Interiors

Taking Off Board for Shafts, Soffits and One-Sided Walls

A riser priced as a two-sided partition buys twice the board, misses the liner completely, and never checks whether the stud height works.
  • 17 minReading time
  • 7Sections
  • 3Calculators inline
  • Last reviewed

The price that came in thirty-eight per cent under and was right

Three subcontract prices came back on the drywall package for a twelve-storey residential block. Two of them landed within four per cent of each other, which is the sort of agreement that makes a buyer relax. The third was thirty-eight per cent under on one bill line — fire-rated riser and duct enclosures, one hour, 486 m² — and the reflex was to assume somebody had dropped a page out of the drawing register. Nobody had. The two agreeing prices had measured every riser the way their takeoff software measures everything, centre-line run by storey height by two faces, and a riser enclosure has one face. The odd price out was the only one that had opened the section.

That two-sided default is not a fault in anybody's software. It is correct for the overwhelming majority of a fit-out, which is precisely why it stops registering as a default at all: a stud partition between two occupied rooms genuinely does take board on both flanks, and after four hundred metres of it the multiplication has become a reflex rather than a decision. What breaks is the minority — and on the buildings that carry the most of it, the minority is not small. A residential floor plate has lift shafts, a smoke shaft, wet and dry risers, electrical and comms risers and a refuse chute. A hospital floor has all of that plus medical gas and pneumatic tube. By item count those enclosures can be a third of the vertical drywall on the sheet, and every one of them is measured wrong by the same reflex.

They break the default in three separate directions, and it pays to keep the three apart because each has a different remedy. The finished face is one face rather than two, so the sheet quantity is not what the model says. The unfinished face is not bare — it is closed with a different product, bought in a different unit, at a rate that has nothing to do with the square-metre rate for board. And the height the stud has to span is not the storey height written on the elevation, because whatever is on the far side of that wall frequently has no floors in it.

Bulkheads fail it in a fourth way: by not appearing on the plan the takeoff was traced from. A boxed soffit hiding a duct run has no wall line to follow. It exists on the reflected ceiling plan as a hatched band and on a section as a small rectangle, and what it generates is a girth along a run rather than an area on an elevation. The sections below take the elevation apart in the order those four problems turn up in, and give the arithmetic each one wants.

Sort the elevation before you scale anything off it

The architectural wall type schedule will call all of this partitions, because a schedule exists to tell a builder what to build rather than to tell an estimator what to buy. Sorting it into what it is priced as is a five-minute job with a highlighter over the general arrangement and the reflected ceiling plan, and it is the only part of this whole exercise that cannot be automated, because the distinction being drawn is not one the drawing bothers to make.

Three questions do the sorting. How many faces receive board. What closes the faces that do not. And whether the item is bought over an area or along a length. Answer those on every wall type and every ceiling detail before the first dimension is scaled, and the rest of the takeoff is arithmetic; leave them until the quantities are already in a spreadsheet and you will be back-solving a total that looks plausible.

How each vertical drywall item is bought, and what a both-sides takeoff does to it
Item on the drawingWhat the two-sided model producesWhat is actually bought
Stud partition, both faces accessibleCorrect — the case the default was written forFace area doubled, at the layer count named in the wall type
Shaftwall or riser enclosureTwice the face board, and no liner whatsoeverFinished face area times the layers on that face, plus liner counted along the run
Lining to existing masonry or concreteA second finished face that does not existOne face only, and no cavity item behind it either
Boxed soffit or bulkheadMissed, or picked up as a partition at full storey heightGirth per metre of run: the exposed sides plus the underside
Column or beam casingMissed, because there is no wall line to traceGirth per metre of height, four faces and four external arrises
Rated bulkhead crossing a rated wallPlain board on a soffit girthThe listed build-up on that girth, at the design's own layer count
How each vertical drywall item is bought, and what a both-sides takeoff does to it

A bulkhead is a girth, not an area

Everything a bulkhead needs comes off two drawings that are rarely open at the same time. The run lengths are on the reflected ceiling plan, where the boxing shows as a band with a note. The drop and the underside width are on the section or on a ceiling detail, and they change more often than anyone expects — a soffit chasing a duct that reduces on its way across a floor plate steps down twice, and each step is a separate entry with its own dimensions rather than an average that splits the difference.

