Job takeoff
Solar panels (PV) with battery storage takeoff
Fit a solar PV array on a pitched roof with a battery: the scaffold face the array is fixed from and a skip or collection for the packaging, with the network operator's (utility's) notice, the roof hooks, the rails and panels, the DC cabling, its isolation and labels, the inverter and its circuit and isolator (disconnect), the battery and any alarm the rules ask for where it stands, and the tests listed and never certified, and the roof's capacity and the array's layout flagged.
A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.
- 5Measurements in
- 2Trades out
Give the job once
Every figure on the right follows these, in the units you choose.
Been given a quote for this job?
Paste it into the solar panel and battery quote check: each line is read against these same calculators — what it leaves out, what it adds, and what to ask.
Check the quoteEvery trade, from those dimensions
then change a dimension, and each line shows what moved.
| Trade | Quantity | |
|---|---|---|
Scaffold face along the eavesScaffold Face Area and Hire Quantity CalculatorFace area along the wall under the panels, up to the eaves: the platform the hooks, rails and panels are fixed from, with the edge protection that stops a fall off the roof and a loading bay for the panels. The weeks you gave stand beside the face in the working. Shown only where you give a length.
Why this quantity?
Resting on
Change any other figure on the Scaffold Face Area and Hire Quantity Calculator | 544.5 ft² of face | |
Skip (dumpster) or a collection for the packagingSkip & Dumpster Size CalculatorThe loose waste over the panels' area at the depth you gave, as light waste: the panels' boxes and pallet, the rails' and hooks' packaging, the inverter's and the battery's cartons, rail and cable offcuts, and any tiles broken as the hooks go in. A load this size goes back in the installer's van as readily as in a skip; the volume is the same. A damaged panel or an old battery is not general waste, and goes back through its maker's or a recycler's take-back.
Why this quantity?
Resting on
Change any other figure on the Skip & Dumpster Size Calculator | 0.679 yd³ | |
Scaffold face along the eavesScaffold Face Area and Hire Quantity CalculatorFace area along the wall under the panels, up to the eaves: the platform the hooks, rails and panels are fixed from, with the edge protection that stops a fall off the roof and a loading bay for the panels. The weeks you gave stand beside the face in the working. Shown only where you give a length.
Why this quantity? | 50 m² of face | |
Skip (dumpster) or a collection for the packagingSkip & Dumpster Size CalculatorThe loose waste over the panels' area at the depth you gave, as light waste: the panels' boxes and pallet, the rails' and hooks' packaging, the inverter's and the battery's cartons, rail and cable offcuts, and any tiles broken as the hooks go in. A load this size goes back in the installer's van as readily as in a skip; the volume is the same. A damaged panel or an old battery is not general waste, and goes back through its maker's or a recycler's take-back.
Why this quantity? | 0.5 m³ |
Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance on the row, or open its reasoning to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.
Labour and programme
Person-hours for the rows going in, from trade rules of thumb: a range for each piece of work, never a price.
- Skip (dumpster) or a collection for the packaging0.5 h (0.3–1.6)
About 0.5 person-hours in the rows that carry them, between 0.3 and 1.6.
Trade by trade
- Labourer1 labourerunder a quarter of a day
About under a quarter of a day, one trade after another at eight hours a day. Left out: drying and curing, deliveries, inspections, trades overlapping.
1 row carries no hours of its own
- Scaffold face along the eaves: Scaffolding is not rated here: it is usually erected by a scaffolding firm and priced as hire, and where your own crew puts it up, the system and the height set the time.
Labour and programme
Person-hours for the rows going in, from trade rules of thumb: a range for each piece of work, never a price.
- Skip (dumpster) or a collection for the packaging0.5 h (0.3–1.5)
About 0.5 person-hours in the rows that carry them, between 0.3 and 1.5.
Trade by trade
- Labourer1 labourerunder a quarter of a day
About under a quarter of a day, one trade after another at eight hours a day. Left out: drying and curing, deliveries, inspections, trades overlapping.
1 row carries no hours of its own
- Scaffold face along the eaves: Scaffolding is not rated here: it is usually erected by a scaffolding firm and priced as hire, and where your own crew puts it up, the system and the height set the time.
