Conversions

Checking Whether a Loft Can Be Converted

Head height, roof type and joist depth, measured off the timber rather than the plaster, and what each one leaves: a room, a dormer, or nothing.
  • 21 minReading time
  • 11Sections
  • 6Calculators inline
  • Last reviewed

Half an hour with a torch decides more than the drawings do

You are standing on two scaffold boards laid across the ceiling joists, one hand on a purlin, insulation up to your shins, and the tape is hooked over a joist top somewhere under all of it. A builder has already been round and said it looks fine. An architect wants a fee to draw it. Neither of them has yet produced the three numbers that decide whether there is anything to draw, and all three can be had in the next half hour with a folding rule, a torch and a pencil.

Those numbers are the height between the top of the existing ceiling joists and the underside of the ridge, the kind of roof holding that ridge up, and the depth and centres of the timbers under your feet. Every later decision hangs off them. Dormer or rooflight, timber or steel, where the stair lands, whether the neighbour has to be served notice — all of it is downstream, and all of it is guesswork until the three are written down.

What comes out is not a design but a category: a straight conversion inside the roof you have, the same with a dormer on the back, a roof taken off and rebuilt, or the ceiling below dropped to borrow height upwards. It can also come out as none of those, and finding that with a torch costs nothing.

Measure to the timber, not to the plaster

The bottom datum is the top of the existing ceiling joists. Not the top of the insulation, which is going somewhere else, and certainly not the ceiling below, which is a finish on the underside of the timber and has nothing to do with where your new floor will sit. Sweep the wool aside with a gloved hand until you can see joist top, sit the end of the rule on it and hold it plumb.

The top datum is the underside of the ridge board, meaning the timber, not the felt sagging between the rafters. On a trussed roof there is frequently no ridge board at all and the apex is a pair of chords meeting at a nail plate; measure to the underside of the plate. And if a collar, a binder or a purlin crosses lower than the ridge does, that timber is your real ceiling — measure to it instead, because a rule held to the apex through a gap between collars produces a number that describes nothing you can stand in.

Take the measurement in at least three places along the ridge. Ceiling joists sag, ridges are rarely dead level over an old house, and a chimney breast or a later dormer can leave one end of the loft half a step different from the other. Take one of those readings where the top of the new flight will arrive, because headroom over a stair is a separate requirement from headroom in a room and it is checked in a different place. While the rule is out, get the clear span wall to wall, the roof pitch — a level held horizontal against a rafter, a foot marked along it, then straight down to the timber — and the height at which any purlin or collar crosses.

Then record what you cannot measure: which way the joists run, whether there is a chimney breast and on which wall, where the cold water tank sits, and whether the soil vent pipe comes up through the space. Photograph the apex, both eaves and every timber crossing the room. Six weeks later, when an engineer asks whether the strut lands on the spine wall, the photograph answers it and a second visit does not have to.

  1. Lay boards across the joists first, and bring a lamp rather than working one-handed off a torch.
  2. Clear insulation off a joist top at three points along the ridge line and mark each one, so the same datum is used every time.
  3. Measure joist top to the underside of the ridge board at all three, and write down the smallest, not the average.
  4. Measure again at the head of the proposed flight, and note anything crossing above it.
  5. Take the clear span wall to wall, and the pitch off a rafter with a level and a rule.
  6. Measure joist depth, width and centres in two places, and record the direction they run.
  7. Photograph the apex, both eaves, every purlin, strut and collar, and the foot of each strut where it lands.