Which faces you count is the decision that goes wrong most often, and it is binary. An island bulkhead standing clear of the walls shows two vertical sides and an underside: three faces, and a girth of two drops plus the width. A bulkhead running tight against a wall shows one side and an underside, so its girth is one drop plus the width — near enough half the material for the same length of run. The top of either is closed against the structure it hangs from and takes no board, which is the one simplification in this whole page that is safe to make. Where a run ends in the open rather than dying into a wall, that returned end is a further small face of drop by width, negligible as area and thoroughly disproportionate as labour.

There is a coincidence in these numbers worth knowing about because it doubles as a sanity check. A 300 mm drop over a 400 mm underside gives a girth of exactly one metre, so on an island bulkhead of those proportions the run length in metres and the board area in square metres are the same number. That makes the total easy to check at a glance and easy to under-respect at the same glance: 24 m of bulkhead reads as 24 m² of board, which is less board than a single decent partition, and it will absorb several times that partition's hours before it is finished.

  1. Take each run separately off the reflected ceiling plan — a soffit that changes direction is two runs, and a soffit that steps is two runs with different sections.
  2. Read the drop and the underside width off the detail for that run, not off the first detail on the sheet.
  3. Decide the face count: two sides for an island bulkhead, one for a run held against a wall.
  4. Add a return face wherever the boxing stops in the open instead of meeting a wall.
  5. Count the external arrises as their own quantity — two per metre of run on an island, one on a wall-side run, plus a vertical pair at every end and every change of direction.
  6. Mark any run that crosses a rated wall or encloses a rated duct, because the girth stays the same and the build-up on it does not.

Run it once per bulkhead section rather than once for the job. It counts two side faces plus the underside, so a run held tight against a wall wants half the actual drop entered to give the single-sided girth.

The horizontal run length of the boxed-in soffit or bulkhead.

How far the soffit drops down from the ceiling on each visible side face.

The width of the flat bottom face of the boxed-in soffit or bulkhead.

Total wrap area

64.19 ft²

High confidence

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

19.5 ft16 in11.75 in
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • Assumes the box dies into a wall at both ends. A soffit that stops in the open has a return face of depth x bottom width at that end — trivial as area, but it brings two more outside corners with it, and the corners are the part that costs time.
  • Area is not the finishing. Every boxed soffit carries two outside corners for its whole length, so a 6 m (20 ft) run needs 12 m (39 ft) of corner bead before a single flat joint is taped, and that quantity tracks the run rather than the area. Boards ordered off this figure with the bead ordered off nothing is how the job stops on the second morning.
  • Says nothing about board thickness or how the box is framed. The bottom is a ceiling, and 12.5 mm board on framing at 600 mm centers sags over a horizontal face — 15 mm board or framing at 400 mm is the fix, and either one changes the sheet order this area converts into.

Two layers on one face weighs the same as one layer on two

Here is why the riser error survives so much review. Take a shaft 2.4 m square, so 9.6 m round, at a 3.0 m storey height: 28.8 m² of face. The two-sided model returns 57.6 m². A one-hour or two-hour listed design that puts two layers of Type X on the single finished face also comes to 57.6 m² of board. The wrong method and the right method have produced the same square metrage, and a checker comparing totals sees agreement. Change the design to one layer, or to three, and the agreement evaporates — but it evaporates quietly, in a direction nobody is looking, because the last job it was checked against happened to be a two-layer wall.

The board total is only ever half the item anyway. What the two-sided model is really claiming is that the shaft side gets sheet, and it does not: it gets a 25 mm (1 in) liner panel, typically 610 mm (24 in) wide, held in the webs of the studs and installed from the corridor. That is a separate product on a separate delivery, counted along the run instead of over the area, and 9.6 m of perimeter at 610 mm centres is sixteen panels per floor before any allowance for openings or breakage. A takeoff that has doubled the sheet quantity and omitted the liner is not one error cancelling another; it is over-ordering one item, missing a second, and pricing a rate against neither.

The layer count itself comes from the listed design and from nowhere else. A fire-resistance rating is the result of a full-scale test to ASTM E119 or UL 263 on one specific assembly, and the listing — in a UL certification directory, or in the Gypsum Association's GA-600 Fire Resistance and Sound Control Design Manual — names the stud, the liner, the board type and thickness, the number of layers and the fastener schedule together. Two designs with the same hourly rating routinely differ in layer count because they differ everywhere else. Reading a layer count off the rating is a guess, and it is a guess that lands squarely on the largest quantity in the package.

