Roofing

Building a Pedestal Paver Terrace

The deck falls, the terrace cannot. That disagreement is measured in millimetres of pedestal, and it is a schedule of heights rather than one height.
  • 17 minReading time
  • 11Sections
  • 5Calculators inline
  • Last reviewed

Two Hundred Millimetres Nobody Put on the Order

Twelve metres from the parapet back to the door, seven metres across, and the deck falling one in sixty towards a single outlet in the far corner. That is 200 mm of drop — a shade under eight inches — between one end of a surface that has to end up dead level and the other. The order that went out asked for 273 pedestals at one height, because 273 is what the grid arithmetic gives and one height is what a supplier's order form invites you to type.

The first four rows go down beautifully. By the middle of the terrace the heads are wound out to the top of their thread and the pavers are still sitting low, and by the outlet corner the installer is stacking offcuts of insulation under base plates to make up 200 mm that was never bought. That is the failure: not a design error, not a product problem, an order placed against area when the governing quantity was fall.

So the order of work is survey, height budget, grid, schedule, purchase — in that order, and the purchase order is last because it cannot be written until the four before it have numbers in them. The sections below follow that sequence, then deal with the things that decide whether the terrace survives its first winter: what the pedestals are standing on, what the wind does to a paver with air underneath it, and how anybody gets back down to a membrane nobody can see.

What a pedestal terrace is stacked from

A rooftop terrace standing level over a deck that falls: pavers carried at their joints on adjustable pedestals that step taller down the slope, each pedestal on a bearing pad over the waterproofing, with cover board and tapered insulation below that and the structural deck at the bottom.
  1. Terrace pavers — loose-laid on the heads with open joints, so they are counted by area but restrained by weight Paver Calculator
  2. Adjustable pedestals — one under every joint and every edge, each a different height, tallest at the low end of the fall, counted off the grid rather than the area Roof Paver Pedestal Grid Calculator
  3. Bearing pads and slip sheet — spreads a base plate's point load and keeps the pedestal foot off the membrane it would otherwise sit on for thirty years
  4. Waterproofing membrane — the layer that becomes unreachable the moment the first paver is laid over it, so it is bought and inspected accordingly Below-Grade Waterproofing Membrane Roll Calculator
  5. Cover board — the sheet that turns a pedestal's concentrated load into something the insulation beneath can actually take Roof Insulation Cover Board Calculator
  6. Tapered insulation — where the fall usually comes from on a flat deck, and the reason the pedestal heights vary at all Tapered Roof Insulation Slope Calculator
  7. Structural deck — carries the pavers, the pedestals, the people and the water, and its deflection moves the fall you surveyed Roof/Floor Deflection Limit Calculator

Survey the Fall You Have, Not the One on the Section

Drawn falls are intentions. Tapered insulation gets cut to a schedule, boards get swapped at the eleventh hour, a sump gets set 15 mm proud, and the deck itself deflects under everything you are about to put on it. On a refurbishment the drawn fall may not exist at all. Take levels on the finished waterproofing, on the grid you intend to build to, and treat the result as the only fall that matters.

Shoot the whole area from one instrument position if you can, because moving the level halfway across is how a systematic error gets built into a height schedule that then looks entirely self-consistent. Record the deck level at every pedestal grid line, not at the corners of the terrace — five spot heights across twelve metres will miss a local flat spot completely, and a flat spot under a pedestal terrace is a pond you have built a lid over. Where the readings disagree with the drawing by more than the pedestal's adjustment can absorb, that is an RFI before it is a purchase order.

Two readings deserve separate attention. The high point governs the shortest pedestal, and the shortest pedestal in most ranges is a fixed or barely-adjustable component — go below its height and the geometry has nowhere to go. The low point governs the tallest, and tall pedestals stop being a stock item and start being a base plus extenders, with a different lead time and a different price. Both ends of the survey therefore land straight on the order.

