Waterproofing

Tanking a Basement Wall Against Standing Water

Below the table a wall has to hold head, not shed it: set the design water level, work out what the ground delivers, then confine the bentonite.
  • 16 minReading time
  • 8Sections
  • 6Calculators inline
  • Last reviewed

The morning the dig came back full

Wellpoints run all week, formation stays dry, the wall goes up, the pumps come off on the Friday and by Monday there is 600 mm of clear water standing against the fresh concrete. Nobody made a mistake. The excavation was always below the table; the dewatering was only ever holding it down for the duration of the works, and the moment the vacuum stopped the aquifer came back to the level it has occupied for the last ten thousand years. Everything the waterproofing does from that point onward is done underwater and cannot be revisited.

That is the condition tanking is for. A barrier applied to the positive face of the structure, continuous across every joint, penetration and re-entrant corner, designed to resist a head that is permanently present rather than to shed water that arrives during a storm. It is not damp-proofing with a bigger tin, and it is not the same trade as intercepting surface water: those work by giving water a cheaper route elsewhere, and there is no elsewhere when the wall is submerged.

BS 8102:2022, Protection of below ground structures against water ingress, is the useful frame even outside Britain because it separates the two questions that get conflated on site. First, what internal environment does this space have to deliver — its grades run from a space where some seepage and damp can be managed, up to a dry, habitable environment. Second, by what mechanism — Type A barrier protection, Type B structurally integral protection using the concrete itself, or Type C drained protection that admits water to a managed cavity. The North American equivalents come at it from the trigger rather than the mechanism: IRC Section R406 and IBC Section 1805 both distinguish dampproofing from waterproofing and require the latter where a high water table or severe soil-water condition is known to exist. Tanking a wall against standing water is Type A, and BS 8102 is emphatic that where the assessed risk is high, one type on its own is thin cover. Combining Type A with Type B, or Type A with Type C, is the normal answer for a Grade 3 space below the table.

Nobody tanks against the level on the day

The design water level is a decision, not an observation, and it is the number every other number on the job hangs off. Water in an open excavation tells you where the table is this week, under this rainfall, with the site drainage in whatever state it is in. It tells you nothing about February, about the river two hundred metres away at its hundred-year stage, about the tidal cycle if the site is estuarine, or about what happens when the neighbouring development stops its own dewatering. Standpipe piezometers installed and developed to ASTM D5092, read over a period long enough to catch a seasonal swing, are the only honest input. One trial pit dug at nine in the morning is not.

Work the level to the top of the structure where the ground can credibly deliver it, then design for that. It matters twice over. Laterally, a 3 m submerged wall height carries a triangular water pressure diagram with a resultant near 44 kN per metre run — roughly 3,000 lb on every foot of wall — acting in addition to the effective soil pressure, and a wall detailed for damp ground is not a wall detailed for that. Vertically, the same head pushes up on the underside of the slab across the whole footprint, and a light basement box below the table wants to float. Eurocode 7, BS EN 1997-1, treats that as its own class of limit state alongside heave and internal erosion, and it is checked against the buoyant weight of the structure and whatever the design chooses to mobilise against it, not against the weight of the walls alone. Get the design level wrong and you have not misjudged a waterproofing detail; you have misjudged the structure.

Enter the design water level rather than the day's, as a depth below the ground, and the water gets a line of its own at full pressure beside the soil's buoyant one. With the level at the surface, the water thrust in the breakdown is the resultant worked above.

The height of soil against the wall, from the base slab to the ground surface behind it.

At rest for a wall held by the floor at its head; an entered value for anything else the designer has set.

The drained friction angle of the retained soil, from the ground investigation.

1 for normally consolidated soil and placed fill; higher for ground that was once under more load.

The weight of the retained soil as it is in service, water in the pores included.

The weight of the soil with its voids full, used below the water table.

How far below the retained surface the design water level sits; the full height or more means no water on the wall.

A load spread over the ground behind the wall — a drive, stored material, a building's floor.

Total thrust on the wall per unit run

3,450 lbf/ft

Medium confidence

At rest: the soil stays where it was placed, which is the state of a wall propped by the floor at its head. A wall genuinely free to lean away could use the lower active coefficient, but only if it can move enough to earn it. Below the water table the soil contributes only its buoyant weight times the coefficient, and the water acts on top of it at full hydrostatic pressure.