Deductions need a colder eye on a shaft than on a partition. Riser enclosures are punched with access panels and louvred doors, and the instinct is to deduct all of them. Deduct only the openings big enough that what comes out of the sheet is a piece somebody will actually use. A run of small penetrations does not save board — it generates offcuts and consumes labour, and deducting their area makes the order short at exactly the moment the wall is being closed up. Where the enclosure crosses a compartment floor, the fire-stopping at the slab and the head detail are their own quantities and belong nowhere near the board line.

One face, the layer count read off the listed design, and openings deducted only where the offcut is worth having. The number it returns should sit alongside a liner quantity, never instead of one.

SettingsSettings for this calculation
Who is doing the work?

The standard allowance most suppliers and estimating guides assume for ordinary work.

The face area of the wall being boarded, measured on one side only.

The coverage area of one board as supplied.

How many layers of board the tested design puts on this one face.

Total area of access doors, louvres and openings you will not board over.

Allowance for cuts, damage and offcuts that cannot start the next run.

Type X boards needed

22 boards

Medium confidence

This counts one face only, which is the point of the page: a shaftwall, a party-wall closure and a one-hour corridor lining are all boarded on a single side, and doubling them for a second face is a straight 100% over-order. Take the layer count from the tested design listing for your exact assembly.

Boards in one layer
11 boards
Net area after opening deductions
320 ft²
Area including the waste allowance
352 ft²

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

What this calculation does not cover

  • Boards only. Screws, joint tape, setting compound, corner bead and the firestopping at the head and the penetrations are separate quantities.
  • Does not verify the assembly. Whether a given layer count achieves the rating you need is settled by the listed design, not by a count.

The stud does not know where the floors are

The elevation says the storey height is 3.0 m, so the wall is 3.0 m, so the stud is a 3.0 m stud and the framing rate is the framing rate. On a partition between two rooms that chain holds, because both ends of the stud are in track against structure and the floor slab is continuous through the line of the wall. On a shaft it can be nonsense. There is no floor inside a lift shaft. A smoke shaft is a clear vertical route by definition. A services riser with a grated or partial floor at each level gives you nothing to brace against even where a slab edge is drawn on the plan. The dimension the framing has to satisfy is the distance between real lateral supports, and on a shaft that can be two, three or a dozen storeys.

The second dimension is the pressure the enclosure is designed against, and it is not a property of the wall. The International Building Code sets a minimum lateral load for interior walls and partitions in its structural design chapter — 5 psf, 0.24 kPa — and shaft enclosures are routinely specified well above it. The figure originates with the lift supplier, who knows what piston effect a car of that speed and size generates in a hoistway of those dimensions, or with the smoke control design, which imposes a pressure difference on purpose. Where the shaft is on the building perimeter it has to be checked against wind as well, at whichever governs. None of these are numbers to assume; all of them are numbers that exist somewhere in the design team's documents before the drywall package is priced.

The deflection limit is the third input and it tracks the finish rather than the fire rating. A shaft face left as liner and a corridor face taking paint are commonly held to L/240; a corridor face carrying tile, stone or a rigid coating goes tighter, because those finishes crack while the framing is still perfectly comfortable. The specification says which, and the difference between L/240 and L/360 on the same stud is a substantial slice of allowable height.

Put those three together and what falls out is a stud — a depth and a gauge — and that is the estimating consequence. Framing is priced per square metre against an assumed member, and a package priced on a light gauge that turns out to need a heavier one is not a small adjustment. It is a rate change on the largest linear quantity in the enclosure, discovered by the framing foreman after award, at the point where the argument is about who should have known. Non-structural framing members are covered by ASTM C645 and installed to ASTM C754, with AISI S220 the North American standard for cold-formed steel framing non-structural members; the section properties that decide height come from the manufacturer's own tables, because the effective stiffness of a thin cold-formed section is not derivable from its outside dimensions.