Timing matters as much as method. Survey after the waterproofing is complete and after any ballast or protection layer is down, because both change the surface the pedestals will actually stand on, and survey before the pedestals are ordered rather than before the insulation is cut. On a long-span deck, take the readings with the deck loaded as far as the programme allows — a bare deck reads flatter than the same deck under the finished weight of the paving, and the fall you sign off is the one the pedestals get wound to.

  1. Set the instrument once, in a position that sees the whole terrace, and note where it stood.
  2. Level the finished waterproofing at every pedestal grid line, working across the fall then along it.
  3. Mark the high point and the low point on the plan and write their readings on it.
  4. Check the run between them with a tape on the deck, not scaled off the drawing.
  5. Flood-test or hose the area and record where water stands, then re-level those spots.

A tape between the two ends and a staff reading at each gives you rise and run, and turning that pair into a percentage and an angle is what lets you argue with the drawn fall rather than assume it.

The vertical change in height over the run.

The horizontal distance over which the rise occurs.

Slope grade

8.974 %

High confidence
Angle
5.13 degrees
39 ft3.5 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • Run is taken as the true horizontal distance between the two ends, and nothing converts a tape laid along the sloping face into that horizontal — measure along the surface instead and the grade reads lower than the ground really is, with the gap widening as the slope steepens.
  • Rise is read as a magnitude only, so a drop and a climb of the same size return the same positive grade and a negative entry is floored to zero; which end is higher stays your own note rather than something the answer carries.
  • Both figures describe a single straight line drawn between the two points you measured, so any crest, dip or bench sitting between them is averaged away, and cross-fall across the width of a drive or path is not part of the arithmetic at all.
  • The output covers grade percent and the matching angle; the sloping distance itself — what you would order ramp board, handrail or edging against, and always longer than the run — is not worked out, nor is the result expressed as the 1-in-X ratio that specifications are often written in.
  • No ceiling is applied to the outcome: a 2% fall and a 45% bank come back with identical confidence, and the accessible-ramp and driveway grade figures quoted in the questions below are context for reading your number, not a test the calculation runs against it.

The Height Budget Runs Downward From the Door

Pedestal height is a remainder, not a choice. It is what is left after the door threshold, the waterproofing upstand and the paver have all taken their share, and on almost every terrace it is the threshold that squeezes hardest. BS 8579, Guide to the design of balconies and terraces, covers the threshold and upstand relationship directly, and the reduced upstand allowed at a level-access door always arrives paired with a drainage channel and a specified detail — never on its own, and never as a site decision.

Work top down and write each line separately, because the moment two of them get combined into a single allowance the argument about who ate the height becomes unwinnable. The number that comes out at the bottom is not a pedestal height; it is the adjustment range the pedestal has to cover at that point on the roof, and it has to be inside what the manufacturer publishes for the head you have specified.

One line in that budget gets forgotten more than the rest: the head itself. A slope-correcting head, a self-levelling head and a plain flat head are three different build-ups, and swapping a flat head for a corrector after the heights are ordered changes every pedestal on the terrace by the difference. Fix the head type before the schedule, not after.

Working the height budget down from the threshold to the deck
LineWhere the number comes fromWhat it does to the pedestal
Threshold or datum levelThe door detail and the upstand it sits above, set by the waterproofing designFixes the ceiling on everything below it
Drop from threshold to finished paverThreshold detail, plus the drainage channel that goes with a reduced upstandSubtract
Paver thicknessProduct data sheet, actual thickness rather than nominalSubtract
Head and corrector build-upPedestal manufacturer's literature for the exact head specifiedSubtract
Deck level under this pedestalThe survey, one reading per grid lineSubtract, and it changes at every grid line
What remainsArithmetic, not judgementThe adjustment range this pedestal must cover
Working the height budget down from the threshold to the deck

Count the Grid Before You Price the Heights

Pedestal count is a grid problem and it is genuinely simple: a line of pedestals every module across the terrace in each direction, plus one to close each run. Twelve metres against a 600 mm module gives twenty bays and twenty-one lines; seven metres gives eleven full bays, a 400 mm remainder and thirteen lines. Twenty-one by thirteen is 273 heads, and that is the figure the material order starts from.

