From this site

One project, every trade

Each calculator adds its lines to a single estimate — consolidated BOM, schedule and cash-flow included.

Open My Project

Sitework

Grading a Site for Drainage

Trace every drop from the divide above the pad to the permitted outlet, and size the grade at each transition it crosses.

Published · Last reviewed

Stand on the high ground first

Water arrives on a site long before the first machine does, and it crosses a boundary no surveyor marked. Walk uphill from the pad until the ground tips away from you in the opposite direction. That line is the divide, the top of the catchment, and everything inside it drains through whatever you build. On a rolling lot the divide may sit fifty feet behind the house; on a bench cut into a hillside it may sit half a mile up in a neighbour's pasture.

Offsite area is the number most often missed. A quarter-acre back yard that also receives two acres of hayfield through a broken fence line carries several times the flow the lot alone produces, and a swale sized from the plot plan will run its banks the first time a thunderstorm parks overhead. Pace it, scale it off county contour mapping, or walk the divide with a rover, but get a number for it before committing to an invert.

Work the elevations backwards from the exit. Find the low corner, the roadside ditch, the inlet grate, the headwall the site is permitted to discharge into, and shoot it. Nothing upstream can sit lower. Crews that set the pad first and hunt for fall afterwards finish with a back yard that needs imported fill, a retaining wall nobody bid, or a sump pump doing work gravity should have done for free.

Soil decides how the catchment behaves between rain events. A lot classified as fat clay under ASTM D2487 Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System) sheds nearly everything and holds standing water in every low spot; a sandy loam absorbs a light rain entirely and never reaches the swale. Where the design leans on infiltration, a dry well, a rain garden, an infiltration trench, the rate needs a field measurement such as ASTM D3385 Standard Test Method for Infiltration Rate of Soils in Field Using Double-Ring Infiltrometer rather than a figure copied off a table.

Roof and pavement into open ground

Every drop that lands on a roof leaves it concentrated. Two thousand square feet of shingle discharging through four downspouts turns a gentle rain into four jets, and bare soil under an open downspout will cut toward the footing in a single season. Splash blocks slow the jet; they do not move the water. Extensions, buried solid pipe with a cleanout at the elbow, or a tie into a storm lateral move it.

Discharge those extensions where they daylight above a swale, not into the middle of one, because a pipe ending mid-slope undercuts its own outlet. Run them past the backfill zone as well. The trench alongside a foundation stays looser than the ground either side of it for years after the pour, and it will draft water straight down to the footing drain if the finished grade lets anything sit over it.

Ground against the wall wants positive fall away from the structure across the first stretch of yard. The International Residential Code sets the model figure for that fall, jurisdictions amend it, and impervious surfaces are treated differently from turf, so the adopted local code rather than the memory of the last job governs the number you build to. Where a wall, a walk or a property line forces a shorter run, the drawings should show a drain, not a flattened slope.

Pavement edges concentrate flow the same way a downspout does, along a line instead of at a point. Sheet flow crossing from asphalt onto turf drops the thickness of the mat, and the lip that forms there scours into a rill that deepens every storm. A compacted aggregate shoulder flush with the pavement, a thickened edge, or a mountable curb with a defined cut solves it at paving time for a fraction of what returning with a skid steer and sod will take.

Keeping it as sheet flow

Past the edges water spreads out and travels as a thin sheet, and that condition is worth protecting. Sheet flow does not scour, does not silt up, and needs no structure. Every foot you keep flow spread is a foot you do not have to line, pipe or armour later.

Minimum grades follow what each surface tolerates, not what looks flat enough from the cab. Turf and planted areas generally want around two percent so they still drain after settlement; concrete and asphalt can be held tighter but leave no margin for a low spot; accessible routes cap cross slope outright, and the accessibility standard adopted by the jurisdiction governs both that cap and the running slope. Convert once, into whatever unit your instrument speaks, percent for a rover, inches per foot for a string line and hand level, ratio for a plan callout, and stay in it across the whole area instead of converting again at every stake.

Subgrade has to mirror the surface it carries. Aggregate base left flat under a sloped pavement becomes a bathtub: water enters through joints and cracks, finds no fall inside the section, and softens the subgrade until the surface fails from below. Blue tops set at the correct depth below finish, checked across the diagonals rather than only along the edges, are the cheapest insurance on the job.

Tolerance in the field is never zero. A tenth of a foot of dish across ten feet is invisible to the eye and will hold water for a day after every rain. The check is a hose on a flat setting, or a walk during an actual storm; birdbaths announce themselves and can be pulled out with a box blade while the equipment is still on site, which stops being true once the sod is down.