Treat the height check as a screening test on the takeoff rather than as design. It tells you whether the wall your rate assumes is anywhere near the wall the drawing needs, and which enclosures to raise as a question before the price goes in. The manufacturer's tabulated limiting height is the lesser of a deflection check and a bending strength check, and it is tied to a tested assembly with its own track, fastening and liner. Where the table is lower than a deflection calculation, strength is governing and the table is the answer.

Put in the unsupported height you are actually facing rather than the storey height, with the design pressure off the specification. If the proposed height eats most of the allowance, the gauge in your rate is the thing to go back and look at.

The lateral pressure the shaft enclosure is designed to resist.

Centre-to-centre spacing of the C-H studs along the wall.

The stud's effective moment of inertia, from the manufacturer's table.

The deflection limit the specification applies to this wall.

The floor-to-floor height you want to run this stud through.

Maximum unsupported height

18.9 ft

Medium confidence

The proposed height uses 32% of the deflection allowance. This is the deflection-governed limit only — the manufacturer's tabulated limiting height is the lesser of this and a bending strength check, and for heavier gauges and higher pressures it is often strength that governs.

Line load carried by one stud
10.44 lbf/ft
Deflection at the proposed height
0.21 in
Allowable deflection at the proposed height
0.65 in
Deflection allowance used at that height
32.37 %
13 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • Deflection only. Bending strength requires the effective section modulus and yield strength for the same stud, which are published alongside the moment of inertia and are not derivable from it.
  • Treats the stud as a simply supported span between tracks. Slip track details, deflection heads and intermediate bracing all change the end conditions and the tabulated heights that go with them.
  • The liner panel is not counted as contributing stiffness. Shaftwall liner is friction-fitted between the studs and is not composite with them, which is why manufacturers publish limiting heights against the stud alone.

Bead, tape and the hours that scale with run rather than area

Bulkhead work is priced badly because the quantity everyone reports is the one that behaves least like the cost. Take a 24 m island bulkhead on a deeper section than the one above — a 400 mm drop over a 600 mm underside, so a 1.4 m girth and 33.6 m² of board — which folded into a partition line at a partition rate looks like nothing at all. Now count the arrises. Two external corners run the full length, one at each junction of side and underside, giving 48 m of external bead before the ends are counted. A straight partition of that same 33.6 m², which at storey height is about fourteen metres of wall, carries external bead at its door reveals and nowhere else — perhaps six metres for a single opening. The bulkhead has eight times the bead for the same board, and bead is an accessory to ASTM C1047 that has to be fixed, coated and sanded on an arris that is at head height and in everyone's sightline.

The internal junctions scale the same way. Every metre of that run has two internal angles where the sides meet the ceiling plane, so the internal taping comes to twice the run — another 48 m on this one — on top of the bead, before a single butt joint between sheets is counted. Compound follows the tape rather than the area, and on wrap-heavy work the compound quantity taken from board area alone comes out visibly short — which is normally discovered as an extra collection rather than as an estimating error, and so never gets fed back into the rate.

Waste on wrap work is geometric, not careless, and it is worth saying so in the pricing notes because it will be challenged. A 400 mm strip ripped from a 1200 mm sheet looks like perfect efficiency on paper and is nothing of the sort on site: run lengths do not divide into sheet lengths, every service crossing and every change of level interrupts the strip, and the offcut from one bulkhead rarely starts the next. The allowance is a judgement you have to be able to defend, and the defensible version is stated per condition — plain long runs low, cut-up runs with steps and returns considerably higher — rather than as one blanket percentage across the package.

The practical conclusion is a reporting one. Bulkheads, casings and shaft enclosures come out of the takeoff as their own lines at their own rates, with the run length carried alongside the area, because the run length is what the labour actually follows. Folding them into a partition square-metre total at the partition rate does not make the estimate simpler. It makes it wrong in a way that only shows up as a productivity shortfall six weeks into the boarding programme, by which point nobody can tell whether it was the takeoff, the rate or the gang.

Which document decides the unit

Whether a bulkhead is bought by the square metre or the linear metre is not a technical question, it is a contractual one, and the answer lives in the method of measurement named in the preliminaries. In UK practice that is normally the RICS New Rules of Measurement, NRM 2, Detailed Measurement for Building Works, which sets out how linings and partitioning are measured and what is given separately. Elsewhere there is often no mandated rulebook at all and the bid documents carry their own measurement rules, or carry none, at which point the unit is whatever the two parties each assumed until the first variation forces the point. Read for it before measuring; re-measuring a package because the client's surveyor takes soffits linearly is a week nobody has.

