The Extra Metre and a Half Is the Whole Job
A rear elevation with a 2.1 m patio door in it, and a drawing that wants 3.6 m. On site that is one line moved 750 mm each way, which sounds like a morning with a disc cutter, and the quotes written on that basis are the ones that end with a prop foot through a ceiling. Above the line sit two and a half metres of cavity wall, a floor landing on the inner leaf, and an existing lintel with brickwork that has been arching quietly over it since the house was built, thrusting its weight sideways into abutments that stop holding the instant they are cut into.
The work splits into two load questions with two different answers. While the wall is open, everything above the line is standing on a row of needles with a prop each side of each one. Once the permanent support is bedded, the inner leaf and the floor stand on a beam, and the outer leaf stands on a steel angle bolted to that beam — a separate member, sized against a separate load, and the item most often missing from a steel schedule that otherwise looks complete.
Answer them in that order and only in that order. The temporary case is not a smaller version of the permanent one. It has its own load path, its own bearings, its own factor of safety and a design life measured in days. Sizing the beam first and then assuming the props will be comfortable because the beam is comfortable is the exact reasoning that puts a needle through a bed joint that cannot hold it.
Read the Wall Before Drawing the Prop Line
Start by establishing what the wall actually is, because every number downstream depends on it and the elevation drawing will not tell you. Take a brick out at the proposed head, or drill a 12 mm hole and put a borescope through, and settle three things by looking: how many leaves there are, whether the cavity is clear or filled, and what the inner leaf is made of. Dense concrete blockwork, aerated blockwork and common brick sit within a factor of two of each other on unit weight, and that factor lands straight on the prop load with nothing to soften it.
Joist direction is worth more than any other single fact and cannot be read off a floorplan. Lift a board on the floor above and look. Joists landing on the inner leaf put a floor line load on top of the masonry line load, and on a domestic wall with a reasonable span the floor share often exceeds the brickwork share — which surprises people who expect masonry to dominate because masonry is what they can see. Joists running parallel are not an exemption either: a trimmer at a stair or a chimney breast frequently lands on the wall anyway, and hangers rotted out of a wall plate have a habit of turning up in the same bay.
Then find the existing lintel and work out what it has been doing. Rake a perp joint above each end of the old opening and look for the bearing. Masonry over a long-standing opening usually arches, shedding load sideways into the abutments, and the first needle hole cut into an abutment removes exactly the material the arch was thrusting against. That is why the first needle position is a structural decision rather than a setting-out convenience, and why the temporary works arithmetic on this site takes the full rectangle above the opening instead of the triangle an arch would allow.
The paperwork is not separate from the survey; it comes out of it. In the UK, needling and propping is temporary works under BS 5975, Code of Practice for Temporary Works Procedures and the Permissible Stress Design of Falsework, which means a brief, a design, a check and a named person before load is transferred. Where the stock predates the ban, disturbing the fabric triggers the Control of Asbestos Regulations 2012 and a refurbishment and demolition survey to the approach in HSE HSG264, Asbestos: The Survey Guide. In the United States the demolition standard, OSHA 29 CFR 1926 Subpart T, requires a written engineering survey by a competent person before structural removal begins, and an occupied house is precisely the situation it was written for.
| What has to be known | Where the answer comes from | What it changes |
|---|---|---|
| Whether the wall is one leaf or two, and which leaf is loaded | A unit removed at the proposed head, or a borescope through a small drilled hole | Whether one needling scheme covers it or two separate schemes are needed |
| Joist direction and what lands on the inner leaf | A board lifted on the floor above, never the floorplan | The floor line load, which on a domestic wall routinely beats the masonry share |
| How much wall stands above the opening before something else takes it | A tape from the new head to the eaves, ring beam or slab soffit | The masonry line load, in direct proportion |
| Whether the existing lintel is arching, and where its abutments sit | A raked perp joint above each end of the old opening | Where the first needle can go without undermining the arch it relies on |
| What is buried in the wall along the cut line | Detection across the full cut, plus a refurbishment survey on older stock | Whether the first cut is an investigation or an incident |
What Each Needle Is Actually Holding
The line load along the wall is the sum of two things that arrive in different units and have to be reconciled before they can be added. The masonry is a height above the opening multiplied by a thickness multiplied by a unit weight, which gives force per metre run directly. The floor is a pressure multiplied by the width of floor this wall carries — half the span each side where floors land from both directions — which gives force per metre run as well. Add them, multiply by the needle spacing, and that is the tributary load one needle takes.