At-rest coefficient K0
0.5
Soil pressure at the base
464.55 psf
Water pressure at the base
312.25 psf
Total pressure at the base
776.8 psf
Soil thrust per unit run
2,673.27 lbf/ft
Water thrust per unit run
780.62 lbf/ft
Height of the resultant above the base
3.13 ft

Add the equipment this sizes

This result is a specification — 3,450 lbf/ft — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

10 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • Characteristic, unfactored pressures for a screening check. A design applies the partial or load factors of the code in force, and the structural engineer sets the design water level and the coefficient the wall is designed to.
  • Horizontal ground behind the wall. A slope rising away from the wall increases the at-rest coefficient — Eurocode 7 multiplies it by (1 + sin β) — and is not modelled here.
  • Compacting backfill in layers against a propped wall can lock in pressures above the at-rest figure near the top of the wall. AASHTO LRFD 3.11 and CIRIA C760 set out methods for it; this page does not add them.
  • The water is static and the soil's cohesion is ignored. Seepage towards a drained wall changes the pore pressures, and a line load or strip footing close to the wall adds pressure that a uniform surcharge does not represent.

What the ground can actually deliver to the wall

Two sites at the same head behave nothing alike. A basement in stiff glacial clay two metres below the table sits in ground that will not pass measurable water in a working lifetime; the same basement in a sand and gravel terrace is a hole in an aquifer, and the difference is permeability, which spans about ten orders of magnitude across ordinary soils. That range is why nobody should be estimating a below-grade job from head alone, and why the first arithmetic on the page is Darcy's law rather than an area takeoff.

Q = k i A. The hydraulic conductivity k is the soil property; the gradient i is the head lost across the flow path divided by the length of that path; A is the cross-sectional area the flow crosses. At a basement wall the useful interpretation of A is the vertical plane of submerged wall face the water has to cross to reach the excavation or the drainage layer, and the useful interpretation of i is the head difference between the far-field table and whatever level is being held at the wall, divided by the distance over which that drop occurs. Where a drainage composite holds the face at atmospheric pressure the drop is steep and local, which raises i sharply — a fact worth noticing, because relieving pressure at the face is exactly the same thing as increasing the seepage the relief system then has to carry.

Get k from a test, not from a table, and be honest about which test. Laboratory values come from a flexible-wall permeameter to ASTM D5084 for fine-grained material, or the constant-head method of ASTM D2434 for granular soils; field values come from a slug test to ASTM D4044 or, better on any job worth the money, a pumping test. Field values are usually higher and always more relevant, because a laboratory specimen has lost the fabric — the sand partings, the fissures, the relic root channels — that actually conveys water. Layered ground is anisotropic by an order of magnitude or more, horizontal conductivity over vertical, and a single k entered into a calculator is a horizontal-flow number whether you meant it to be or not.

Run the figure and then read it for what it is. A 3 m by 8 m submerged wall face in silty sand at 1 × 10⁻⁵ m/s under a gradient of 0.5 delivers about 0.12 litres per second — roughly 10 m³ a day, near 2,700 US gallons — which is a trivial flow for a pump and a serious flow for a barrier that is supposed to admit none of it. The number is not what leaks through a tanked wall; it is what the surrounding ground can hand to the excavation while it is open, and what a relief layer would have to carry forever if you chose to give the water somewhere to go. Darcy assumes laminar flow through saturated, homogeneous, isotropic soil, so treat a result in open gravel or fissured rock as an order of magnitude rather than a quantity.

Published typical hydraulic conductivity ranges by soil description. Use them to sanity-check a measured k, never to replace one.
Soil descriptionTypical k (m/s)What it means for a below-grade box
Clean gravel10⁻² to 10⁻¹Effectively an open channel; dewatering dominates the programme
Clean sand, sand and gravel10⁻⁵ to 10⁻²Free draining; expect a real inflow and a real relief decision
Fine and silty sand10⁻⁷ to 10⁻⁵The awkward middle — enough flow to matter, fine enough to pipe
Silt, glacial till10⁻⁹ to 10⁻⁷Slow seepage; head is the problem rather than volume
Intact clayBelow 10⁻⁹Water arrives through fabric and fissures, not through the matrix
Published typical hydraulic conductivity ranges by soil description. Use them to sanity-check a measured k, never to replace one.

