt accumulated snow.

Based on the building's risk category, per ASCE 7.

Flat-roof design snow load

21.93 psf

High confidence

Add the equipment this sizes

This result is a specification — 21.93 psf — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

What this calculation does not cover

  • The page returns pf from the equation alone, and ASCE 7 also sets a minimum roof snow load pm that governs instead on low-slope roofs: where the ground snow load is 20 psf (about 0.96 kPa) or less, pm is Is times pg, and above that it is 20 psf times Is. No floor is applied here, so the page's default pg of 1.5 kPa with an exposure factor of 0.9 returns 0.945 kPa, which is 19.7 psf and already below that 20 psf minimum.
  • This is the balanced load spread evenly over the whole roof. Drift against a parapet, a roof step or a rooftop unit is a separate ASCE 7 calculation that puts a triangular surcharge over a limited width and can reach several times pf, so a rafter or beam sized on this figure can still be badly under-designed where the snow actually piles up. Sliding snow off an upper roof, and the rain-on-snow surcharge of about 5 psf (0.24 kPa) that applies to low-slope roofs where the ground snow load is 20 psf or less, are added on top of pf rather than contained in it.
  • pf is a pressure on the horizontal projection of the roof, not on the sloped surface. Applying it to the true roof area counts the pitch twice: at 6:12 the sloped surface is 11.8 per cent larger than the plan area, so the snow total comes out that much high. Dead loads run the other way and do act on the sloped area, which is why the two are never taken over the same area.
  • Ce, Ct and Is are multiplied exactly as typed and are never checked against the tables they come from. Entering Ce as 0.7 rather than 1.0 removes 30 per cent of the load on the strength of a wind exposure that has to hold for the life of the building, and conifers grow, a taller neighbour goes up, a screen wall gets added. The field also accepts Ce up to 1.3, beyond the 1.2 top of the ASCE 7 exposure table that its own help text describes, without objecting.
  • The form used here, with a separate importance factor, is the pre-2022 one. ASCE 7-22 rebuilt the snow chapter around reliability-targeted ground snow loads mapped for each risk category and dropped Is from the flat-roof equation, so a pg read off those newer maps and then multiplied by Is of 1.2 applies the risk category twice and overstates pf by 20 per cent. Which edition your jurisdiction has adopted decides which of the two pg values belongs in the box.

Bar Centres, and the Fact That Every Bar Is Also a Gutter

The arithmetic overhead is the same shape and the consequences are not. A rooflight 9.6 metres across, with a maximum bar spacing of 0.9 metres set by the pane's capacity under the combined snow and dead case, divides to 10.67, which rounds up to eleven gaps and twelve bars at 873 millimetre centres. Subtract the cap width and the joint to get the ordered pane width, exactly as on the wall.

What differs is everything the bar has to do besides hold glass up. It is a drained and ventilated channel, so any water that gets past the cap gasket and any condensate that forms on the underside of the pane run down inside the bar to a termination at the eave. It carries a bedding gasket the panes sit on, setting blocks at the low edge to stop them creeping down the slope, and a pressure cap clamping the joint from above. Every extra bar in the count is therefore another two runs of gasket, another length of cap, two more end closures and one more drainage termination to detail and to test. The linear items on a glass roof scale with the bar count, not with the glazed area, which is why a modest tightening of centres costs more than the aluminium suggests.

Deflection is the serviceability limit that decides whether any of that works. A bar that sags takes the pane out of plane with it, opens the cap gasket line at midspan and turns a drained joint into a leaking one, so the limit is set by the system supplier and is usually tighter than a bare strength check would demand. AAMA TIR-A11, Maximum Allowable Deflection of Framing Systems for Building Cladding Components at Design Wind Loads, is where the convention for cladding support members is written down, and the supplier's own tested limit for the bar section governs over any general rule.