It starts from it rather than ends at it. The remainder strip along the seven-metre dimension is a row of cut pavers, and cut pavers need support along a sawn edge that the corner-bearing grid does not provide; add heads there, at planter kerbs, at drain surrounds where a slab is trimmed around an access frame, at any step or level change, and along the parapet where the last course lands on a support rather than a shared corner. Module comes from the paver and the loading rather than from preference, so if the specification changes across the terrace — heavier units at the exposed corner, a lighter unit in the sheltered pocket — the module can change with it, and the count becomes two grids added together instead of one grid over the whole area. On a terrace carrying much furniture those extras stop being a rounding allowance and become a line of their own on the take-off.

This is the grid figure the order starts from: heads per line in each direction, multiplied. Run it at the module the paver manufacturer requires, then add the perimeter, the cuts and the drain surrounds by hand.

The length of the paver deck area.

The width of the paver deck area.

The spacing between pedestal grid lines, set by the paver system manufacturer.

Pedestals needed

437 pedestals

High confidence

A pedestal paver system on a roof is designed for wind uplift first and for foot traffic second. The pedestal count follows the grid; whether the assembly stays on the roof follows the paver's weight and the corner or edge zone it sits in.

Pedestals along length
23
Pedestals along width
19
Cut paver down the deck
0 ft
Cut paver across the deck
0.5 ft

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

1.5 ft33 ft23 at 1.5 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • Wind uplift is not checked here. Corner and perimeter zones on a roof see substantially higher uplift than the field, and paver weight or mechanical restraint must be assessed for each zone.
  • Excludes the slope-compensating or height-adjustable heads needed to bring a level walking surface off a falled roof, which are a different and more expensive component.
  • Does not check the point load on the membrane and insulation beneath. A pedestal concentrates load onto a small area, and the insulation's compressive strength governs.

One Location at a Time, Then Bought in Bands

A pedestal height is calculated for one place on the roof. Finish height above the deck at that point, less the paver thickness, less what the correction at that location consumes, and the answer applies to that pedestal and its immediate neighbours only. Read the first term carefully: it is the height above the deck under that pedestal, not above a single datum for the whole terrace. Feed a roof-wide datum into a location-specific formula and the fall comes out with the wrong sign, which is precisely the mistake that produced 273 identical pedestals in the first place.

Once the survey exists the schedule is arithmetic. On the terrace above, with the shortest pedestal at the high point set to 60 mm and the deck dropping 10 mm per 600 mm grid line, the heights run 60, 70, 80 and on up to 260 mm at the outlet corner — twenty-one nominal heights across the fall, thirteen pedestals wide at each of them.

Nobody orders twenty-one nominal heights, because a threaded pedestal covers a range rather than a value. You group the grid lines into the ranges the manufacturer publishes, count the heads in each group, and order bands. Three bands is typical for a fall of this size; a shallower fall over the same run may collapse into two, and a terrace stepping over a downstand beam will need a band of its own for the step.

Bison Innovative Products and Buzon Pedestal International both publish range tables for their bases, extenders and slope-correcting heads, and the bands below are grouped against a range set of that shape rather than against any one product. Take the actual break points from the literature for the system specified, because a band boundary in the wrong place turns into a site full of pedestals wound to the last thread — which is where they creep, and where they rock.

Then add the components the bands do not contain. Slope correctors for wherever the fall exceeds what a flat head can sit on. Extenders as a separate line, not folded into the base count. Spare heads at a sensible percentage, because damaged threads on a windy roof are ordinary. And a small stock of the shortest component in the range, since the high corner is always tighter than the survey suggested.