Put the measured k, the gradient across the flow path and the submerged wall face into it before anyone decides between a resisting box and a drained one — the answer sets the dewatering, the relief layer and the argument about both.

The soil's hydraulic conductivity. Scientific notation is accepted — type 1e-9 rather than counting zeros.

The head loss per unit length of flow path (dimensionless).

The cross-sectional area perpendicular to the flow direction.

Seepage flow rate

0.108 CFM

Medium confidence

Darcy's Law assumes laminar flow through a fully saturated, homogeneous, isotropic soil — it becomes less accurate in highly fractured rock, karst, or coarse gravel where flow may be turbulent.

Equivalent in m³/day
4.41 m³/day
Equivalent in m³/year
1,611.38 m³/year

Add the equipment this sizes

This result is a specification — 0.108 CFM — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

What this calculation does not cover

  • Darcy's Law here treats the ground as one uniform block with a single hydraulic conductivity, a single gradient and a single area. It does not account for layering, anisotropy (horizontal permeability is commonly several times the vertical), or preferential paths — sand seams, fissures, root channels, backfill around old services — which often carry most of the real flow.
  • The answer is a flow rate at one instant under one fixed gradient. It does not model transient drawdown, release from storage, recharge from rainfall, or tidal and seasonal movement of the water table, so it will not tell you how inflow to an excavation changes over the first days of pumping.
  • This is a flow rate, not a dewatering design and not a stability check. It says nothing about exit gradient, piping, heave, base stability or the settlement of neighbouring ground that drawdown can cause, and it makes no allowance for wellpoint entrance and filter losses, surface water and rainfall entering the dig, or standby capacity — so it does not size a pump on its own. Discharge of the pumped water is normally consented separately.
  • Accuracy is dominated by the conductivity you type, which this calculator does not derive and which spans ten orders of magnitude. A published table value for "sand" can be a long way off the sand on your site, and the law itself loses validity where flow turns turbulent — open-graded gravel, rockfill, fractured rock and karst. The input ceilings (a conductivity of 0.1 m/s — 0.33 ft/s — and a gradient of 1) sit at the edge of that territory and anything beyond them is pulled back to the ceiling.
  • The area entered is the gross cross-section, so the result is a bulk Darcy flux across that face. It is not the speed water actually travels between the grains — that requires dividing by effective porosity, which this does not do — so it gives you no contaminant or tracer travel time.

A panel that only works once it is squeezed

Bentonite waterproofing is a granular sodium bentonite core held between a woven and a non-woven geotextile, or bonded to an HDPE carrier sheet, and it is unusual among barriers in that it is not waterproof when you install it. It is a dry clay in a bag. It becomes waterproof by getting wet: the sodium montmorillonite takes water into its interlayers, the clay expands many times its dry volume, and the resulting gel has a hydraulic conductivity in the region a manufacturer will quote against a flexible-wall index flux test to ASTM D5887. The material's whole appeal below the table follows from that mechanism — a gel can flow into a form-tie hole, close a shrinkage crack and re-seal itself around a puncture, which is exactly the kind of small local defect that sinks a sheet membrane.

The mechanism has a condition attached, and it is the condition that gets skipped. Swelling clay does one of two things depending on what is around it. Confined, it develops swelling pressure against the restraint and consolidates into a dense, low-permeability seal at the interface. Unconfined, it simply expands, loses density, disperses and washes away, and the panel that looked correct on Tuesday is a stained geotextile by the following spring. Every bentonite manufacturer states a minimum confining condition in its product literature — CETCO's Voltex data sheets express it in those terms — and it is expressed either as a depth of backfill over the panel or as a confining pressure. That figure is a performance requirement, not a recommendation, and it is why a bentonite panel on a blindside application against a shoring wall behaves differently from the same panel on a positive-side application backfilled with 200 mm lifts of well-graded fill.

Specify by test method, because the trade name tells you nothing. The relevant ones are all indices of the clay rather than of the finished panel: swell index by ASTM D5890, reported in millilitres per two grams and commonly specified at 24 mL/2 g or better for a sodium grade; fluid loss by ASTM D5891; mass per unit area by ASTM D5993, which is the number the swell arithmetic below actually consumes; and index flux by ASTM D5887. ASTM D6102 covers installing the material. A calcium bentonite, or a sodium bentonite that has undergone cation exchange in calcium-rich or brackish groundwater, gives up most of its swell — the exchange is progressive and irreversible, and it is the standard failure mode on coastal sites, on ground contaminated with hydrocarbons, and anywhere the groundwater chemistry was never sampled. Polymer-modified grades exist for exactly those conditions and cost what they cost.