The count itself is narrower than it looks. It is the number of parallel bars across one flat width and it is nothing else: hip bars, the ridge, the eave beam, the perimeter members and any transom lines where the panes step up the slope are all separate quantities taken off the layout. The bars also have to land on something — reconcile the bar positions against the rafter or purlin grid underneath before the layout becomes a fabrication drawing, because a bar that falls between two supports is a change to the steelwork, not to the glazing.

What sits on a glazing bar line

A glazed roof taken through one bar line: the rafter carrying it, the structural glazing bar sitting on the rafter, the bedding gasket and setting blocks across the bar face, the two laminated units spanning away on either side, and the pressure cap clamping the joint from above.
  1. Pressure cap and cap gasket — clamps the joint closed and is the only weather line above the glass; bought by the metre of every bar, hip and ridge in the layout Glazing Gasket/Wedge Linear Footage Calculator
  2. Laminated glazed units — span from bar to bar, so the ordered pane width is the bar centre less the cap and the joint, and their weight lands on the bar below Architectural Glass Weight Calculator
  3. Bedding gasket and setting blocks — beds the pane on the bar face and stops it creeping down the slope; blocks are counted per pane rather than per metre Window Setting Block Count Calculator
  4. Structural glazing bar — the member whose spacing this page is about, working as a beam under snow and as a drainage channel at the same time Skylight Glazing Bar Spacing Calculator
  5. Rafter or purlin under the bar line — the steel the bars land on, whose own spacing has to reconcile with the bar layout before either becomes a fabrication drawing Steel Z/C Purlin Spacing Calculator

It counts parallel bars across one flat width, which is the base quantity — add hips, ridge, eave and perimeter members from the layout separately rather than expecting this number to contain them.

The overall width of the skylight to be spanned by glazing bars.

The maximum allowable center-to-center spacing between glazing bars, per the glass panel's span capacity.

Glazing bars needed

9 glazing bars

High confidence
Bays across the skylight
8
Bar centres across the opening
2.44 ft

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

5 ft1 m19.5 ft5.94 m2.44 ft0.743 m

What this calculation does not cover

  • The count assumes a glazing bar sits at each edge of the width, so the two perimeter members are included in the figure. Where the skylight lands in a kerb or a proprietary frame that already supports the glass edge, those two are frame profiles rather than glazing bars, and only the returned figure minus two needs ordering as intermediate bars.
  • The centres above are the delivered ones — the width divided by one less than the bar count, which lands at or below the maximum entered: a 6 m (20 ft) width at a 0.7 m (2.3 ft) maximum is nine bays at 0.667 m (2.2 ft). They are not glass sizes. A panel is that figure less the width of the bar face it sits between, and the bar face is not an input here, so nothing on this page sizes a sealed unit.
  • Nothing here checks the bar itself. The maximum spacing entered is a limit on the glass panel's span across the width, whereas the bar's own span down the slope, its section properties and its deflection limit are a separate calculation this does not perform.
  • Spacing is taken as an input and is never derived from load. Snow accumulating on a pitched rooflight, drifting against an upstand or a parapet, and wind uplift concentrated at the panel corners can each pull the allowable spacing below the uniform-load figure printed in a glass span table.
  • It assumes bars can be placed at equal centres across the whole width. An opening light, a smoke vent actuator, a hip, or a structural line beneath the glazing pins a bar to a fixed position and leaves unequal bays, and it is the widest remaining bay rather than the average that has to stay inside the maximum spacing.

Where the Division Stops Working

A single division answers a straight run of constant width and very little else. A wall that turns a corner is two runs sharing one fin. A wall interrupted by a revolving entrance or a pair of doors is two runs with a structural opening between them, and the fins either side of that opening are usually not the field fins at all. A rooflight on a tapered plan has a different bar count at each end and is set out by dividing each end and interpolating, or by accepting a fan layout with a varying pane width and a fabrication schedule to match. In every one of those cases the honest method is to divide each straight, constant-width segment on its own, then reconcile the members the segments share before anything is ordered.