What the rule is measuring through

A section through a pitched loft between the ceiling below and the ridge above: the covering on the outside, the rafters under it, the insulated lining that will close the slope, the new structural floor that will carry the room, and the existing ceiling joists and plaster beneath.
  1. Covering, battens and felt — sits outside the structure and outside the measurement, but has to come off for anything that raises or re-pitches the roof
  2. Rafters, purlins and collars — the depth already inside your reading, and the members whose spacing and support decide whether the roof is cut or trussed Common Gable Rafter Length Calculator
  3. Insulation and lining on the slope — comes off the top of the height budget wherever the rafters are too shallow to hold the insulation and an air path together Insulation Batt Calculator
  4. New structural floor — joists spanning to the walls with the deck over them, taking height off the bottom of the budget unless they can be dropped level with the old ceiling joists Ceiling Joist Spanning Lineal Lumber Aggregator
  5. Existing ceiling joists and ceiling — the bottom datum for every measurement above it, and a ceiling that was never designed to be walked on

The height you measure is not the height you keep

What is on the rule is a gross figure. Two build-ups come out of it, one at each end, and neither is a specification choice you can trim your way out of: a new structural floor at the bottom, insulation and a lining under the rafters at the top. What survives between them is what a person stands in, and it is routinely 300 to 400 mm less than the number that got everybody excited in the loft.

The floor is the larger and the more variable of the two. Existing ceiling joists hold up a ceiling; new floor joists hold up people, furniture, a partition and a bath. They generally span wall to wall clear of the old ones. If they can be landed on new plates or on steels at the same level as the existing joists, the loss is the deck alone. If they have to sit over the top of the old ones — which is what happens when there is nowhere to form a bearing at the right height — you lose their full depth as well, and a 195 or 220 mm joist plus a deck is most of a stair riser gone before anything else is decided.

The top end is set by how the slope gets insulated. Rafters in a house built before insulation was taken seriously are often 100 mm deep, and 100 mm will not hold a modern insulation thickness and a clear ventilation path at the same time. The depth therefore goes either over the rafters, which means the covering comes off and the job changes category, or under them, which means it comes straight out of your head height. Where there is a flat ceiling at collar level the same subtraction happens up there instead. Settle which of those it is before believing any figure, because the two answers differ by more than the amount most schemes have to spare.

Which heights are rules and which are habits

The figure quoted at homeowners more than any other is 2.3 m, and it is not a building regulation anywhere in the United Kingdom. It comes from the Technical housing standards — nationally described space standard, a planning document asking for 2.3 m floor to ceiling over at least 75 per cent of the gross internal area, and it bites only where a local plan has adopted it. The 2.2 m an experienced builder mutters while looking up at your ridge is a different thing again: a trade habit about what feels like a room, worth listening to and worth labelling as habit.

England's Building Regulations set no general minimum ceiling height for a habitable room. What they set is headroom over the stair, and that is the constraint that actually fails conversions here. Approved Document K asks for 2 m of clear headroom on a flight, with a concession written specifically for loft conversions where 2 m cannot be achieved — a reduced height measured at the centre of the stair width and a lower one again at the side, with the figures given in the edition in force. Scotland works to the Building Standards Technical Handbook and Northern Ireland to its own technical booklets. Note where the pinch lands: not in the middle of the new room, but at the head of the flight, under the slope of the roof you are climbing into.

Under the International Residential Code the room itself is regulated and the arithmetic is harder to argue with. Section R305 asks for 7 ft of ceiling height in a habitable space, and for a room under a sloping ceiling it does two things at once — at least half of the required floor area has to reach that 7 ft, and any part of the floor where the ceiling is below 5 ft does not count towards the required area at all. Section R311.7 governs the stair, at 6 ft 8 in of headroom. That 5 ft line is the one that changes the conversation, because it stops the question being whether the loft fits a room and starts it being how much of the loft is a room.

Where the lines fall is trigonometry and it is worth doing on the spot. Height above the joist tops falls away from the ridge at the tangent of the pitch: 839 mm for every metre out from the centreline on a 40 degree roof, 577 mm on a 30 degree one. Take a semi spanning 6.2 m at 40 degrees, which puts the ridge 2.6 m above the joist tops before any deductions. The 7 ft line falls 555 mm either side of centre, a full-height strip 1.1 m wide. The 5 ft line falls 1.28 m either side, so the strip that clears it is 2.56 m across in a house 6.2 m deep. Both of those are lines on the raw geometry, drawn between joist top and rafter, and the code measures its own from finished floor to finished ceiling: put the 300 to 400 mm of build-up back in and each line walks in towards the ridge, the 5 ft one by about 0.4 m on each side and the 7 ft one until there is very little strip left at all. Do it both ways, because the gap between the footprint and the floor is the whole reason dormers exist, and it is also why a cost per square metre taken over the footprint is a number that flatters every scheme it touches.

