Worked example · Roofs and lofts

A 40 m² (431 sq ft) flat roof stripped and recovered, warm-roof build-up

The takeoff for a small warm flat roof, in the order the decisions are actually made — outlets first, because the falls run to them and everything above follows: the tapered scheme, the insulation volume, the membrane area and the number of seams.
  • 8Steps, in order
  • 3Figures computed
  • UK, metric firstModelled for

The job

Modelled, not recorded. Every figure on this page is re-run through the calculator it names whenever the site is built; the estimate is worked, but no job was carried out, so the last section gives the mechanism of each likely error rather than a measured overrun.

A flat roof takeoff looks like an area calculation and is really a drainage problem with an area attached. The roof is not flat: it falls to its outlets, and where those outlets are decides the tapered insulation scheme, which decides the insulation volume, which decides the upstand heights, which decides the membrane area.

So the first decision on this job is not a quantity at all. It is whether the existing outlets stay where they are. Keeping them is cheaper and constrains the scheme; moving one can halve the tapered insulation on a roof of this size. That decision is made in the first ten minutes and it dominates the cost.

The build-up here is a WARM roof: deck, vapour control layer, insulation, membrane — insulation above the structure, so the deck stays warm and there is no ventilated void to detail. That is the common arrangement for a recover, and it is why the upstands, the outlets and the thresholds all have to be checked for height before anything is ordered: adding insulation raises the roof surface, and every upstand has to still be high enough above the finished level afterwards.

The area is where estimators under-order, and not because the arithmetic is hard. A flat roof's membrane quantity is the plan area PLUS every upstand, every return into an outlet, every overlap and every seam — and on a small roof with a parapet, the upstands can be a substantial fraction of the plan area.

What was measured, and how

  • Plan area, corner to corner in both directions

    About 8.0 × 5.0 m (26 ft 3 in × 16 ft 5 in), checked on both diagonals

    Measured at deck level rather than from a drawing, because a recover works to what is there. Diagonals taken as well — a roof that is out of square changes how sheets lay out and how much is wasted at the edges.

  • Outlet positions and their invert levels

    Two outlets, both on the long parapet side

    Located and levelled before anything else, because they are the low points the falls run to. The invert — the level water actually leaves at — matters more than the outlet's position on plan.

  • Upstand heights available at every edge

    Parapet gives ample height; the door threshold is the tight one

    Measured from the existing deck to the top of each parapet, threshold, door sill and abutment. This is the constraint that decides how much insulation can be added, not a preference.

  • The existing build-up, by opening up

    Timber deck, existing insulation dry at the opening

    A small opening cut to see what is actually there: deck type, whether there is existing insulation, whether it is wet. A recover over wet insulation traps the water permanently.

  • Every penetration and abutment

    One soil vent, one wall abutment along the 8 m (26 ft) side

    Counted and measured individually — soil vents, flues, handrail bases, an abutment to the house wall. Each is a detail with its own membrane, and collectively they are where the time goes.

The takeoff, in order

Each step needs something from the one before it, which is why the order is part of the answer.

Working along0 of 8 run
  1. Set the tapered insulation scheme from the outlets

    Needs
    The outlet positions and inverts, the plan dimensions, and the minimum fall required — all from the measurements above.
    Produces
    The taper layout and, crucially, the minimum and maximum build-up depths. Everything downstream depends on this, which is why it is first. On this roof the fall crosses the 5.0 m (16 ft 5 in) width, from the house-wall abutment down to the outlets on the parapet side. At the 1 in 40 design fall that BS 6229 is commonly read as pairing with a 1 in 80 finished fall, that run adds 125 mm (4.9 in) to the starter at the outlets, so the thickest point lands against the house wall; the 50 mm (2.0 in) starter is an assumption until the board schedule fixes it.

    Result175 mm (6.9 in) at the house wall, from a 50 mm (2.0 in) starter at the outlets

    Tapered Roof Insulation Slope Calculator
  2. Check the build-up against the upstand heights

    Needs
    The maximum build-up depth from the taper scheme, against the measured upstand and threshold heights.
    Produces
    Whether the scheme fits. If the threshold is too low for the thickest point, the scheme changes here — before anything is ordered rather than after it arrives.
  3. Quantify the insulation and the cover board

    Needs
    The plan area and the taper scheme's depths, since a tapered layout consumes a volume rather than an area times one thickness.
    Produces
    The board quantities by thickness, and the cover board that protects the insulation from the membrane's fixing and foot traffic. Unlike the tapered boards, the cover board is one thickness over the whole plan, so it really is an area: 14 whole sheets over the 40 m² (431 sq ft), before the cuts at the edges and round the soil vent.

    Result14 sheets of 2.88 m² (31 sq ft) board over 40 m² (431 sq ft) of plan

    Roof Insulation Cover Board Calculator
  4. Quantify the membrane

    Needs
    The plan area PLUS every upstand, return and overlap — the extents from the measurements, not the plan area alone.
    Produces
    The roll count and, from the roll width against the roof's dimensions, how many seams there will be.
  5. Quantify the seam treatment

    Needs
    The seam count and length from the roll layout in the step above.
    Produces
    The tape and primer. Seams are where a single-ply roof fails, so the layout that minimises them is worth choosing deliberately.
  6. Detail the outlets

    Needs
    The outlet positions and the finished build-up depth, because the outlet has to be dressed down into the falls.
    Produces
    The sump and outlet details. An outlet left proud of the finished falls is a roof that ponds around its own drain.
  7. Check the overflow provision

    Needs
    The roof area, the rainfall intensity and the primary outlet capacity.
    Produces
    The overflow size and position. On a parapet roof this is not optional — a blocked outlet with no overflow puts the water inside the building.
  8. Quantify the deck repairs and the vapour control layer

    Needs
    The deck area, plus whatever the opening-up found needed replacing.
    Produces
    The vapour control layer area including laps and upstands, and the deck material for repairs. On the 40 m² (431 sq ft) deck the lap allowance brings the sheet to 44.0 m² (474 sq ft), inside one of the 93 m² (1,000 sq ft) rolls the calculator counts in; the turn-ups at the parapet and the abutment are extra area rather than lap, and the repair material stays provisional until the strip.