Measure the height above the opening to whatever genuinely stops the load coming down, not to a convenient line. A slab soffit that spans elsewhere stops it. A ring beam stops it. A window head two courses up does not stop anything; it simply hands its own load back into the same wall. Where there is nothing above but more brickwork all the way to a gable, the honest measurement is the lot, and a gable is where a routine job quietly becomes a heavy one.
On a cavity wall, needle each leaf separately unless somebody has demonstrated that the ties are carrying the outer leaf on the inner one — and on a wall built before the current durability rules, they are usually not. Wall ties are a restraint against wind, designed to keep two leaves acting as one panel out of plane. They are not a vertical load path, and butterfly ties in a wall old enough to want widening are frequently corroded through at the mortar line where nobody can see them. Two leaves means two schemes, two sets of holes, and two sets of props that have to miss each other.
Needle spacing is set by coursing as much as by arithmetic. Closer spacing lightens each needle and multiplies the holes; every hole cuts a bed joint, and two holes badly placed on adjacent courses turn a length of brickwork into a hinge. Set the positions on a course line first, check what load that spacing produces second, and adjust the spacing rather than the course. The masonry between needles has to span from one to the next in bed-joint tension it barely has, so a needle that ends up 200 mm off its designed position is a change to the scheme and not a detail.
Build the line load from the masonry above and the floor bearing on the wall, share it onto needles at the spacing the coursing allows, and get the sole plate area each prop needs — run it once per leaf, because the two leaves carry different things.
From the head of the new opening up to the top of the wall, or to the next support.
The thickness of the masonry being held, excluding any leaf that is not being supported.
The bulk unit weight of the wall being held, mortar included.
The clear width of the opening being formed under the supported wall.
Centre-to-centre spacing of the needles through the wall.
The combined permanent and imposed load of any floor framing into this wall.
How much floor this wall carries — normally half the span of the floor either side of it.
What the surface the props stand on can take without settling or punching through.
Load carried by each needle
3.63 kips
Needling and propping is temporary works. This gives the loads to design to; it does not select the props, check them for buckling at their extended length, or confirm that what the props stand on can take them. All three belong to a temporary works designer.
- Load carried by each prop
- 1.81 kips
- Needles across the opening
- 4 needles
- Combined line load along the wall
- 1,208.77 lbf/ft
- Masonry share of that line load
- 707.52 lbf/ft
- Floor share of that line load
- 501.25 lbf/ft
- Sole plate bearing area required beneath each prop
- 0.87 ft²
They open the calculator with your figures already in it
Needle and Prop Load Calculator (Temporary Masonry Support): 3.63 kips — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Add the equipment this sizes
This result is a specification — 3.63 kips — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.
What this calculation does not cover
- Takes the full rectangle of masonry above the opening. That is deliberately conservative — arching can carry some of it away, but only in sound masonry with enough height and no nearby opening.
- Does not check the prop itself. A prop's safe working load falls sharply with extension and with any eccentricity at the head, and the manufacturer's chart is the only place that answer lives.
- Does not check the needle. Bending, shear and bearing on the masonry at the needle hole all need sizing against the load this page gives.
- Assumes props each side of the wall share equally. A single-sided scheme, or props at different extensions, does not.
The Prop Is the Easy Half
What the prop stands on decides more jobs than what the prop is. A prop delivers several tonnes through a foot plate barely wider than a hand, and almost no floor takes that undiluted. On a ground-bearing slab the sole plate spreads it into something with a defensible allowable pressure; on a suspended timber floor it has to spread across more than one joist, and the joists themselves then need checking for a point load nobody designed them for. The calculator above returns a required bearing area, but the allowable pressure that produces it has to come from the temporary works designer looking at what is under that specific prop, not from a figure someone remembered.
