Mini-split installation takeoff

Capacity for the room, the plan area the outdoor unit and a margin round it take up, and the fall its condensate needs.

Measurements in
4
Trades out
3
Calculators
3
Going in
3of 3
My Project
Not in it

No figures of yours yet: a takeoff you add to My Project, or a setup you save, fills these boxes in one press.

Dimensions

Give the job once

Every figure on the right follows these, in the units you choose.

Every trade, from those dimensions

then change a dimension, and each line shows what moved.

Every trade's quantity · 3 rows

3 of 3 going in
ItemQuantityOrderWaste / allowance
Air Conditioner Size8600 BTU/h––
HVAC Equipment Pad/Curb Footprint8.67 sq ft8.67 sq ftno pack size recordednone
HVAC Condensate Drain Pipe Slope2.06 in––

Every trade's quantity · 3 rows

3 of 3 going in
ItemQuantityOrderWaste / allowance
Air Conditioner Size8611.13 BTU/h––
HVAC Equipment Pad/Curb Footprint0.78 m²0.78 m²no pack size recordednone
HVAC Condensate Drain Pipe Slope52.08 mm––

Estimates, not a quote. Each row gives its base, the allowance on top, the adjusted figure and what to order; change an allowance in its cell, or open the row to see every figure it rests on. A trade's own page carries what it does not cover — open the one you are about to order against.

3 of 3 trades chosenNot pricedNot in project
Kept on this deviceUnitsImperialMetricMy Projectnot in it yetQuantities only · your own rates · not a structural check

About this job

A takeoff is the trade word for the shopping list a job produces — every material, and how much of each, worked out by its own cited calculator.

Mini-splits are oversized more often than any other piece of domestic plant, and oversizing one makes the room worse rather than better. A unit with too much capacity satisfies the thermostat quickly, shuts down, and never runs long enough to dehumidify — so a correctly sized unit and an oversized one reach the same temperature and only one of them reaches it comfortably. The capacity row here is a rule-of-thumb estimate from floor area and a few conditions; a real selection is a room-by-room load calculation.

The footprint row is the one people discover late. An outdoor unit needs a level base, clearance for airflow on every side it breathes from, and enough room in front for somebody to service it — and the clearance, not the unit, is what usually decides whether the chosen spot works. Those clearances differ side by side and come from the unit's installation manual; the row adds a uniform 0.15 m (6 in) all round, so it is a first check on the space, not the clearance and not the concrete. The base only has to carry the unit — a technician can stand on gravel.

The condensate row looks trivial and causes a surprising share of callbacks. An indoor head produces litres of water a day in summer and drains it by gravity, so the line needs a continuous fall over its whole run. A drain that sags, or that rises to get over a joist, backs up into the unit and puts the water on the wall below it.

How each line reads

Base
What the calculator gives for these dimensions, before anything is added.
Allowance
Cutting waste, a lap or spare stock — named, with where it comes from, and changeable on the row.
Adjusted
The base with its allowance on top.
Order
What to buy: the adjusted figure in whole boards, bags, rolls or lengths.

The order this happens in

Quantities do not tell you the sequence, and on this job the sequence is where the money goes wrong.

  1. Size on the room's load, not on its floor area alone — and be suspicious of a round number.
  2. Choose the indoor position for the air throw, and the outdoor position for the clearance and the noise.
  3. Set the pad level and clear of the ground, where snow and leaves will not bury it.
  4. Core the wall with a slight fall to the outside, and sleeve it.
  5. Run the line set with generous bends, pressure-test and evacuate properly — this is what decides the lifespan.
  6. Confirm the condensate falls continuously along its whole run before commissioning.

What this takeoff does not cover

  • A real load calculation. Room-by-room heat gain and loss is what a selection should rest on.
  • The line set, its length limit, the additional refrigerant charge a long run needs, and the electrical supply.
  • Wall penetration, bracket, trunking and the seal around the core.
  • Noise at the boundary, which is what planning conditions and neighbours are concerned with.
  • Anything requiring refrigerant handling, which is licensed work nearly everywhere.
  • The manufacturer's airflow, discharge and service clearances, and the base's size, thickness and what goes under it.

Labour by trade

Person-hours from trade rules of thumb at each opening size, one crew per trade working in turn: a planning aid, never a price. The Labour tab follows your own figures.

Metric opening

Room floor area 40 m² · Outdoor unit width 0.9 m · Outdoor unit depth 350 mm and 1 more of the page's opening figures

No row of this job carries a production rate yet, so it has no hours here.

Imperial opening

Room floor area 430 sq ft · Outdoor unit width 3 ft · Outdoor unit depth 14 in and 1 more of the page's opening figures

No row of this job carries a production rate yet, so it has no hours here.

Quote check

Been given a quote for this job?

Paste it into the mini-split installation quote check. Every line of it is read against these same calculators and your measurements. Quantities only, never prices.

  • What it leaves out

    Every line this takeoff has that nothing on the quote reads as.

  • What it adds

    Labour, removal, hire, fees — each named for what it is.

  • What to ask

    One list of questions, ready to copy. Never a verdict.

More takeoffs

Other job takeoffs

All job takeoffs

Frequently asked questions

What does the mini-split installation takeoff give for a typical job?
Opened at Room floor area 40 m² · Outdoor unit width 0.9 m · Outdoor unit depth 350 mm · Condensate run 5 m, it orders: Air Conditioner Size, 8,611 BTU/h; HVAC Equipment Pad/Curb Footprint, 0.78 m²; HVAC Condensate Drain Pipe Slope, 52.1 mm. Opened at Room floor area 430 sq ft · Outdoor unit width 3 ft · Outdoor unit depth 14 in · Condensate run 16.5 ft: Air Conditioner Size, 8,600 BTU/h; HVAC Equipment Pad/Curb Footprint, 8.67 sq ft; HVAC Condensate Drain Pipe Slope, 2.06 in. Every figure follows the dimensions you give it.
Which calculators does the mini-split installation takeoff run?
3 calculators, one to a line: Air Conditioner Size Calculator, HVAC Equipment Pad/Curb Footprint Calculator, HVAC Condensate Drain Pipe Slope Calculator. Each has a page of its own with its formula and its sources; the takeoff runs them all on one set of dimensions.
What does the mini-split installation takeoff leave out?
6 things, each named on this page: A real load calculation; The line set, its length limit, the additional refrigerant charge a long run needs, and the electrical supply; Wall penetration, bracket, trunking and the seal around the core; Noise at the boundary, which is what planning conditions and neighbours are concerned with; Anything requiring refrigerant handling, which is licensed work nearly everywhere; The manufacturer's airflow, discharge and service clearances, and the base's size, thickness and what goes under it.
Can I check a quote for this job against the takeoff?
Yes. The mini-split installation quote check reads a quote's lines against these same calculators and your measurements, and reports what it leaves out, what it adds and what to ask. It reads quantities, never prices.