The 12 m × 7 m terrace at 1:60, pedestals on a 600 mm module, banded for ordering
Grid lines from the high pointDeck drop below the high pointPedestal height requiredPedestals in the band
Lines 1 to 50 to 40 mm60 to 100 mm65
Lines 6 to 1150 to 100 mm110 to 160 mm78
Lines 12 to 21110 to 200 mm170 to 260 mm130
All lines200 mm total fall60 to 260 mm273
The 12 m × 7 m terrace at 1:60, pedestals on a 600 mm module, banded for ordering

Work it at the high point and at the low point first — those two answers set the range the whole order has to cover — then step through the grid lines between them to build the bands.

The target finished walking-surface height above the roof deck.

The thickness of the paver unit itself.

The additional height reduction needed at this specific pedestal to compensate for the sloped roof deck below.

Required pedestal height

0.342 ft

Medium confidence

Slope compensation varies at each pedestal location across a sloped roof deck — this calculates one location at a time; a full layout needs a pedestal height schedule across the roof's slope, typically provided by the pedestal system manufacturer's layout service.

paver 1.5 inpaver 0.0381 mpedestal 4.11 inpedestal 0.104 mslope shim 0.39 inslope shim 0.00991 mroof deck6 in0.152 m

What this calculation does not cover

  • Gives a height, not a load path. Each pedestal carries about a quarter of the four pavers meeting on its head plus the live load on them - a terrace or plaza is commonly designed at 4.8 kPa (100 psf) - and the pedestal, the paver and everything below the membrane has to take it. The insulation is the part usually forgotten: a pedestal is a point load onto a board specified for compressive strength, and the wrong board grade dishes under it and takes the finished level with it.
  • Tall pedestals are not simply longer ones. Past a modest height, which varies by system but often falls somewhere between 300 and 600 mm (24 in), manufacturers require the field to be tied together with bracing, spacer rails or a clip system, because a forest of slender columns has nothing resisting sideways force otherwise - and their published allowable load per pedestal drops as the height rises. This sum returns a dimension; whether that dimension is legal at that load comes from the manufacturer's table.
  • Answers with a continuous number, and pedestals adjust in steps. Products come in fixed height ranges with a threaded adjustment and a slope corrector that typically tops out around 5%, so the computed height has to land inside a range you can actually buy, and a deck steeper than the corrector's limit needs a different product or shimming. The figure is also only true if the deck is where you think it is - a 10 mm (0.39 in) hollow in the membrane under one pedestal is 10 mm (0.39 in) of rock in the paver above it, which is why the field gets levelled off the pavers as it is laid.
  • Nothing here about wind. Pedestal pavers are a loose-laid ballast system held down by their own weight, and uplift at a roof's corners and perimeter zones runs several times the pressure in the middle of the field - which is why edge zones commonly need heavier or thicker units, interlocking clips, or a restraint at the parapet. A paver can be exactly the right thickness for this height calculation and still leave the roof in a gale.

What the Pedestal Is Actually Standing On

A pedestal gathers the load of a module of terrace and puts it through a base plate. On a 600 mm grid that is 0.36 m² of tributary area — the pavers, the people, the planters and whatever the code assigns as imposed load for an accessible terrace — arriving on a base plate of a few hundred square centimetres. Three and a half thousand square centimetres of terrace resolving onto two or three hundred is the number to hold on to. Below the plate sit the membrane, the cover board and the insulation, and it is almost never the membrane that governs. It is the insulation's compressive behaviour.

That behaviour is specified, not assumed. ASTM C578, Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation, and ASTM C1289, Standard Specification for Faced Rigid Cellular Polyisocyanurate Thermal Insulation Board, both grade product by compressive resistance, and the underlying measurement is ASTM D1621, Standard Test Method for Compressive Properties of Rigid Cellular Plastics. Two cautions come with those figures. The compressive resistance is quoted at a stated deformation from a short-term test, and the load under a terrace is permanent — manufacturers publish a separate long-term or creep design stress for exactly this reason, and it is a good deal lower. Second, the grade that is adequate under a membrane in the open field is frequently a grade or two short of what a paved area needs, so the insulation specification often has to change under the terrace and stay changed at the boundary.