Write the takeoff so the buyer and the foreman are reading the same document. Every enclosure line wants six things against it: the quantity, the unit, how many faces receive board, how many layers on those faces, the board type and thickness, and the listed design reference the layer count came from. The liner sits on its own line in panels, not folded into a square-metre total. Workmanship standards belong in the same note where they affect what is bought — ASTM C840 and the Gypsum Association's GA-216 in North America, BS 8000-8 with boards to BS EN 520 in the UK, AS/NZS 2589 in Australia and New Zealand — because a specification calling for a higher level of finish on a visible bulkhead is a coating and labour quantity as much as a quality clause.

Then flag the assumptions as assumptions, in the price rather than in your own file. The stud gauge is the one that matters: state the member the framing rate is built on and state that it is subject to the limiting height check against the design transverse pressure, which the specification is expected to give. A qualification like that costs nothing at tender and settles the entire argument later. Somebody on the job is going to discover that the lift shaft needs a heavier stud than the corridor walls, and the only question worth controlling is whether that discovery happens while the price is still a document or after it has become a contract.

Before the enclosure lines go into the price

The workspace opens on a 24 m island bulkhead with a 400 mm drop and a 600 mm underside — 33.6 m² of wrap. Replace it with your own run and work down.

  • Every vertical item sorted by face count first — Two faces, one face, or a girth. Do it with a highlighter over the general arrangement and the reflected ceiling plan before any dimension is scaled.
  • Bulkheads measured run by run, not as one total — A soffit that steps or turns is two entries with two sections. Note whether each run is an island or held against a wall, because that halves the girth.
  • External arrises counted as their own quantity — Two per metre of island bulkhead, one per metre against a wall, plus a pair at every end and every change of direction.
  • Layer count taken from the listed design, never from the rating — Two assemblies at the same hourly rating routinely carry different layer counts, and the layer count multiplies the biggest quantity in the package.
  • Liner on its own line, in panels along the run — 25 mm panel at 610 mm wide is a different product on a different delivery. A perimeter divided by panel width is the count, before openings and breakage.
  • Unsupported height read off the section, not the storey height — Shafts have no floors in them. The height that matters is between real lateral supports, and it decides the stud gauge your framing rate assumes.
  • Design transverse pressure found in the specification — It comes from the lift supplier or the smoke control design. The code minimum for interior partitions is a floor, not the figure a hoistway is priced against.
  • Method of measurement checked in the preliminaries — Whether soffits are area or linear is a contractual answer. Finding out after the price is in means re-measuring the package.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • ASTM C840 — Standard Specification for Application and Finishing of Gypsum Board
  • ASTM C1396/C1396M — Standard Specification for Gypsum Board
  • ASTM C645 — Standard Specification for Nonstructural Steel Framing Members
  • ASTM C754 — Standard Specification for Installation of Steel Framing Members to Receive Screw-Attached Gypsum Panel Products
  • ASTM C1047 — Standard Specification for Accessory Products for Gypsum Panel Products
  • ASTM E119 — Standard Test Methods for Fire Tests of Building Construction and Materials
  • UL 263 — Fire Tests of Building Construction and Materials
  • Gypsum Association GA-600 — Fire Resistance and Sound Control Design Manual
  • Gypsum Association GA-216 — Application and Finishing of Gypsum Panel Products
  • AISI S220 — North American Standard for Cold-Formed Steel Framing, Nonstructural Members
  • AISI S100 — North American Specification for the Design of Cold-Formed Steel Structural Members
  • International Building Code — Chapter 7, Fire and Smoke Protection Features (shaft enclosures) and Chapter 16, Structural Design (minimum lateral load on interior walls and partitions)
  • ASME A17.1/CSA B44 — Safety Code for Elevators and Escalators
  • RICS New Rules of Measurement, NRM 2 — Detailed Measurement for Building Works
  • BS 8000-8 — Workmanship on construction sites: Code of practice for plasterboard partitions and dry linings
  • BS EN 520 — Gypsum plasterboards: Definitions, requirements and test methods
  • AS/NZS 2589 — Gypsum linings: Application and finishing

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.