    Result1 roll — 44.0 m² (474 sq ft) with laps, at 93 m² (1,000 sq ft) a roll

    Vapor Barrier Calculator

The figures

Each step’s computed figure for this job
StepCalculatorFigure
Set the tapered insulation scheme from the outletsTapered Roof Insulation Slope Calculator175 mm (6.9 in) at the house wall, from a 50 mm (2.0 in) starter at the outlets
Quantify the insulation and the cover boardRoof Insulation Cover Board Calculator14 sheets of 2.88 m² (31 sq ft) board over 40 m² (431 sq ft) of plan
Quantify the deck repairs and the vapour control layerVapor Barrier Calculator1 roll — 44.0 m² (474 sq ft) with laps, at 93 m² (1,000 sq ft) a roll

The waste factors, and why these ends of the ranges

The waste factor applied to each material, and why
MaterialAppliedWhy
MembraneExtents plus laps, then rounded to whole rollsThe roll width against the roof's dimensions dominates. A roof a little wider than a roll means a second roll mostly wasted, and the offcut is rarely usable on a small job. Choosing the roll direction before ordering is worth more than any percentage.
Tapered insulationThe scheme's own quantities, with an allowance for cutting at edgesTapered boards are supplied to a designed layout rather than as a stock item, so the quantity is the scheme's rather than an area times a thickness. The waste is at the perimeter and around penetrations, where boards are cut to the falls.
Seam tape and primerThe seam length with a generous allowanceRunning short mid-seam is not the same as running short of a board. Seams are the failure point of a single-ply roof and a joined-up seam made in two sessions is a weakness — this is one to over-order.
Deck repair materialA provisional allowance, confirmed after the stripWhat the deck needs cannot be known from one opening. The honest approach is a provisional quantity and a decision on the day rather than a confident figure taken off an unopened roof.

Where this estimate is most likely to be wrong

  • Membrane area

    usually under

    The plan area is the easy part. Upstands at parapets and abutments, returns into outlets, the dressing around every penetration and the laps between sheets all consume membrane, and on a small roof with a parapet on one side those extents are a substantial fraction of the plan area rather than a rounding.

    Narrow it by: Measuring every upstand height and every penetration before ordering, and adding them to the plan area rather than applying a percentage to it.

  • Deck repairs

    usually under

    Nobody knows what the deck is like until the old covering is off. One inspection opening shows one spot, and the areas most likely to have failed are the ones under the old outlets and at the abutments — which is exactly where an opening is least likely to be cut.

    Narrow it by: Carrying it as a provisional item with a rate agreed in advance, rather than as a fixed quantity that will have to be varied.

  • Tapered insulation

    either way

    The scheme follows the outlets. Keeping existing outlets constrains the layout and can force a much thicker maximum build-up; moving one outlet can change the volume substantially on a roof this size. The decision is made before any quantity exists, and it moves this line more than any allowance.

    Narrow it by: Pricing the taper scheme both ways — outlets as they are, and outlets relocated — before deciding, since the insulation saving can exceed the drainage work.

  • Detailing time rather than material

    usually under

    The estimate counts area and the work is in the details. A soil vent, a wall abutment, two outlets and a door threshold are each a separate hand-formed detail, and on a 40 square metre roof they can take longer than the field membrane they interrupt.

    Narrow it by: Counting the details as items with their own allowance rather than treating the roof as an area with some edges.

Tools this job needs

Frequently asked questions

How thick does tapered insulation get on a small flat roof?
On this roof the water runs 5.0 m (16 ft 5 in) from the house wall to the outlets on the parapet side. At a 1 in 40 design fall the taper rises 125 mm (4.9 in) over that run, so on an assumed 50 mm (2.0 in) starter board at the outlets the build-up reaches 175 mm (6.9 in) at the wall. Any flat base board the U-value needs, plus the cover board and the membrane, adds to that depth.
How many cover boards does a 40 m² flat roof need?
Fourteen for this 8.0 × 5.0 m (26 ft 3 in × 16 ft 5 in) roof: 40 m² (431 sq ft) divided by a 1.2 × 2.4 m board of 2.88 m² (31 sq ft), rounded up to whole sheets. A 4 × 8 ft board of 32 sq ft (2.97 m²) also comes to 14. That covers the plan only; the cuts at the parapet, the abutment and round the soil vent come on top.
How much vapour control layer does a 40 m² warm roof need?
One roll of the 93 m² (1,000 sq ft) sheet the calculator counts in: the 40 m² (431 sq ft) deck plus a lap allowance of a tenth comes to 44.0 m² (474 sq ft). The turn-ups at the parapet and the house-wall abutment are extra area rather than lap, so they are measured and added, and on a roof this size they sit well inside the same roll. A system VCL sold in another roll size divides into 44.0 m² instead.