The arithmetic is a two-step and worth doing on paper before the panels are on a pallet. Divide the bentonite content per unit area by the dry bulk density to get the dry clay thickness spread across the panel, then multiply by the volumetric swell factor for a confined condition to get the gel thickness that will actually stand between the water and the concrete. A panel carrying 5 kg/m² of clay at a dry density of 800 kg/m³ holds a layer only 6.25 mm thick before it sees water, and at a tenfold swell that becomes about 62 mm of gel. Both halves of that are informative: 6 mm is how little material is doing the work, and 62 mm is how much room the swell needs to find, which is a real question at a tight blindside gap or against a rigid protection layer that cannot yield.

Take the areal content and dry density off the manufacturer's data sheet and the swell factor from the grade you are actually buying, then check the gel thickness against the space the detail gives it to swell into.

The mass of bentonite clay per unit area of the waterproofing panel.

The unhydrated (dry) bulk density of the bentonite clay.

How many times larger the bentonite's volume becomes once fully hydrated.

Hydrated (swollen) gel thickness

2.46 in

Medium confidence

Swell factor varies by bentonite grade and confinement condition — this is a general reference figure. Bentonite panels require adequate confining pressure (backfill or structural confinement) to develop their full sealing performance; unconfined swell can behave differently.

Dry (unhydrated) thickness
0.25 in

Add the equipment this sizes

This result is a specification — 2.46 in — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

What this calculation does not cover

  • The swell factor on a data sheet is measured in clean water. Sodium bentonite gives up much of that swell where the groundwater is saline, hard or rich in calcium, because calcium displaces sodium in the clay and the hydrated volume collapses toward a fraction of the laboratory figure — on brackish or contaminated ground the panel has to be a contaminant-resistant grade, and the number above stops describing it.
  • A gel thickness is not a seal. Bentonite waterproofing leaks at panel laps, at pipe penetrations, at the footing-to-wall joint and at the top termination, not through the middle of a panel, and every one of those needs its own lap width, granular bentonite or detail strip — none of which follows from the thickness computed here.

Backfill is the last trade to touch the waterproofing

Everything above the panel exists to get it to its confined working state without damaging it on the way. Protection board is the first item and it is not optional on a job with standing water: it takes the point loading from angular fill, the gouging from a bucket working close to the wall, and the abrasion of settlement dragging down the face for the next decade. Board it as a plane, butted and taped or adhered per the membrane manufacturer, and take it below the level of the finished fill rather than stopping it where the backfill starts, because the corner at the base is where a bucket tooth arrives.

Then the fill itself, placed in controlled lifts and compacted with plant appropriate to the wall, which for a basement wall usually means hand-guided equipment in the first metre of the face and nothing tracked closer than the designer allows. Two constraints run at once. The wall is not designed for one-sided backfill until it is propped by the ground floor slab or by temporary props, and a permanent basement wall pushed inward at first lift is a demolition, not a defect. And the confinement the bentonite needs builds with the fill, so premature hydration — a panel left exposed through a wet week before any fill arrives — swells the clay with nothing to swell against and produces a low-density gel that will never recover its density when the fill finally lands. Sheeting exposed panels, and sequencing the fill to follow the waterproofing rather than the other way round, is what stops that.

Where a drainage composite goes in against the tanking, it goes over the protection board, not directly against the panel, and its geotextile face turns toward the soil. The rule is uncomfortable but consistent: nothing that channels water is allowed to sit between the barrier and the concrete, because a drainage layer inside the barrier is a distribution system for whatever gets past it.