The remedies are all about area. A cover board over the insulation spreads the plate load into something the board below can carry; a bearing pad or a proprietary load-spreading disc under the base does the same job at the other end; a slip sheet keeps the pedestal foot off the membrane so that three decades of small movements do not wear a hole in it. Get the sequence right and the loads resolve. Get it wrong and the evidence is a dimple pattern in the membrane on a 600 mm grid, found the first time anybody lifts a paver.

Cover board under a pedestal terrace is a structural layer rather than a substrate improvement, so it is bought to the paved area including the perimeter strip the pavers do not quite reach.

The total roof area to be covered with cover board.

The coverage area of a single cover board sheet.

Cover board sheets needed

51 sheets

High confidence

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

What this calculation does not cover

  • Counts boards and nothing that holds them down. In many assemblies one screw and plate passes through the cover board AND the insulation beneath it in a single shot, so the fastener length is set by board thickness plus the whole insulation stack plus the embedment the deck needs, and that fastener quantity belongs to the stack rather than to this layer. A board count on its own will not tell you whether you are buying one set of fasteners or two.
  • Board thickness and type are not asked, and the sheet count comes out identical whichever you pick. What the board has to be — gypsum, HD polyiso, cement board, mineral — is set by the assembly's fire and hail classification and by what the membrane above it has to bond to, and those are the decisions carrying the cost difference between two roofs of the same area.
  • An adhered installation is not ordered by sheet count at all. Adhesive goes on by coverage rate — a volume per unit of area, or ribbon spacing across each board, tightened at the perimeter and corners — so the pail count follows that rate and the zone layout, and it does not track the number of boards.

Wind Gets Under a Raised Paver Before It Gets Over It

A ballasted membrane holds down because stone sits on it. A pedestal paver has open air beneath it and an open joint at every edge, so pressure equalises under the slab and the aerodynamics are not the same thing at all. ANSI/SPRI RP-4, Wind Design Standard for Ballasted Single-ply Roofing Systems, addresses ballast; a raised paver deck is assessed through the components-and-cladding route of ASCE 7, Minimum Design Loads and Associated Criteria for Buildings and Other Structures, together with the paver and pedestal manufacturer's own wind testing. FM Global Property Loss Prevention Data Sheet 1-29, Roof Deck Securement and Above-Deck Roof Components, governs on FM-insured work. Which of those applies is a project question with a written answer, and it is not one to settle with a rule of thumb about slab weight.

What every one of them agrees on is that a roof is not one wind zone. The corners see the worst of it, the perimeter strip sees more than the field, and the width of those zones is a calculated dimension driven by the building's least horizontal plan dimension and its mean roof height. On a terrace that sits in the corner of a building — which is where terraces tend to sit, because that is where the views are — a large fraction of the paved area can fall inside the corner and edge zones. That changes the paver specification, not just a note on the drawing.

Responses run in a familiar order: heavier units in the high-pressure zones, mechanical clips or interlocking heads, a restraint at the perimeter, or a solid perimeter course laid directly on a support rather than on adjustable heads. Each of those alters the take-off — heavier pavers change the module, clips are a fixing count, a restrained perimeter is a linear item — so the wind assessment belongs before the material order, not after the drawings are stamped.

Wind also arrives during the build, and the part-finished deck is the weakest the assembly will ever be. Loose pavers stacked on temporary heads have none of the restraint the finished terrace relies on, and a corner course set but not yet clipped is exactly the unit the design identified as most exposed. Weight down or strap anything left overnight in the zones the calculation flagged, and stop laying in the corner when the forecast turns rather than working to the edge and hoping.

The zone widths matter here as much as the pressures: mark the corner and edge strips on the terrace plan and you can see immediately how much of the paving needs the heavier specification.

The mapped basic wind speed for the site, at the risk category of the building.

