Measure the Room You Have, Not the One on the House Plans
Finishing a basement starts with a tape measure, not a drawing. The house plans give the outside of the foundation; what you can finish is the inside face of the concrete less whatever is in the way, a column, a beam, a duct run, the furnace and the water heater, the drain stack, the electrical panel. Walk the basement with a sketch pad and mark each one, and measure the clear height under the lowest beam or duct, because that height, not the floor-to-joist height, is what the ceiling will be.
Then decide what stays raw. Almost every finished basement keeps an unfinished corner for the equipment, where the furnace can be serviced and a leak can be seen. Put the partition for it where the equipment is, not where it would look tidy on plan, and leave space in front of the panel and the burner that an inspector would accept.
The worked example is the basement-finish template: a basement 9 by 7 metres (30 by 23 feet) inside, a utility room 3 metres (10 feet) wide at the east end, the rest a family room, and a stair up to the ground floor.
A Level Below the Ground Floor
In the Construction Canvas add a Basement level below the ground floor, with its floor-to-floor height, and a Ground floor level above it so the stair has somewhere to arrive. The concrete walls and the slab are not drawn. They exist, nothing is bought for them, and drawing them would put concrete in the list that nobody pours. What you draw is what goes in.
That makes a basement drawing a little unusual: its outermost walls are not the building's outside walls but the stud walls framed a short distance in from the concrete, leaving a gap so the studs never touch a surface that can be damp. Draw them as one closed loop of the stud partition type, by their inside faces, and give them the interior role; the list then counts their studs as it does any partition, and the rooms inside take their floors from the studs' faces.
- Add a Basement level below the ground floor and a Ground floor level above it.
- Draw a closed loop of stud walls a little in from the concrete, by their inside faces.
- Add a partition for the utility room, with a door.
- Name the finished room and the utility room with the room tool.
Lay it out, row by row
Finishes That Suit a Room Below Ground
Click inside the family room with the room tool, name it and choose its finishes. Below ground, the choices that matter are on the walls and the floor. Answer yes to insulating the walls and to new plasterboard on the walls and the ceiling, and the list counts batts between the studs, board for both surfaces, the screws for the ceiling, the joint tape and the compound, then primer and paint over the top. Whether those walls also want a vapour control layer, and on which side, depends on your climate and how the wall is built, and your building office has a view.
The floor is the other decision. Carpet over a cushion is warm underfoot; a click floor lifts and dries if water ever comes in, which is why many basements choose it. Both are counted over the room's floor area from the inside faces of the walls. If the slab is uneven, answer yes to levelling first and give the average depth, which only a straightedge across the floor can tell you.
Name the utility room as well, but keep its walls, ceiling and floor as they are. It still appears in the list for the trim round its door, which is a reminder that even the raw room has a finished doorway.
The Ceiling Is Lower Than You Think
Basement ceilings are the most common surprise in a finish. The joists above are rarely clear: a main beam crosses the room, heating ducts hang below the joists, a drain pipe runs at a slope to the stack, and the panel's cables fan out from one corner. A flat ceiling under all of them can end up well below the height you measured between the joists, sometimes below what your building code allows for a habitable room.
There are three usual answers, and the canvas can show what each takes. Box in only the beam and the ducts, leaving the rest of the ceiling at joist height: draw the room as one space and note the bulkheads, because the board for their sides is extra to the ceiling area. Hang a suspended grid ceiling just below the lowest obstruction, which keeps every service reachable: the room's ceiling finish then stays as it is in the list, and the grid and tiles are ordered from the room's floor area. Or board the whole ceiling at one level below everything, which is simplest to build and gives up the most height.
Whichever you choose, set the room's ceiling height in its properties to the finished figure rather than leaving it at the level's height, so the wall board, insulation and paint are worked over the walls you will actually finish. A few centimetres (an inch or two) on every wall adds up across a whole basement.
Light, Power and the Stair
Basements are dark, so plan more light than upstairs: recessed downlights in a grid across the family room, on a switch at the top and at the bottom of the stair, and a plain ceiling light in the utility room. Outlets go round the walls at the spacing your electrical rules set; the room can be asked for the minimum the spacing rule gives, to check the drawn count against. Each is a point of its kind, and the list counts them.
Draw the stair on the Basement level along the wall it runs beside, climbing to the Ground floor. If the stair is already there and staying, draw it anyway so the plan reads right, then remember its stringer row is not something you are buying. Headroom over the stair is where many basement finishes fail inspection: the new ceiling board and any boxing-in around ducts can take it below what the code allows, so measure it before committing to a ceiling height.
Adding a Bathroom
A basement bathroom is the most common addition and the most constrained, because the waste has to reach the sewer, which may sit higher than the basement floor. In the drawing, a shower room is a partition across one end of the utility area with its own door, a room with tiled walls and floor, and the fixtures as points: WC, basin, shower and a floor drain. The template's second variant draws exactly that, and comparing its list with the plain one shows what the bathroom adds.
What the drawing cannot show is how the waste gets out. Below the sewer line, that means a pump or an up-flush unit, and its size, venting and discharge route are a plumber's design. Draw the fixtures where you want them, then ask the plumber whether they can go there before the partition goes up.
Reading the List and Planning the Order
The list groups the work in the order a basement finish is built. Walls first: the studs for the framing and the partitions. Then the room rows: insulation, board, tape and compound, paint, the floor, skirting and casing, room by room. Then the counted points, which are the electrician's schedule, and the stair. Send it to My Project and the rows stay attached to the drawing for the next change.
Try two things before ordering. Drag the utility partition a metre to see how much finished room the equipment takes from you. And switch the floor from carpet to a click floor to see how the floor rows change. Both take seconds and both are decisions worth making with the list in front of you.
Dry First, and Who Decides the Rest
Never finish a basement that is wet or that has been wet recently: board and carpet hide water until the smell gives it away. Cure the water first, with drainage outside, a sump inside or tanking on the walls, and give the walls a season to show they stay dry. Escape windows for any room used for sleeping, the stair's headroom and guard, smoke alarms, and anything touching the furnace's air supply are set by your building code and checked by your building office, and the electrical and plumbing work usually needs licensed trades. The drawing counts the finish; it does not decide that the basement is fit to finish.
Try the calculation
Check the room rows
The finished room's rows come from these pages. Check them for your own room's size.
- Wall insulation — Batts for the wall area between the studs.
- Plasterboard — Sheets for the walls and the ceiling.
- Wall paint — Paint for the walls after the openings are taken out.
- Carpet — Roll length for the room's floor.