A tanked wall from the soil face inward

A basement wall taken through its thickness from the soil face inward: granular backfill placed in compacted lifts, a dimpled drainage composite, protection board across the whole face, the bentonite panel that swells against the concrete, and the water-resisting wall with a waterstop cast into its kicker joint.
  1. Granular backfill — placed in controlled lifts against a wall that is not propped until the ground floor is on, and it is the fill that develops the confining pressure the panel needs Backfill Compaction Lift Count Calculator
  2. Drainage composite — dimpled core with its filter fabric turned toward the soil, rated per metre of width at a stated compressive load rather than unloaded on a bench Foundation Sheet Drain Drainage Rate Calculator
  3. Protection board — takes the point loads and the settlement drag that would otherwise arrive on the panel, and is counted in sheets against the whole submerged wall face Foundation Waterproofing Protection Board Calculator
  4. Bentonite panel — dry clay on delivery and a sealing gel only after it has hydrated under confinement, lapped to the width the manufacturer states and never left exposed to a wet week Bentonite Waterproofing Swell Thickness Calculator
  5. Water-resisting wall and waterstop — the second line of defence in a combined design: low-permeability concrete with crack widths controlled and every construction joint sealed along its full length Waterstop Linear Footage Calculator

Board count is the submerged wall face divided by the sheet you are actually buying, and the two standard sheets are not the same size — a 1.2 by 2.4 m board and a 4 by 8 ft board differ by about 3%, which shows up as a short pallet on a big perimeter.

The total below-grade foundation wall area to be protected.

The area of a single protection board sheet.

Protection board sheets needed

17 sheets

High confidence

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

What this calculation does not cover

  • The count is wall area divided by sheet area, with no allowance for cutting waste, offcuts around window wells and pipe penetrations, or the extra coverage some specifications require at corners and footing turn-downs. Rounding up is not that allowance: 50 m² of wall on 2.88 m² boards gives 18 sheets, which is 1.84 m² of spare board across the whole job.
  • Sheet area is the only property of the board this page uses, so a thin asphaltic hardboard, a dimpled polymer sheet and a rigid insulation panel all return the same count for the same wall. Whether the board's thickness and compressive strength survive the backfill material, the lift depth and the compaction plant is a separate judgement the sheet count does not make.
  • Only the boards are counted. The mastic dabs, tape, termination bar and mechanical fixings that hold the board against the wall until backfill is placed are not in the result, and neither is the membrane, the primer or the perimeter drain the board exists to protect.
  • The sheet area field runs from 1 to 6 m² (10.8 to 64.6 sq ft), so a protection course supplied as a roll cannot be entered as a single unit, and the wall area field replaces anything above its 1,000 m² maximum (about 10,760 sq ft) with that maximum. A wall larger than that has to be run in sections and the counts added, which rounds up once per section.

Water finds the joints, so the joints get designed twice

A tanked wall almost never fails through the middle of a panel or the body of a pour. It fails at the kicker joint, at the day joint on a long wall, at the tie holes, at the pile heads breaking through the slab, and at every service passing through the box. Those are not incidental details; on a typical basement they are the majority of the risk, and they are the reason BS 8102 pushes toward combined protection rather than trusting a single barrier over a structure that is full of discontinuities.

The concrete side of the answer is Type B: a low-permeability mix, adequate cover, and crack widths controlled by reinforcement and by joint layout rather than by hope. ACI 224R, Control of Cracking in Concrete Structures, is the standing reference for the crack-width thinking, and ACI 350, the code for environmental engineering concrete structures, is where the liquid-tightness discipline is written down properly — it is a code for tanks, and a basement below the table is a tank with the pressure on the outside. Waterstop is the joint-by-joint part of it: PVC or rubber profiles cast continuously into every construction and expansion joint that has to hold water, spliced by heat welding rather than by overlap and taped, with proprietary fittings at corners and T-intersections. The US Army Corps of Engineers specification CRD-C 572 covers the PVC material. Hydrophilic strips are the other common tool and behave like the bentonite above — they swell to seal, which means they must be positioned where they are confined, and they must not be allowed to hydrate before the pour arrives.

Take the joint length off the drawing rather than off the wall length. On a rectangular basement the kicker joint runs the full internal perimeter, then every vertical day joint in the wall adds its height, then the slab joints and every construction joint at a return. It adds up faster than crews expect, and waterstop is the item that stops a pour at four in the afternoon because a corner fitting is missing. Carry a real waste allowance: splices, corners and cut-and-fit around reinforcement all consume material that a straight-run measurement does not see.

Total every joint that has to hold water — perimeter kicker, wall day joints, slab joints, returns — then add the waste that splices and corner fittings genuinely consume.

SettingsSettings for this calculation
Who is doing the work?

The standard allowance most suppliers and estimating guides assume for ordinary work.