A prop's safe working load is a function of its extension, and the fall is steep. BS EN 1065, Adjustable Telescopic Steel Props — Product Specifications, Design and Assessment by Calculation and Tests, classifies props precisely because a prop near the top of its range is a different member from the same prop half-closed. Nothing on this page settles it and no rule of thumb does either: read the figure off the chart for the make and model in front of you, at the extension it is actually set to. Then keep the prop plumb, pin it with the proper pin rather than a nail or a bolt found in the van, and re-check plumb after the first cut — a prop that has gone out of true has lost capacity nobody has recalculated and nobody can see.
The failure that hurts people is not vertical. A needled wall with its bottom taken out is a free-standing panel of masonry restrained only by whatever is left at its ends and by the needles themselves, and it has no more tensile strength than the mortar in its beds. Wind through a newly open rear elevation, a scaffold board leaned against it, or a lorry passing on a suspended floor is all it takes. Restraint out of plane is a separate item in the scheme with its own raking props or its own bracing, and it is the part that gets left off when the vertical numbers look reassuring.
Cutting It Out Without Shaking It Down
Nothing about this cut is a demolition cut. Percussion loosens the beds either side of where you are working, and mortar in a wall old enough to be worth widening has very little to give up before it stops holding the courses above onto the needles. Stitch-drill the corners, run a diamond blade between them, and take the last of the material out by hand so that the course you are supporting is left bearing on brickwork you have not disturbed. Where the outer leaf is fair-faced and going to be seen, the same discipline is also the only way to leave a reveal worth pointing.
Silica is the other reason the method matters. Dry cutting brick and block with a handheld saw produces respirable crystalline silica far above any exposure limit within minutes, and OSHA's construction standard, 29 CFR 1926.1153, sets out the controls: for a handheld power saw, an integrated water delivery system running continuously, with the respiratory protection the standard's Table 1 attaches to the task duration. In the UK the same exposure is controlled under the Control of Substances Hazardous to Health Regulations 2002, and the practical answer is identical — water or on-tool extraction, every cut, indoors most of all, where there is no wind to help and the dust settles into the room the client is going to live in.
- Set out needle positions on a course line rather than on an even division of the opening — each hole has to land in a bed joint the wall can spare.
- Cut the needle holes instead of driving them: drill the corners, cut between, hand-clean the last of it, and leave the course above bearing on sound work.
- Thread the needles, wedge them hard up to the underside of that course, then bring the props up on their sole plates until the wall is standing on the scheme and not on the material about to be removed.
- Check every prop plumb once tightened, and again after the first course comes out.
- Take the opening down in courses from the top, working outward from the middle rather than starting at a reveal.
- Cut the two leaves as separate operations, each supported in its own right before the other is disturbed.
- Form the bearing pockets last, and cut them generous enough that the beam can be offered up rather than driven in — a beam hammered into a tight pocket unloads the needles above it on the way through.
- Clean the bearing surfaces down to sound material before anything is bedded on them; a padstone set on cutting dust is a padstone that settles.
The Piers Either Side Inherit the Difference
Widening an opening loads the remaining piers twice over, and only one of the two increases is obvious. The pier gets narrower, so its net area falls. It also picks up half of every extra metre of opening, so the load arriving on it rises at the same time. Take 750 mm off each side of a 2.1 m opening in a wall with a window nearby and the pier between them can lose a third of its section while gaining a quarter of its load, which is a change of a different order from anything the beam calculation reports.
What is under the pier matters as much as the pier. A strip footing under a wall was sized for a distributed load along its length; after the opening is widened it is carrying a concentrated reaction at two points with nothing between them. On shrinkable clay, on made ground, or under a wall that was underpinned in the past, that redistribution is worth a trial hole rather than an assumption. The same goes for the padstone: a reaction that used to be spread over metres of wall now arrives on a bearing a few hundred millimetres long, and local crushing at the top of the pier is a separate check from the capacity of the pier as a whole.