The height lines a loft survey actually uses, what each one is measured between, and which document sets it. Confirm every figure against the edition in force where you are building.
Height lineMeasured betweenWhat sets it
Raw survey heightTop of the existing ceiling joists to the underside of the ridge boardNothing — it is a gross figure, and both build-ups come out of it
Finished height at the highest pointFinished floor to finished ceilingIRC Section R305 sets 7 ft; England's Building Regulations set no general minimum for a room
The 5 ft line under a slopeFinished floor to the sloping ceilingIRC Section R305 — floor below this line does not count towards the required habitable area
The 7 ft line under a slopeFinished floor to the sloping ceilingIRC Section R305 — at least half the required floor area has to reach it
2.3 m over 75 per cent of the areaFinished floor to finished ceiling, across the gross internal areaTechnical housing standards — nationally described space standard, where a local plan has adopted it
Headroom over the new flightPitch line of the stair, vertically to whatever is above itApproved Document K at 2 m with a loft-conversion concession; IRC Section R311.7 at 6 ft 8 in
Height at the eavesJoist top to the rafter, at the wall plateNothing regulates it — but it decides where the cupboards, the bed and the shower can go
The height lines a loft survey actually uses, what each one is measured between, and which document sets it. Confirm every figure against the edition in force where you are building.

Put in the width of the strip that clears the height line rather than the width of the house, and the length of loft it runs for, and the area that comes back is the one every later figure per square metre should be divided by.

Total area

150 sq ft13.9 m²

Square feet
149.5 sq ft
Square yards
16.61 sq yd

Look up: webs, or purlins

Roof type is visible in a torch beam and it moves the price bracket more than head height does. A cut roof, built on site rafter by rafter, has rafters at 400 or 450 mm centres bearing on one or two purlins per slope, with struts running down from those purlins to a wall below and collars or binders tying the pairs. The middle of the volume is open, which is why a cut roof converts: its members sit around the edges of the space rather than through it, and the ones that do cross can usually be replaced by something designed to take their place.

A trussed roof is a series of engineered frames at roughly 600 mm centres with diagonal webs crossing the middle in a W, and those webs are not spare timber. Each truss is designed as a single object with every member in a calculated state of tension or compression, and cutting one web hands its force to a member that was never asked to take it. Nothing in a trussed roof is cut on site without a replacement structure designed for it, which in practice means steel beams, a new floor spanning between them and a new set of rafters over the top — a different job in a different bracket, and one a homeowner needs to understand before the cheapest quote arrives. Trussed Rafter Association technical literature is the reference for what may and may not be done to a trussed rafter on site.

A minority of houses built from the 1990s onward have attic trusses, designed from the outset with a clear rectangle down the middle and a bottom chord sized for habitable loading. If the webs are pushed out to the sides and there is standing room along the centre of an obviously modern roof, that is very likely what you have, and the job has just become straightforward. The original truss design or the manufacturer's stamp on a chord confirms it; the shape alone does not.

On a cut roof, follow the struts down. The assumption behind the whole structure is that they land on a load-bearing wall carried to the foundations, and a strut whose foot sits on a stud partition somebody put up in the 1970s is carrying part of your roof on nothing at all. Note where the purlins run too. A purlin crossing 1.6 m above the joists on the exact line where the bed was going is not a detail to resolve later; on that side of the room it is the ceiling, and either the scheme accommodates it or a new structure replaces it.