Fix the fall for each surface before anyone drives a stake: work between percent, ratio and inches per foot, and read the drop across the reach you are actually grading.

39 ft3.5 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

Slope grade

8.974 %

High confidence
Angle
5.13 degrees

At the values currently entered, the slope grade works out to 8.97 %. Figures are shown in United States units and terminology; switch the market above if you are building elsewhere.

The topsoil layer moves your grade

Stripped topsoil comes back at the end and moves every elevation you set. Measure the actual strip depth in test holes across the site instead of trusting the note on the plan, because organic depth runs from a couple of inches on a scraped field to a foot in an old garden, and that difference decides whether the site balances or whether trucks are coming.

Stockpile outside the catchment low ground, off future pavement, with a silt fence at the toe. A pile sitting in the swale line is a dam, and a pile left bare through a wet month loses its fines into whatever lies below it. Seed the stockpile if it will stand more than a few weeks.

Respread thickness is the trap that catches experienced crews. Subgrade cut exactly to design finish grade, then covered with four to six inches of loose topsoil, does not produce design finish grade; it produces a lot riding four to six inches high with the shallow swale filled in. Cut the subgrade low by the settled thickness of the layer, and allow for the fact that loose respread drops noticeably from spread depth once it takes rain and root.

Resist compacting the layer you just placed. Track-packed topsoil will not take root, sheds almost like pavement, and turns a two percent lawn into a pond fed by its own surface. Scarify the subgrade before spreading so the interface keys together instead of forming a slick plane that perches water and slides on a slope.

Take the strip and the respread off the same numbers: area against settled depth gives the volume to stockpile and the thickness your subgrade has to sit low by.

Topsoil Calculator

10 ft4 ft8 in
Schematic, drawn to the proportions you entered — not to scale on screen.

Estimated topsoil needed

0.9877 cubic yards

High confidence
Area
40 ft²

Running these inputs gives 0.99 cubic yards as the result. Currently reading for United States — pick a different market above and the figures re-cast accordingly.

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

When sheet flow becomes a channel

Somewhere down the catchment, sheet flow gathers into a channel, and that transition marks the point at which a site erodes if it is going to. A swale is the controlled version of what water will otherwise do on its own, and the whole job of grading one is to keep flow slow, shallow and inside a section you chose.

Longitudinal slope has a working window. Under roughly one percent a grassed swale silts in, stands water and grows cattails; above roughly five percent ordinary turf on bare soil starts to move and the channel needs a liner, whether turf reinforcement mat, sod over mat, or rock. Between those bounds a properly shaped and established grass channel handles a residential catchment indefinitely on nothing but mowing.

Shape matters as much as fall. Broad and shallow with a flat bottom spreads flow and drops velocity; narrow and deep speeds it up and cuts. Side slopes at four horizontal to one vertical mow safely, three to one is the practical maximum for equipment, and two to one belongs only where the face is stabilized and nobody has to walk it.

Lining choice follows velocity, and velocity follows slope and depth together: rock sized off a gradation such as ASTM D448 Standard Classification for Sizes of Aggregate for Road and Bridge Construction on the steep reach, vegetation on the flat. Permissible velocity guidance published for grassed waterways by the USDA Natural Resources Conservation Service is the usual reference where a project specification stays silent.

Cut the swale early and protect it rather than scratching it in on the last day. Channels shaped after a lot has been tracked flat by haul traffic never drain the way the drawing says, because the compacted plateau either side holds the sheet flow that was supposed to reach them.

Crossings: the pipe under the drive

A crossing is the tightest constraint in the catchment, because a pipe fixes both an elevation and a capacity at a single point. Set the culvert invert to the flow line of the ditch it continues, not to the driveway above it: an inlet set high ponds upstream and an outlet set low undercuts and eventually drops the pipe.

Length comes from the embankment, not from the pipe list. Top width of the drive, plus the horizontal projection of both side slopes, plus any skew where the ditch crosses at an angle, decides where the ends land; cutting a pipe short and steepening the fill to reach it is the most common one-year repair on a rural approach.

Bedding and haunching decide whether flexible pipe keeps its shape. ASTM D2321 Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications covers material and placement for thermoplastic, AASHTO M294 Corrugated Polyethylene Pipe covers the pipe itself, and ASTM C76 Standard Specification for Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe covers the rigid alternative. Backfill shoved under the springline with a bucket instead of worked into the haunch is why pipes come back deflected past whatever limit the project specification states.