The sum of all construction/expansion joint lengths requiring a waterstop seal.

Extra material for splices, corners, and cuts.

Waterstop needed

182 linear ft

Medium confidence

Corners and T-intersections need factory or field-fabricated waterstop fittings, which use more material than a straight run — increase the waste factor for joint layouts with many corners.

Base joint length (no waste)
165 ft

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

165 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • This returns a length, not a specification. Waterstop width, profile — flat dumbbell, centerbulb, ribbed, hydrophilic — and material are selected from hydrostatic head, expected joint movement and chemical exposure, and none of those are inputs here.
  • Prefabricated corner, tee and cross fittings are not counted. Those are ordered as individual pieces off the joint layout rather than as linear stock, and the waste percentage pads the straight run instead of producing a fitting schedule.
  • The figure is a raw length, not a coil count. Waterstop ships in fixed-length rolls, and the offcuts left where a roll does not divide evenly into a joint run are not modelled — the waste factor is a flat percentage, not a per-splice or per-roll calculation.
  • It does not decide which joints need a seal. You supply the total; water table depth, hydrostatic head and the project's waterproofing design determine which construction and expansion joints require waterstop, and this take-off is not a substitute for that design.
  • Nothing beyond the waterstop itself is included. Hydrophilic strips, injectable hose, joint sealant, bond breakers, split formwork, and the hog rings or tie wire that hold the waterstop centred and upright during the pour are all separate items.

Resist it, relieve it, or both, and know which you have chosen

A drainage composite against a tanked wall is not decoration and it is not a second membrane. It is a decision to cut the head at the face, and it changes the whole problem: the barrier now sees a much lower pressure, the seepage the ground delivers goes up because the gradient at the wall went up, and something downstream has to accept that flow in perpetuity. Above the water table this is nearly free. Below it, the composite discharges to a drain that is itself below the standing level, which means the discharge has to be pumped, which means the building has committed to a permanently powered, permanently maintainable system for the life of the structure — the Type C bargain, and a legitimate one when the sump, the duty and standby pumps, the alarm and the access are all designed as a maintainable installation rather than added at handover.

Check the arithmetic against the seepage before this becomes an argument. A composite rated at 5 litres per second per metre of width, over a 40 m perimeter, has a nominal capacity around 200 litres per second. Put the seepage on the same 40 m of wall before comparing: the silty-sand example delivered 0.12 litres per second across an 8 m face, so the same ground across the full perimeter hands over about 0.6 litres per second — still more than two orders of magnitude below what the sheet is rated to carry. The drainage plane is essentially never the constraint. The collector pipe, the sump, the pump curve at real total head and the outfall are the constraint, every time, and the rated capacity of the sheet is quoted at a stated compressive load that the backfill will exceed if nobody checks. Design the chain, not the sheet.

Scale the product's rated per-metre capacity across the wall run and set it beside the seepage figure from earlier in this article — the comparison is what tells you which component in the chain is actually doing the limiting.

The drainage product's rated flow capacity per unit width, from the manufacturer's data sheet.

The total width of foundation wall covered by the sheet drain.

Total drainage capacity

213 CFM

Medium confidence

Rated flow capacity varies by product and compressive load condition (capacity typically decreases under soil/backfill load) — use your specific sheet drain product's rated capacity under expected field loading, not an uncompressed lab value.

Add the equipment this sizes

This result is a specification — 213 CFM — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

66 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • This is the supply side only. A capacity means nothing until it is set against the flow that actually arrives at the wall, and that comes from the catchment above and around the excavation, the permeability of the backfill and the natural soil behind it, and the design storm — none of which appear on this page. A drain rated at three times the flow it will ever see and one rated at a tenth of it return the same confident number here.
  • Rated flow assumes the drain stays open, and what keeps it open is the filter fabric. Fines migrating out of the backfill blind the geotextile over years, and once it blinds, the core behind it is dry and useless whatever the lab rating says. The fabric's opening size has to be matched to the actual backfill gradation — a silty or fine sand backfill against the wrong fabric is the usual way a drainage plane stops draining.
  • Capacity assumes an unbroken path in and out. The sheet has to start at the footing drain and run continuously up to near grade, with the top terminated so surface water and soil cannot get in behind the fabric, and every joint lapped in the direction of flow. A plane stopped short of the footing, or one torn during backfill, delivers a fraction of this figure regardless of what the product is rated at.