The terrain roughness upwind of the building, over the distances the code specifies.

Average of eave height and ridge height, measured from grade.

The shorter of the building's two plan dimensions.

The pitch of the roof plane being checked, in degrees.

Read from the components-and-cladding figure in your adopted code, for this zone and effective area.

Design uplift pressure in the selected zone

30.5 psf

Medium confidence

The external pressure coefficient is the value you entered, not one this page supplies, so the answer is only as good as the figure you read off. This is a low-slope roof, so the low-slope coefficient figure applies and the corner zone wraps the full perimeter corner. The topographic factor is taken as 1.0, which is wrong on a hill, a ridge or an escarpment.

Velocity pressure at mean roof height
25.82 psf
Velocity pressure exposure coefficient
0.9 (Kz)
Internal pressure component included
4.65 psf
Corner and edge zone width, measured in from each roof edge
3.9 ft
Corner zone plan area at each corner
15.21 ft²

Add the equipment this sizes

This result is a specification — 30.5 psf — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

19.5 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • Enclosed building assumed. A partially enclosed building carries a much larger internal pressure coefficient and a building with a large dominant opening larger still.
  • Kzt = 1.0 assumed. Speed-up over a hill or an escarpment can raise the pressure by half again, and that is a separate calculation.
  • Gives pressure, not fastener spacing. Turning pressure into a clip or fastener layout needs the tested assembly's own rated resistance and its safety factor.

The Course That Cannot Sit on Four Corners

Everything in the field of a pedestal deck bears on shared corners, and everything at the edge does not. The last course against a parapet has heads on three corners of each slab and a support of its own on the fourth, or a continuous edge support, or a cut slab carried on a bearing strip — and whichever it is, it needs to be drawn rather than resolved by the installer at four o'clock on the last day. A cut slab is also lighter than a full one, which puts the least-restrained unit precisely where the uplift is highest.

Set out from the constraint that cannot move. Usually that is the door or the parapet line the terrace reads against, not an arbitrary corner, and pushing the cut strip to the side nobody stands on costs nothing at setting-out. Keep joint widths consistent with the head's spacer tabs, keep a movement gap at every upstand rather than butting slabs to the parapet, and carry any structural movement joint straight through the terrace as a joint in the paving too — a paver deck cannot bridge one, and a movement joint that has been paved over is discovered by the crack that appears above it.

Water Still Leaves Underneath, and Somebody Has To Get Down There

The whole point of the system is that rain goes through the joints, runs across the membrane and reaches the outlets as it always did. The consequence is that the drainage layer is now under a floor. Leaves, grit, cigarette ends and windblown soil from planters all end up in the same place, and an outlet blocked under a paved terrace announces itself as water at the threshold rather than as a puddle anyone can see.

Design the access before you need it. A removable panel over every outlet, its position recorded on a drawing and marked in a way that survives new tenants; enough clear space around the outlet body that a hand and a tool fit; and a maintenance regime that lifts those panels on a schedule rather than after a flood. BS 6229, Flat roofs with continuously supported flexible waterproof coverings — Code of practice, and the NRCA Roofing Manual: Membrane Roof Systems both treat access and maintenance as part of the roof rather than as an afterthought, and a terrace is the case where that is most easily forgotten.

Overflow provision deserves the same thought. If the primary outlet is under the deck and it blocks, the water rises under the pavers with nothing visible on top until it reaches the threshold or the parapet. Where a secondary outlet or overflow scupper exists, its invert is another line in the height budget worked down from the threshold, and the terrace surface has to sit in a sensible relationship to it. Where the roof carries a rainwater-retention or blue-roof function, the design water level does the same job and it constrains the pedestal heights directly.

Setting Out, Locking Off and Walking It Loaded

Pedestals are set to a level, not to the deck. Establish the finished level from the datum in the height budget, run string lines or a rotating laser across the terrace, and set the first row along the constraint line before anything else. Then work outward, checking level every few rows against the datum rather than against the row behind, because a run that references its own last row accumulates error in the same direction all the way to the parapet.