The governing document depends on where you are working. TMS 402/602, Building Code Requirements and Specification for Masonry Structures, sets the allowable stresses and the slenderness reduction in the United States, with loads from ASCE/SEI 7; BS EN 1996-1-1 and its accompanying PD 6697 do the same job in the UK. Both reduce the capacity of a pier as it gets taller relative to its thickness, and both handle a load applied off the centroid as bending in a material with almost no tension to offer. Whether the check is legally required at all is a question for the adopted existing-building code — the alteration provisions of the International Existing Building Code trip at a small percentage increase in gravity load, and widening an opening is one of the few renovation moves that clears that threshold without anyone intending it to.
Take the net section left after the opening is widened and see what a short unreinforced pier can be argued to carry — a first pass that has to be handed to an engineer the moment the pier is slender or the load lands off-centre.
The specified compressive strength of the masonry assembly.
The pier's net (solid/grouted) cross-sectional area.
Allowable axial capacity
60 kips
This is a simplified SHORT-pier estimate that ignores slenderness (height-to-thickness) effects — TMS 402 applies an additional reduction factor for taller or slimmer piers that can significantly lower usable capacity. A licensed structural engineer must verify the actual slenderness reduction for your specific pier geometry.
- Equivalent in lbs
- 60,000 lb
They open the calculator with your figures already in it
Masonry Pier Axial Capacity Calculator: 60 kips — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Add the equipment this sizes
This result is a specification — 60 kips — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.
What this calculation does not cover
- No pier height or thickness is asked for, so the slenderness reduction is simply absent. The figure applies to a short, stocky pier only — a tall or slim one carries less, and how much less cannot be read off this page.
- The load is assumed to arrive on the centroid. There is no input for load position, so a beam or padstone bearing towards one face — the usual case when an opening is widened — is not covered; that becomes a combined axial-plus-bending check on the real geometry.
- Reinforcement contributes nothing. Bars, bond beams and confinement are outside the model, and grout reaches the answer only through whatever grouted cells you counted into the net area.
- Local crushing under the padstone is a separate check this does not make, and so is everything below the pier: the footing, the soil, and whether a footing sized for a load spread along a wall can take the concentrated reaction the pier now delivers.
- f'm is taken as given rather than assessed, so nothing here tests whether a cracked, weathered, lime-bedded or rubble-cored pier actually reaches the strength you entered. This is a first sizing check, not a code check and not a design — sizing or accepting a loaded pier is a licensed structural engineer's work.
What Holds the Outer Leaf When the Props Come Out
The inner leaf and the floor go onto the beam. The outer leaf has three realistic options and they are not interchangeable. A combined lintel is one unit shaped to carry both leaves and is the tidiest answer where the section suits the cavity width and the load. A steel angle bolted to the web or the top flange of the beam is the usual answer where the beam was sized for the inner leaf and the veneer has to be picked up alongside it. A proprietary masonry support system — Ancon and IG both publish load and deflection tables for theirs — is what you specify when the brickwork above is tall, the cavity is wide, or the bracket has to reach past insulation to find structure.
The load on that angle starts as a line load and is easy to get: the height of brickwork it supports, times the thickness of the leaf, times the unit weight of the masonry. That is force per metre run of angle. It becomes a beam problem the moment the angle crosses the opening, because the angle is then spanning between its end supports carrying that line load as a uniformly distributed one, and span enters deflection to the fourth power. Two identical angles carrying identical brickwork over 1.2 m and over 3.6 m are not remotely the same member.
Measure the supported height to the next thing that takes the veneer, exactly as with the temporary case. On a two-storey rear elevation with no support above, that is every course from the angle to the eaves, and the number gets uncomfortable quickly. Where the veneer is picked up again at a floor line higher up, the angle over the opening carries only the panel below that support, and a compressible horizontal joint beneath the upper angle is what keeps the two panels independent instead of stacking one on the other.