Three ways to buy height, and what each one costs

A dormer is the cheapest of the three per square metre of usable floor: vertical cheeks and a flat or pitched roof pushed out of the slope, adding full standing height across its width and moving the 5 ft line out to the dormer face. In England a rear dormer is often permitted development under Class B of the Town and Country Planning (General Permitted Development) (England) Order 2015, subject to a volume allowance — commonly cited as 40 m³ on a terraced house and 50 m³ on a detached or semi-detached one — and to the conditions attached to that class. Those rights do not exist for flats, are removed in conservation areas and wherever an Article 4 direction applies, and any previous enlargement has already spent part of the allowance. Check it against the house's history before the dormer is drawn.

A raised roof means taking the covering and the structure off and rebuilding higher, steeper, or both. It buys height across the whole plan rather than in a strip, and it needs planning permission virtually every time, because it changes the outline of the house as seen from the street. It is also the only one of the three where rafter length stops being a curiosity and becomes a quantity: a proposed ridge height over a known span gives a pitch, and that pitch over the same span gives the rafters a carpenter has to cut, plus the sloping ceiling area somebody has to line.

The third move is downwards. Strip the ceiling of the room below and re-form it lower, or hang the new floor structure below the old ceiling line, and the height comes out of a room that already has some to spare. In a Victorian house that is frequently true and in a 1970s estate house it never is, so this option is decided by measuring the room below rather than by preference. It is disruptive in the specific way that having a bedroom out of use for three weeks is disruptive, and it takes the door heads, the window heads, the picture rails and the wiring down with it.

In a terrace or a semi, all three run into the wall you share. Raising a gable, cutting a pocket for a steel bearing into a party wall, or building a dormer up to it is notifiable work under the Party Wall etc. Act 1996, which sets out the notice that has to be served and what happens if the neighbour dissents. It is a civil process running alongside the job, not a planning matter, and building control will not raise it. Left until the steels are ordered, it is what stops a conversion for a season. None of the three schemes should be chosen from a brochure in any case: each answers a different shortfall, and the measurements say which shortfall you have.

Set it out along the run

For a raised or re-pitched roof, the span and the intended pitch — entered as rise per 12 of run, not as the degrees used above — give the rafter length including the tail, the first real quantity in that scheme and the length that tells you how much sloping ceiling will need lining afterwards.

Total rafter length (incl. overhang)

16 ft4.88 m

Rafter length to ridge (no overhang)
14.53 ft4.43 m
Overhang tail length
1.49 ft0.45 m

The joists were only ever holding up a ceiling

Get a rule into the side of a joist and take the depth, the width and the centres, in two places rather than one. In a pre-war house this is commonly 100 by 50 at 400 mm, sized for lath and plaster below and one person crawling to a tank above. The codes are explicit about the difference. IRC Table R301.5 designs an uninhabitable attic without storage for 10 psf, one with limited storage for 20 psf, and a habitable attic or an attic served by a fixed stair for 30 psf. Eurocode 1, BS EN 1991-1-1 with its UK National Annex, draws the same line between a roof with access for maintenance only and a floor inside a dwelling. A ceiling joist sits on the wrong side of that line by design, not by age.

So a new structural floor is standard scope rather than an upgrade, and a survey looking for a way to save it is wasting its own time. New joists span wall to wall, often at an angle to the old ones and frequently onto steel, because the depth available will not span the room and the walls that would have helped run the wrong way. An engineer sizes them against the span, the loading and the timber grade; the survey's job is narrower — record the span, the centres you expect, and every place a bearing could plausibly be formed.

Depth is where the height budget and the structure argue, and the argument has no clipboard answer. A deeper joist spans further and eats more of the height you measured; a shallower one protects the height and needs a steel under it, and that steel needs a pocket in a wall which may turn out to be the party wall. What the survey can do is turn that into two priced options instead of a shrug.

Span, length of loft and the centres you intend to use give the joist count and the total lineal timber — a first-pass figure for the largest single element in the job, before the engineer moves the depth and the centres.