Setups you have saved
The build-up, the dimensions and any allowance you changed — kept on this device, and reusable on any job. Your prices are not copied in: they stay in your price book, so a setup never holds a stale one.
How far does a budget go?
At your own prices, with this build-up unchanged.
About this job
A solar array on a pitched roof is fixed through the covering to the rafters beneath it. On a tiled or slated roof the tiles are lifted at each fixing, a hook is screwed to the rafter, and the tile beneath is notched so the tiles lie flat over it again; on an asphalt shingle roof a flashed mount goes through the covering and is lapped under the course above. Aluminium rails bolt to the hooks, and the panels (modules) clamp to the rails. How many panels, how they are strung together and how large the inverter and the battery are come from the array's design for the roof's direction, its shading and what the house uses; the solar pages on this site that answer those are sizing pages, and none is a row here. Where the panels may go is the design's too: in the US the codes keep clear pathways and setbacks round an array for firefighters, and in the UK the mounting system's wind design may keep panels off the roof's edges. Whether the rafters carry the array, with the wind and snow on it, is an engineer's question on an older or altered roof, a question this page raises and leaves to the engineer, and the hooks are a provisional item, their number known once the rafters are found.
Almost everything after the rails is electrical work, and most of it is on the DC side, which cannot be switched off while light falls on the panels. Each panel's leads are clipped to its frame as it goes on, and plugging them into strings is the installer's work as the DC cable is run down through the roof to the inverter; where that cable enters the roof it is weathered with a cable-entry tile or a sealed gland. The inverter hangs where it can shed its heat, with a DC isolator beside it, or with rapid shutdown devices at the array where the US code asks for them, and its AC side is a new circuit to its own way in the consumer unit (service panel) through a local isolator (a disconnect). Labels at the board, the meter and every isolator tell the next electrician, or a firefighter, that the house has a second source of supply. The battery connects to the inverter or to its own, and where it may stand is written down: PAS 63100 in the UK, and the residential code's energy storage rules and NFPA 855 in the US, restrict where it may go, keeping it out of bedrooms among other places, and may ask for a smoke or heat alarm where it stands.
The rows are the two things on this job a page measures: the scaffold face the array is fixed from, with the edge protection at the eaves and a loading bay for the panels, and the waste. A British installer works from a scaffold; a North American crew also works from ladders, harnessed to anchors on the roof, and where no scaffold goes up its length is 0 and its row goes too. Everything else is listed, with its condition where it has one: the network operator's notice or application (G98 or G99 in Great Britain, the utility's interconnection agreement in North America), the hooks, the rails and panels, the DC cabling, its isolation and labels, the inverter with its generation meter, its circuit and isolator, a new board where the old one cannot take a second source, the battery and any alarm the rules ask for, bird mesh where it is wanted, and the tests. The inverter's settings, with any export limit the network operator sets, are entered as it is switched on after the tests. In the UK an export payment or a grant rests on the installation being registered under MCS, and its MCS certificate comes with the handover; across North America the permit's inspections and the utility's permission to operate come before the system runs.
How each line reads
- Base
- What the calculator gives for these dimensions, before anything is added.
- Allowance
- Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
- Adjusted
- The base with its allowance on top.
- Order
- What to buy: the adjusted figure in whole boards, bags, rolls or lengths.
The order this happens in
Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.
- Have the array designed for the roof: the panels, how they are strung, the inverter and the battery, and where each may go, including the pathways a US roof keeps clear and the edge zones of a UK mounting system; have the rafters looked at where the roof is old or altered, and apply to or notify the network operator (utility) as its rules ask.
- Where the soffit, the roof covering or the board the inverter goes on is old enough, have it checked for asbestos; put up the scaffold with its loading bay, or set the ladders and the roof anchors, and protect the route through the house to where the inverter and the battery go.
- Lift the tiles or slates at each fixing, find the rafters, fix the hooks and notch the tiles back over them, or fix and flash the mounts on a shingle roof; bolt the rails, then lift the panels and clamp them with their leads clipped to the frames.
- Core the holes through the walls and ceilings, weather the cable's entry through the roof, and have the installer make up the strings and run the DC cable down to the inverter, fire-stopping it wherever it passes into a garage or through another fire-separating wall or ceiling; then, with the strings made up and the scaffold still standing, fit bird mesh round the array's edges.