Lock every adjustment. A head still turnable by hand once the paver is down will find its own height under vibration and foot traffic, and the paver above it will rock. Where the system uses a locking collar or a grub screw, use it; where it relies on thread friction, confirm what the manufacturer says about it rather than assuming. Then walk the finished deck loaded before anybody else does, corner to corner and along every edge, and lift and re-set anything that moves.

  1. Fix the finished level from the height budget and mark it at the threshold, then transfer it to the parapet.
  2. Set the first row along the constraint line — usually the door or parapet, not a corner.
  3. Place heads by band, working from the high point downslope so the tallest pedestals go in last.
  4. Check every third or fourth row against the datum, never against the row behind it.
  5. Lock every head, then load-walk the deck and re-set anything that rocks.
  6. Fit the perimeter supports and cut course last, once the field is level and locked.

What the Client Gets Besides a Level Floor

Hand over the survey, not just the terrace. The recorded deck levels, the height schedule against the grid, the band break points and which pedestal component went where are the only way anybody lifts a paver in ten years and puts it back at the right level. Add the wind zone plan, marked with which areas carry the heavier or clipped specification, so that a future repair does not replace a corner unit with a field unit.

The rest is the safety file. Access to the terrace for maintenance is work at height once someone is lifting panels near an edge, and the regulation that covers it is not the one that covered the build: in the United States the installation sat under OSHA 29 CFR 1926 Subpart M, Fall Protection, as construction work, while the caretaker who comes back to clear an outlet is general industry and falls under 29 CFR 1910 Subpart D, Walking-Working Surfaces. Elsewhere the equivalent national work-at-height regulations draw the same line. Record the anchor positions if there are any, record the route to the outlets, and record the load the deck was designed for so that the first person who wants to put a hot tub on it has something to read before they do.

Ordering a pedestal terrace off the survey

Every line below is a number the survey produces and the purchase order consumes. None of them can be filled in from an area figure alone.

  • Deck levels at every grid line — One reading per pedestal line in both directions, taken on the finished waterproofing from a single instrument position.
  • High and low pedestal height — The two ends of the range. The high point tests the shortest component available; the low point decides bases plus extenders.
  • Grid head count — Lines in each direction multiplied, then perimeter supports, cut-course bearing, drain surrounds and planter kerbs added by hand.
  • Pedestals per range band — Grid lines grouped into the manufacturer's published ranges, counted, and ordered as bands rather than as one height.
  • Slope correctors and extenders — Separate line items, quantified where the fall exceeds what a flat head sits on and where a base alone cannot reach.
  • Wind zone areas — Corner, edge and field areas measured separately, because the paver specification and restraint change between them.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • ASCE/SEI 7 - Minimum Design Loads and Associated Criteria for Buildings and Other Structures (components and cladding wind provisions, and the corner and edge zone widths)
  • ANSI/SPRI RP-4 - Wind Design Standard for Ballasted Single-ply Roofing Systems
  • FM Global Property Loss Prevention Data Sheet 1-29 - Roof Deck Securement and Above-Deck Roof Components
  • BS 8579 - Guide to the design of balconies and terraces
  • BS 6229 - Flat roofs with continuously supported flexible waterproof coverings. Code of practice
  • ASTM C578 - Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation
  • ASTM C1289 - Standard Specification for Faced Rigid Cellular Polyisocyanurate Thermal Insulation Board
  • ASTM D1621 - Standard Test Method for Compressive Properties of Rigid Cellular Plastics
  • NRCA Roofing Manual: Membrane Roof Systems
  • OSHA 29 CFR 1926 Subpart M - Fall Protection (construction)
  • OSHA 29 CFR 1910 Subpart D - Walking-Working Surfaces (general industry, the maintenance visit)
  • Bison Innovative Products - pedestal system technical literature
  • Buzon Pedestal International - pedestal and slope corrector technical literature

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.