Three things the line load does not include, all of which have caused failures. The angle's own weight, which is small but real once it is 3.6 m of substantial section. The eccentricity: veneer sits on the toe of the angle, offset from the bolt line, and that offset turns a vertical load into a torsion on the angle and a tension in the top row of fixings. And deflection, which is not governed by the steel's strength at all but by what the brickwork above will tolerate before a bed joint opens — a limit that comes from the support manufacturer's system approval, not from a general rule. Get any of those from a supplier's table rather than from arithmetic.
Durability is the quiet one, because the angle sits in a cavity where water runs down the back of the outer leaf and lands on it. Brackets and masonry support fall under BS EN 845-1, Specification for Ancillary Components for Masonry — Wall Ties, Tension Straps, Hangers and Brackets, and austenitic stainless is the normal specification for anything permanently in a cavity; galvanized steel to BS EN ISO 1461 is a lesser answer with a service life you have to be willing to defend. A cavity tray sits over the angle with stop ends and weeps above it, to BS 8215, Code of Practice for Design and Installation of Damp-Proof Courses in Masonry Construction, because the angle has just turned the cavity into a shelf and everything running down it now has somewhere to collect.
The head of the finished opening
- Outer leaf over the opening — every course from the angle up to the next support is dead load the angle carries, so the height it is measured over decides the whole answer Brick Calculator
- Cavity tray, stop ends and weeps — the angle turns the cavity into a shelf, so the tray over it needs sealed ends and weeps in the perp joints directly above Cavity Wall Weep Hole Spacing Calculator
- Brick support angle — carries the veneer as a line load along its span and takes torsion from the offset between the toe and the bolt line Masonry Veneer Shelf Angle Load Calculator
- Beam over the opening — sized for the inner leaf and the floor, and then asked to hold the angle and its bolts as well Masonry Lintel Uniform Load Capacity Calculator
- Padstone at each bearing — spreads a reaction that used to run along metres of wall into a bearing a few hundred millimetres long Masonry Lintel Bearing Length Checker
- Pier each side of the opening — loses section to the widening and gains load from it at the same time, on a footing sized for neither Masonry Pier Axial Capacity Calculator
Turn the height of brickwork above the angle into the line load it has to carry, then take that figure to the support manufacturer's tables — the number here is veneer dead load, and the angle also has to survive the eccentricity and the deflection limit.
The height of brick veneer resting on this shelf angle before the next angle below.
The nominal thickness of the brick veneer.
The density of the brick material.
Load on shelf angle
396 lbf/ft
This is the veneer dead load only — the shelf angle and its anchor bolts must also be checked for the angle's own weight, any eccentricity from the veneer's offset from the angle's support point, and deflection limits, all outside this calculator's scope.
- Equivalent in lb/ft
- 395.51 lb/ft
They open the calculator with your figures already in it
Masonry Veneer Shelf Angle Load Calculator: 396 lbf/ft — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Add the equipment this sizes
This result is a specification — 396 lbf/ft — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.
What this calculation does not cover
- This is the weight of the veneer only. The shelf angle's own weight, its anchors and flashing, and anything else bearing on the same run — a lintel over an opening, a sill course, a parapet or coping — are not in the figure. Where an opening interrupts the wall, the tributary height above the angle is not simply the floor-to-floor height either.
- It is a service load, not a design. Nothing here sizes the angle, its anchor bolts or the connection back to the frame, applies a load factor, or accounts for the moment and torsion from the veneer bearing outboard of the angle's support point, or for the angle's deflection limit. Those are engineering checks and this number is only the starting input to them.
- The veneer is modelled as a solid wythe at one bulk density. Enter the thickness of the brick alone — not brick plus air space, sheathing or insulation — and expect the real weight to move with coring, mortar joint size and how saturated the brickwork is.
- The density field stops at 2,400 kg/m³ (about 150 pcf), which covers clay and concrete brick. Dense natural stone veneer sits above that ceiling — granite and marble run roughly 2,600-2,750 kg/m³ — and a density typed above the maximum is capped back to it, so the load comes back low.