Total ceiling joist lumber needed

507 ft155 m

Number of joists
26
Whole bays between joists
24

The stair has to land in a room that already has a use

Loft conversions die on the floor below far more often than they die in the loft. The flight has to rise from inside the enclosure that will protect the escape route, it has to be long enough to divide the height into risers of a legal size, and the length it needs is measured across a floor that is currently somebody's bedroom, landing or bathroom.

The arithmetic is quick and it uses a figure you now have. Total rise is finished floor to finished floor, and the loft's finished floor level came out of the height budget rather than out of the air. Divide that rise into equal risers near the target height, then multiply the goings — one fewer than the risers — by the going you intend to build. A 2.7 m rise at fourteen risers is 193 mm each; at a 220 mm going, that flight occupies 2.86 m of floor before a landing at either end. Draw a 2.9 m line on the plan of the room below and look honestly at what is left of the room.

Winders, a half landing turned back over the existing flight, and the loft-conversion headroom concession are the three moves that recover a scheme sitting 400 mm short. Alternating tread stairs exist, and they are a last resort with conditions attached rather than a way of making a bad plan work. Whichever route it takes, fix the riser count now: it sets the flight length, the length of the opening that has to be trimmed through the new floor, and the finished floor level itself, and changing it later changes all three at once.

Put the floor-to-floor rise in with the going you intend to build and the code your officer works to, and the riser count and the compliance check come back together — which is the pair that decides how much of the room below the flight consumes.

Number of risers needed

15 risers

Actual riser height
7.2 in182.88 mm
Number of treads (steps)
14 treads

The hole in the floor, and the rail around it

The flight needs an opening trimmed through the new floor, and it runs longer than most sketches allow because it is set by headroom rather than by the flight: it has to reach far enough up the slope for a person to climb the last few treads upright. That opening then has to miss the purlin above it, the chimney breast beside it and a good many of the joists you were about to order, and the doubled trimmers around it are timber no linear-footage figure includes.

Then it needs guarding. Rail along the pitch line of the flight, rail around the new landing at the top, and rail back along however much of the existing landing is now open to the stairwell. The sloped run is simply the hypotenuse of the rise and the total going, and it is worth knowing early for a duller reason than the cost of balustrade: if the rail run around the new landing is longer than the landing is deep, what has been drawn is a corridor with a hole in it rather than a landing.

The same rise and run that sized the flight give the sloped rail length and the stock lengths it comes off the rack in, which is the quickest check on whether the landing at the top is a real one.

Handrail length needed

15.9 linear ft4.84 m

Sloped rail length (before waste)
14.42 linear ft4.4 m
Sticks needed
2 x 8 ft sticks

Only now is there anything to cost

The survey has not produced a price. It has produced the two things a price cannot be assembled without: the usable floor area, meaning the part above the height line rather than the footprint, and the category the roof falls into. Everything a builder quotes is conditional on those two, which is why quotes obtained before the survey vary so wildly, and why the cheapest of them is so often the one that assumed a cut roof.

Four items outside the shell decide the total, and three come straight off the half hour with the torch: the new structural floor, the staircase together with the room it consumes, and the dormer or the rooflights. The fourth is fire safety and escape, triggered by the arrival of a third storey rather than chosen, and reaching down through two floors nobody intended to touch. That one is a job of its own with its own guide; what matters here is that it is neither optional nor an upgrade.

Keep the contingency high. A roof is genuinely unknown until it is open, and this survey was carried out through an insulation layer, in the dark, from two boards. Rot in a wall plate, a purlin bearing that turns out to be four courses of loose brick, a chimney taken out below and left standing above — all ordinary findings, none of them visible today. Treat the number that falls out of the arithmetic as the floor of a range rather than the middle of one.

  1. Write down the smallest of your three ridge-to-joist readings, not the average.
  2. Subtract the floor build-up and the slope lining, and state the finished height you expect to hand over.
  3. Mark the height lines on a section, and measure the width of the strip that clears them.
  4. Name the roof — cut, trussed or attic-trussed — with a photograph attached to the answer.
  5. Record joist depth, width, centres and direction, and the walls a new floor could bear on.
  6. Draw the flight on the plan of the floor below and see what remains of that room.
  7. Only then take the area, the scheme and the roof category to a cost, with a contingency against what the roof is hiding.