What travels to the fabricator is a schedule, and a schedule that survives contact with the shop floor carries the reasoning as well as the numbers. Put the design pressure, the approved maximum centre and the makeup it was checked against on the same sheet as the count, because the count is only defensible in their company — and the person who asks about it in eight weeks will be doing so with a variation attached.

  1. Get the approved maximum centre in writing, together with the design pressure, the pane makeup and the fin or bar section it was checked against.
  2. Measure the as-built opening rather than the drawn one, taking the width at head, mid-height and sill, and use the smallest.
  3. Divide by the maximum, round up to whole gaps, add one — then delete any end member the adjoining structure already provides, and confirm exact divisions by hand.
  4. Divide the width back by the gap count and put that built centre on the drawing, clearly distinguished from the maximum it came from.
  5. Subtract the joint or cap width from the centres to get the ordered pane width, and schedule the end panes on their own line.
  6. Weigh one typical pane and one fin, then check the lift route, the door widths and the floor loading before any access method is priced.

Settle these before the toughening slot is booked

The count decides the pane, the pane decides the plant, and none of it can be revisited once the glass is in the autoclave. Work down the list in this order.

  • Approved maximum centre, in writing — Valid only alongside the design pressure, the pane makeup and the member section it was checked against — record all four together.
  • End conditions on the plan — Returns, columns and shared corner members that already provide an end support, so the plus-one is not bought twice.
  • Built centres, not the maximum — The width divided back by the gap count, marked on the drawing as the set-out dimension in its own right.
  • Pane and member schedule — Field panes, end panes, fins or bars and perimeter members listed separately by type, never as one glass count.
  • One pane and one fin weighed — Drives the access method, the lift route, the door widths and the floor loading the plant needs — all decided before the order.
  • Roof bar and steel reconciliation — Bar positions checked against the rafter or purlin grid below, with hips, ridge, eave and perimeter counted apart from the field bars.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • ASCE/SEI 7, Minimum Design Loads and Associated Criteria for Buildings and Other Structures
  • BS EN 1991-1-4, Eurocode 1: Actions on Structures — Wind Actions
  • BS EN 1991-1-3, Eurocode 1: Actions on Structures — Snow Loads
  • ASTM E1300, Standard Practice for Determining Load Resistance of Glass in Buildings
  • BS EN 16612, Glass in Building — Determination of the Lateral Load Resistance of Glass Panes by Calculation
  • BS EN 16613, Glass in Building — Laminated Glass and Laminated Safety Glass — Determination of Interlayer Viscoelastic Properties
  • CEN/TS 19100, Design of Glass Structures
  • Institution of Structural Engineers, Structural Use of Glass in Buildings
  • ASTM E2751/E2751M, Standard Practice for Design and Performance of Supported Glass Walls
  • ASTM C1172, Standard Specification for Laminated Architectural Flat Glass
  • BS EN 14449, Glass in Building — Laminated Glass and Laminated Safety Glass — Evaluation of Conformity
  • ASTM C1048, Standard Specification for Heat-Strengthened and Fully Tempered Flat Glass
  • ASTM C1401, Standard Guide for Structural Sealant Glazing
  • ASTM C1184, Standard Specification for Structural Silicone Sealants
  • ASTM C1249, Standard Guide for Secondary Seal for Sealed Insulating Glass Units Used in Structural Sealant Glazing Applications
  • International Building Code, Chapter 24 Glass and Glazing, including Section 2405 Sloped Glazing and Skylights
  • AAMA TIR-A11, Maximum Allowable Deflection of Framing Systems for Building Cladding Components at Design Wind Loads
  • CWCT Standard for Systemised Building Envelopes, Centre for Window and Cladding Technology
  • ACR[M]001, Test for Non-Fragility of Roofing Assemblies, Advisory Committee for Roofsafety

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.