- None of the lateral side is covered: wind and seismic pressure on the veneer, the tie spacing that carries it back to the backup wall, and the soft compressible joint that must sit under the angle so the veneer below is not loaded are all separate calculations.
Handing the Load Back
The transfer is where schemes fail, not the peak load. Once the beam is offered up and the padstones are in, there is a gap between the top of the beam and the underside of the masonry, and everything depends on that gap being filled solid across the whole bearing before anything is struck. Dry pack worked in hard, slate and mortar, or a non-shrink grout — full width, full length, no dabs and no timber packers left in as a convenience. Leave it to gain strength for the period the material's own data sheet states rather than the period the programme would prefer.
Strike in stages and never one prop at a time to zero. Ease each prop a little, work along the row, come back and ease again, so the load transfers gradually across the whole line rather than dumping onto whichever bay released first. Between stages, look at the packing: a joint that is closing up is telling you the pack was not solid, and the moment to find that out is while there are still props holding most of the weight. On a two-leaf scheme the inner and outer supports get struck separately, in whatever order the temporary works design says, which is not always the order that suits the scaffold.
Then measure something and write it down. A level along the beam soffit and a reading at midspan against a fixed datum before striking, after part-striking and after full release costs twenty minutes and settles an argument that is otherwise unwinnable. Telltales across any crack that already existed, dated, do the same job for the wall. If a crack turns up over the door in month four, that short record is the difference between a structure that has moved exactly as predicted and one where a bearing gave way — and between those two answers sits the cost of taking the opening apart again.
The Openings That Should Not Get Wider
Some of these jobs should be priced as a refusal. Where the pier left beside the opening cannot be argued adequate and there is nowhere to widen it, the honest answer is a narrower opening or a post — and a post in the middle of a kitchen island is a conversation held before the steel is ordered, never after. Where the footing under the pier is a shallow strip on clay, a concentrated reaction lands somewhere that has been happily carrying a distributed one for a century, and the underpinning that follows costs several times the opening.
Party walls are their own gate and have nothing to do with structural capacity. In England and Wales, cutting into a party structure — which includes needling into it and bearing a new beam on it — is notifiable under the Party Wall etc. Act 1996, and the notice on the adjoining owner goes out well ahead of the start date, not the week before. Discovering this after the props are up is expensive in a way no calculator on this site can help with.
The last one is the wall that is not behaving as a wall. Bulging on a face, beds that have washed out, a cavity packed with rubble from a 1960s repair, or a leaf that rings hollow across a whole panel all mean the masonry above the opening cannot be relied on to span between needles at any spacing. That is a case for a full-height support scheme designed for the wall you actually have, not a case for closer needles — and the load figures on this page are the input to that design rather than a substitute for it.
Settle these before a needle hole is drilled
The stack opens on the inner leaf, with the height above the opening, the leaf thickness, the widened span and a needle spacing that suits the coursing already in. Run it a second time for the outer leaf with the floor figures taken out, because nothing bears on it.
- Leaf construction and unit weight, per leaf — Established by opening up, not from the elevation. Aerated blockwork and dense brick differ by a factor of two, and it lands straight on the prop load.
- Height of masonry above the new head — Measured to whatever genuinely stops the load — a spanning slab soffit, a ring beam or the top of the gable. A window head two courses up stops nothing.
- Floor load and tributary width onto the inner leaf — From a lifted board, not a floorplan. Half the joist span each side where floors land from both directions, plus any trimmer that trims onto the wall.
- Allowable bearing pressure under each prop — From the temporary works designer, against what is actually under that prop. On a suspended floor the joists need checking for the point load as well.
- Supported veneer height above the outer-leaf angle — To the eaves where nothing picks the veneer up higher, or to the next support where something does. Sets the line load the angle spans the opening with.
- Net pier section left each side, and what is under it — Section lost and load gained happen together. A trial hole at the footing where the ground is shrinkable or the wall has been underpinned before.
Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.