Both ends need protecting. Flared end sections or headwalls hold the embankment, a riprap apron at the outlet stops the scour hole walking back under the barrel, and a defined inlet keeps the ditch from cutting around the pipe rather than through it. An inlet buried in grass and trash is a culvert with no capacity at all, which the owner discovers during the exact storm that needed it.

Basins and grates in a paved catchment follow the same logic: rim set a fraction below the surrounding surface so flow actually enters, sump below the outlet invert to catch grit, and the pavement graded into a valley that leads to the grate rather than past it.

The outlet and what you owe downstream

The exit point is a legal question before it is a drainage question. Concentrating flow onto a neighbouring parcel where it previously arrived as sheet flow creates liability, and which doctrine applies, reasonable use, civil law, or common enemy in one of its modified forms, depends on the state. Local stormwater ordinance and recorded easements govern that discharge; the operator with the machine does not.

Rate control sits separate from routing. Many jurisdictions require post-development peak discharge no greater than pre-development for one or more design storms, which is what turns a grading job into a detention basin, an underground chamber, or a restricted outlet structure. Those requirements, their design storms and their release rates come from the adopted ordinance and differ across a county line.

Energy has to go somewhere at the discharge. A pipe or swale arriving at a receiving ditch at full velocity digs a hole, and that hole migrates upstream until it takes the structure with it. Aprons, plunge pools, rock, and level spreaders that convert concentrated flow back into sheet flow all do the same work; the choice depends on how much fall is being dissipated.

Check the tailwater before assuming free discharge. An outlet that runs open in a small rain may sit submerged in a large one, and a system designed as though it always discharges into air will back up into the lowest inlet on the site. Where the receiving ditch or stream carries a known high-water mark, use it.

Proof before the equipment leaves

Grade is not finished when it looks finished. Shoot the as-built on a grid tight enough to catch a dish: swale flow lines at every station and every grade break, inlet rims, pad corners, top and toe of every slope, then compare against design before the equipment leaves the site.

Test it with water. A hose left running at the head of a swale for twenty minutes shows the flat spots, the reverse fall, and the place the flow line wanders out of the bottom, and all three are minutes of work while the box blade is still hooked up.

Fill settles, and settlement changes drainage. Backfill over a utility trench crossing a yard is the usual culprit; a trench that drops two inches after a wet season turns a cross-fall into a collector aimed straight at the house. Density verified against ASTM D698 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Standard Effort, or ASTM D1557 for modified effort, and measured in place by a method such as ASTM D6938 Standard Test Methods for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth), is what prevents the callback.

Stabilization runs on a clock. Disturbed ground carries deadlines for temporary or permanent cover under the NPDES construction stormwater permit as issued by the state or delegated authority, and the number of days differs between programs. Perimeter controls come out only after cover establishes; pulling silt fence off a thin new stand of grass hands a whole season of sediment to the outlet you just built.

Catchment takeoff

Work the list in the order water travels, from the divide above the pad down to the point the site is permitted to discharge into.

  • Divide and contributing areaWalk the high ground and record any offsite acreage entering across a fence line, road crown or field ditch.
  • Outlet elevationShoot the permitted discharge point before anything else; nothing upstream can be built lower than it.
  • Design grade by surfaceTurf, pavement and accessible routes each carry their own minimum; settle on one unit and hold it across the area.
  • Strip and respread depthTest holes for actual organic depth, then cut subgrade low by the settled thickness of the returning layer.
  • Swale stations and reachesFlow line at every station and grade break, with reaches flagged where slope pushes past what turf will hold.
  • Crossing geometryInlet and outlet inverts, embankment top width, side slopes and any skew across the ditch.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • ASTM D2487 Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
  • ASTM D3385 Standard Test Method for Infiltration Rate of Soils in Field Using Double-Ring Infiltrometer
  • ASTM D448 Standard Classification for Sizes of Aggregate for Road and Bridge Construction
  • ASTM D2321 Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications
  • ASTM C76 Standard Specification for Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe
  • AASHTO M294 Corrugated Polyethylene Pipe
  • ASTM D698 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Standard Effort
  • ASTM D1557 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort
  • ASTM D6938 Standard Test Methods for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
  • International Residential Code (as adopted and amended by the local jurisdiction)
  • NPDES Construction General Permit (as issued by the state or delegated permitting authority)
  • USDA Natural Resources Conservation Service guidance for grassed waterways

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.