Enter the usable area you measured rather than the footprint, and build the total up element by element from your own quoted rates — the structural floor, the stair and the dormer are where this survey changes the answer most.

Use the Loft Conversion Cost calculator

What a tape measure cannot tell you

A survey of this kind establishes whether it is worth paying for drawings. It does not establish that the roof structure is sound, that the walls a steel wants to bear on are load-bearing to the foundations, or that the footings will take the extra load. Those are questions for a structural engineer, answered with calculations rather than a rule. Nor does it settle drainage for a shower tucked into the eaves, or whether the existing boiler will carry another bathroom.

It does replace an argument with three numbers, before anybody has been engaged. If the smallest ridge-to-joist reading is comfortably over what the deductions will take, the roof is cut, the struts land on masonry and the flight fits on the floor below, you have a scheme worth drawing. If two of those four come back badly, you have saved a design fee — which is worth considerably more than the half hour cost.

Try the calculation

The survey sheet, in the order the rule comes out

Seven things to leave the loft with. Everything a designer, an engineer or an estimator asks for in the first week is derived from this list, and none of it needs a second visit.

  • Smallest ridge-to-joist height, of three readings — Top of the ceiling joist to the underside of the ridge board, plus a separate reading taken where the head of the new flight will arrive.
  • The two deductions, stated before anybody celebrates — New floor build-up at the bottom and slope lining at the top; whether the new joists can land level with the old ones is the single largest variable in it.
  • Span, pitch, and the height of anything crossing — Clear span wall to wall, pitch off a rafter with a level, and the height at which each purlin, collar or binder crosses the room.
  • Roof category, with a photograph attached — Cut, trussed or attic-trussed. A trussed roof is a different job in a different price bracket and nothing in it is cut without a designed replacement.
  • Joist depth, width, centres and direction — Two readings, not one, plus where the struts land and whether that wall is masonry to the foundations or a later stud partition.
  • Usable area above the height line — The width of the strip that clears the line, times the length of loft it runs for — the denominator every cost per square metre should use.
  • The flight drawn on the plan of the floor below — Riser count, going and flight length marked on the room it lands in, with the trimmed opening length set by headroom rather than by the flight.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • Approved Document K: Protection from falling, collision and impact (England) — stair headroom and the reduced-headroom provisions written for loft conversions. Read the figures out of the edition in force
  • Approved Document B (Fire safety), Volume 1: Dwellings — what the arrival of a third storey requires of the stairway and the escape route
  • Building Standards Technical Handbook — Domestic (Scotland)
  • Technical housing standards — nationally described space standard (2015) — the source of the 2.3 m over 75 per cent of gross internal area figure, a planning standard rather than a building regulation
  • International Residential Code, Section R305 Ceiling Height — including the provisions for rooms with sloping ceilings
  • International Residential Code, Section R311.7 Stairways
  • International Residential Code, Table R301.5 Minimum Uniformly Distributed Live Loads — uninhabitable attics, attics with limited storage, and habitable attics served by a fixed stair
  • BS EN 1991-1-1 (Eurocode 1), Actions on structures. General actions. Densities, self-weight, imposed loads for buildings, with the UK National Annex
  • BS EN 1995-1-1 (Eurocode 5), Design of timber structures. General. Common rules and rules for buildings
  • BS 5395-1, Stairs. Code of practice for the design of stairs with straight flights and winders
  • Trussed Rafter Association technical literature on the alteration of trussed rafters on site
  • TRADA Wood Information Sheets on domestic roof and floor construction
  • The Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2, Part 1, Class B — enlargement of a dwellinghouse consisting of an addition to or alteration of its roof
  • Party Wall etc. Act 1996 — notifiable work to a party structure, including beam pockets and gable raising
  • National Construction Code (Australia), Volume Two — ceiling heights and habitable room requirements

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.