- Run the AC circuit to a new way in the consumer unit (panel) with the board isolated while it is connected, replacing the board where it cannot take a second source; fit the isolator (disconnect), hang the inverter and the battery where the rules allow, fit the DC isolation, and fit any smoke or heat alarm the rules ask for where the battery stands.
- Label the board, the meter and every isolator; test the DC strings and the AC circuit and record them, then switch on, enter the inverter's grid settings and any export limit, and set up the battery and the monitoring.
- Strike the scaffold, make good the holes, clear the packaging, and hand over the certificates, the network operator's acknowledgement, the inverter's settings and the warranties and manuals.
What this takeoff does not cover
- The design of the system and its figures: how large it is, how its strings are made up and what it yields, which the designer works out. The site's sizing pages answer those figures, and none is reached here.
- A structural check of the roof and any strengthening of its rafters, which is flagged; and roof repairs found when the tiles come up, such as broken tiles, rotten battens or perished underlay.
- The network operator's or utility's approval itself, any export limit it sets and any larger supply it calls for; the notice or application is listed.
- The supplier's or utility's work on the meter, such as a smart or bidirectional meter fitted for export.
- Deciding where the energy store may stand beyond naming the rules that decide it; a smoke or heat alarm those rules ask for is listed.
- An export tariff, a grant, and the paperwork for either, beyond what the installer hands over.
- A ground-mounted rack, frames ballasted on a flat roof, solar water heating (solar thermal), and a charger for an electric vehicle: each is a job of its own.
- The scaffold's design and its inspection record, which are the scaffolder's.
Quote check
Been given a quote for this job?
Paste it into the solar panel and battery quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.
What it leaves out
Every line this takeoff has that nothing on the quote reads as.
What it adds
Labour, removal, hire, fees — each named for what it is.
What to ask
One list of questions, ready to copy. Never a verdict.
More takeoffs
Other job takeoffs
Electrical rough-in
3 tradesA starting outlet count by the North American spacing rule, the lighting load and the conduit run for first-fixing a single room.
Run this takeoffService panel upgrade
3 tradesCalculated service load by the NEC methods, a simplified floor to read it against, and the main breaker for the service being considered.
Run this takeoffRecessed lighting layout
3 tradesWhether the fittings you plan give the room enough light, how many a target level needs and at what spacing, and whether the circuit will carry them.
Run this takeoff
Frequently asked questions
- What does the solar panel and battery takeoff give for a typical job?
- Opened at Scaffold along the wall below the array 10 m · Height to the eaves 5 m · Weeks the scaffold stands 2 · Roof the panels cover 20 m² · Loose waste, as a depth over the panels 0.03 m, it orders: Scaffold face along the eaves, 50 m² of face; Skip (dumpster) or a collection for the packaging, 0.5 m³. Opened at Scaffold along the wall below the array 33 ft · Height to the eaves 16.5 ft · Weeks the scaffold stands 2 · Roof the panels cover 220 sq ft · Loose waste, as a depth over the panels 1 in: Scaffold face along the eaves, 545 ft² of face; Skip (dumpster) or a collection for the packaging, 0.68 yd³. Every figure follows the dimensions you give it.
- Which calculators does the solar panel and battery takeoff run?
- 2 calculators, one to a line: Scaffold Face Area and Hire Quantity Calculator, Skip & Dumpster Size Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
- What does the solar panel and battery takeoff leave out?
- 8 things, each named on this page: The design of the system and its figures; A structural check of the roof and any strengthening of its rafters, which is flagged; and roof repairs found when the tiles come up, such as broken tiles, rotten battens or perished underlay; The network operator's or utility's approval itself, any export limit it sets and any larger supply it calls for; the notice or application is listed; The supplier's or utility's work on the meter, such as a smart or bidirectional meter fitted for export; Deciding where the energy store may stand beyond naming the rules that decide it; a smoke or heat alarm those rules ask for is listed; An export tariff, a grant, and the paperwork for either, beyond what the installer hands over; A ground-mounted rack, frames ballasted on a flat roof, solar water heating (solar thermal), and a charger for an electric vehicle; The scaffold's design and its inspection record, which are the scaffolder's.
- Can I check a quote for this job against the takeoff?
- Yes. The solar panel and battery quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.