The last look anybody will ever get

A Type A barrier below the water table has no repair path from the inside. Once the fill is in, the wall is inaccessible for the life of the building, and an injection repair from within is fighting a permanent head through a defect it cannot see. That asymmetry is why the pre-backfill inspection carries more weight here than in any other part of the envelope, and why it belongs to somebody with authority to stop the machine.

Photograph everything, geolocated and dated, before each lift goes in. Not for the file — for the day in eleven years when a damp patch appears at one internal corner and the only useful question is what was actually built behind it.

  1. Confirm the design water level in the waterproofing specification matches the piezometer record, not the level in the open dig.
  2. Walk every lap on the panels against the manufacturer's stated lap width, and check that laps run so the upper sheet sheds onto the lower one.
  3. Check every penetration collar, pipe seal and pile-head detail against the specialist's drawing rather than against the general arrangement.
  4. Verify the waterstop is continuous through corners with fittings, heat-welded at splices, and held in position so the pour cannot fold it over.
  5. Confirm nothing that channels water — no drainage composite, no free-draining fill — sits between the barrier and the concrete anywhere on the face.
  6. Check the panel termination at grade is protected, mechanically fixed and sealed to the detail, since that edge is the one that will be disturbed later by landscaping.
  7. Confirm the panels are dry and unhydrated at the moment the fill goes in, and that the first lifts are placed to the compaction requirement rather than tipped.
  8. Record the whole face photographically, then hand the owner a maintenance description for anything pumped, with the pump duty, the alarm and the access route named.

Settle these before the shoring comes out

Seven figures that decide whether this is a resisting box, a drained one, or both — and all of them are cheaper to argue about now than after the fill is in.

  • Design water level — Highest credible level for the design life, from piezometer records, not the level standing in the dig.
  • Measured hydraulic conductivity — From a field slug or pumping test where possible; note whether the value is horizontal or vertical.
  • Seepage at the wall face — k, gradient and submerged face area through Darcy — the number that sizes dewatering and any relief layer.
  • Gel thickness under confinement — Areal bentonite content divided by dry density, times the swell factor for the grade being bought.
  • Confining requirement — Depth of fill or confining pressure the panel manufacturer states, and the lift plan that reaches it.
  • Joint length holding water — Perimeter kicker, wall day joints, slab joints and returns, plus waste for splices and corner fittings.
  • Protection board sheets — Submerged wall face divided by the actual sheet size — the metric and imperial boards are not the same area.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • BS 8102:2022 Protection of below ground structures against water ingress — Code of practice
  • BS EN 1997-1 Eurocode 7: Geotechnical design — General rules, on hydraulic failure by uplift, heave and internal erosion
  • International Residential Code Section R406, Foundation Waterproofing and Dampproofing
  • International Building Code Section 1805, Dampproofing and Waterproofing
  • ASTM D5092 Standard Practice for Design and Installation of Groundwater Monitoring Wells
  • ASTM D4044 Standard Test Method for (Field Procedure) for Instantaneous Change in Head (Slug) Tests for Determining Hydraulic Properties of Aquifers
  • ASTM D5084 Standard Test Methods for Measurement of Hydraulic Conductivity of Saturated Porous Materials Using a Flexible Wall Permeameter
  • ASTM D2434, the constant-head permeability test for granular soils
  • ASTM D5890 Standard Test Method for Swell Index of Clay Mineral Component of Geosynthetic Clay Liners
  • ASTM D5891 Standard Test Method for Fluid Loss of Clay Component of Geosynthetic Clay Liners
  • ASTM D5993 Standard Test Method for Measuring the Mass Per Unit Area of Geosynthetic Clay Liners
  • ASTM D5887 Standard Test Method for Measurement of Index Flux Through Saturated Geosynthetic Clay Liner Specimens Using a Flexible Wall Permeameter
  • ASTM D6102 Standard Guide for Installation of Geosynthetic Clay Liners
  • ACI 224R Control of Cracking in Concrete Structures
  • ACI 350 Code Requirements for Environmental Engineering Concrete Structures
  • US Army Corps of Engineers CRD-C 572, Specification for Polyvinylchloride Waterstop
  • CETCO Voltex bentonite waterproofing membrane product literature, for confinement and lap requirements

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.